CM25000 Project 3 Spring 2020 Page 1 of 2 CM25000 Project 3 – 200 Points- INDIVIDUAL PROJECT Background Reference to the Vortex Business Center. Objectives By the end of the project the students should be able to: 1. Read construction documents including specifications and drawings of a project to extract information for the construction phase. 2. Practice proper documentation for a construction project through submitting RFIs, submittals, documenting/understanding MEP systems, and project sequences. 3. Relate MEP materials, means, and methods to a construction project throughout the project lifecycle and schedule work sequence for MEP construction of a project. 4. Integrating technology use on a construction project during the construction phase using BIM technology for reading project documents, visualizing projects, extracting project information, merging BIM models from different stakeholders, and applying project sequencing and simulation for structural construction. 5. Show professionalism by applying proper communication within a construction project utilizing Procore and its tools. Procedure: Students are to work individually and submit one final package on Blackboard by the due date. Submission Deadline: April 23, 2020 at 11:59 PM, on Blackboard • Submit one package (Project 03) Final deliverable Project 03 (200 pts): Each student should submit their project on Blackboard as a single ZIP file with the name “CM25000-StudentInitials-Project3.zip” containing the following: • Folder 1 – MEP Documentation (50 pts): Construction Documents and RFIs a) Prepare three RFIs for MEP items that need clarification with screenshot of the issue from the drawing set or 3D model (15 pts). Include a proposed solution to each RFI. b) Prepare three submittals packages for MEP equipment listed or found in the construction documents (i.e., minimum of one submittal for each MEP category. One Mechanical item, One Electrical item, & One Plumbing item – 35 pts) CM25000 Project 3 Spring 2020 Page 2 of 2 • Folder 2 – MEP Report (150 pts): MEP systems, BIM, and Project Synthesis a) Prepare a report describing the MEP systems for the Vortex Project. Be sure to use specific terms and terminology that is applicable to what you have learned in lectures/labs (100 pts) b) Describe how each major project participant (Owner, Architect, Engineers, GC Project manager, Superintendent and Subcontractor) would use the BIM models that you have used in this project. (25 pts – 5 pts for each role including: how used, support given to BIM modeling, and how information is added to the model) c) Now that you have completed Projects 1 and 2, determine the relationships between MEP and other areas such as Site Supervision, Site Planning, Cost Controls, and Site Layout. Write at least one full page describing how MEP affects each area. (25 pts)
CM25000 Project 3 Spring 2020
Page 1 of 2
CM25000 Project 3 – 200 Points- INDIVIDUAL PROJECT
Background
Reference to the Vortex Business Center.
Objectives
By the end of the project the students should be able to:
1. Read construction documents including specifications and drawings of a project to
extract information for the construction phase.
2. Practice proper documentation for a construction project through submitting RFIs,
submittals, documenting/understanding MEP systems, and project sequences.
3. Relate MEP materials, means, and methods to a construction project throughout the
project lifecycle and schedule work sequence for MEP construction of a project.
4. Integrating technology use on a construction project during the construction phase
using BIM technology for reading project documents, visualizing projects, extracting
project information, merging BIM models from different stakeholders, and applying
project sequencing and simulation for structural construction.
5. Show professionalism by applying proper communication within a construction project
utilizing Procore and its tools.
Procedure:
Students are to work individually and submit one final package on Blackboard by the due date.
Submission Deadline: April 23, 2020 at 11:59 PM, on Blackboard
• Submit one package (Project 03)
Final deliverable Project 03 (200 pts):
Each student should submit their project on Blackboard as a single ZIP file with the name
“CM25000-StudentInitials-Project3.zip” containing the following:
• Folder 1 – MEP Documentation (50 pts): Construction Documents and RFIs
a) Prepare three RFIs for MEP items that need clarification with screenshot of the
issue from the drawing set or 3D model (15 pts). Include a proposed solution to
each RFI.
b) Prepare three submittals packages for MEP equipment listed or found in the
construction documents (i.e., minimum of one submittal for each MEP category.
One Mechanical item, One Electrical item, & One Plumbing item – 35 pts)
CM25000 Project 3 Spring 2020
Page 2 of 2
• Folder 2 – MEP Report (150 pts): MEP systems, BIM, and Project Synthesis
a) Prepare a report describing the MEP systems for the Vortex Project. Be sure to
use specific terms and terminology that is applicable to what you have learned in
lectures/labs (100 pts)
b) Describe how each major project participant (Owner, Architect, Engineers, GC
Project manager, Superintendent and Subcontractor) would use the BIM models
that you have used in this project. (25 pts – 5 pts for each role including: how
used, support given to BIM modeling, and how information is added to the
model)
c) Now that you have completed Projects 1 and 2, determine the relationships
between MEP and other areas such as Site Supervision, Site Planning, Cost
Controls, and Site Layout. Write at least one full page describing how MEP
affects each area. (25 pts)