Title: Online Stud Farm Management System
Define scope and scope management plan
The management plan develops the scope of this online booking system, which collects requirements of both customer as well as project stakeholders. They are eliminated the conflicting requirements, track agreed scope to be delivered and verify the agreed project related deliverables. The plan is included of processes to prepare detailed scope statement.
In-scope:
- Provide platform for customers to manage ticket bookings.
- The customers can reserve online tickets and do payments throughout secured gateways.
- Launch of web application
- Online view of the information
- Email reminders for the customers
- Allow rescheduling of tickets
- System testing
- Complete plan within 3 months
- Requirements documents are collected and recorded
- Testing review and project specifications
Out-scope:
- Unable to cancel of tickets information online
- Reminder of reservation schedules to the customers
Assumptions are:
- Proper follow of the design of online booking system.
- There are proper client/server architecture, hardware, software and network.
- The new system should provide of real time information and future returns.
Constraints are:
- The project is completed within 3 months.
- The project plan should meet its budget of AUD $100,000.
- The plan should meet its scope to implement of online booking system.
- People
|
Resource |
Standard rate |
|
Project Manager |
$ 100.00/hr |
|
Marketing Manager |
$ 80.00/hr |
|
Production Manager |
$ 50.00/hr |
|
Finance Manager |
$ 80.00/hr |
|
IT Manager |
$ 70.00/hr |
|
Project Sponsor |
$ 40.00/hr |
|
Client Manager |
$ 90.00/hr |
|
Project Team |
$ 60.00/hr |
|
Analyst |
$ 90.00/hr |
|
Software Developer |
$ 60.00/hr |
|
Tester |
$ 50.00/hr |
|
Research & Development Manager |
$ 30.00/hr |
|
Risk Manager |
$ 40.00/hr |
|
Human Resource Manager |
$ 50.00/hr |
|
Project Planner |
$ 60.00/hr |
- Technology
|
Hardware |
Graphic card, network interface card, RAM, serial port, optical disc, CPU |
|
Network |
Hubs, stitches, routers, gateways, wireless access points |
|
Software |
HTML, Java and PHP |
- Facilities
The team is suited of onsite facilities to work into the organizational environment.
- Other
|
Travel requirements |
Travel allowance |
|
Training requirements |
Training programs |
Milestones for each phase and deliverable
|
Task Name |
Start |
|
Milestone: Completed system planning phase |
Fri 3/2/18 |
|
Milestone: Completed system development phase |
Wed 4/25/18 |
|
Milestone: Completed system testing phase |
Tue 5/29/18 |
|
Task Name |
|
Online booking system |
|
System Planning Phase |
|
Understand and explain the system requirements |
|
Utilize project specifications |
|
Meeting with project stakeholders |
|
Identify the project team |
|
Plan schedule and budget |
|
Milestone: Completed system planning phase |
|
System Development Phase |
|
Using flow chart of system processes |
|
Initial selection of process |
|
Start of system development |
|
Installation and change |
|
Focused on training |
|
Milestone: Completed system development phase |
|
System testing phase |
|
Design meets with business goals |
|
Check for errors |
|
Code review |
|
Verification and validation |
|
Written code of program |
|
Installation of developed system |
|
Milestone: Completed system testing phase |
|
Task Name |
Resource Names |
|
Online booking system |
|
|
System Planning Phase |
|
|
Understand and explain the system requirements |
IT Manager ,Project Manager ,Finance Manager ,Marketing Manager ,Production Manager ,Project Sponsor ,Project Team ,Research & Development Manager ,Risk Manager ,Analyst ,Client Manager ,Human Resource Manager ,Project Planner ,Software Developer ,Tester |
|
Utilize project specifications |
Project Manager ,Project Planner ,IT Manager ,Marketing Manager ,Production Manager ,Project Sponsor ,Project Team ,Research & Development Manager ,Risk Manager |
|
Meeting with project stakeholders |
Marketing Manager ,Production Manager ,Project Manager ,Research & Development Manager ,Human Resource Manager ,IT Manager ,Client Manager ,Finance Manager ,Project Planner ,Project Sponsor ,Analyst ,Project Team ,Risk Manager ,Software Developer ,Tester |
|
Identify the project team |
Project Manager ,Project Planner ,Analyst ,Client Manager ,Finance Manager ,Project Team ,Research & Development Manager |
|
Plan schedule and budget |
Finance Manager ,Project Manager ,Project Planner ,Project Sponsor ,Client Manager ,Human Resource Manager ,IT Manager ,Project Team ,Research & Development Manager ,Analyst ,Marketing Manager ,Production Manager ,Risk Manager |
|
Milestone: Completed system planning phase |
Project Manager |
|
System Development Phase |
|
|
Using flow chart of system processes |
Research & Development Manager ,Software Developer |
|
Initial selection of process |
Project Manager |
|
Start of system development |
Software Developer ,Tester |
|
Installation and change |
Software Developer |
|
Focused on training |
Human Resource Manager ,IT Manager ,Project Team |
|
Milestone: Completed system development phase |
Project Manager |
|
System testing phase |
|
|
Design meets with business goals |
Marketing Manager ,Project Manager ,Project Planner |
|
Check for errors |
Software Developer ,Tester |
|
Code review |
Analyst ,IT Manager ,Software Developer |
|
Verification and validation |
Software Developer ,Tester |
|
Written code of program |
IT Manager ,Software Developer ,Tester |
|
Installation of developed system |
Software Developer ,Tester |
|
Milestone: Completed system testing phase |
Project Manager |
|
Task Name |
Duration |
Start |
Finish |
|
Online booking system |
67 days |
Mon 2/26/18 |
Tue 5/29/18 |
|
System Planning Phase |
5 days |
Mon 2/26/18 |
Fri 3/2/18 |
|
Understand and explain the system requirements |
1 day |
Mon 2/26/18 |
Mon 2/26/18 |
|
Utilize project specifications |
1 day |
Tue 2/27/18 |
Tue 2/27/18 |
|
Meeting with project stakeholders |
1 day |
Wed 2/28/18 |
Wed 2/28/18 |
|
Identify the project team |
1 day |
Thu 3/1/18 |
Thu 3/1/18 |
|
Plan schedule and budget |
1 day |
Fri 3/2/18 |
Fri 3/2/18 |
|
Milestone: Completed system planning phase |
0 days |
Fri 3/2/18 |
Fri 3/2/18 |
|
System Development Phase |
38 days |
Mon 3/5/18 |
Wed 4/25/18 |
|
Using flow chart of system processes |
5 days |
Mon 3/5/18 |
Fri 3/9/18 |
|
Initial selection of process |
7 days |
Mon 3/12/18 |
Tue 3/20/18 |
|
Start of system development |
11 days |
Wed 3/21/18 |
Wed 4/4/18 |
|
Installation and change |
5 days |
Thu 4/5/18 |
Wed 4/11/18 |
|
Focused on training |
10 days |
Thu 4/12/18 |
Wed 4/25/18 |
|
Milestone: Completed system development phase |
0 days |
Wed 4/25/18 |
Wed 4/25/18 |
|
System testing phase |
24 days |
Thu 4/26/18 |
Tue 5/29/18 |
|
Design meets with business goals |
2 days |
Thu 4/26/18 |
Fri 4/27/18 |
|
Check for errors |
4 days |
Mon 4/30/18 |
Thu 5/3/18 |
|
Code review |
6 days |
Fri 5/4/18 |
Fri 5/11/18 |
|
Verification and validation |
2 days |
Mon 5/14/18 |
Tue 5/15/18 |
|
Written code of program |
2 days |
Wed 5/16/18 |
Thu 5/17/18 |
|
Installation of developed system |
8 days |
Fri 5/18/18 |
Tue 5/29/18 |
|
Milestone: Completed system testing phase |
0 days |
Tue 5/29/18 |
Tue 5/29/18 |
|
Task Name |
Cost |
|
Online booking system |
$100,000.00 |
|
System Planning Phase |
$32,000.00 |
|
Understand and explain the system requirements |
$7,600.00 |
|
Utilize project specifications |
$4,240.00 |
|
Meeting with project stakeholders |
$7,600.00 |
|
Identify the project team |
$5,840.00 |
|
Plan schedule and budget |
$6,720.00 |
|
Milestone: Completed system planning phase |
$0.00 |
|
System Development Phase |
$38,000.00 |
|
Using flow chart of system processes |
$3,600.00 |
|
Initial selection of process |
$5,600.00 |
|
Start of system development |
$11,920.00 |
|
Installation and change |
$2,480.00 |
|
Focused on training |
$14,400.00 |
|
Milestone: Completed system development phase |
$0.00 |
|
System testing phase |
$30,000.00 |
|
Design meets with business goals |
$3,840.00 |
|
Check for errors |
$3,520.00 |
|
Code review |
$10,560.00 |
|
Verification and validation |
$1,760.00 |
|
Written code of program |
$3,280.00 |
|
Installation of developed system |
$7,040.00 |
|
Milestone: Completed system testing phase |
$0.00 |
Amrollahi, A., Ghapanchi, A. H., & Talaei-Khoei, A. (2014). Three decades of research on strategic information system plan development.Communications of the Association for Information Systems, 34(1), 84.
Coronel, C., & Morris, S. (2016). Database systems: design, implementation, & management. Cengage Learning.
Galliers, R. D., & Leidner, D. E. (2014). Strategic information management: challenges and strategies in managing information systems. Routledge.
Goetsch, D. L., & Davis, S. B. (2014). Quality management for organizational excellence. pearson.
Hubicki, M. (2014). Risk Management Plan.
Kerzner, H. R. (2013). Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.
Stark, J. (2015). Product lifecycle management. In Product Lifecycle Management (pp. 1-29). Springer International Publishing.