Define scope and scope management plan

The management plan develops the scope of this online booking system, which collects requirements of both customer as well as project stakeholders. They are eliminated the conflicting requirements, track agreed scope to be delivered and verify the agreed project related deliverables.  The plan is included of processes to prepare detailed scope statement.

In-scope:

  • Provide platform for customers to manage ticket bookings.
  • The customers can reserve online tickets and do payments throughout secured gateways.
  • Launch of web application
  • Online view of the information
  • Email reminders for the customers
  • Allow rescheduling of tickets
  • System testing
  • Complete plan within 3 months
  • Requirements documents are collected and recorded
  • Testing review and project specifications

Out-scope:

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper
  • Unable to cancel of tickets information online
  • Reminder of reservation schedules to the customers

Assumptions are:

  • Proper follow of the design of online booking system.
  • There are proper client/server architecture, hardware, software and network.
  • The new system should provide of real time information and future returns.

Constraints are:

  • The project is completed within 3 months.
  • The project plan should meet its budget of AUD $100,000.
  • The plan should meet its scope to implement of online booking system.
  • People

Resource

Standard rate

Project Manager

$ 100.00/hr

Marketing Manager

$ 80.00/hr

Production Manager

$ 50.00/hr

Finance Manager

$ 80.00/hr

IT Manager

$ 70.00/hr

Project Sponsor

$ 40.00/hr

Client Manager

$ 90.00/hr

Project Team

$ 60.00/hr

Analyst

$ 90.00/hr

Software Developer

$ 60.00/hr

Tester

$ 50.00/hr

Research & Development Manager

$ 30.00/hr

Risk Manager

$ 40.00/hr

Human Resource Manager

$ 50.00/hr

Project Planner

$ 60.00/hr

  • Technology

Hardware

Graphic card, network interface card, RAM, serial port, optical disc, CPU

Network

Hubs, stitches, routers, gateways, wireless access points

Software

HTML, Java and PHP

  • Facilities

The team is suited of onsite facilities to work into the organizational environment.

  • Other

Travel requirements

Travel allowance

Training requirements

Training programs

Milestones for each phase and deliverable

Task Name

Start

      Milestone: Completed system planning phase

Fri 3/2/18

      Milestone: Completed system development phase

Wed 4/25/18

      Milestone: Completed system testing phase

Tue 5/29/18

Task Name

Online booking system

   System Planning Phase

      Understand and explain the system requirements

      Utilize project specifications

      Meeting with project stakeholders

      Identify the project team

      Plan schedule and budget

      Milestone: Completed system planning phase

   System Development Phase

      Using flow chart of system processes

      Initial selection of process

      Start of system development

      Installation and change

      Focused on training

      Milestone: Completed system development phase

   System testing phase

      Design meets with business goals

      Check for errors

      Code review

      Verification and validation

      Written code of program

      Installation of developed system

      Milestone: Completed system testing phase

Task Name

Resource Names

Online booking system

   System Planning Phase

      Understand and explain the system requirements

IT Manager ,Project Manager ,Finance Manager ,Marketing Manager ,Production Manager ,Project Sponsor ,Project Team ,Research & Development Manager ,Risk Manager ,Analyst ,Client Manager ,Human Resource Manager ,Project Planner ,Software Developer ,Tester

      Utilize project specifications

Project Manager ,Project Planner ,IT Manager ,Marketing Manager ,Production Manager ,Project Sponsor ,Project Team ,Research & Development Manager ,Risk Manager

      Meeting with project stakeholders

Marketing Manager ,Production Manager ,Project Manager ,Research & Development Manager ,Human Resource Manager ,IT Manager ,Client Manager ,Finance Manager ,Project Planner ,Project Sponsor ,Analyst ,Project Team ,Risk Manager ,Software Developer ,Tester

      Identify the project team

Project Manager ,Project Planner ,Analyst ,Client Manager ,Finance Manager ,Project Team ,Research & Development Manager

      Plan schedule and budget

Finance Manager ,Project Manager ,Project Planner ,Project Sponsor ,Client Manager ,Human Resource Manager ,IT Manager ,Project Team ,Research & Development Manager ,Analyst ,Marketing Manager ,Production Manager ,Risk Manager

      Milestone: Completed system planning phase

Project Manager

   System Development Phase

      Using flow chart of system processes

Research & Development Manager ,Software Developer

      Initial selection of process

Project Manager

      Start of system development

Software Developer ,Tester

      Installation and change

Software Developer

      Focused on training

Human Resource Manager ,IT Manager ,Project Team

      Milestone: Completed system development phase

Project Manager

   System testing phase

      Design meets with business goals

Marketing Manager ,Project Manager ,Project Planner

      Check for errors

Software Developer ,Tester

      Code review

Analyst ,IT Manager ,Software Developer

      Verification and validation

Software Developer ,Tester

      Written code of program

IT Manager ,Software Developer ,Tester

      Installation of developed system

Software Developer ,Tester

      Milestone: Completed system testing phase

Project Manager

Task Name

Duration

Start

Finish

Online booking system

67 days

Mon 2/26/18

Tue 5/29/18

   System Planning Phase

5 days

Mon 2/26/18

Fri 3/2/18

      Understand and explain the system requirements

1 day

Mon 2/26/18

Mon 2/26/18

      Utilize project specifications

1 day

Tue 2/27/18

Tue 2/27/18

      Meeting with project stakeholders

1 day

Wed 2/28/18

Wed 2/28/18

      Identify the project team

1 day

Thu 3/1/18

Thu 3/1/18

      Plan schedule and budget

1 day

Fri 3/2/18

Fri 3/2/18

      Milestone: Completed system planning phase

0 days

Fri 3/2/18

Fri 3/2/18

   System Development Phase

38 days

Mon 3/5/18

Wed 4/25/18

      Using flow chart of system processes

5 days

Mon 3/5/18

Fri 3/9/18

      Initial selection of process

7 days

Mon 3/12/18

Tue 3/20/18

      Start of system development

11 days

Wed 3/21/18

Wed 4/4/18

      Installation and change

5 days

Thu 4/5/18

Wed 4/11/18

      Focused on training

10 days

Thu 4/12/18

Wed 4/25/18

      Milestone: Completed system development phase

0 days

Wed 4/25/18

Wed 4/25/18

   System testing phase

24 days

Thu 4/26/18

Tue 5/29/18

      Design meets with business goals

2 days

Thu 4/26/18

Fri 4/27/18

      Check for errors

4 days

Mon 4/30/18

Thu 5/3/18

      Code review

6 days

Fri 5/4/18

Fri 5/11/18

      Verification and validation

2 days

Mon 5/14/18

Tue 5/15/18

      Written code of program

2 days

Wed 5/16/18

Thu 5/17/18

      Installation of developed system

8 days

Fri 5/18/18

Tue 5/29/18

      Milestone: Completed system testing phase

0 days

Tue 5/29/18

Tue 5/29/18

Task Name

Cost

Online booking system

$100,000.00

   System Planning Phase

$32,000.00

      Understand and explain the system requirements

$7,600.00

      Utilize project specifications

$4,240.00

      Meeting with project stakeholders

$7,600.00

      Identify the project team

$5,840.00

      Plan schedule and budget

$6,720.00

      Milestone: Completed system planning phase

$0.00

   System Development Phase

$38,000.00

      Using flow chart of system processes

$3,600.00

      Initial selection of process

$5,600.00

      Start of system development

$11,920.00

      Installation and change

$2,480.00

      Focused on training

$14,400.00

      Milestone: Completed system development phase

$0.00

   System testing phase

$30,000.00

      Design meets with business goals

$3,840.00

      Check for errors

$3,520.00

      Code review

$10,560.00

      Verification and validation

$1,760.00

      Written code of program

$3,280.00

      Installation of developed system

$7,040.00

      Milestone: Completed system testing phase

$0.00

Amrollahi, A., Ghapanchi, A. H., & Talaei-Khoei, A. (2014). Three decades of research on strategic information system plan development.Communications of the Association for Information Systems, 34(1), 84.

Coronel, C., & Morris, S. (2016). Database systems: design, implementation, & management. Cengage Learning.

Galliers, R. D., & Leidner, D. E. (2014). Strategic information management: challenges and strategies in managing information systems. Routledge.

Goetsch, D. L., & Davis, S. B. (2014). Quality management for organizational excellence. pearson.

Hubicki, M. (2014). Risk Management Plan.

Kerzner, H. R. (2013). Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.

Stark, J. (2015). Product lifecycle management. In Product Lifecycle Management (pp. 1-29). Springer International Publishing.