Project Management Analysis Of Luxury Care Home For Elderly People

The Role of Project Management in Construction Activities

The project management plays a significant role in the development of the construction activities and alignment of the operations for developing the operations (Mir & Pinnington, 2014). The integration of the system development would be allowed for forming the alignment of the project operations. The construction, system development, event management, software alignment, website development, and other projects would allow the integration for the management of the improved operations and functions.  

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper

The following assignment consists of analysis of a specific plan for the development of the luxury home for elderly people. The Mendelow matrix would be formed for ensuring that the project is formed for analysis of the project stakeholders. The conflict management planning and potential issue management are formed in the report.

The project of Luxury Care Home for Elderly People was made with the help of the agile methodology as it would allow the planner for developing effective and efficient deployment of the activities. The deployment of the activities would allow the modification of the operations for carrying out the specific modification of the building development plan for the organization to carry out the planned activities. The construction and project development would help the business organizations to carry out the project successfully. The project plan consists of four phases namely project initialization, project planning, project execution, and project closure (Boud, Cohen & Sampson, 2014). The implication of the agile development for planning would allow the development of the project plan as follows,

Project Initiation: The project initiation consists of analysis of the project scope, scope development, charter documentation, change requirement analysis, project initiation document, document submission, and review and signing of the documents activities.

Project Planning: The project planning consists of schedule planning, scope management planning, change management planning, risk management planning, and plans approval activities.

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper

Project Execution: The project execution consists of resource accumulation, external contractor employment, procurement and agreement, site development, site clearing and cleaning, construction operations (including laying of building pillars, building infrastructure is formed, and floors are built), equipments and facilities are installed, and fire safety and medical kits are installed activities.

Project Closure: The project closure consists of development of final documents, submission of final documents, review and signing of the documents and project is closed activities.

WBS

Task Name

Duration

Start

Finish

Predecessors

Resource Names

0

Luxury Care Home for Elderly People

88 days

Mon 1/1/18

Wed 5/2/18

1

   Project Initiation

14 days

Mon 1/1/18

Thu 1/18/18

1.1

      Analysis of the project scope

2 days

Mon 1/1/18

Tue 1/2/18

Analyst

1.2

      Scope Development

4 days

Wed 1/3/18

Mon 1/8/18

2

Project Manager

1.3

      Charter Documentation

3 days

Wed 1/3/18

Fri 1/5/18

2

Documenter

1.4

      Change Requirement Analysis

2 days

Tue 1/9/18

Wed 1/10/18

3

Analyst

1.5

      Project Initiation Document

3 days

Thu 1/11/18

Mon 1/15/18

5, 3, 4

Documenter

1.6

      Document Submission

1 day

Tue 1/16/18

Tue 1/16/18

6

Documenter

1.7

      Review and Signing of the document

2 days

Wed 1/17/18

Thu 1/18/18

7

Project Manager

2

   Project Planning

7 days

Fri 1/19/18

Mon 1/29/18

2.1

      Schedule Planning

5 days

Fri 1/19/18

Thu 1/25/18

8

Planner

2.2

      Scope Management Planning

3 days

Fri 1/19/18

Tue 1/23/18

8

Project Manager

2.3

      Change Management Planning

4 days

Fri 1/19/18

Wed 1/24/18

8

Analyst

2.4

      Risk Management Planning

4 days

Fri 1/19/18

Wed 1/24/18

8

Risk Analyst

2.5

      Plans Approval

2 days

Fri 1/26/18

Mon 1/29/18

10, 11, 12, 13

Client

3

   Project Execution

61 days

Tue 1/30/18

Tue 4/24/18

3.1

      Resource Accumulation

5 days

Tue 1/30/18

Mon 2/5/18

14

Project Manager

3.2

      External Contractor Employment

3 days

Tue 2/6/18

Thu 2/8/18

16

Client

3.3

      Procurement and Agreement

2 days

Fri 2/9/18

Mon 2/12/18

17

Client, Contractor

3.4

      Site Development

3 days

Tue 2/13/18

Thu 2/15/18

18

Contractor

3.5

      Site Clearing and Cleaning

2 days

Fri 2/16/18

Mon 2/19/18

19

Contractor

3.6

      Construction Operations

32 days

Tue 2/20/18

Wed 4/4/18

3.6.1

         Laying of building pillars

7 days

Tue 2/20/18

Wed 2/28/18

20

Workers

3.6.2

         Building Infrastructure is formed

10 days

Thu 3/1/18

Wed 3/14/18

22

Workers

3.6.3

         Floors are built

15 days

Thu 3/15/18

Wed 4/4/18

23

Workers

3.7

      Equipments and Facilities are installed

9 days

Thu 4/5/18

Tue 4/17/18

24

Engineer

3.8

      Fire Safety and Medical Kits are installed

5 days

Wed 4/18/18

Tue 4/24/18

25

Contractor

4

   Project Closure

6 days

Wed 4/25/18

Wed 5/2/18

4.1

      Development of final documents

3 days

Wed 4/25/18

Fri 4/27/18

26

Documenter

4.2

      Submission of final documents

1 day

Mon 4/30/18

Mon 4/30/18

28

Documenter

4.3

      Review and Signing of the document

1 day

Tue 5/1/18

Tue 5/1/18

29

Project Manager

4.4

      Project is Closed

1 day

Wed 5/2/18

Wed 5/2/18

30

Client

The Gantt chart of the project of Luxury Care Home for Elderly People is given below,

The Luxury Care Home for Elderly People project is developed for the development of the effective and improved building construction plan for the elderly people (Flyvbjerg, 2013). The aims of the project are,

Agile Development Methodology

Development of the Luxury Home Centre: The primary aim of the project is to develop a luxury home centre for the elderly people. The people are suffering from health issues and it tolls a certain amount of resources for the development of the specific care for the people. The luxury home development would allow the integration of the construction and project management principles for the development of the improved project completion.

Project Plan Development: The complete plan development would require the use of the project management concepts and activities for aligning the specific project management operations. The integration of the concise project development would help the project in carrying out the deployed system development. The project plan development would cause the modification of the activities for successful completion of the project.  

Usage of resources: The development of the effective project resources would allow the formation of the improved project operations for carving the development of the project. The resources are required for forming the alignment of the project operations and successful completion of the project. The resource management is done in order to successfully form the development of the effective project integration management. The other roles of the project are developed for forming the deployment of the schedule for the project for developing improved system development.

The project of Luxury Care Home for Elderly People is formed for the deployment of the functions and operations. The building site development would comprise of forming the development of the specific project construction activities. The objectives of the Luxury Care Home for Elderly People project are,

  • To develop specific luxury home for the elderly people supporting their lifestyle
  • To evaluate the deployment of the operations for fixing the management of the construction activities of the project
  • To consider the development of the specific project integration for the planning, scheduling, and developing project

The various stakeholders of the project are classified into three sections namely Governance, Managerial, and Operational (Wu et al., 2015). The project of Luxury Care Home for Elderly People would involve the external contractor also for the development of the site. Each of the stakeholders of the project would be responsible for the development of the project operations and carrying it out for the successful completion of the project. The following table would provide a view of the stakeholders and their involvement in the project.

Stakeholder’s name

Category

Activities Involved in

Client

Governance

Plans Approval

External Contractor Employment

Procurement and Agreement

Project Manager

Managerial

Scope Development

Review and Signing of the document

Scope Management Planning

Resource Accumulation

Review and Signing of the document

Project is Closed

Contractor

Managerial

Procurement and Agreement

Site Development

Site Clearing and Cleaning

Fire Safety and Medical Kits are installed

Elderly People

Operational (user)

Using the Luxury Home made in the project

Analyst

Operational

Analysis of the project scope

Change Management Planning

Change Requirement Analysis

Change Requirement Analysis

Documenter

Operational

Charter Documentation

Project Initiation Document

Document Submission

Development of final documents

Submission of final documents

Planner

Operational

Schedule Planning

Risk Analyst

Operational

Risk Management Planning

Workers

Operational

Laying of building pillars

Building Infrastructure is formed

Floors are built

Engineer

Operational

Equipments and Facilities are installed

 

The Mendelow Matrix is developed for analysing the development of the effective and improved functions of the project (Kuo et al., 2014). The Mendelow Matrix is develoepd by considering the power and interest of the various stakeholders of the project. The development of the profound system development would allow the project for developing the luxury home for the elderly people. The various stakeholders of the project were Client, Project Manager, Contractor, Elderly People, Analyst, Documenter, Planner, Risk Analyst, Workers, and Engineer. The various stakeholders of the project are classified into governance, managerial, and operational. The stakeholders would allow the development of the activities for entailing the deployment of the effective project integration. The features of the Mendelow matrix is given below,

Interest

Low

High

Power

Low

Category A:

Minimal Effort

Category B:

Keep Informed

High

Category C:

Keep Satisfied

Category D:

Key Player

The Four Phases of the Project Plan: Initialization, Planning, Execution, and Closure

The Mendelow Matrix for the project of Luxury Care Home for Elderly People is given below,

Interest

Low

High

Power

Low

Analyst

Risk Analyst

Planner

Documenter,

Workers

Engineer

High

Contractor

Elderly People

Client

Project Manager

The point that should be noted from the Mendelow Matrix is that the operational department comprises of the Category A with less power and interest and hence they need to be motivated and kept close eye on for ensuring completion of the project.

Developing Contracts and Agreements are the legal methods for ensuring that the personal delivers the promised outcomes and Rewards and Recognition are the non-legal solutions for motivating them to perform efficiently.

Contracts and Agreements are the most prominent method used as once the person is bounded by the contract, he/she must finish the project work in the estimated time and budget. However, the contracts and agreements act more like a hook that does not perform the employees to work better and more enthusiastically. Rewards and Recognition serve the purpose of motivation to the employees for performing more efficiently. However, the employees are not bounded to deliver better outcomes and they are free to opt for delivering better or not.

Conflict Management can be defined as the process of improving the opportunity for improving the situations and strengthening the relationship among the people (Einarsen et al., 2016). The issues of the operational level identified in the previous Mendelow’s matrix need to be managed and form the deployment of the improved services. The conflict management can be implied in six steps as explained below,

Clarification of the Disagreement: The first step of the conflict management is the clarification of the disagreement among the parties. The project team members might have conflict of some other reasons which they would not express easily. The project manager or leader would have to ensure that the real reason for the conflict or the factor of disagreement must be known prior before solving the conflict.

Establishment of Common Goal: The common goal is a negotiable outcome of the disagreement between the conflicting parties (Stipanowich & Lamare, 2014). The conflict can be shortened with the help of developing a common muse in between the project team members for developing the proper solution to their disagreement. The common goal would allow the users for the development of the profound agreement among the project team members.

Discussion for Achievement of Common Goal: The discussion of the achievement of the common goal would ensure that there are no issues in the development of the project. The conflict management would evaluate the development of the specific management of the operations and integration of the system integration (Hylli et al., 2015). The common goal would be achieved for developing the profound system development and conflict resolution. The members would have to somehow develop improved operations for the management of the specific alignment.

The Gantt Chart of Luxury Care Home for Elderly People

Determination of Barriers of Common Goal: The determination of barriers of the common goals would allow the users for the formation of the improved system alignment. The conflict management would be done by achievement of the common goals for the parties. The goal management is formed for integrating the deployment of the profound system development. The integration of the operations would allow the formation of the solution for the specific conflict.

Agreement on a Way for Achievement of Common Goal: The agreement on a single way for the achievement of the common goal is developed for ensuring that the project would work profoundly for the development of the conflict management. The conflict management plays a key role in developing the profound alignment of the operations for the development of the system integrated operations. The two parties must agree on a single method of achievement of the common goal for ensuring the conflict management.

Acknowledgement of the Solution: The parties must acknowledge the solution formed and should provide the deployment of the specific and improved functional development. The work should be divided in two parties in such a way that both of the parties would accept the work division. The solution would be accomplished by the deployment of the improved function development.

The potential issues that can be faced while development of the luxury home for the elderly people are,

  • Delay in Operation
  • Cost Overrun
  • Conflict among Team Members

The potential issue management can be implied with the help of proper issue management for luxury home building development project (Bhat et al., 2017). There are seven steps of implementing issue management in project and they are awareness of the responsibilities, contingency planning, change management, meeting deadlines, effective communication, collaborative actions, and understanding of the problems. They have been explained below,

S. No.

Step Name

Description

1

Awareness of the Responsibilities

The awareness of the responsibilities are implied for ensuring that the person understands his/her responsibilities effectively. It would help in overcoming the question of who’s responsible.

2

Contingency Planning

The contingency planning helps in overcoming any problem as it is the Plan B for any operation. Contingency plan is implied when the plan is not working properly and there are issues in developing proper solution to the issues.

3

Change Management

Change Management is implied for adjusting and implementing the changes in the project successfully.

4

Meeting Deadlines

Meeting deadline would help in overcoming the issue of delay in completion of the project. The supplementary development of the deadlines would help in forming the improved performance for the people.

5

Effective Communication

Effective communication would help in forming the development of the transfer of information which would help in reducing the probability of occurrence of various issues and problems.

6

Collaborative Actions

Collaborative actions are implied for ensuring that the operations of the project are aligned to the goals and objectives.

7

Understanding of the Problems

The problem understanding is one of the most important factor that can help in overcoming the occurrence of the problem.

Conclusion

It can be concluded from the assignment that project management had been playing a significant for the successful project development. The development of the improved functions for the project had allowed the deployment of the effective and profound system development. The plan was formed for ensuring that the proper documentation would be made for the project. The schedule formed had been aligned with the specific formation of the luxury house and it had integrated the development of the improved professional development. The report had also provided the analysis of the aims and objectives of the project, stakeholder involvement in the project, and analysis of the project.

References

Bhat, M., Shumaiev, K., Biesdorf, A., Hohenstein, U., & Matthes, F. (2017, September). Automatic extraction of design decisions from issue management systems: a machine learning based approach. In European Conference on Software Architecture (pp. 138-154). Springer, Cham.

Boud, D., Cohen, R., & Sampson, J. (Eds.). (2014). Peer learning in higher education: Learning from and with each other. Routledge.

Burke, R. (2013). Project management: planning and control techniques. New Jersey, USA.

Einarsen, S., Skogstad, A., Rørvik, E., Lande, Å. B., & Nielsen, M. B. (2016). Climate for conflict management, exposure to workplace bullying and work engagement: a moderated mediation analysis. The International Journal of Human Resource Management, 1-22.

Elsaid, A., Salem, R., & Abdul-Kader, H. (2017). Research Article A Dynamic Stakeholder Classification and Prioritization Based on Hybrid Rough-fuzzy Method.

Fleming, Q. W., & Koppelman, J. M. (2016, December). Earned value project management. Project Management Institute.

Flyvbjerg, B. (2013). From Nobel prize to project management: getting risks right. arXiv preprint arXiv:1302.3642.

Hylli, O., Mattila, A. L., & Systä, K. (2015). Collecting issue management data for analysis with a unified model and API descriptions. In SPLST (pp. 251-265).

Kerzner, H. (2017). Project management metrics, KPIs, and dashboards: a guide to measuring and monitoring project performance. John Wiley & Sons.

Kuo, M. C., Lin, F. Y., Lin, C. Y., & Chen, F. S. (2014, April). A Study on Relationships among Conflict Management and School Effectiveness. In 2014 International Conference on e-Education, e-Business and Information Management (ICEEIM 2014). Atlantis Press.

Larson, E. W., & Gray, C. (2013). Project Management: The Managerial Process with MS Project. McGraw-Hill.

Leach, L. P. (2014). Critical chain project management. Artech House.

Mir, F. A., & Pinnington, A. H. (2014). Exploring the value of project management: linking project management performance and project success. International journal of project management, 32(2), 202-217.

Schwalbe, K. (2015). Information technology project management. Cengage Learning.

Stipanowich, T. J., & Lamare, J. R. (2014). Living with ADR: Evolving Perceptions and Use of Mediation, Arbitration, and Conflict Management in Fortune 1000 Corporations. Harv. Negot. L. Rev., 19, 1.

Turner, R. (2016). Gower handbook of project management. Routledge.

Verzuh, E. (2015). The fast forward MBA in project management. John Wiley & Sons.

Walker, A. (2015). Project management in construction. John Wiley & Sons.

Wu, G., Wu, J., Jiao, Y., Wang, L., Wang, F., & Zhang, Y. (2015). Rosiglitazone infusion therapy following minimally invasive surgery for intracerebral hemorrhage evacuation decreases matrix metalloproteinase-9 and blood–brain barrier disruption in rabbits. BMC neurology, 15(1), 37.