Optimizing Time And Resources In A Two-Unit Construction Project

 The procedures through which time and resources are optimized include:

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper

Using mixed strategy: Mixed strategy is utilized by the project for optimizing both time as well as resources of the project. It is identified that in the plan as well as lock up phase, both the units are build together thus it assists in optimizing time as well as resources of the project.

Proper tracking: Proper track must be kept on the project so that the entire project can be completed successfully within the estimated time and budget without creating any challenges.

Proper management: It is quite important to manage both the resources as well as time of the project so that the entire project can be completed successfully within the estimated time and budget by optimizing the utilization of resources and time

Training to the workers: The workers are trained so that they are capable of working efficiently in completing the construction related tasks of the project properly.

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper

 1.2.1 Duration of the project

 The entire duration that is required for completing the entire project successfully is around 156 days. It is estimated that in 156 days both the units are constructed successfully. If the project managers are not able to complete the project then the project faces number of issues as well as challenges.

The entire cost that is estimated for completing the project is around $71,696. The project must be completed within this budget. If the project managers are unable to complete the project on this budget then they will face financial crisis.

  The resources that are required in the project for completing the project successfully are as follows:

Resources

Number

Draftsperson

10

Electrician

9

Plumber

12

Concreter

10

Carpenter

8

Laborer

25

Painter

12

Supervisor

2

Cabinet Maker

8

Roof Tier

8

Bricklayer

8

Plasterer

12

It is identified that currently the unit 1 is in the “Fit Out” phase and is completing the activity of plastering walls whereas unit 2 is completed up to “lock up” phase.  The technique of tracking is utilized with the help of the Gantt chart is order to keep track on the project activities. It is identified that mixed strategy is used in both “plan and site” and “lock up phase” in order to complete the work activities of both the phase properly.

Task Name

Duration

Start

Finish

Construction of units

156 days

Thu 10/12/17

Thu 5/17/18

   Plans and Site

23 days

Thu 10/12/17

Mon 11/13/17

      Creation of site plan for unit 1

3 days

Thu 10/12/17

Mon 10/16/17

      Creation of site plan for unit 2

3 days

Tue 10/17/17

Thu 10/19/17

      Council permitance arrangement for unit 1

4 days

Fri 10/20/17

Wed 10/25/17

       Council permitance arrangement for unit 2

4 days

Fri 10/20/17

Wed 10/25/17

      Preparation of site for unit 1

2 days

Thu 10/26/17

Fri 10/27/17

      Preparation of site for unit 2

2 days

Thu 10/26/17

Fri 10/27/17

      Organizing materials for unit 1

4 days

Mon 10/30/17

Thu 11/2/17

      organizing materials for unit 2

4 days

Mon 10/30/17

Thu 11/2/17

      Laying foundations for unit 1

3 days

Fri 11/3/17

Tue 11/7/17

      Laying foundations for unit 2

3 days

Fri 11/3/17

Tue 11/7/17

       Plumbing for unit 1

2 days

Wed 11/8/17

Thu 11/9/17

      Plumbing for unit 2

2 days

Wed 11/8/17

Thu 11/9/17

       Pouring slab for unit 1

2 days

Fri 11/10/17

Mon 11/13/17

      Pouring slab for unit 2

2 days

Fri 11/10/17

Mon 11/13/17

   To lock up

15 days

Tue 11/14/17

Mon 12/4/17

      Erection of frame for unit 1

3 days

Tue 11/14/17

Thu 11/16/17

      Erection of frame for unit 2

3 days

Tue 11/14/17

Thu 11/16/17

      Roofing for unit 1

4 days

Fri 11/17/17

Wed 11/22/17

      Roofing for unit 2

4 days

Fri 11/17/17

Wed 11/22/17

      Development of brick wall for unit 1

5 days

Thu 11/23/17

Wed 11/29/17

      Development of brick wall for unit 2

5 days

Thu 11/23/17

Wed 11/29/17

      Doors and windows fitting for unit 1

3 days

Thu 11/30/17

Mon 12/4/17

      Doors and windows fittings for unit 2

3 days

Thu 11/30/17

Mon 12/4/17

   Fit out

118 days

Tue 12/5/17

Thu 5/17/18

      Implementation of electrical cables for unit 1

10 days

Tue 12/5/17

Mon 12/18/17

      Plumbing for unit 1

12 days

Tue 12/19/17

Wed 1/3/18

      Wall plaster for unit 1

13 days

Thu 1/4/18

Mon 1/22/18

      Fitting doors for unit 1

14 days

Tue 1/23/18

Fri 2/9/18

      Kitchen development for unit 1

15 days

Mon 2/12/18

Fri 3/2/18

      Bathroom installation for unit1

12 days

Mon 3/5/18

Tue 3/20/18

      Electrical fitting for unit 1

11 days

Wed 3/21/18

Wed 4/4/18

      Final fittings of plumbing for unit 1

10 days

Thu 4/5/18

Wed 4/18/18

      Paint for unit 1

9 days

Thu 4/19/18

Tue 5/1/18

      Approval of council for unit 1

12 days

Wed 5/2/18

Thu 5/17/18

      Implementation of electrical cables for unit 2

10 days

Tue 12/5/17

Mon 12/18/17

      Plumbing for unit 2

12 days

Tue 12/19/17

Wed 1/3/18

      Wall plaster for unit 2

13 days

Thu 1/4/18

Mon 1/22/18

      Fitting doors for unit 2

14 days

Tue 1/23/18

Fri 2/9/18

      Kitchen development for unit 2

15 days

Mon 2/12/18

Fri 3/2/18

      Bathroom installation for unit2

12 days

Mon 3/5/18

Tue 3/20/18

      Electrical fitting for unit 2

11 days

Wed 3/21/18

Wed 4/4/18

      Final fittings of plumbing for unit 2

10 days

Thu 4/5/18

Wed 4/18/18

      Paint for unit 2

9 days

Thu 4/19/18

Tue 5/1/18

      Approval of council for unit 2

12 days

Wed 5/2/18

Thu 5/17/18

2.3.2 Variance table for cost

Task Name

 

Resource Names

Cost

Construction of units

$71,696.00

   Plans and Site

$12,304.00

      Creation of site plan for unit 1

Draftsperson

$960.00

      Creation of site plan for unit 2

Draftsperson

$960.00

      Council persistence arrangement for unit 1

Draftsperson

$1,280.00

       Council persistence arrangement for unit 2

Draftsperson

$1,280.00

      Preparation of site for unit 1

Carpenter, Laborer

$496.00

      Preparation of site for unit 2

Carpenter, Laborer

$496.00

      Organizing materials for unit 1

Supervisor

$896.00

      organizing materials for unit 2

Supervisor

$896.00

      Laying foundations for unit 1

Carpenter, Concreter, Laborer

$1,176.00

      Laying foundations for unit 2

Carpenter, Concreter, Laborer

$1,176.00

       Plumbing for unit 1

Plumber

$560.00

      Plumbing for unit 2

Plumber

$560.00

       Pouring slab for unit 1

Carpenter, Concreter, Laborer

$784.00

      Pouring slab for unit 2

Carpenter, Concreter, Laborer

$784.00

   To lock up

$6,064.00

      Erection of frame for unit 1

Carpenter

$456.00

      Erection of frame for unit 2

Carpenter

$456.00

      Roofing for unit 1

Plumber, Roof Tier

$1,600.00

      Roofing for unit 2

Plumber, Roof Tier

$1,600.00

      Development of brick wall for unit 1

Bricklayer

$520.00

      Development of brick wall for unit 2

Bricklayer

$520.00

      Doors and windows fitting for unit 1

Carpenter

$456.00

      Doors and windows fittings for unit 2

Carpenter

$456.00

   Fit out

$53,328.00

      Implementation of electrical cables for unit 1

Electrician

$2,640.00

      Plumbing for unit 1

Plumber

$3,360.00

      Wall plaster for unit 1

Plasterer

$1,456.00

      Fitting doors for unit 1

Carpenter

$2,128.00

      Kitchen development for unit 1

Cabinet Maker

$2,400.00

      Bathroom installation for unit1

Cabinet Maker, Plumber

$5,280.00

      Electrical fitting for unit 1

Electrician

$2,904.00

      Final fittings of plumbing for unit 1

Plumber

$2,800.00

      Paint for unit 1

Painter

$1,008.00

      Approval of council for unit 1

Supervisor

$2,688.00

      Implementation of electrical cables for unit 2

Electrician

$2,640.00

      Plumbing for unit 2

Plumber

$3,360.00

      Wall plaster for unit 2

Plasterer

$1,456.00

      Fitting doors for unit 2

Carpenter

$2,128.00

      Kitchen development for unit 2

Cabinet Maker

$2,400.00

      Bathroom installation for unit2

Cabinet Maker, Plumber

$5,280.00

      Electrical fitting for unit 2

Electrician

$2,904.00

      Final fittings of plumbing for unit 2

Plumber

$2,800.00

      Paint for unit 2

Painter

$1,008.00

      Approval of council for unit 2

Supervisor

$2,688.00

Heldman, K., 2015. PMP project management professional exam deluxe study guide: updated for the 2015 Exam. John Wiley & Sons.

Kerzner, H., 2013. Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.

Leach, L.P., 2014. Critical chain project management. Artech House.

Martinelli, R.J. and Milosevic, D.Z., 2016. Project management toolbox: tools and techniques for the practicing project manager. John Wiley & Sons.

Mir, F.A. and Pinnington, A.H., 2014. Exploring the value of project management: linking project management performance and project success. International journal of project management, 32(2), pp.202-217.

Phillips, J., 2013. PMP, Project Management Professional (Certification Study Guides). McGraw-Hill Osborne Media.

Schwalbe, K., 2015. Information technology project management. Cengage Learning.