Level Crossing Removal Project: Scope, Change Management, Scheduling, And Financial Management

Change Control Management

The paper mainly focuses on the level crossing removal of Buckley Street, Essondon that is considered as one of the key arterials in inner North West of Melbourne that mainly connects Keilor as well as Avondale heights in the west. The boom gates of the Buckley Street are down for about 78 minutes in the morning and as result, the traveller faces congestion as well as disruption while passing. In order to resolve this problem, the Victorian government took an important step and as per it, they wants to remove the level crossing at Buckley Street so that the passengers can easily travel and which further can be able to reduce traffic congestion as well as assists in improving safety. 

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper

Change identification

Purpose

Change analysis

Change request approval

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper

Change tracking

 Utilizing technically advanced equipments

 It is identified that use of technically advanced equipments helps in removing the level crossing at Buckley Street quite easily.

 The construction engineers understand the change viability.

 The change viability in the project is mainly approved by the project managers

 Proper master logbook is maintained in order to ensure that the construction engineers use proper equipment.

 Utilizing appropriate quality of materials

 It is very much necessary to use proper quality of materials in order to construct the pathways.

 The quality analyst understands the viability of proper quality of materials in the project.

 The request for maintain proper quality materials is mainly approved by the project manager

Appropriate logbook is generally maintained in order to make sure those proper quality materials is used in the project.

 Schedule and time management

Task Name

Start

      Milestone 1: Completion of project initiation phase

Mon 23-05-16

      Milestone 2: Completion of planning phase

Thu 15-12-16

      Milestone 3 : Completion of procurement phase

Wed 06-12-17

      Milestone 4: Completion of Construction phase

Thu 08-08-19

      Milestone 4: Completion of project closure phase

Wed 20-11-19

Task Name

Duration

Start

Finish

% Complete

Essendon & Buckley Street level crossing removal

985 days

Thu 11-02-16

Wed 20-11-19

57%

   Initiation phase of the project

73 days

Thu 11-02-16

Mon 23-05-16

100%

      Identifying objectives of the project

15 days

Thu 11-02-16

Wed 02-03-16

100%

      Undertaking feasibility study

20 days

Thu 03-03-16

Wed 30-03-16

100%

      Establishing project charter

16 days

Thu 31-03-16

Thu 21-04-16

100%

      Appointing team members of the project

22 days

Fri 22-04-16

Mon 23-05-16

100%

      Milestone 1: Completion of project initiation phase

0 days

Mon 23-05-16

Mon 23-05-16

100%

   Planning phase of the project

148 days

Tue 24-05-16

Thu 15-12-16

100%

      Site investigations

22 days

Tue 24-05-16

Wed 22-06-16

100%

      Solution announced

20 days

Thu 23-06-16

Wed 20-07-16

100%

      Community information sessions

25 days

Thu 21-07-16

Wed 24-08-16

100%

      Trader consultation

26 days

Thu 25-08-16

Thu 29-09-16

100%

      Assessment of design options

26 days

Fri 30-09-16

Fri 04-11-16

100%

       Lowering Buckley street under rail line

29 days

Mon 07-11-16

Thu 15-12-16

100%

      Milestone 2: Completion of planning phase

0 days

Thu 15-12-16

Thu 15-12-16

100%

   Procurement phase

254 days

Fri 16-12-16

Wed 06-12-17

100%

      Community input on design elements

32 days

Fri 16-12-16

Mon 30-01-17

100%

       North west alliance project partner announced

39 days

Tue 31-01-17

Fri 24-03-17

100%

       Construction partner announced

44 days

Mon 27-03-17

Thu 25-05-17

100%

      Community consultation

47 days

Fri 26-05-17

Mon 31-07-17

100%

      Refinement of design including community inputs

50 days

Tue 01-08-17

Mon 09-10-17

100%

      Finalizing design

42 days

Tue 10-10-17

Wed 06-12-17

100%

      Milestone 3 : Completion of procurement phase

0 days

Wed 06-12-17

Wed 06-12-17

100%

   Construction phase

436 days

Thu 07-12-17

Thu 08-08-19

19%

       On-going community consultation

32 days

Thu 07-12-17

Fri 19-01-18

100%

      Construction commences

34 days

Mon 22-01-18

Thu 08-03-18

100%

       Preparatory work commenced

43 days

Fri 09-03-18

Tue 08-05-18

42%

      Finalized design released to the community

45 days

Wed 09-05-18

Tue 10-07-18

0%

      Contract awarded for Buckley street level crossing removal project

52 days

Wed 11-07-18

Thu 20-09-18

0%

      Early works commence

57 days

Fri 21-09-18

Mon 10-12-18

0%

      Major works commence

48 days

Tue 11-12-18

Thu 14-02-19

0%

      Boom gates removed

60 days

Fri 15-02-19

Thu 09-05-19

0%

      Finalizing landscapes

65 days

Fri 10-05-19

Thu 08-08-19

0%

      Milestone 4: Completion of Construction phase

0 days

Thu 08-08-19

Thu 08-08-19

0%

   Closure phase

74 days

Fri 09-08-19

Wed 20-11-19

0%

      Post-project review

20 days

Fri 09-08-19

Thu 05-09-19

0%

      Stakeholder-sign off

30 days

Fri 06-09-19

Thu 17-10-19

0%

       Documentation

24 days

Fri 18-10-19

Wed 20-11-19

0%

      Milestone 4: Completion of project closure phase

0 days

Wed 20-11-19

Wed 20-11-19

0%

Task Name

Duration

Predecessors

Essendon & Buckley Street level crossing removal

985 days

   Initiation phase of the project

73 days

      Identifying objectives of the project

15 days

      Undertaking feasibility study

20 days

2

      Establishing project charter

16 days

3

      Appointing team members of the project

22 days

4

      Milestone 1: Completion of project initiation phase

0 days

5

   Planning phase of the project

148 days

      Site investigations

22 days

6

      Solution announced

20 days

8

      Community information sessions

25 days

9

      Trader consultation

26 days

10

      Assessment of design options

26 days

11

       Lowering Buckley street under rail line

29 days

12

      Milestone 2: Completion of planning phase

0 days

13

   Procurement phase

254 days

      Community input on design elements

32 days

14

       North west alliance project partner announced

39 days

16

       Construction partner announced

44 days

17

      Community consultation

47 days

18

      Refinement of design including community inputs

50 days

19

      Finalizing design

42 days

20

      Milestone 3 : Completion of procurement phase

0 days

21

   Construction phase

436 days

       On-going community consultation

32 days

22

      Construction commences

34 days

24

       Preparatory work commenced

43 days

25

      Finalized design released to the community

45 days

26

      Contract awarded for Buckley street level crossing removal project

52 days

27

      Early works commence

57 days

28

      Major works commence

48 days

29

      Boom gates removed

60 days

30

      Finalizing landscapes

65 days

31

      Milestone 4: Completion of Construction phase

0 days

32

   Closure phase

74 days

      Post-project review

20 days

33

      Stakeholder-sign off

30 days

35

       Documentation

24 days

36

      Milestone 4: Completion of project closure phase

0 days

37

Cost/Budget management

Task Name

Duration

Resource Names

Cost

Essendon & Buckley Street level crossing removal

985 days

$114,664,480.00

   Initiation phase of the project

73 days

$254,480.00

      Identifying objectives of the project

15 days

Project manager

$34,800.00

      Undertaking feasibility study

20 days

Project manager

$46,400.00

      Establishing project charter

16 days

Project manager, Project planner

$72,960.00

      Appointing team members of the project

22 days

Project manager, Project planner

$100,320.00

      Milestone 1: Completion of project initiation phase

0 days

$0.00

   Planning phase of the project

148 days

$7,765,120.00

      Site investigations

22 days

Supervisor, Construction manager

$89,760.00

      Solution announced

20 days

Construction technician, Contractor, Equipment cost[1]

$7,081,600.00

      Community information sessions

25 days

Construction manager, Contractor

$102,000.00

      Trader consultation

26 days

Construction manager, Contractor

$106,080.00

      Assessment of design options

26 days

Construction manager, Contractor, Sub-contractor

$156,000.00

       Lowering Buckley street under rail line

29 days

Architect, Construction manager, Construction technician, Sub-contractor

$229,680.00

      Milestone 2: Completion of planning phase

0 days

$0.00

   Procurement phase

254 days

$34,070,960.00

      Community input on design elements

32 days

Cost for removing level crossing[1], Supervisor, Architect, Construction technician, Equipment cost[1]

$16,194,560.00

       North west alliance project partner announced

39 days

Supervisor, Architect, Construction manager, Contractor, Procurement manager

$396,240.00

       Construction partner announced

44 days

Supervisor, Architect, Construction technician, Contractor, Procurement manager

$447,040.00

      Community consultation

47 days

Cost for removing level crossing[1],Architect, Construction technician, Contractor

$9,285,760.00

      Refinement of design including community inputs

50 days

Architect, Construction technician, Contractor, Financial manager, Procurement manager

$492,000.00

      Finalizing design

42 days

Supervisor, Architect, Equipment cost[1],Procurement manager

$7,255,360.00

      Milestone 3 : Completion of procurement phase

0 days

$0.00

   Construction phase

436 days

$72,236,480.00

       On-going community consultation

32 days

Supervisor, Architect, Contractor, Procurement manager, Sub-contractor

$322,560.00

      Construction commences

34 days

Cost for removing level crossing[1], Project manager, Architect, Construction technician, Procurement manager

$9,282,880.00

       Preparatory work commenced

43 days

Cost for removing level crossing[1], Supervisor, Architect, Construction technician, Contractor, Equipment cost[1],Sub-contractor

$16,433,440.00

      Finalized design released to the community

45 days

Supervisor, Architect, Construction manager, Construction technician, Procurement manager

$453,600.00

      Contract awarded for Buckley street level crossing removal project

52 days

Cost for removing level crossing[1], Project manager, Architect, Construction technician, Contractor, Sub-contractor

$9,536,640.00

      Early works commence

57 days

Cost for removing level crossing[1],Architect, Construction manager, Construction technician, Equipment cost[1]

$16,342,000.00

      Major works commence

48 days

Cost for removing level crossing[1], Project manager, Supervisor, Architect, Construction manager, Construction technician, Sub-contractor

$9,591,360.00

      Boom gates removed

60 days

Cost for removing level crossing[1], Project manager,  Architect, Construction manager, Construction technician, Contractor

$9,624,000.00

      Finalizing landscapes

65 days

Architect ,Construction manager, Construction technician Contractor, Sub-contractor

$650,000.00

      Milestone 4: Completion of Construction phase

0 days

$0.00

   Closure phase

74 days

$337,440.00

      Post-project review

20 days

Project manager, Project planner

$91,200.00

      Stakeholder-sign off

30 days

Project manager, Project planner

$136,800.00

       Documentation

24 days

Project manager, Project planner

$109,440.00

      Milestone 4: Completion of project closure phase

0 days

$0.00

Quality management

Identification of factors

Purpose

Measurement of project quality

Analyzing project quality

Quality control

 Training to the project stakeholders

 Proper training to the project stakeholders would be helpful in completing the project successfully on time by managing the challenges and issues properly on time.

 Proper training facility is not provided to the workers of the project team.

  Due to unavailability of training it is reflects that the project team members faces little bit of challenges in completing the project work successfully.

 Proper training facility not only helps in managing the project work but will also help in maintaining the quality of the project.

Use of proper quality off materials

 Proper use of quality materials would be quite advantageous for the project.

The materials that are supplied by the suppliers for the construction of the pathway is of poor quality.

 The materials that are used in the project must be checked before using it for construction purpose.

 Proper quality of materials must be used in order to enhance the quality of the project.

Human resource management

Role

Project Responsibility

Skills Required

Number of Staff Required

Duration Required

Project Team

4 years

Project manager

 The project manager is the person who is mainly responsible of initiating, planning, managing as well as executing the project successfully.

 Project management

3

 Financial manager

 The financial manager is the person who mainly reviews the financial requirement of the project

 Construction

4

4 years

Contractor

 The contractor is the person who mainly involves in constructing the pathways after the removal of  level crossing

Construction

1

4 years

 Site supervisor

 Site supervisor is the person who mainly helps in providing proper guidance to the various organizational staffs.

Construction

10

4 years

Communication management

Communication Type

Objective

Medium

Frequency

Audience

Owner

Deliverable

 Project status report

 The meeting is mainly arranged  in order to gather information about the project status in order to make sure that the project is on right track

 Audio and video conferencing,

 Weekly

 Project manager

 Project stakeholders

 Meeting minutes

 Project team meeting

 The project meetings is mainly arranged in order to know about the various challenges that the workers of the project are facing while working with the project.

Face to face

Whenever required

 Project manager

Project team

Agenda

 Kick off meetings

 It is arranged before initiation of the project in order to get information about the schedule, budget as well as resources required in order to execute the project successfully.

 Face to face

Once

Stakeholders of the project

 Project manager

 Meeting minutes as well as agenda

 Monthly project meetings

 Monthly meetings is necessary in the project in order to make sure that the budget of the project are correctly utilized

 Face to face conversation

 Monthly

 Project manager

 Finance manager

Budget report

 Risk management

Risk

Type of risk

 Risk statement

Impact

Probability

Risk exposure

Risk mitigation

 Budget shortfall

 Negative risk

 If the project managers does not estimate the budget of the project then during the project progress the project managers can face budget shortfall, which can create number of financial as well as budget related issues within the project.

Major

Probable

 Medium

 It is necessary for the project managers to undertake market analysis properly in order to know the current cost of project resources that are used in the project.

Extending project schedule

Positive risk

 It is identified that sometimes the project managers generally extends the schedule of the project in order to provide quality based outcome  within the project.

Moderate

 Probable

Low

 The changes that re needed within the project must be done appropriately in order to bring positive outcome within the project.

Use of improper quality materials

Negative risk

 It is necessary to use proper quality materials in order to construct the pathways after the removal of the level  crossing.

Moderate

 Likely

 Medium

 Proper quality of materials must be used in the project so that the project can be completed successfully without facing any type of quality related challenges.

Improper management

Negative risk

 If the project managers are not able to manage the project successfully then they generally faces issues in executing the project successfully within the estimated budget and time.

Major

Very likely

High

 It is necessary to hire experienced project managers who will be able to manage the project successfully so that the entire project will be successfully completed on proper time an budget.

Impact

 Extreme

Major

 Budget shortfall

Improper management

Moderate

Use of poor quality of materials

 Extension of schedule

Minor

Insignificant

 Remote

Unlikely

Possible

Probable

Highly probable

Likelihood

 Procurement management

Type of contract

Procurement risk

Procurement risk management

Performance metrics

Firm fixed price

 Unrealistic schedule

 The schedule must be created with the help of experienced project managers.

Acceptable

Firm fixed price

 Improper framework for the level crossing removal

 Proper framework must be created for the level crossing removal

Acceptable

Firm fixed price

Conflict related on contract

 Conflict must  be resolved by arranging meetings

Acceptable

 Quality baseline

Metrics

Standard

Frequency

Report

 Successful completion of project on time

 The project will be successfully completed by 2019.

Once

Quality management report

 Successful removal of level crossing

 Removal of level crossing will be completed by early 2019.

Yearly

Yearly quality management report

Buckley Street, Essendon. (2018). Your Level Crossing. Retrieved 3 April 2018, from https://your.levelcrossings.vic.gov.au/buckley-street-essendon

De Carvalho, M. M., Patah, L. A., & de Souza Bido, D. (2015). Project management and its effects on project success: Cross-country and cross-industry comparisons. International Journal of Project Management, 33(7), 1509-1522.

Fitzpatrick, B. J. (2016). Determining the Optimal Work Breakdown Structure for Defense Acquisition Contracts. Air Force Institute of Technology WPAFB United States.

Heldman, K. (2018). PMP: project management professional exam study guide. John Wiley & Sons.

Hornstein, H. A. (2015). The integration of project management and organizational change management is now a necessity. International Journal of Project Management, 33(2), 291-298.

Joslin, R., & Müller, R. (2015). Relationships between a project management methodology and project success in different project governance contexts. International Journal of Project Management, 33(6), 1377-1392.

Kerzner, H. (2017). Project management metrics, KPIs, and dashboards: a guide to measuring and monitoring project performance. John Wiley & Sons.

Mir, F. A., & Pinnington, A. H. (2014). Exploring the value of project management: linking project management performance and project success. International journal of project management, 32(2), 202-217.

Po?o?ski, M. (2015). Application of the work breakdown structure in determining cost buffers in construction schedules. Archives of Civil Engineering, 61(1), 147-161.

Sequeira, S., & Lopes, E. (2015). Simple Method Proposal for Cost Estimation from Work Breakdown Structure. Procedia Computer Science, 64, 537-544.

Sharon, A., & Dori, D. (2015). A Project–product model–based approach to planning work breakdown structures of complex system projects. IEEE Systems Journal, 9(2), 366-376.

Snyder, C. S. (2014). A guide to the project management body of knowledge: PMBOK (®) guide. Project Management Institute: Newtown Square, PA, USA.

Svejvig, P., & Andersen, P. (2015). Rethinking project management: A structured literature review with a critical look at the brave new world. International Journal of Project Management, 33(2), 278-290

Too, E. G., & Weaver, P. (2014). The management of project management: A conceptual framework for project governance. International Journal of Project Management, 32(8), 1382-1394.

Order your essay today and save 30% with the discount code ESSAYHELP