Assignment1-ProposalEvaluation ExampleProposalEvaluation-GartnerLee3 ExampleProposalEvaluation-GartnerLee3 Assignment1-ProposalEvaluation-EvaluationForm1 Proposal-BrownfieldRemediation-CH2MHILL1
Environmental Project Management (ETEP 5131)
Page 1
ASSIGNMENT ONE
PROPOSAL EVALUATION
OBJECTIVE
To review and evaluate a professional environmental proposal and provide a written record of the review.
INTRODUCTION
This assignment may be worked on in groups of 1-4.
TASKS
1. Review the proposal, complete the evaluation form and calculate an overall score for this proposal.
2. Prepare a memo to the “Financial Officer” recommending whether or not to proceed with this project and summarizing the cost involved and the rational for your decision. Upload one word file (one per group) containing the memo and evaluation form to DC Connect.
RESOURCES
Please refer to DC Connect for additional resources (evaluation form, proposal, example memo, etc.
CITY OF ORILLIA
TO: Members of Council
FROM: MURF Design Committee
DATE: April 5, 2006
SUBJECT: Design and Construction Administration Services for a Gas
Venting System – MURF
Recommendation
THAT as recommended by Gartner Lee Ltd., a contract for Design and
Construction Administration Services for a Gas Venting System at the Multi-use
Recreation Facility located at 255 West Street South, be awarded to R. J.
Burnside and Associates Limited at the cost of $139,360, as set out in their
proposal dated March 31, 2006.
Background
Gartner Lee was retained to prepare a Request for Proposals (RFP) for the
detailed design and construction administration for the gas venting system, to
undertake an evaluation of the proposals received and make recommendations
to the City on award.
Discussion
The attached memorandum, dated April 5, 2006, from Mr. Mark Sungaila of
Gartner Lee provides background information on the invitation for proposals and
an evaluation of the two bids that were received.
The Design Committee concurs with the recommendations set out in the
memorandum and recommends acceptance of the R. J. Burnside and Associates
Limited proposal (Burnside).
Both proposals met the base criteria requirements of the Request for Proposals.
Even though there is a considerable price difference in the bids, the Gartner Lee
report identified a more comprehensive workplan in the Burnside proposal. The
additional scope of work includes an independent baseline assessment of soil
gas distribution and concentrations within the footprint of the building through on-
site sampling and monitoring. Installation of a network of flux boxes will simulate
an impermeable barrier and allow for an assessment of vapour migration and
collection below floor slabs, parking lots etc. A Pilot Scale Test will also be
undertaken. A 5m x 5m test plot will be constructed on the area of highest level
of contamination on the site and essentially simulates the system and verifies the
assumptions for the completion of the detailed design. With the public concerns
previously expressed about the effectiveness of the gas venting system, this
additional workplan will be beneficial. The Burnside proposal also includes the
preparation of a construction cost estimate and life cycle costing, which will
consider both capital and operating cost for a lifespan of 50 years.
Schedule
Both proposals contemplate a project start of April 11th and completion by mid to
late July, 2006.
In the next few weeks, Council will be considering remediation options to deal
with the source area contamination on the site, including potential building
relocation scenarios. It is recommended by Gartner Lee that relocation of the
building may have a significant impact on the consultants work. In order to
address this concern it is recommended that the timing of the commencement of
the work be dependent upon further discussions with Gartner Lee and Burnside
to determine if any portion of the workplan can commence prior to the outcome of
the upcoming discussions on building relocation.
Financial Impact
Once it was identified that a gas venting system was required, Shore Tilbe Irwin
& Partners advised that their professional insurance did not allow them to
undertake the design of the environmental components and therefore the City
was required to retain the consultant to undertake detailed design.
Although the capital cost for the gas venting system was included in the last
costing undertaken by Curran McCabe, no allowance has been made in the
consulting budget for the design. This budget will need to be increased to reflect
the design cost.
_____________________________________
Councillor Ralph Cipolla, Chair
CITY OF ORILLIA
TO: Members of Council
FROM: MURF Design Committee
DATE: April 5, 2006
SUBJECT: Design and Construction Administration Services for a Gas
Venting System – MURF
Recommendation
THAT as recommended by Gartner Lee Ltd., a contract for Design and
Construction Administration Services for a Gas Venting System at the Multi-use
Recreation Facility located at 255 West Street South, be awarded to R. J.
Burnside and Associates Limited at the cost of $139,360, as set out in their
proposal dated March 31, 2006.
Background
Gartner Lee was retained to prepare a Request for Proposals (RFP) for the
detailed design and construction administration for the gas venting system, to
undertake an evaluation of the proposals received and make recommendations
to the City on award.
Discussion
The attached memorandum, dated April 5, 2006, from Mr. Mark Sungaila of
Gartner Lee provides background information on the invitation for proposals and
an evaluation of the two bids that were received.
The Design Committee concurs with the recommendations set out in the
memorandum and recommends acceptance of the R. J. Burnside and Associates
Limited proposal (Burnside).
Both proposals met the base criteria requirements of the Request for Proposals.
Even though there is a considerable price difference in the bids, the Gartner Lee
report identified a more comprehensive workplan in the Burnside proposal. The
additional scope of work includes an independent baseline assessment of soil
gas distribution and concentrations within the footprint of the building through on-
site sampling and monitoring. Installation of a network of flux boxes will simulate
an impermeable barrier and allow for an assessment of vapour migration and
collection below floor slabs, parking lots etc. A Pilot Scale Test will also be
undertaken. A 5m x 5m test plot will be constructed on the area of highest level
of contamination on the site and essentially simulates the system and verifies the
assumptions for the completion of the detailed design. With the public concerns
previously expressed about the effectiveness of the gas venting system, this
additional workplan will be beneficial. The Burnside proposal also includes the
preparation of a construction cost estimate and life cycle costing, which will
consider both capital and operating cost for a lifespan of 50 years.
Schedule
Both proposals contemplate a project start of April 11th and completion by mid to
late July, 2006.
In the next few weeks, Council will be considering remediation options to deal
with the source area contamination on the site, including potential building
relocation scenarios. It is recommended by Gartner Lee that relocation of the
building may have a significant impact on the consultants work. In order to
address this concern it is recommended that the timing of the commencement of
the work be dependent upon further discussions with Gartner Lee and Burnside
to determine if any portion of the workplan can commence prior to the outcome of
the upcoming discussions on building relocation.
Financial Impact
Once it was identified that a gas venting system was required, Shore Tilbe Irwin
& Partners advised that their professional insurance did not allow them to
undertake the design of the environmental components and therefore the City
was required to retain the consultant to undertake detailed design.
Although the capital cost for the gas venting system was included in the last
costing undertaken by Curran McCabe, no allowance has been made in the
consulting budget for the design. This budget will need to be increased to reflect
the design cost.
_____________________________________
Councillor Ralph Cipolla, Chair
PROPOSAL EVALUATION FORM
Evaluation Category |
Points |
Comments |
|||||||||||||||
Qualifications and Experience |
/3 0 |
||||||||||||||||
The Firm’s Qualifications, experience and past performance on similar projects. |
/5 |
· |
|||||||||||||||
Experience and Qualifications of the Project Lead |
|||||||||||||||||
Experience and Qualifications of the Qualified Person |
/10 |
||||||||||||||||
Experience and Qualifications of the Remaining Proponent Team Members. |
|||||||||||||||||
Project Plan |
/40 |
||||||||||||||||
Project Objective |
/3 | ||||||||||||||||
Risk Assessment |
|||||||||||||||||
Review of Remedial Strategy |
|||||||||||||||||
Prequalification of Contractors |
|||||||||||||||||
Greenfield Restoration |
|||||||||||||||||
Contract Administration and Oversight |
|||||||||||||||||
Project Management |
|||||||||||||||||
Communications Strategy |
|||||||||||||||||
Project Schedule , Cost and Work Plan |
|||||||||||||||||
Project Schedule |
/15 |
||||||||||||||||
Project Costs and Work Plan |
|||||||||||||||||
Total Score |
/100 |
Proposalfor
Environmental Consultant Services for the Completion of
Risk Assessments and the Provision of Contract
Administration and Construction Oversight Services for
the Sydenham Pearl Brownfield Site
March 2013
Submitted to Submitted by
The Corporation of
the City Of Brantford
E
S
0
1
0
6
1
2
1
8
2
3
0
9
K
W
O
CH2M HILL and our associates, consider(s) the data and information contained in this proposal to be proprietary.
This proposal and any information contained herein shall not be disclosed outside of The Corporation of the City of Brantford
and shall not be duplicated, used or disclosed in whole or in part for any purpose other than to evaluate this proposal.
ENVIRONMENTAL CONSULTANT SERVICES REQUIRED TO COMPLETE A REMEDIATION STRATEGY FOR THE SYDENHAM PEARL BROWNFIELD SITE
431602_ES010612182309KWO i
USE OR DISCLOSURE OF DATA CONTAINED ON THIS SHEET IS SUBJECT TO
THE RESTRICTION ON THE BACK OF THE TITLE PAGE OF THIS PROPOSAL.
Contents
City Form of Proposal – Step
1
1. Proponent’s Qualifications, Experience, and Past Performance with Similar Projects …………………… 1-1
1.1 Project #1 – West Don Lands Site Brownfield Redevelopment ……………………………………………….. 1-1
1.2 Project #2 – Hamilton Health Sciences ……………………………………………………………………………….. 1-
2
1.3 Project #3 – Confidential Client, Amherstburg, Ontario ………………………………………………………….. 1-4
1.4 Project #4 – Sydenham Pearl ESAs ……………………………………………………………………………………. 1-4
2. Experience and Qualifications of the Project Lead ………………………………………………………………………. 2-1
3. Experience and Qualifications of the Qualified Person ………………………………………………………………… 3-1
4. Experience and Qualifications of Remaining Proponent Team Members ………………………………………. 4-1
5. Comprehensive Project Understanding, Approach, and Methodology ………………………………………….. 5-1
5.1 Introduction ……………………………………………………………………………………………………………………… 5-1
5.2 Project Objective ……………………………………………………………………………………………………………… 5-2
5.3 Risk Assessments ……………………………………………………………………………………………………………. 5-2
5.3.1 Integrate data from Phase Two ESA ……………………………………………………………………….. 5-2
5.3.2 Complete and Submit Pre-Submission Form to the MOE …………………………………………… 5-3
5.3.3 Completion of the Risk Assessment (Human Health and Ecological) …………………………… 5-3
5.3.4 MOE Review Process and Issuance of a Certificate of Property Use (if required) ………………. 5-4
5.4 Review of Remedial Strategy …………………………………………………………………………………………….. 5-4
5.5 Prequalification of Contractors …………………………………………………………………………………………… 5-5
5.6 Greenfield Restoration and Remediation Specification Preparation …………………………………………. 5-5
5.6.1 General Conditions and Agreement ………………………………………………………………………… 5-7
5.6.2 Review and Final Approval …………………………………………………………………………………….. 5-7
5.7 Contract Administration, Remediation/Greenfield Restoration Oversight and Reporting ……………… 5-7
5.8 Record of Site Conditions ………………………………………………………………………………………………….. 5-8
5.9 Project Management ………………………………………………………………………………………………………… 5-8
5.10 Communications Strategy …………………………………………………………………………………………………. 5-9
6. Project Schedule, Costs and Work Plan ………………………………………………………………………………………. 6-1
6.1 Project Schedule ……………………………………………………………………………………………………………… 6-1
6.2 Project Costs and Work Plan ……………………………………………………………………………………………… 6-1
6.3 Project Terms and Conditions ……………………………………………………………………………………………. 6-2
Exhibits
2-1 Organizational Chart…………………………………………………………………………………………………………………….. 2-2
4-1 Qualifications and Experience ……………………………………………………………………………………………………….. 4-2
5-1 Example Table of Contents …………………………………………………………………………………………………………… 5-6
5-2 Proposed Public Information Sessions ………………………………………………………………………………………….. 5-10
6-1 Schedule of Major Project Tasks ……………………………………………………………………………………………………. 6-1
Appendices
A Résumés
B Charts and Schedules
i) Anticipated Project Schedule
ii) Resource Allocation Matrix
ENVIRONMENTAL CONSULTANT SERVICES REQUIRED TO COMPLETE A REMEDIATION STRATEGY FOR THE SYDENHAM PEARL BROWNFIELD SITE
431602_ES010612182309KWO 1-1
USE OR DISCLOSURE OF DATA CONTAINED ON THIS SHEET IS SUBJECT TO
THE RESTRICTION ON THE BACK OF THE TITLE PAGE OF THIS PROPOSAL.
1. Proponent’s Qualifications, Experience, and Past Performance with
Similar Projects
CH2M HILL Canada Limited (CH2M HILL) is a global leader in full-service engineering, construction, and operations
services. What differentiates CH2M HILL is our strong commitment to partnering with clients to achieve their full
strategic and operational agendas. Our goal on every project is not just to meet requirements but to outperform,
delivering innovative, yet practical solutions. The result: a distinguished track record of value-creating client
successes on projects of every scope and size across every continent.
With a network of 10 offices across the country, CH2M HILL serves eastern and central Canada through its Canadian
headquarters in Toronto and offices in Ottawa and Kitchener/Waterloo. We are also able to draw on the strength of the
CH2M HILL family of companies’ global network, which allows our clients to access the resources and expertise of a
staff of more than 30,000 in nearly 350 offices around the world. Since its formation, CH2M HILL has been winning
awards from Canada’s most recognized engineering associations and all levels of government for innovation and
excellence in its engineering projects. Of particular relevance to this project are our capabilities as an industry-leading
environmental firm. We have extensive experience in carrying out environmental site assessments (ESAs) and risk
assessment (RAs), preparing remediation strategies, and providing contract administration and construction oversight
on challenging environmental projects. Our expertise in these areas are reflected in the long-standing working
relationships we enjoy with our environmental clients, as well as in our projects that have been selected as recipients of
a “Brownie” Award by the Canadian Urban Institute (http://canadianbrownfields.ca/) over the last 5 years. We are proud
of these awards recognizing our excellence in brownfield redevelopment at sites in Hamilton and Toronto.
The following project descriptions demonstrate our qualifications, expertise, knowledge, and experience in carrying
out ESAs, RAs, and remediation strategies, and in providing contract administration and construction oversight for
assignments similar to those proposed.
1.1 Project #1 – West Don Lands Site Brownfield Redevelopment
The environmental characterization of the West Don Lands (WDL) site is a typical project delivered by CH2M HILL’s
Environmental Business Group. Assessing a brownfield property, preparing RAs, reporting on findings, and
conducting remediation are all typical to an environmental characterization project. The biggest determining factor in
the WDL’s success was whether it was possible to meet the extremely aggressive schedule for this very public
project in the midst of a changing regulatory environment in Ontario. The short answer is: yes. It was.
Understanding the Vision – Revitalizing the site involved preparing 36 hectares (ha) for the 2015 Pan/Parapan
American Games Athletes’ Village (PAAV), in the short term, and in the longer term, mixed-use buildings, housing,
parks, and roads. The future land owners and the Ontario Ministry of the Environment (MOE) had to be assured that
the site’s environmental status had been characterized and mitigated, as appropriate. This involved understanding
the contaminant distribution across the site and employing the appropriate measures, including risk management
measures (RMMs), as determined through the RA process, remediation, or a combination. From project startup, the
Infrastructure Ontario (IO)/CH2M HILL team was clear about how success would be defined for WDL. Success would
mean that development of the lands would not be delayed, that schedules would be met for all milestones, that
quality deliverables would expedite stakeholder endorsement, and that developers would be engaged with clear
understanding of constraints and risks. In addition to these goals, CH2M HILL strove to exceed client expectations –
and our reputation as a leader in performing RAs for brownfield development was further enhanced.
ENVIRONMENTAL CONSULTANT SERVICES REQUIRED TO COMPLETE A REMEDIATION STRATEGY FOR THE SYDENHAM PEARL BROWNFIELD SITE
1-2
431602_ES010612182309KWO
USE OR DISCLOSURE OF DATA CONTAINED ON THIS SHEET IS SUBJECT TO
THE RESTRICTION ON THE BACK OF THE TITLE PAGE OF THIS PROPOSAL.
Key Components of the Project – In April 2010, CH2M HILL initiated work, conducted field investigations, and
prepared multiple Phase One, Phase Two, and RA reports concurrently in order to meet the aggressive project
schedule. The reports complied with Ontario Regulation (O. Reg.) 153/04 under the Environmental Protection Act, as
amended by O. Reg. 511/09, so that Records of Site Condition (RSCs) were obtained on the properties prior to
development. At each step of characterization, risk assessment, risk management, and remediation, multiple
stakeholders were engaged, including the MOE.
In summary, four Phase One reports were produced, along with eight Phase Two reports, eight RA reports, and eight
Remedial Options Feasibility (ROFS) reports. Eleven Certificates of Property Use were also finalized, and 13 RSCs
were finalized and acknowledged by the MOE.
Risk Assessment – CH2M HILL assembled an RA team to complete 8 RAs for the 60 blocks in the WDL and obtain
MOE endorsement/acceptance on them. The accelerated schedule required technical and team leadership to secure
consensus from the MOE and other stakeholders throughout the process. An added challenge to successful delivery
included a recent change in the regulations governing RA activities in Ontario, as well as uncertainty surrounding the
implementation of the new regulations, given the timing of the RAs and RSC filing. Strategic communication with the
regulator and client was critical for the RAs to meet the new regulations, as appropriate.
To complete the RAs on time, approximately 25 RA staff (including human health and ecological risk assessors) were
used for the duration of the project, and communication systems were put in place to support the effective flow of
information both between RA team members and other teams contributing to the RA reports (that is, the Site
Assessment, Risk Management, and Publications Services teams). In addition, the RA team worked to automate and
streamline multiple RA processes, and to achieve consensus on the building blocks and technical approach to the
RAs with the client and regulator prior to report production. The
success of this strategy and team structure was evident in the
consistent ability of the team to produce high-quality RA reports,
each compiled within 2 weeks; typically, this process takes
about 3 months.
In all, 25 risk assessors were coordinated, 8 draft and 8 final
reports were produced, and more than 100,000 pieces of data
were considered.
Communications – During the project, CH2M HILL
communicated with numerous stakeholders involved with the
WDL site, many of whom did not have experience operating
within the environmental arena. To work with them successfully,
we educated them on the site’s regulatory process. This
education started with kick-off meetings with each stakeholder
and continued throughout the project, with regular meetings held
weekly and biweekly.
1.2 Project #2 – Hamilton Health Sciences
To support its plans for the potential acquisition of the site from the City of Hamilton, Hamilton Health Sciences (HHS)
retained CH2M HILL to conduct detailed Phase One and Phase Two ESAs, a designated substance and building
waste survey, an RA, and a remedial action plan (RAP) on the Wellington Development Block, located immediately
west of Hamilton General Hospital (HGH). CH2M HILL prepared all demolition and remediation specifications for this
project and managed the abatement, demolition, remediation, and restoration work. We also assisted in
redevelopment options for the various parcels of land that make up the larger property.
Phase One activities included a site history review, site inspections, interviews, an evaluation of information and
reporting. The Phase One ESA concluded that the Block has the potential for soil and groundwater contamination,
with 19 potential areas of concern noted, including metals, polychlorinated biphenyls (PCBs), asbestos-containing
materials, gasoline, diesel, and underground storage tanks (USTs).
Remediation – Project Site Details:
Services Provided:
– Phase One and Two ESAs
– Risk Assessments and Develop Remedial Strategies
– Construction Oversight
Remediation approach: Excavation and removal to
meet the site-specific standards and capping
Standards achieved: Site-Specific Standards
Timeline: 18 months
Costs: Confidential
Award: This project won the 2011 Brownie Award as
the project that best demonstrated Excellence in
Project Development at the Neighbourhood Scale and
the 2012 Brownie Award for Best Small Scale Project
and Contribution to Public Realm
Reference: Monisa Nandi, Environmental Specialist,
Infrastructure Ontario, 416-327-8001,
Monisa.Nandi@infrastructureontario.ca
ENVIRONMENTAL CONSULTANT SERVICES REQUIRED TO COMPLETE A REMEDIATION STRATEGY FOR THE SYDENHAM PEARL BROWNFIELD SITE
431602_ES010612182309KWO 1-3
USE OR DISCLOSURE OF DATA CONTAINED ON THIS SHEET IS SUBJECT TO
THE RESTRICTION ON THE BACK OF THE TITLE PAGE OF THIS PROPOSAL.
The goal of the Building Waste and Designated Substance Survey was to identify wastes and substances that would
present health and safety or environmental concerns and the associated management and abatement requirements
for these substances.
The Phase Two ESA characterized the Block’s geology and hydrogeology, to support a RAP and associated cost
estimate. It involved collecting chemical data associated with subsurface soil and groundwater, and assessing the
potential impacts to the subsurface based on MOE criteria. Tasks included reviewing and interpreting previous
environmental reports, conducting site reconnaissance, and developing a borehole drilling program and a soil and
groundwater analytical program to provide additional characterization of the Block.
A site-specific RA feasibility study was performed as part of the Phase Two ESA to provide a preliminary
determination as to whether contaminants at the Block could be managed in place.
The screening-level RA demonstrated that there was no need for supplemental RMMs beyond isolating contaminants
of concern (COCs), monitoring the groundwater, and maintaining barriers as required. It was determined that
applying an RA approach as part of the RAP was likely to provide a successful, cost-effective approach to managing
the soil and groundwater impacts identified at the site.
On behalf of HHS, CH2M HILL completed a MOE-approved comprehensive RA for the property to develop Property
Specific Soil and Groundwater Standards in accordance with O. Reg. 153/04.
The cost of the ESAs and RA were offset by a Federation of Canadian Municipalities’ Green Municipal Fund grant of
$175,000, along with a $20,000 grant provided through the City of Hamilton’s Environmental Remediation and Site
Enhancement (ERASE) program.
CH2M HILL developed tender documents and contract
specifications for the demolition of the former Steel Company of
Canada (SCOC) Facility located on the property; and oversaw
the demotion activities, which included management and
abatement of designated susbstances. The demolition was
completed on schedule and below the estimated budget.
CH2M HILL developed tender documents and contract
specifications to remediate soil at the former SCOC facility
located north of HGH and immediately east of the Wellington
Block. Prior to the start of the project, CH2M HILL negotiated
with the remediation contractor to reduce their bid price by
approximately $120,000. Our team oversaw the soil remediation
activities, which included filing an RSC for the property before
HGH expansion onto remediated lands, which the MOE
recognized on June 12, 2007. The remediated lands previously
served as a parking area for hospital staff. Following demolition of the former SCOC facility and MOE acceptance of
the Wellington Block RA, the parking lot was relocated to the Wellington Block.
The Canadian Urban Institute recognized the HHS Wellington Development Block Brownfield Redevelopment project
with a 2009 Brownie Award for its leadership, innovation, and environmental sustainability in Brownfields
redevelopment. HHS president and CEO Murray Martin called the award “an outstanding achievement for our team
at Hamilton Health Sciences and our contractor CH2M HILL. I am deeply proud not only of the final product, but the
fact that Hamilton Health Sciences is able to play a large role in the economic and environmental rehabilitation of this
area of Hamilton.”
Remediation – Project Site Details:
Services Provided:
– Phase One and Two ESAs
– Risk Assessments and Develop Remedial Strategy
– Preparation of Tender Document, Procurement,
Contract Administration
– Construction Oversight
Remediation approach: On-site isolation/ barrier
controls, Monitored natural attenuation
Standards achieved: Site-Specific Standards
Timeline: 20 months
Costs: Confidential
Award: This project won the 2009 Brownie Award for
Brownfield Redevelopment
Reference: Beth Manganelli, Director of Economic
Development, Hamilton Health Sciences,
905-521-2100 ext 77446
ENVIRONMENTAL CONSULTANT SERVICES REQUIRED TO COMPLETE A REMEDIATION STRATEGY FOR THE SYDENHAM PEARL BROWNFIELD SITE
1-4 431602_ES010612182309KWO
USE OR DISCLOSURE OF DATA CONTAINED ON THIS SHEET IS SUBJECT TO
THE RESTRICTION ON THE BACK OF THE TITLE PAGE OF THIS PROPOSAL.
1.3 Project #3 – Confidential Client, Amherstburg, Ontario
CH2M HILL is currently decommissioning and demolishing a large abandoned chemical manufacturing facility;
including the removal, disposal, and treatment, as required, of all designated substances, raw materials and product;
as well as hazardous and non-hazardous materials and waste contained within the existing process equipment,
tanks, reservoirs, and piping.
This facility was abandoned abruptly when the former owner
declared bankruptcy and was vacant for a number of years
before acquired by Amherstburg Land Holdings. Because it
had remained vacant for so long, the site was in disarray and
the buildings in advanced structural deterioration due to the
products and byproducts of the former manufacturing process.
CH2M HILL worked with the client to provide support through
the purchase of the site, then arranged and commissioned a
series of engineering assessments to gather sufficient
information to develop a bid package for the demolition. The
engineering studies included structural assessments of the
property to determine those buildings that unsafe for further
entry and concurrently arranged for the consolidation, labeling,
classification, and registration of the quantity of subject wastes
that remained on the property. In addition, a hazardous
building material assessment was completed to identify and
quantify the presence, location, and quantities of designated substances at the site. Following completion of the
engineering assessments, CH2M HILL developed bid specifications and arranged an invitation to bid to a select
group of experienced demolition firms that were capable of completing the full scope of work. CH2M HILL supported
the bidding process and helped our client select the best demolition contractor for the work. Subsequently, we
successfully negotiated an alternative bid with specific salvage management and asset recovery requirements. This
eventually resulted in a cash positive position for the client. In addition, we met with the regulators, to establish
appropriate monitoring during demolition.
We are currently providing onsite construction management services during demolition and are documenting
compliance with plans and applicable regulations.
1.4 Project #4 – Sydenham Pearl ESAs
The Sydenham Pearl Brownfield in downtown Brantford
consists of two properties, 17 and 22 Sydenham Street, with a
total area of 2.4 ha. The site’s long industrial history dates back
to the early 1900s and consists primarily of roofing material and
electrical fixture manufacturing. The onsite buildings were razed
in the early 2000s, and the brownfield is currently vacant and
undeveloped. The City of Brantford became the owner of the
site in 2006 following unsuccessful tax sales. Concurrent with
and following the tax sale, City staff conducted an extensive
public consultation program to identify neighbourhood priorities
for redevelopment of the site. The public response was focused
on future residential and parkland redevelopment.
In the spring of 2012, CH2M HILL was retained to provide
environmental consulting services focused on future
residential/parkland land uses. The work conducted by
CH2M HILL included Phase One and Two ESAs and the
Remediation – Project Site Details:
Services Provided:
– Data Gap Review and Phase Two ESA
– Risk Assesment and Development of Remedial
Strategy
– Preparation of Tender Document, Procurement,
Contract Administration (ongoing)
– Construction Oversight (ongoing)
Remediation approach: Demolition, excavation and
removal, capping, monitored natural attenuation
Standards achieved: Site-Specific Standards
Timeline: 2010 – Ongoing
Costs: Confidential
Reference: Richard W. Galloway, Remediation
Manager, tel: 973-455-4640, email:
rich.galloway@honeywell.com
Remediation – Project Site Details:
Services Provided:
– Phase One and Two ESAs
– Develop Remedial Strategy
– Risk Assessment and Review Remedial Strategy
– Preparation of Tender Document, Procurement,
Contract Administration
– Construction Oversight
Proposed Remediation approach: Excavation and
removal, barrier wall, in-situ contaminant treatment,
monitored natural attenuation
Standards proposed: Site-Specific Standards
Timeline: 2012 (For ‘Services Provided’)
Costs: Confidential
Reference: Mr. Paul Moore, Manager of Policy
Planning, City of Brantford, 519-759-4140 ext. 2348
ENVIRONMENTAL CONSULTANT SERVICES REQUIRED TO COMPLETE A REMEDIATION STRATEGY FOR THE SYDENHAM PEARL BROWNFIELD SITE
431602_ES010612182309KWO 1-5
USE OR DISCLOSURE OF DATA CONTAINED ON THIS SHEET IS SUBJECT TO
THE RESTRICTION ON THE BACK OF THE TITLE PAGE OF THIS PROPOSAL.
development of a Remediation Strategy for the brownfield. Concurrent with completion of this work, meetings were
held with Brantford municipal personnel, a public consultation program was conducted to both obtain information from
the public and to communicate the results of work being completed, and the final reports were presented to the
Brantford City Council.
The Remedial Strategy includes the completion of a risk assessment, followed by various actions to either manage or
actively remediate contaminants. While the preferred remedial strategy will be reviewed and potentially revised upon
completion of the RA, currently contemplated remedial activities include limited ‘hot spot’ excavation, the construction
of treatment barriers, and in-situ contaminant treatment.
ENVIRONMENTAL CONSULTANT SERVICES REQUIRED TO COMPLETE A REMEDIATION STRATEGY FOR THE SYDENHAM PEARL BROWNFIELD SITE
431602_ES010612182309KWO 2-1
USE OR DISCLOSURE OF DATA CONTAINED ON THIS SHEET IS SUBJECT TO
THE RESTRICTION ON THE BACK OF THE TITLE PAGE OF THIS PROPOSAL.
2. Experience and Qualifications of the Project Lead
As illustrated on the organizational chart in Exhibit 2-1, Ed Taves will be the Project Lead (PL). He holds a Double
Honours B.A. (Chemistry and Biology) and an M.A. (Biochemistry), is licensed as a Professional Geoscientist
(P.Geo. Ltd.) and Chartered Chemist (C.Chem.), and is designated as a Qualified Person for ESA (QPESA) by the
MOE. Ed has more than 23 years’ experience in Phase One/Two ESAs, ROA, and site remediation programs,
including contract administration projects. For the last 15 years he has typically served as the PL, responsible for
understanding clients’ project objectives (technical deliverables) and the cost/schedule limitations, then developing
and maintaining project teams with the required designations, experience, and availability to complete the project
successfully. Ed recognizes that effective communication – including client, public, and regulatory liaison – is a critical
component of every project. He has worked directly with municipal departments, presenting to municipal councils, the
public, and the MOE. Ed has served as the PL for many projects for municipal clients, including projects in support of
Brownfield assessment and acquisition subsequent to failed tax sales, and ROA and implementation for all types of
land uses, including parkland and residential. Remedial options considered have included RA for the development of
PSSs, reducing active remedial requirements and costs. Ed has served as the PL for nearly half of CH2M HILL’s
projects resulting in the filing of RSCs post July 1, 2011 under the current requirements in O. Reg. 153/04. Ed was
the PL for the following representative projects; refer to his resume in Appendix A for further information:
West Don Lands (WDL); Ontario Infrastructure and Lands Corporation (IO); Toronto, Ontario (see Section 1
for a full project description). As the PL, Ed developed and maintained a team to complete 4 Phase Ones, 8
Phase Twos, and 8 ROAs concurrently, in support of 8 RAs and the filing of 13 RSCs,
under an aggressive schedule. A team of approximately 70 professional, technical, and
support staff; and subcontracted trades was established. He was responsible for
reviewing project needs, identifying specialist resources identified, and adjusting prior
specialist commitment to meet project needs. Roles were defined, staff chartered, and
the team maintained through vacations, sickness, and changing priorities. Contact was maintained with the client,
Account Manager, and QPESA to identify and meet project objectives.
Phase Two ESA, Remedial Action Planning, Contract Administration;
Reichhold Industries Limited, Ontario. Ed is the PL providing ongoing
assistance to Reichhold for the management of environmental matters for
two former chemicals plants. Work has included Phase One/Two ESA
activities, groundwater monitoring in association with ongoing monitored
natural attenuation and phytoremediation programs, soil gas assessment,
remedial action planning, demolition activities, contaminant excavation, in-
site contaminant treatment, contract administration/ construction oversight
in support of demolition and remediation programs. Remedial options evaluated have included in situ chemical
oxidation and bioremediation, soil mixing with zero valent iron, excavation and offsite disposal, and RA activities. Ed
played a leading role in the presentations that have been made to public and legal audiences. Targeted excavation
and offsite disposal, and in situ chemical oxidation and bioremediation projects have been completed.
Confidential Client, Amherstburg, Ontario (see Section 1, Project 3 for a full project description). As the
environmental task manager, Ed managed the team to complete data gap analysis and Phase Two ESA activities.
RA and remedial option analysis activities are occurring at this time.
City of Brantford (see Section 1, Project 4 for a full project description). Ed was the PL for the completion of the
Phase One and Two ESAs, and the development of the remedial strategy. He also played a lead role in the public
consultation program and provided a presentation to Council.
Project Site Details and
Reference: Please refer to
Project #1 in Section 1
Project Site Details:
Timeline: 3 years, ongoing
Costs: Confidential
Reference: Brian Kanzler, Site
Remediation – Environmental Engineering
Manager, Reichhold Inc., 1-919-990-7509,
Brian.Kanzler@reichhold.com
ENVIRONMENTAL CONSULTANT SERVICES REQUIRED TO COMPLETE A REMEDIATION STRATEGY FOR THE SYDENHAM PEARL BROWNFIELD SITE
2-2 431602_ES010612182309KWO
USE OR DISCLOSURE OF DATA CONTAINED ON THIS SHEET IS SUBJECT TO
THE RESTRICTION ON THE BACK OF THE TITLE PAGE OF THIS PROPOSAL.
Exhibit 2-1 – Organizational Chart
City of Brantford
Project Lead
Ed Taves*
Qualified Person (QPESA)
Kurt Hansen*
Principal/Senior Advisors
Brian Whiffin*
James Sprenger*
Communications Lead
Meggen Janes*
Subcontractors
Driller (Profile) / Laboratory (ASL) / Surveyor (West Ruuska)
Health & Safety
Lisa Moffat
Site Assessment
Lead: Dirk Scheurlen*
Hydrogeologist
Jinlong Zang
Environmental Technician
Michael Shiry
Project Engineer
Tania McCarthy
Project Chemist
Almudena Camacho
GIS Lead
April Bates
Contract Administration/
Construction Oversight Lead
Terry Lorentz*
Remedial Strategy Review
Meggen Janes*
Wayne Cooley*
Contract Administration/
Tender Documents
Ryan Manning*
Cost Estimator
Janie Brenner*
Construction
Oversight
Jamie Freeman
Qualified Person (RA)
Krista Barfoot Kinsie*
Risk Assessment Lead
(Human Health
Andrea Wojtyniak*
Risk Assessment Lead
(Ecological)
James Kroetsch*
Risk Management Measures
Meggen Janes*
Risk Assessment Support
Katherine Appleby
Notes:
•Resumes Provided (Resumes can be provided upon request, for other individuals shown)
•Project staffing subject to change based on availability at time work is to be completed.
ENVIRONMENTAL CONSULTANT SERVICES REQUIRED TO COMPLETE A REMEDIATION STRATEGY FOR THE SYDENHAM PEARL BROWNFIELD SITE
431602_ES010612182309KWO 3-1
USE OR DISCLOSURE OF DATA CONTAINED ON THIS SHEET IS SUBJECT TO
THE RESTRICTION ON THE BACK OF THE TITLE PAGE OF THIS PROPOSAL.
3. Experience and Qualifications of the Qualified Person
As shown in Exhibit 2-1, Kurt Hansen will be the Qualified Person (QP) for this project. He holds a B.E.S. and a M.E.S.
in Environmental Studies and is a licensed P.Geo. Kurt has more than 22 years’ experience in Phase One and Two
ESAs, site remediation programs, and field investigations involving soil and groundwater sampling and monitoring. Kurt
is a QPESA, and has been responsible for filing more RSCs post July 1, 2011 under the current requirements in O.Reg.
153/04 than any other QPESA within CH2M HILL. These RSCs were also formally acknowledged by MOE, submitted with
approved risk-based standards, and often involved remediation to address contamination. Kurt is well versed in current
reporting methods for Phase One and Two ESAs to support RSC filing and understands in detail the current RSC and
RA regulatory process. He was QPESA for the following representative projects*:
WDL; IO; Toronto, Ontario (see Section 1, Project #1 for a full project description). As QPESA for the WDL
project, Kurt managed and directed field investigations and prepared 4 Phase One reports and 6 Phase Two ESA
reports for 60 blocks of the 36-ha WDL under an accelerated schedule. The ESA team supervised by Kurt evaluated
data at approximately 290 areas of potential environmental concern (APECs) identified through the Phase One ESAs
and over 500 sample locations across the site (including more than 290 monitoring wells). Data generated was used
to build a conceptual site model (CSM) for each RSC Property to comply with post July 1, 2011 regulatory
requirements. As QPESA, Kurt led the ESA reporting and the associated site assessment summaries that were
included in the RA Reports, liaised with the MOE to integrate current requirements into the ESA reports and RSC
documents, was responsible for the completion of the 13 acknowledged RSCs to date, served as technical liaison
with the RA teams to realize efficiencies, and certified that the remediation strategy was
implemented. This effort clearly demonstrates his expertise in developing and
implementing site remediation work for the purposes of obtaining an RSC(s) with the
MOE. Two of the acknowledged RSCs were under O. Reg. 153/04 (before July 1, 2011)
and 11 were under O. Reg. 153/04 as amended by 511/ (after July 1/11).
One Wellington Development Block Brownfield Redevelopment; Hamilton Health Sciences; Hamilton, Ontario;
2004 to 2007. Kurt was Site Assessment Lead Phase One ESA and Senior Technical Advisor for this project which
involved the completion of Phase One and Phase Two ESAs, a designated substance and
building waste survey, risk assessment, and a remedial action plan on the Wellington
Development Block located immediately west of Hamilton General Hospital (HGH), in
support of plans for the potential acquisition of the site from the City of Hamilton.
CH2M HILL prepared all demolition and remediation specifications for this project and
managed the abatement, demolition, remediation and restoration work. CH2M HILL also assisted in redevelopment
options for the various parcels of land that makeup the larger property.
As senior ESA lead, Kurt served as site assessment lead for completion of Phase One activities, which included a site
history review, site inspections, interviews, an evaluation of information and reporting. The Phase One environmental
site assessment concluded that the Block has the potential for soil and groundwater contamination, with 19 potential
areas of concern noted, including metals, PCBs, asbestos-containing materials, gasoline, diesel, and USTs. Kurt
provided senior technical guidance and support to subsequent phases of the project as required.
Sydenham Pearl Brownfield; City of Brantford; Brantford, Ontario; 2012. Kurt was the
Qualified Person for the ESA and Preparation of the Remediation Strategy for this project,
which involves two parcels of land in downtown Brantford, both with industrial legacies
dating back to the early 1900s. CH2M HILL was retained to conduct Phase One and Two
ESAs, and to prepare a Remedial Action Strategy to revitalize the properties for potential
residential development. Work included consultation with city staff, a public meeting, and
presentations to City Council. Work was completed to the satisfaction of the City, the public, and City Council, and
resulted in the approval of funds for implementation of the remedial strategy.
Project Site Details
and Reference: Please
refer to Project #1 in
Section 1
Project Site Details
and Reference: Please
refer to Project #2 in
Section 1
Project Site Details
and Reference: Please
refer to Project #4 in
Section 1
ENVIRONMENTAL CONSULTANT SERVICES REQUIRED TO COMPLETE A REMEDIATION STRATEGY FOR THE SYDENHAM PEARL BROWNFIELD SITE
3-2 431602_ES010612182309KWO
USE OR DISCLOSURE OF DATA CONTAINED ON THIS SHEET IS SUBJECT TO
THE RESTRICTION ON THE BACK OF THE TITLE PAGE OF THIS PROPOSAL.
Port Stanley ESA, RA, and RAP; PWGSC; Port Stanley,
Ontario (see Section 1 for a full project description).
Kurt supervised the initial 2006 Phase Two ESA and ROA
leading to the selection of RA in conjunction with
remediation to address “hot spot” contamination areas
(under federal requirements) as the recommended
remediation strategy. In 2008, under Kurt’s direction as
QPESA, a data gap evaluation and supplemental were
completed to address provincial regulatory requirements for
filing an RSC imposed as part of the transfer of lands to the
municipality. In 2010, Kurt supported the public consultation
program and represented the client at the information
sessions. As a result of regulatory changes that came into
force in mid-2011, Kurt is acting as QPESA for a Phase Two
to address the new regulatory requirements for completion of the RA and filing of RSCs on four distinct properties.
Redevelopment of King & Adelaide Property; Toronto
Community Housing Corporation; Toronto. Kurt was the
Project Manager and QPESA managing and supervising the
updated Phase One and Two ESAs, remedial strategy evaluation,
subsequent remediation, and RSC filing. The site was located at
288 King Street East and 501 Adelaide Street East in Toronto.
Based on the ESA findings, Kurt delineated the volume of
subsurface materials requiring remediation, evaluated remedial
options, and estimated remedial costs. Subsequently, Kurt led the
development of tender documents and specifications for
remediation and provided contract administration and remediation
oversight. Upon completion of remediation, CH2M HILL filed an
RSC under O. Reg. 153/04 documenting the change from industrial to residential land use. MOE acknowledged
the RSC.
Project Site Details:
Land area: 11.7 ha
Volumes of contamination remediated: 87,000 m3
Remediation approach: RA with “hot spot” remediation
Standards achieved: Risk-based property-specific
standards
Timeline: 2008 to date
Costs: $437,000 (Phase One/Two ESA & RA-’08-‘11);
$351,000 (Phase Two update-’11-‘12)
Reference: (i) Brad Simpson, Senior Environmental
Specialist, PWGSC, 416.512.5732, brad.simpson@pwgsc-
tpsgc.gc.ca (ii) Donald Leitch, Chief Administrative Officer &
Clerk, Municipality of Central Elgin, 519-631-4860 Ext. 276,
dleitch@centralelgin.org
Project Site Details:
Land area: 0.3 ha
Volumes of contamination remediated: 4,675 m3
Remediation approach: Excavation
Standards achieved: Residential land use
Timeline: 3 months
Costs: $49,429
Reference: Peter Zimmerman, Housing
Development Manager, Development Division,
TCHC, 416-981-4404,
Peter.zimmerman@torontohousing.ca
ENVIRONMENTAL CONSULTANT SERVICES REQUIRED TO COMPLETE A REMEDIATION STRATEGY FOR THE SYDENHAM PEARL BROWNFIELD SITE
431602_ES010612182309KWO 4-1
USE OR DISCLOSURE OF DATA CONTAINED ON THIS SHEET IS SUBJECT TO
THE RESTRICTION ON THE BACK OF THE TITLE PAGE OF THIS PROPOSAL.
4. Experience and Qualifications of Remaining Proponent Team Members
The remaining project team members are included in the organizational structure shown in Exhibit 2-1, and an
overview of their qualifications and experience for this project is provided in Exhibit 4-1 on the following page. All
project team members will report through the PL and work under the technical oversight of the QPESA (see
Sections 2/3). Other key team members include the following:
i. Task Leads
Meggen Janes, Communication and Remedial Strategy
Dirk Scheurlen, Site Assessment Lead
Krista Barfoot, Risk Assessment/ Qualified Person (QPRA)
Terry Lorentz, Contract Administration/Construction Oversight
ii. Prinicipal/Senior Advisors
Brian Whiffin
James Sprenger
A drilling contractor (Profile), analytical lab (ASL), and surveyor (West & Ruuska) will be subcontracted if additional
intrusive work is required. No subconsultants are proposed. CH2M HILL confirms that all project team staff are
currently available to fulfill their proposed role on this project. If key staff changes are required at the time work is to
be completed, Brantford personnel will be consulted for their concurrence. References and contact information are
provided for each team member in Exhibit 4-1. The numbers cited under References and Common Experience refer
to the projects highlighted in Section 1.
ENVIRONMENTAL CONSULTANT SERVICES REQUIRED TO COMPLETE A REMEDIATION STRATEGY FOR THE SYDENHAM PEARL BROWNFIELD SITE
4-2 431602_ES010612182309KWO
USE OR DISCLOSURE OF DATA CONTAINED ON THIS SHEET IS SUBJECT TO
THE RESTRICTION ON THE BACK OF THE TITLE PAGE OF THIS PROPOSAL.
Exhibit 4-1 –Qualifications and Experience
Project Team
Member/Role
Personal Skill or Specialty that applies to
this Project
Qualifications, Expertise, and Past Performance on Similar Projects1 References
and Common
Experience 2,3 Education Designations Years Similar Projects
Meggen Janes
Communications,
Remedial Strategy, RMMs
Effective communicator for environmental projects
and remediation strategies developed from
completing many high-profile similar assignments
B.A.Sc.
M.Sc.
P.Eng.
PMP
QPESA
22 – Communications lead on Projects #1, 2 & 4, responsible for managing stakeholder and public
communications
– RSC team lead for Project #1, responsible for filing 13 RSCs
#1, 2 & 4
other
Brian Whiffin
Principal/ Senior Advisor
Contributes environmental remediation strategy
gained from similar projects and as a Task
Force Member for the National Brownfield
Strategy
B.A.Sc.
M.Eng.
P.Eng.
F.E.C.
QPESA
30 – QPESA for RSC filing following the remediation of a former Stelco property to facilitate redevelopment for
health care facilities which received a Brownie Award in 2009
– Senior advisor, project manager or senior consultant for numerous brownfield project, including developing
and facilitating public information sessions, advising on remediation programs
#2 & 4
Other
James Sprenger
Principal/ Senior Advisor
Senior risk assessor and QPRA for multiple RAs
prepared under the amended regulation and for
filing of RSCs
B.Sc.
M.Sc.
(candidate)
QPRA 19 – Senior human health risk assessor and senior consultant for the development of risk management plans for
multiple RAs, 8 of which have been accepted by MOE and used to support filing of an RSC for Project #1
– Senior human health risk assessor for Project #3
#1
#3
Other
Dirk Scheurlen
Site Assessment Lead
Thorough knowledge of Phase Two
requirements under O. Reg. 153/04 (as
amended)
Diploma OACETT 22 – Coordinated multiple field teams leading to MOE acceptance of Phase Two documentation and
acknowledgement of 13 RSCs for Project #1
– Project manager for Project #2, and Site Assessment Task Lead for Project #4
– Project manager/investigation lead for a Stelco site remediation leading to an RSC filing
#1, 2 & 4
other
Krista Barfoot
QPra, Human Health RA
Senior risk assessor for completion of multiple
RAs leading to filing an RSC under the amended
regulation
B.Sc.
M.Sc.
Ph.D.
QPRA 9 – Senior risk assessor for completion of 8 RAs that have been acknowledged by MOE including the
development of PSSs leading to the filing of RSCs for Project #1
-Served as RA Task Manager for Project No.
3
#1 & 3
Other
Terry Lorentz
Contract Admin/
Construction Oversight
Lead
Extensive experience in contracting and cost
estimating for site remediation
BES, Post-
Grad
Diploma
N/A 13 – Construction advisor providing support for remedial options feasibility studies, construction costing, excavation,
soil management, and soil disposal. Provided support related to preparing and developing remediation bid
documents for Project #1 and 3.
– Construction advisor supporting remedial options feasibility studies and construction costing for Project #4
#1, 3 & 4
Other
Jinlong Zang
Hydrogeologist
Thorough understanding of hydrogeological
requirements under O. Reg. 153/04 (as amended)
B.A.Sc.
M.A.Sc.
P.Eng. 15 – Hydrogeologist responsible for hydrogeological testing and analysis to support filing of 13 RSCs as part of
Project #1
– Hydrogeologist for Project #4, and for Phase Two update to support a planned RSC filing for Project #3
#1, 3 & 4
other
Andrea Wojtyniak Risk
Assessment Lead
Intermediate risk assessor for completion of
multiple RAs leading to filing an RSC under the
amended regulation
B.Sc. N/A 7 – Intermediate risk assessor for completion of 8 RAs that have been acknowledged by MOE including the
development of PSSs leading to the filing of RSCs for Project #1
-Intermediate risk assessor for RA being completed for Project #3, as well as numerous other projects
#1 & 3
Other
Michael Shiry
Environmental
Technician
Knowledge and experience with new Phase Two
sampling requirements as field technician for
multiple ESAs leading to RSC filing under
O. Reg. 153/04 (as amended)
B.E.S. N/A 4 – A key environmental technician responsible for borehole drilling, soil sampling well installation and
environmental sampling under the stringent requirements of O. Reg. 153/04 (as amended) leading to the filing
of multiple RSCs, Project #1
– Lead environmental technician for Project #3, responsible for groundwater sampling for Project #4
#1, 3 & 4
Other
Tania McCarthy
Project Engineer
Proven track record for successful reporting of
Phase One and Twos under O. Reg. 153/04 (as
amended)
B.A.Sc. N/A 9 – Under the direction of the QP, prepared Phase One and Two reports and RA sections to support filing of 13
RCS under Project #1
– Project engineer for Projects #3 and 4. Played key role in data management, interpretation and reporting.
#1, 3 & 4
Other
Almudena Camacho
Project Chemist
Thorough understanding of data quality
management and documentation requirements
under O. Reg. 153/04 (as amended)
B.Sc.
MQM
C of P –
Industrial
Hygiene
8 – Under the direction of the QP, reviewed all laboratory test reports relative to data quality objectives and
produced data quality documentation for Project #1, 3 and 4
#1, 3 & 4
Other
April Bates
GIS Lead
Insights into spatial data management and
mapping requirements for MOE acceptance of
RSCs and related documentation
BES N/A 11 – Managed spatial data and produced mapping to meet the data quality and accuracy requirements for
successful filing of 6 RCS under the amended regulation for Project #1
#1, 2, 3 & 4
Other
Wayne Cooley
Remediation Strategy
Strong focus on the development and
implementation of site remediation plans
B.A.Sc.
M.A.Sc.
P.Eng. 16 – Senior engineer for remediation option assessment, key contributor for vapour control considerations,
contributor to Project # 3
#3
Other
Jamie Freeman
Construction Oversight
Strong technical knowledge and practical
experience leading field activities for
environmental and construction projects
B.Sc. C.E.P.I.T 10 – Senior engineer for evaluation and costing of remedial options for Project #1
– Program lead for Environmental Engineering Post-Diploma program at Conestoga College
#1, 2 & 3
Other
Jim Kroetsch
Ecological RA
Extensive insights into the ecological RA
requirements for filing of RCSs
F.W.T.
B.Sc.
M.Sc.
QPRA
CCEP
24 – Senior ecological risk assessor for Project #1 including MOE acceptance of 8 RAs prepared to address the
requirements of the amended regulation
– Senior ecological risk assessor for Projects #2 and #3
#1, #2
#3
Other
Ryan Manning
Tender Documents/
Contract Administration
Design and construction engineer for
remediation projects including development of
specification and tender documents, plus
contract administration
B.A.Sc. P.Eng. 12 -Project engineer to develop remedial cost estimates for Project #3
– Development of specifications and tender documents for the Deloro Mine Site Cleanup
– Construction engineer/contract administration for remediation of chlorinated solvents in soil
– Onsite supervision of hydrocarbon remediation at a site in the Yukon Territory
#3
Other
NOTE: The above tabular summary presents a concise overview with the following additional notations:
1. Please see appended resumes for further information on the experience and qualification of the project team
2. The project numbers in this column refer to Projects #1 to 4 presented in Section 1 – Where applicable, additional common projects where the team has worked together are shown as “other”
3. References have been limited to the projects in Section 1 – Additional references can be provided upon request
ENVIRONMENTAL CONSULTANT SERVICES REQUIRED TO COMPLETE A REMEDIATION STRATEGY FOR THE SYDENHAM PEARL BROWNFIELD SITE
431602_ES010612182309KWO 5-1
USE OR DISCLOSURE OF DATA CONTAINED ON THIS SHEET IS SUBJECT TO
THE RESTRICTION ON THE BACK OF THE TITLE PAGE OF THIS PROPOSAL.
5. Comprehensive Project Understanding, Approach, and Methodology
5.1 Introduction
The City retained CH2M HILL in March 2012 to provide environmental services for two properties known as the
Sydenham-Pearl Brownfield, located within Brantford at 17 and 22 Sydenham Street. The City required
environmental services to complete Phase One ESAs, Phase Two ESAs, and a review of remedial strategies to
support the redevelopment and/or potential sale of the site for residential/parkland land use. The recently completed
site assessment activities at the Site were initiated to assess the current subsurface environmental conditions and
develop technically-feasible and cost-competitive management strategies to manage impacted soil and groundwater.
The results of the Phase One and Phase Two ESAs recently completed by CH2M HILL between June and
September 2012 were documented in the following reports:
i. CH2M HILL Canada Limited (CH2M HILL). 2012. Phase One Environmental Site Assessment,
17 Sydenham Street, Brantford, Ontario. September 6, 2012, (CH2M HILL, 2012)
ii. CH2M HILL Canada Limited (CH2M HILL). 2012. Phase One Environmental Site Assessment,
22 Sydenham Street, Brantford, Ontario (Final Report). September 6, 2012, (CH2M HILL, 2012a)
iii. Phase Two Environmental Site Assessment, 17 Sydenham Street, Brantford. Prepared by CH2M HILL for
Brantford, dated September 26, 2102, Final Report, (CH2M HILL, 2012b)
iv. Phase Two Environmental Site Assessment, 22 Sydenham Street, Brantford. Prepared by CH2M HILL for
Brantford, dated September 26, 2102, Final Report, (CH2M HILL, 2012c)
Based on the results of the Phase Two ESAs, it was determined that the Phase Two Properties did not meet the
applicable Ministry of the Environment (MOE) Site Condition Standards for various contaminants of concern in both
soil and groundwater. Remediation of impacts above the Table 3 SCS would be required and/or the development of
property specific standards (PSS) under the completion of a risk assessment (RA) would be warranted, in order for a
Record of Site Condition (RSC) to be obtained for the Phase Two Properties.
Upon completion of the Phase Two ESAs, and as required as part of the previous scope of work, CH2M HILL
completed a Remedial Options Evaluation for each Phase Two property. The focus of the Remedial Options
Evaluations was to assess and evaluate various management strategies that could be employed to address the soil and
groundwater impacts identified during the completion of the recent Phase Two ESAs and that would facilitate the future
filing of a RSC for a future parkland/residential land use scenario. The reports also provided opinions regarding probable
cost to manage impacted soil and groundwater present at the properties. Based on the Phase Two ESA findings, this
evaluation considered general subsurface conditions, such as the degree of delineation of the contaminants of concern
(COCs), suspected volume of material requiring remediation, and potential pathway connections.
The results of the Remedial Options Evaluation recently completed by CH2M HILL for the subject properties were
documented in the following reports:
i. CH2M HILL Canada Limited (CH2M HILL). 2012. Remedial Options Feasibility Study, 17 Sydenham Street,
Brantford, Ontario, dated October 12, 2012, Final Report
ii. CH2M HILL Canada Limited (CH2M HILL). 2012. Remedial Options Feasibility Study, 22 Sydenham Street,
Brantford, Ontario, dated October 12, 2012, Final Report
As summarized in the above noted Remedial Options Evaluation reports, based on the review of environmental
management options and their comparison to the evaluation criteria, it was recommended that the City undertake the
steps to complete an RA for both Sites. It is anticipated that the RA will indicate that supplemental remediation efforts
(example, hot spot excavation) will likely be required to reduce reported maximum contaminant concentrations and
mitigate the off-Site migration of contaminated groundwater. In addition, for the 22 Sydenham Site it was further
ENVIRONMENTAL CONSULTANT SERVICES REQUIRED TO COMPLETE A REMEDIATION STRATEGY FOR THE SYDENHAM PEARL BROWNFIELD SITE
5-2 431602_ES010612182309KWO
USE OR DISCLOSURE OF DATA CONTAINED ON THIS SHEET IS SUBJECT TO
THE RESTRICTION ON THE BACK OF THE TITLE PAGE OF THIS PROPOSAL.
recommended that the limited excavation approach be completed in conjunction with the UST decommissioning
activities to achieve effective remediation of the Site.
5.2 Project Objective
CH2M HILL understands the project objectives to be as follows:
i. Obtain an RSC for each of 17 and 22 Sydenham Street, to facilitate the potential future redevelopment of the
properties for residential or parkland uses
ii. Improve the aesthetic appeal of each property by removing remaining construction demolition debris, and
concrete slabs and footings
The principal work activities to be completed to meet these objectives are:
i. Completion of an RA for each of 17 and 22 Sydenham Street to establish PSSs and to identify Risk
Management Measures (RMMs) required for future development. Completion of the RA will require
consultation and review by both the public and MOE and is estimated to require 10 months to complete
(detailed in Sections 5.3 and 6.1, Schedule)
ii. Refinement of the Remedial Strategy documents to meet the requirements of the RAs (detailed in
Section 5.4)
iii. Prequalification of contractors for construction of the anticipated Remedial Strategy (detailed in Section 5.5)
iv. Preparation of tender documents, tendering, and assisting the City with the award of a contract(s) to satisfy
the Remedial Strategy (detailed in Section 5.6)
v. Contract administration and construction oversight, acting as the City’s Engineer (detailed in Section 5.7)
vi. Project Management (detailed in Section 5.9)
vii. Filing of RSC for each of 17 and 22 Sydenham Street (detailed in Section 5.8)
viii. Communication strategy, including public information sessions and presentation to Council (detailed in
Section 5.10)
The following sections outline our proposed approach and methodology for meeting the project objectives.
5.3 Risk Assessments
Based on our current understanding of the soil and groundwater concentrations and the recommendations outlined in
the Remedial Options Feasibility Studies, the RA approach is considered the most practical and cost effective means
to obtain an RSC for the subject sites. One RA will be completed for 17 and one RA for 22 Sydenham Street, in
support of obtaining two separate RSC. CH2M HILL has had recent communication with the MOE that suggests that
a joint RA may be permissible under Regulation 153/04 for an area that will have two RSCs, and we will pursue this
approach further to provide, if one RA is permitted, additional efficiencies to the City.
CH2M HILL proposes to complete an RA to support a risk-based RSC, using the requirements set out under
O. Reg. 153/04, as amended. The main tasks will be as follows:
i. Task 1.1: Integrate data from Phase Two ESAs
ii. Task 1.2: Complete and Submit the Pre-Submission Forms (PSF) to the MOE
iii. Task 1.3: Complete the RA (Human Health and Ecological)
iv. Task 1.4: MOE Review Process and Issuance of a Certificate of Property Use (if required)
5.3.1 Integrate data from Phase Two ESA
The Phase Two ESA reports recently completed will provide input into the RA for ready use of the dataset
documenting maximum site concentrations.
ENVIRONMENTAL CONSULTANT SERVICES REQUIRED TO COMPLETE A REMEDIATION STRATEGY FOR THE SYDENHAM PEARL BROWNFIELD SITE
431602_ES010612182309KWO 5-3
USE OR DISCLOSURE OF DATA CONTAINED ON THIS SHEET IS SUBJECT TO
THE RESTRICTION ON THE BACK OF THE TITLE PAGE OF THIS PROPOSAL.
5.3.2 Complete and Submit Pre-Submission Form to the MOE
A Pre Submission Form (PSF) is completed early in the RA process as part of the initial Problem Formulation phase
of the RA. The PSF must be submitted by the Qualified Person for Risk Assessments (QPRA) before the completed
RA is submitted. The purpose of the PSF is to provide the MOE with information regarding the site from the
Phase One and Two ESAs, and to outline the receptor scenarios that are being included in the RA, as identified in
the Conceptual Site Model (CSM). This provides the MOE with the opportunity to comment on the scope and
approach chosen for the RA.
The City also retained CH2M HILL to assess the groundwater quality hydraulically downgradient of the subject sites.
Volatile organic compound (VOC)-impacted groundwater has been identified on both Sites, specifically chlorinated
aliphatic hydrocarbons (CAHs), including trichloroethylene (TCE), 1,1,1-trichloroethane (TCA), and their degradation
products. Additional soil and groundwater samples were collected as part of this additional work in the fall of 2012 to
assess the soil and groundwater quality at six off-Site drilling locations. In addition, a further round of groundwater
samples was collected from both the six off-Site wells as well as 21 selected on-Site wells. The results of the
additional soil and groundwater sampling conducted at both offsite and onsite locations recently completed by
CH2M HILL are documented in the following report:
i. CH2M HILL Canada Limited (CH2M HILL). 2013. Results of Additional Soil and Groundwater Sampling
Sydenham-Pearl Brownfield 17 and 22 Sydenham Street, Brantford, Ontario. February 7, 2013.
Based on the findings from the directly above-noted report, and the findings from the previously completed Phase
Two ESAs, it is anticipated that some limited additional intrusive investigation work will be required to address
potential issues that may be flagged by the MOE during their review of the PSF. More specifically, we anticipate the
need to install a few soil vapour probes as well as some limited additional soil and groundwater sampling to address
concerns that may be raised by the MOE during the review of the PSF. CH2M HILL has included a budget allowance
for this additional work, as outlined in the cost summary section of this proposal. Prior to conducting any additional
intrusive work, a work plan will be prepared for review and approval by the City in advance documenting the
proposed additional sampling and associated methodology and rationale.
For scheduling purposes, following our submission of the PSF to the MOE for review, the MOE will prepare a letter of
response concerning the scope of the RA and confirming the review timeline for the RA. To date, the MOE has not
established a timeframe for their review of the PSF, although they have an unofficial target of 4 to 6 weeks. Should
there be a significant delay in receiving comments on the PSF, portions of the RA could proceed to the draft report
stage. However, it will be necessary to wait for the MOE’s comments on the RA approach (as intended by the PSF)
before finalizing the RA.
5.3.3 Completion of the Risk Assessment (Human Health and Ecological)
The RA will be completed following the Procedures for the Use of Risk Assessment Under Part XV.I of the
Environmental Protection Act (MOE, 2005) and the generic risk approach presented by the MOE in their Rationale for
the Development of Soil and Ground Water Standards for Use at Contaminated Sites in Ontario (revised version
April 15, 2011). The receptor scenarios will focus on potential scenarios associated with the potential for residential
development.
Additional necessary information regarding plausible receptor exposure scenarios and the characteristics of the Site
will be determined during the data review and in consultation with others, to identify potential future Site activities.
Under O. Reg. 53/04, it is not sufficient to estimate the magnitude of risk to human health and the environment. As part
of the RA process, numeric PSSs must be determined for each COC, based on the methodology used in the RA. In
accordance with the regulation guidance, this would be addressed and included in Section 6 of the RA report.
Risk management may include strategies to limit receptors’ contact with COCs at the site, if deemed necessary as a
result of the risk evaluation. The RA will recommend RMMs that may be necessary to be protective of human and
ecological receptors, both on- and off-site. This Risk Management Plan (RMP) must identify exposure pathways and
environmental media that the RMP intends to address. The proposed risk management strategies would be included
ENVIRONMENTAL CONSULTANT SERVICES REQUIRED TO COMPLETE A REMEDIATION STRATEGY FOR THE SYDENHAM PEARL BROWNFIELD SITE
5-4 431602_ES010612182309KWO
USE OR DISCLOSURE OF DATA CONTAINED ON THIS SHEET IS SUBJECT TO
THE RESTRICTION ON THE BACK OF THE TITLE PAGE OF THIS PROPOSAL.
as Section 7 of the RA report. Conceptual design of RMMs, if needed, will be completed in the RA; detailed design
will need to be completed during site development engineering and planning, which is outside of our scope. Ensuring
that areas of the properties remain paved or covered would be considered risk management. Risk management
strategies may also include remediation to reduce contaminant exposure to the PSSs. The development of
remediation targets and risk management measures can be an iterative approach in which the balance between
remediation and Greenfield (concrete removal) restoration is considered and optimized to suit the City’s objectives. If
RMMs such as long term groundwater monitoring are required, the costs for such RMMs will not be included in the
scope of work, cost and scheduling considerations provided herein.
CH2M HILL will prepare a draft report in PDF and text in Microsoft Word format for review by the City. After we
receive the City’s comments, CH2M HILL will prepare the final report and provide the City with two signed hard
copies of the final report and one signed electronic copy in PDF format. Reports will be signed by the project QPRA.
Under O. Reg. 153/04 as amended, there are mandatory requirements for RA reports, and the report must include
sections as listed in Table 1 of Schedule C of O. Reg. 153/04. The MOE also mandates the number of copies for RA
submissions, and we will fulfill these requirements for distribution and submission of the RA. For the purpose of this
workplan and budget estimate, it has been assumed that one MOE review cycle will be required for
acknowledgement of the RA.
The City should be aware that it is often difficult to predict the time and level of effort that may be required to address
MOE PSF and RA review comments. Given the nature of the process, it has been our experience that, in many
instances, the MOE does not acknowledge and accept RAs following the first review, and they often have comments
and requested modifications that are required before acceptance. CH2M HILL has assumed an estimated budget to
address the MOE’s review comments. However, upon receipt of these comments, CH2M HILL will determine the level
of effort required to address them. If there are any potential budget implications as a result of the level of effort required,
CH2M HILL will prepare a scope change for review and approval by the City prior to proceeding with any additional
work. CH2M HILL has included some time during this process to generally liaise with the MOE and to provide updates
to the City. It is important that the City understand that, once comments are incorporated into the RA, the 16-week
timeline starts again (potential for up to 32 weeks of review or more if two RA submissions are required.
5.3.4 MOE Review Process and Issuance of a Certificate of Property Use (if required)
After the RA report is finalized, it will be submitted to the MOE for review. The current prescribed period of time (22
weeks for a Wider Area of Abatement [WAA] RA or 16 weeks if it is not designated WAA) for review begins when the
RA report is received by the MOE and the MOE confirms that the report meets the requirements of the regulation.
Once the MOE’s review is complete, the objective is to obtain formal MOE approval of the RA, which is a prerequisite
to filing the RSC.
The MOE may issue a Certificate of Property Use (CPU) for any property for which an RA has been completed; this
is issued at the discretion of the MOE Director, based on the results of the RA. Typically, if risk management is
required, a CPU will be issued to ensure the longevity of any RMMs. A CPU may limit use of the property, restrict
construction of certain types of buildings, or require certain actions (such as ongoing monitoring and reporting). The
municipality is notified when a CPU is issued; this may require registration of the property title and the provision of
financial assurance by the City or future developer/owner, if applicable. We expect that the local District Office of the
MOE will engage the City in the development of the draft CPU. We can review the CPU to verify content and
consistency with the RA. The draft CPU is then posted to the EBR for public review. As previously noted; if RMMs
such as long term groundwater monitoring are required in the CPU, the costs for such RMMs will not be included in
the scope of work, cost and scheduling considerations provided herein.
5.4 Review of Remedial Strategy
Once the Risk Assessments are completed and the Property Specific Standards (PSSs) have been established and
approved by the MOE, the final requirements for excavation and in-situ remediation or other remedial measures can
be finalized.
ENVIRONMENTAL CONSULTANT SERVICES REQUIRED TO COMPLETE A REMEDIATION STRATEGY FOR THE SYDENHAM PEARL BROWNFIELD SITE
431602_ES010612182309KWO 5-5
USE OR DISCLOSURE OF DATA CONTAINED ON THIS SHEET IS SUBJECT TO
THE RESTRICTION ON THE BACK OF THE TITLE PAGE OF THIS PROPOSAL.
Once the remediation targets are established, the conceptual design presented in the Remedial Options Feasibility
Study (ROFS) can be refined. The remedial excavation and in-situ remediation program will be tailored to the Site-
specific needs. The conceptual design in the ROFS can then be refined at this stage so that we can review the cost
estimate, prepare tender documents, support Brantford with the tender review and selection of a preferred contractor,
oversee execution of the remediation contract as the City’s representative (Owner agent), and collect confirmatory
samples and complete the associated reporting. Other initiatives related to greenfield restoration – such as concrete
and foundation removal – can be incorporated into the onsite remedial works program to optimize contractor
procurement and avoid conflicts between remedial and restoration objectives. We therefore recommend including
greenfield restoration activities in the remedial contractor’s scope of work.
5.5 Prequalification of Contractors
Subsequent to MOE review of the RAs and concurrent with their finalization for MOE approval, remediation
contactors will be prequalified for consideration for remediation activities as will be outlined in the tender
specifications to be prepared as summarized in Section 5.6. It is anticipated that:
i. The City will provide their ‘Request for Prequalification’ form (RFPQ) to CH2M HILL for use
ii. The RFPQ will functionally serve as a stand-alone information request as opposed to the first part of a 2-part
tender process
iii. CH2M HILL will revise the RFPQ form to identify the information to be supplied by prospective contractors
iv. The draft RFPQ will be supplied to the City for their review. It is anticipated that any review comments will be
received within one week. It is not anticipated that a meeting will be required with City technical staff at this
stage
v. The City will post the RFPQ on the City’s website and complete any advertising. CH2M HILL will provide
reasonable assistance to the City by identifying the name and contact particulars for any contractors it feels
may be interested or capable or responding. It is anticipated that information will be required from
prospective contractors three weeks after the RFPQ is posted
vi. A copy of the responses received will be provided to CH2M HILL by the City
vii. CH2M HILL will evaluate the responses and provide Brantford with a draft evaluation. One meeting will be
held in Brantford with City technical staff to review the draft evaluation
viii. CH2M HILL will finalize the evaluation including concerns raised at the meeting
ix. Brantford will manage contractor concerns/queries. CH2M HILL will not be the direct point of contact for the
contractors. CH2M HILL will provide reasonable assistance to the City in responding to question raised by
contractors.
5.6 Greenfield Restoration and Remediation Specification Preparation
This task will involve the development of technical specifications (tender documents) for the planned environmental
remediation work and concrete and foundation removal activities and associated site restoration of the subject facilities.
The general sequences of events that will need to be addressed in the technical specifications are as follows:
Mobilization and Site Preparation
Mobilize necessary resources to Site
Contractor control of Site security and health and safety
Establish Contractor Site facilities and utilities
Establish a project equipment and material handling areas
Foundation Removal Activities
Blind or disconnect utilities
Break all concrete or to a specified grade or depth
ENVIRONMENTAL CONSULTANT SERVICES REQUIRED TO COMPLETE A REMEDIATION STRATEGY FOR THE SYDENHAM PEARL BROWNFIELD SITE
5-6 431602_ES010612182309KWO
USE OR DISCLOSURE OF DATA CONTAINED ON THIS SHEET IS SUBJECT TO
THE RESTRICTION ON THE BACK OF THE TITLE PAGE OF THIS PROPOSAL.
Remediation Activities
Segregate at-grade and below-grade demolition waste streams
Excavate impacted soils (if applicable)
Other on Site/in-situ remedial strategies as outlined in the finalized Remedial Strategy reports (Sec. 5.4)
Collect stockpile samples for disposal characterization
Transport waste streams and soils to provincially-approved receivers
Site Restoration and Demobilization
Remove all demolition related materials from the Site
Fill all Excavations to Restore Site Drainage
The sequence of events would be summarized in the technical specification using the Master Specification
numbering format. The Master Specification formats used by CH2M HILL (bid documents, contract forms, and
contract conditions) are all formatted in accordance with the Engineer’s Joint Contract Documents Committee
(EJCDC®), while the Division 1 through 16 specifications follow the national guidelines of the Construction
Specifications Institute (CSI). An example table of contents prepared for a similar project is shown in Exhibit 5-1:
Exhibit 5-1 – Example Table of Contents
Spec No. Title
01000 General Requirements
01010 Summary of Work
01015 Site Access
01020 General
01030 Schedule
01040 Coordination
01200 Project Meetings
01300 Submittals
01645 Owner-Furnished Products
01700 Safety
01705 Training
01710 Interferences
01720 Permits
01730 Security
01735 Execution Plan
01740 Damages
01750 Utilities
01755 Temporary Facilities and Services
01760 Items Not Included in Project
01800 Tanks and Reservoirs
01810 Pits and Slabs
01815 Subsurface Structures
01820 Soil Compaction
01840 Cuts and Caps
01850 Site Work
01860 Scrap and Salvage
01870 Waste Disposal
01880 Air Monitoring, Dust, and Noise Control
01890 Material Control
02000 Earthworks and Environment
01101 Environmental General Requirements
01570 Environmental Management Plan
02080 Asbestos Removal
02201 Remediation Earthworks
02210 Petroleum Storage Tank Removal (if applicable)
02222 Designated Substances Management
ENVIRONMENTAL CONSULTANT SERVICES REQUIRED TO COMPLETE A REMEDIATION STRATEGY FOR THE SYDENHAM PEARL BROWNFIELD SITE
431602_ES010612182309KWO 5-7
USE OR DISCLOSURE OF DATA CONTAINED ON THIS SHEET IS SUBJECT TO
THE RESTRICTION ON THE BACK OF THE TITLE PAGE OF THIS PROPOSAL.
5.6.1 General Conditions and Agreement
CH2M HILL has assumed that the City will provide the general conditions, financial terms, and agreement terms for
the bid document and has not allowed for this task. CH2M HILL is able to assist the City in the development of these
documents; however, the City will ultimately be legally bound by these documents and should therefore develop them
in conjunction with legal counsel.
5.6.2 Review and Final Approval
CH2M HILL would propose to allow for two review stages in the preparation of the technical specifications. This will
allow CH2M HILL to break down the review of the document into manageable component sizes. The result will be a
more efficient review process, mitigating the potential for repetition and redundant language. The two review steps
will generally conform to the following:
60 Percent Review Stage. At the 60 percent review stage, CH2M HILL will provide the City with a completed
table of contents, the sections relevant to the proposed works, and a framework for the bid form and associated
documents. Our proposed schedule assumes that the City will return its review comments to CH2M HILL within
10 business days of receipt of the documents.
90 Percent Review Stage. At the 90 percent review stage, CH2M HILL will provide the City with the final draft
technical specifications. Our schedule assumes that the City will return its review comments to CH2M HILL within
15 business days of receipt of the documents.
Additional review stages caused by changes in the decommissioning scope of work after notice to proceed have not
been included in the cost estimates for the technical specifications.
CH2M HILL will assist the City in bidding the remediation and concrete and foundation removal work by attending the
Site tour and preparing an evaluation matrix for the bids. Addendum services during the bid period will also be
provided.
CH2M HILL will review the supplier quotations and request clarifications where appropriate. CH2M HILL will attend a
joint evaluation meeting to review the results of the tender request with the City where we will present our concerns
and recommendations. CH2M HILL will provide bound copies of the final technical specifications.
5.7 Contract Administration, Remediation/Greenfield Restoration Oversight and Reporting
This task will involve overseeing and executing the remediation contract as the City’s Representative (Owner agent).
It will also include the collection of confirmatory samples and preparation of associated reporting documenting the
remedial activities completed that will be required to support the planned filing of RSCs for the subject sites.
The key tasks and activities that will be completed are briefly summarized as follows:
i. Check that a site health and safety plan is in place
ii. Check that the contractor has a construction quality control plan
iii. Have a representative on-Site on a full-time basis (assumed 10 hrs/day, 5 days per week, for an estimated
period of 7 months) for remediation activities
iv. Oversee contractor activities and approach to ensure that remediation costs are minimized to the extent
possible through prudent staging and segregation of impacted soils
v. Monitor Site environmental management (noise, dust, runoff, traffic, etc.) as provided by the contractor
vi. Specify mobilization of support equipment, such as trailer, electrical, telephone, office equipment, etc.
vii. Monitor the daily activities of the remediation contractor, including dispute resolution and change order
management, track quantities as applicable and appropriate
ENVIRONMENTAL CONSULTANT SERVICES REQUIRED TO COMPLETE A REMEDIATION STRATEGY FOR THE SYDENHAM PEARL BROWNFIELD SITE
5-8 431602_ES010612182309KWO
USE OR DISCLOSURE OF DATA CONTAINED ON THIS SHEET IS SUBJECT TO
THE RESTRICTION ON THE BACK OF THE TITLE PAGE OF THIS PROPOSAL.
viii. Prepare daily site documentation requirements, including daily progress reports, daily work orders, field logs,
photographs, daily chronology of events, and visitor logs
ix. Facilitate weekly progress meetings with HHS and the remediation contractor
x. Monitor that regulatory reporting requirements are satisfied
xi. Monitor adherence to the technical specifications by the contractors
xii. Monitor the project schedule
xiii. Review contractor progress payment certificates and provide recommendations for payment as appropriate
xiv. Provide recommendation to the Owner when substantial completion has been achieved
xv. Prepare a written report documenting the remediation activities at the subject sites for inclusion in a final
revised Phase Two ESA Report for each site as required under O. Reg 153/04
5.8 Record of Site Conditions
Records of Site Conditions will be prepared for both 17 and 22 Sydenham Properties. The RSC summarizes the
environmental condition of the subject properties as determined by the Qualified Person (QP) for the subject sites,
which is then filed in the Environmental Site Registry. The type of information on an RSC includes site description,
property ownership, property use, site assessment information, certification statements by the owner and the QP,
remedial action/mitigation, and any supporting documentation. This task will involve the completion of the required
RSC application form for each of the subject sites (RSC completed using Property Specific Standards). Some of the
administrative information needed for these forms will require input and authorization from others and can be
obtained concurrent to the tasks described above.
The items required for RSC filing include:
Provided by the City:
i. Lawyer’s letter consisting of legal description
ii. Property deed, transfer or other document
iii. Current plan of survey
iv. Owner Certification statement
Provided by the MOE and data entry by CH2M HILL:
i. Table of PSSs with maximum site concentrations
Completed by CH2M HILL
i. List and Figure showing Areas of Potential Concern for each property
ii. Table of Current and Past Uses of property
iii. Phase Two Conceptual Site Model
CH2M HILL will compile the applicable RSC forms for submittal to the MOE. The MOE upon reviewing the
submission will provide a written acknowledgment of the filing to the owner and QP. If there are any deficiencies in
the submission (in our experience, this is often administrative details such as the plan of survey or lawyer’s letter), the
MOE will require us to resubmit the RSC. We will attempt to mitigate this through advance communication with the
MOE to verify that the documentation meets their requirements and have budgeted accordingly.
5.9 Project Management
A project management task has been included to provide general support to the City related to the proposed site
remediation activities, and to assist in the development, planning, and implementation of future subsurface remediation
and foundation removal tasks and associated decommissioning activities. Project management will be required to
ENVIRONMENTAL CONSULTANT SERVICES REQUIRED TO COMPLETE A REMEDIATION STRATEGY FOR THE SYDENHAM PEARL BROWNFIELD SITE
431602_ES010612182309KWO 5-9
USE OR DISCLOSURE OF DATA CONTAINED ON THIS SHEET IS SUBJECT TO
THE RESTRICTION ON THE BACK OF THE TITLE PAGE OF THIS PROPOSAL.
facilitate the implementation of the program and the management of the selected remediation contractor for completion
of the Site restoration and remediation work, and to assist the City in implementing the planned remediation activities
safely with an acceptable level of quality and in resolving problems and issues should they occur.
As shown in Section 5.10, CH2M HILL proposes to hold a project kickoff meeting, in Brantford, Ontario at City Hall
upon commencement of the project. The kickoff meeting will provide an opportunity for project team members to
discuss key project issues and procedures, obtain additional information, and discuss any clarifications or issues
related to the project schedule or changes to the scope of work. CH2M HILL has budgeted for our core project team
to attend the initial kickoff meeting. We have budgeted what, based on our experience on other projects, is an
appropriate level of effort for consultation and technical support to the City for issues related to environmental
requirements/remediation and general contract support.
5.10 Communications Strategy
It is important to develop a communication strategy to proactively involve stakeholders early and on a continued basis
in the project planning process, and to develop tailored activities and protocols to encourage and facilitate public
participation and communication in an open and transparent forum. Early and continued consultation and dialogue is
important for stakeholders – particularly for a complex project of long duration with significant community interest.
The City has initiated communication through neighbourhood meetings and presentations at the Brownfields
Community Advisory Committee. Leveraging the communication networks currently in place and established by the
City, our communication strategy is based on the following objectives:
i. To conduct open and inclusive activities that will engage a broad spectrum of the community in the project
ii. To provide sound science and technical information in an accessible and understandable format
iii. To focus effort on the Project rather than other agendas
iv. To provide diversity in opportunities to participate
v. To track and manage issues throughout the project to achieve community support and endorsement in the
project
We suggest five meetings with the City’s technical team as part of the Scope of Work: (1) Kick-off; (2) RA review;
(3) finalization of remedial options; (4) review of bids; and (5) remediation closure. Three points of public engagement
are planned as part of the Scope of Work and include Brownfields Community Advisory Committee presentations and
neighbourhood meetings (or public information session): (1) summarize the work previously completed and the scope
and anticipated outcomes of the current scope of work; (2) present the findings of the RA, finalization of remedial options
and timing and presentation of the remediation team; and (3) remediation closure. We propose to present the final
remedial results and RA to City Council after the completion of the project. We also understand that the City’s technical
team will be updating Council from time to time, and to that end, we will provide support with the information updates.
Details on the key presentations are provided in Exhibit 5-2. The project schedule in Appendix B provides proposed
dates for the five meetings with the City technical team, the three public meetings and the City Council meeting. It is
anticipated that these dates will be rescheduled to accommodate both project progress and City technical staff and
Council schedule constraints.
We anticipate that our role in attending the public engagement meetings will be to provide a display of project
information, make a brief presentation followed by a question and answer period, and prepare “take-away” materials
for easy reference following the session. As before, the City will arrange the location and will prepare a Notice of
Neighbourhood Meeting and direct mailing to the elected officials for that area, government and non-government
offices (such as the Grand River Conservation Authority), and special interest groups. Materials for the meetings will
be prepared in draft form for review and approval by the City prior to production. Once finalized, the material will be
provided to the City for posting to the City’s website.
Our team recognizes that attendance at public meetings is just the beginning in engaging members of the public and
public advisory groups. We are adept at preparing and delivering significant amounts of technical information in easily
ENVIRONMENTAL CONSULTANT SERVICES REQUIRED TO COMPLETE A REMEDIATION STRATEGY FOR THE SYDENHAM PEARL BROWNFIELD SITE
5-10 431602_ES010612182309KWO
USE OR DISCLOSURE OF DATA CONTAINED ON THIS SHEET IS SUBJECT TO
THE RESTRICTION ON THE BACK OF THE TITLE PAGE OF THIS PROPOSAL.
understood terms, as is evident through the three project examples presented in Section 1. Our team anticipates that
public concerns with this project may be consistent in theme with the issues identified during other brownfield
activities in the City and elsewhere. Accordingly, we have identified the following potential community interests that
will require attention during the meetings: noise, sustainability, public health and safety, air quality, groundwater
protection, waste materials, access to information, traffic, post- and during-construction aesthetics, and short-
term/long-term use. CH2M HILL’s dedicated public communication strategy lead, Meggen Janes, will take the
initiative in anticipating and addressing the public’s concerns and interest areas. She will lead the development of the
presentation tools with input from the project team and attend the public meetings. Our team will use the intelligence
gathered through the Brownfields Community Advisory Committee meeting to fine-tune the critical components of the
overall remedial strategies presentation for the neighbourhood meeting. Similarly, the neighbourhood meeting will be
used to gather additional public insight on concerns regarding the remediation/risk management.
Exhibit 5-2 shows an outline and schedule of the proposed public information sessions.
Exhibit 5-2 – Proposed Public Information Sessions
Public Information Session #1 (June 27, 2013)
Purpose A brief overview of existing environmental conditions to be addressed
Outline the overall plan for the project and provide a forum to discuss key aspects of the plan and what it means
for the community
Respond to issues that may have arisen to date
Key Content Explain purpose of the project and what the community can expect when it is complete
Overall high-level assessment of the risk
Report on findings of the off-site investigation
Major and minor project activities and sequencing
High-level review of project schedule and schedule for construction
“Things to Know and What to Expect”
Contact names and information for Questions Update on remedial options
Next steps
Expected
Outcome
The opportunity to engage directly with the community upon project initiation will encourage adaptive management
to facilitate continued efforts to deliver a successful project (as determined by both the project team and the
community).
Value to the
Project
With the opportunity to obtain current community opinions and concerns we will be able to adapt future
presentations and written materials to include responses to community concerns, thereby improving the chances
for community acceptance of the project objectives and outcomes.
Public Information Session #2 – Presentation of Remediation Team (September 4, 2014)
Purpose Present an overview of the RA and finalization of remedial options and timing
Introduce the construction team to the community prior to the commencement of activities onsite
Outline the overall plan for the construction program and provide a forum to discuss key aspects of the plan and
what it means for the community
Key Content Report on findings of the RA, and finalization of remedial options
Major and minor construction activities and sequencing
Schedule for construction
Mitigation and monitoring, contingency plans and what they mean
“Things to Know and What to Expect”
Contact names and information for Questions Update on remedial options
Explanation and graphic presentation of the steps in the construction process, including timing of major activities
and approvals, where the soil is going, the community engagement and communications plans, and contact
information
Community concerns and initial actions
Emergency and contingency planning
Next steps
ENVIRONMENTAL CONSULTANT SERVICES REQUIRED TO COMPLETE A REMEDIATION STRATEGY FOR THE SYDENHAM PEARL BROWNFIELD SITE
431602_ES010612182309KWO 5-11
USE OR DISCLOSURE OF DATA CONTAINED ON THIS SHEET IS SUBJECT TO
THE RESTRICTION ON THE BACK OF THE TITLE PAGE OF THIS PROPOSAL.
Expected
Outcome
The opportunity to engage directly with the community after the completion of the RA will encourage adaptive
management to facilitate continued efforts to deliver a successful project (as determined by both the project team
and the community).
Local residents and business owners will have an increased awareness of the projects and key activities to expect.
This will be the first contact between the project team and the community, as well as an opportunity to establish a
public relationship and develop profile for the project.
Value to the
Project
Our team will use the information generated through the efforts of Public Information Session #1 to help fine-tune
the critical components of the overall project. We will also have a clearer understanding of the current community
concerns and issues and will be able to begin to address them before the start of major construction activities.
Public Information Session #3 – Remediation Closure (March 12, 2015)
Purpose Update the community on the construction phase of the project and any follow-up requirements
Provide details on construction completion (demobilization), post-construction activities, restoration, reporting,
approvals and Year 1 monitoring activities
Key Content Status review of major and minor construction activities, challenges encountered, change management issues,
success stories
Update on schedule for Project completion and schedule for short-term/long-term ongoing activities
“Things to Know and What to Expect” for the final phases of activities
Contact names and information for questions
Expected
Outcome
Community members will have information on the remainder of the planned project activities, including what to
expect and when. They will also be provided with a take-away Facts Sheet with key reminders and contact
information for the post-construction period.
Value to the
Project
Because the Project may continue for some time following the physical construction stage, this point of contact with
the community will demonstrate our commitment to continued communication during the final stages of the project.
The team will also be able to gain an indication of the community’s collective opinion on the success of the Project.
Presentation to Council (April 20, 2015)
Purpose Update Council on the remediation and short-term/long-term risk management requirements
Provide details on construction completion (demobilization), post-construction activities, restoration, reporting,
approvals and Year 1 monitoring activities
Report on the public consultation process or other public feedback on the Project
Key Content Status review of major and minor construction activities, challenges encountered, change management issues,
success stories
Actual cost against budget; value-added components, and cost savings
Update on future Site requirements and schedule
Public consultation statistics
Expected
Outcome
Council will have information on the closure of the remediation and the future requirements, including what to
expect and when.
Value to the
Project
The Project continues following the physical construction stage, so this point of contact with the Council will serve
as a final wrap-up of the remediation results and provide information on next steps.
ENVIRONMENTAL CONSULTANT SERVICES REQUIRED TO COMPLETE A REMEDIATION STRATEGY FOR THE SYDENHAM PEARL BROWNFIELD SITE
431602_ES010612182309KWO 6-1
USE OR DISCLOSURE OF DATA CONTAINED ON THIS SHEET IS SUBJECT TO
THE RESTRICTION ON THE BACK OF THE TITLE PAGE OF THIS PROPOSAL.
6. Project Schedule, Costs and Work Plan
6.1 Project Schedule
The anticipated project schedule, attached as Appendix B, shows the proposed timing of tasks and related
interdependencies. Task lengths were based on the anticipated level of effort that is shown in the Resource
Allocation Matrix (RAM), entitled “Hours Breakdown by Task,” which is also included in Appendix B.
The schedule of major project tasks outlined in Exhibit 6-1 is based on an anticipated project approval date of
May 15, 2012.
Exhibit 6-1 – Schedule of Major Project Tasks
RA, from PSFs to MOE approval of draft RAs June 2013 to April 2014
Review of remedial strategy April 2014 to May 2014
Contract administration and construction oversight May 2014 to March 2015
Remediation report, finalization of RA and filing of RSC March 2015 to May 2015
The following will be occurring concurrent with the major project tasks shown above:
i. The communication program – including meetings with City technical staff, public meetings and the meeting
with Council – will be ongoing from June 2013 to April 2015
ii. Project management activities will be ongoing from project initiation in June 2013 through to anticipated
project completion in May 2015
The project schedule includes a project contingency period of approximately 3 months from late May to early August
2015. The project schedule as shown is based on CH2M HILL’s professional experience. The City will be kept
informed of significant changes in the project schedule as they occur. For the filing of the RSC we have assumed that
the RSC can be filed immediately upon completion of the remediation and that there is no long term groundwater
monitoring to be complete per O. Regulation 153/04 prior to filing the RSC.
The project schedule does not include any post-remediation environmental monitoring requirements, as the nature
and scope of these requirements cannot be known until the completion of the RA and remediation activities.
Environmental monitoring requirements that may be reasonably anticipated would include soil vapour assessment
activities, additional groundwater monitoring activities, and maintenance of any barrier or other in-situ treatment
systems.
6.2 Project Costs and Work Plan
The Resource Allocation Matrix provided in Appendix B provides a summary of the anticipate level of effort by
individual project team members for the major project work elements. The RAM indicates project costs of $966,937
plus applicable taxes. Considerations in the calculation of these costs included the following:
i. Hourly rates for staff are similar to those provided to the City for previous work associated with the Site.
ii. Costs will be incurred on a time and materials basis to the limits shown on the RAM.
iii. The RA budget includes an allowance for additional intrusive work. The need for and potential scope of this
work cannot be known until completion of RA activities.
iv. The budget for finalization of the Remediation Strategy includes an allowance for some additional intrusive
work. The need for and potential scope of this work cannot be known until the Remediation Strategy is
complete.
ENVIRONMENTAL CONSULTANT SERVICES REQUIRED TO COMPLETE A REMEDIATION STRATEGY FOR THE SYDENHAM PEARL BROWNFIELD SITE
6-2 431602_ES010612182309KWO
USE OR DISCLOSURE OF DATA CONTAINED ON THIS SHEET IS SUBJECT TO
THE RESTRICTION ON THE BACK OF THE TITLE PAGE OF THIS PROPOSAL.
v. Costs associated with construction oversight are based on a construction period for remediation activities of
7 months. As CH2M HILL’s true costs for construction oversight cannot be known at this time, these costs
are based on the allowances included in the Remediation Strategy reports previously submitted to the City
(CH2M HILL, 2012b) and (CH2M HILL, 2012c).
vi. It is assumed that costs can be transferred between work activities shown on the RAM based on project
needs as they occur.
vii. The time period for final review and approval of the RA and RSC by the MOE is beyond the control of
CH2M HILL, and we cannot predict with a great degree of certainty the exact date when the RSC will be
accepted.
viii. It is CH2M HILL’s understanding that others will assume responsibility for certain documentation required by
the MOE related to the deed/land transfer; therefore, CH2M HILL is not responsible for any delays resulting
from this task which may impact final RSC acceptance date.
ix. Actual time to complete the work may vary depending on a number of factors, only some of which are directly
controlled by CH2M HILL.
We will work in a collaborative manner with the City to drive additional cost efficiencies and implementation
improvements at the Sydenham-Pearl Brownfield. We will continually search for ways to improve our performance
and achieve a cost-effective remediation and risk assessment approach.
We do this by:
i. Providing regular updates on regulatory changes and trends in the market place so we can make informed
decisions and advise the City on the requirements for the sites. For instance, as previously noted,
development of one RA instead of two may provide some cost savings.
ii. Remedial process optimization through decision science tools and processes to optimize remedial plans.
iii. Reductions in monitoring to identify actions that will result in the same objective being achieved but through
less expensive means.
iv. Collaborating with the City on the decision making to integrate their land re-use strategy with the risk
assessment with a goal to come up with the highest economic and environmental value of the land.
v. Using a procurement system and contract development basis to apply sound business practices to
procurement activities and help the City achieve best value in acquired goods and services.
vi. Preparing scopes of work for each task to pre-define project specific requirements, overall productivity and
performance and to clearly define strategic objectives. This is then leveraged for capture of improvement
opportunities and value added in cost savings, cost avoidance or new asset value.
vii. Applying our volume discounts from our regular subcontractors to the City. Occasionally, opportunities also
arise with our remedial contractors where savings can be found due to our ability to either manage the
schedule of the project or leverage the overall work we are doing to pass on savings to the Client. On one
project, we were able to renegotiate hazardous waste disposal rates with a waste receiver in the middle of a
project that resulted in a savings of approximately $1M.
viii. Leveraging our familiarity with the project to jump start the next phase of risk assessment and remediation.
6.3 Project Terms and Conditions
CH2M HILL proposes to perform the services detailed herein in accordance with the same terms as set out in the
duly executed Agreement dated March 14, 2012 by and between the City and CH2M HILL.
431602_ES010612182309KWO
USE OR DISCLOSURE OF DATA CONTAINED ON THIS SHEET IS SUBJECT TO
THE RESTRICTION ON THE BACK OF THE TITLE PAGE OF THIS PROPOSAL.
Appendix A
Résumés
1
Edgar H. Taves
Project Lead
Education
M.Sc. (Biochemistry), University of Western
Ontario
B.Sc., Double Honours (Chemistry and Biology), University of Waterloo
Professional Registrations
P. Geo., Limited (Ontario)
QPESA under O.Reg. 153/04
C.Chem.
Distinguishing Qualifications
Over 21 years of professional experience in environmental consulting
Specializes in environmental due diligence assessments (Phase I and II Environmental Site Assessments
[ESAs]), site characterization, risk assessment, remedial option analysis, contaminant hydrogeology, facility
decommissioning and Brownfield redevelopment, preparation of Record of Site Conditions (RSCs), regulatory
compliance, site assessment plans and environmental management, waste site evaluation, site investigation
and remediation, remedial planning, data analysis and interpretation, and hazardous waste management.
Relevant Experience
Ed Taves has over 21 years of professional experience in environmental consulting. He specializes in environmental
due diligence assessments (Phase I and II ESAs), site characterization, risk assessment, remedial option analysis,
contaminant hydrogeology, facility decommissioning and brownfield redevelopment, RSC preparation, regulatory
compliance, data analysis and interpretation, and hazardous waste management. Clients have included a variety of
federal and provincial departments and ministries, municipal governments, industries, as well as members of the
legal, financial, accounting, and land development communities. Projects have been completed for a wide variety of
contaminants including petroleum hydrocarbons (PHCs); a variety of volatile organic carbons (VOCs) including
chlorinated aromatics and polynuclear aromatic hydrocarbons (PAHs); a variety of metals; polychlorinated biphenyls
(PCBs); pesticides; nutrients such as phosphorus and ammonia; energetic, unexploded ordnance; chemical warfare
agents, and radiologicals. He has acted in a number of roles including project manager, task manager, senior technical
consultant, and public and regulatory agency liaison.
Representative Projects and Dates of Involvement
Project Lead; ESA and Preparation of Remediation Strategy; Sydenham Pearl Brownfield; City of Brantford;
Brantford, Ontario; 2012. The Sydenham Pearl Brownfield consists of two parcels of land in downtown Brantford,
both with industrial legacies dating back to the early 1900s. CH2M HILL was retained to conduct Phase One and Two
ESAs, and to prepare a Remedial Action Strategy to revitalize the properties for potential residential development.
Work included consultation with city staff, a public meeting, and presentations to City Council. Work was completed
to the satisfaction of the City, the public, and City Council, and resulted in the approval of funds for implementation
of the remedial strategy.
Environmental Task Manager, Senior Environmental Scientist; Former Amherstburg Manufacturing Facility,
Environmental Site Assessment, Risk Assessment, Remedial Planning, Contract Administration and Demolition
Oversight; Confidential Client, 2010 to Present. CH2M HILL was retained to provide environmental advisory and
construction management services for the decommissioning of a large abandoned chemical manufacturing facility.
Services provided have included Phase Two ESAs, Risk Assessment activities, preparation of tender documents and
tendering for facility demolition and remediation services, project administration and construction oversight.
Work is being conducted with regular consultation with the client, the public, and municipal and regulatory
personnel. Onsite environmental activities have been coordinated with the demolition of over 300,000 ft
2
of
Edgar H. Taves
2
manufacturing space, with strict observance of health and safety protocols. Responsible for the design and
implementation of intrusive field programs for the characterization of soil and groundwater quality, and for
management of the completion of risk assessment activities. Intrusive field activities were coordinated with a
large scale demolition project, requiring ongoing vigilance regarding the health and safety of field personnel.
Senior Environmental Scientist; West Don Lands; Ontario Infrastructure and Lands Corporation (IO); Toronto,
Ontario; 2010 to Present. The largest brownfield site currently under development in Ontario, this former
industrial site will encompass mixed‐use residential and commercial development, as well as a substantial
parkland component, after it serves as the Pan American Athletes’ Village (PAAV) for the 2015 Pan/Parapan
American Games (Pan Am Games). The PAAV will house over 8,000 athletes and coaching staff. This revitalization
project involved an aggressive schedule to secure the environmental approvals required in advance of
infrastructure and building construction by development partners. Site characterization, risk assessment (RA),
remedial option feasibility studies (ROFSs), remediation, and risk mitigation measures (RMMs) are key project
components. CH2M HILL Canada Limited (CH2M HILL) conducted field investigations and prepared multiple Phase
One and Phase Two environmental site assessment (ESA), ROFS, and RA reports in parallel in order to meet the
development schedule. The reports complied with Ontario Regulation (O. Reg.) 153/04 under the Environmental
Protection Act, as amended by O. Reg. 511/09, such that Records of Site Condition (RSCs) will be obtained on
properties prior to development. Currently, CH2M HILL is acting as the third‐party Ontario Ministry of the
Environment (MOE) Qualified Person (QP) to audit compliance with the Certificates of Property Use (CPUs) and
RAs during the implementation of the RMMs.
In October 2011, the WDL project was selected by the Canadian Urban Institute for the 2011 Brownie Award as
the project that best demonstrated Excellence in Project Development at the Neighbourhood Scale. The annual
Brownie Awards program recognizes leadership, innovation, and environmental sustainability in brownfield
redevelopment across Canada.
Providing senior review functions for the completion of Phase I and II ESA, and risk assessment programs. The subject
site includes a large block of land with a wide variety of industrial occupancy over a 150‐year period. A variety of
assessment methods and remedial solutions are being implemented to facilitate the intended completion of
numerous RSCs for varying end land uses.
Project Manager / Senior Environmental Scientist; Environmental Advisory Services, Historical Chemicals Plant;
Reichhold Inc. Facility; Brampton, Ontario; 2010 to Present. Providing environmental advisory and management
services as required for the management of environmental conditions associated with a former chemicals plant.
Services provided include preparation and implementation of an annual groundwater quality monitoring program,
liaison with neighbouring land owners, soil gas sampling activities in support of a risk assessment program;
monitoring of an ongoing phytoremediation program.
Project Manager and Senior Consultant; Environmental Assessment of Shamrock Industrial Subdivision; City of
London; London, Ontario; 2007 to 2009. Project Manager for the investigation of latent environmental liabilities
in association with a 5‐hectare (ha) Brownfield property which was contaminated with various industrial and
municipal wastes including pesticides, solvent and metals. The City of London was considering acquiring the site
subsequent to a failed tax sale. Due diligence activities were completed, including detailed Phase I and II ESAs,
remedial options analysis and cost estimating. Several presentations were made to municipal Council.
Project Manager; Environmental Investigation in Support of a Property Transaction; Natrel Inc.; London,
Ontario; 2005 to 2007. Managed the completion of due diligence activities in support of the divestiture of a parcel
of Brownfield land known to be contaminated with free phase coal gasification wastes. Managed negotiations
between the vendor and the City of London. Environmental risks were successfully characterized and the property
title was successfully transferred.
1
Brian Whiffin
Principal/Senior Advisor
Education
M.Eng., Civil Engineering, University of Ottawa (jointly with University of Waterloo)
B.A.Sc., Civil Engineering, University of Waterloo
Professional Registrations
Professional Engineer: Ontario
Relevant Experience
Brian Whiffin’s career has encompassed a variety of hazard evaluation and liability management projects for
chemical, biological, radioactive, and explosive risk. This has included characterization and reduction of risk/
liability from environmental, waste and munitions. He has filled a number of roles including project and program
management, senior technical consultant, and regulatory agency liaison.
Representative Projects and Dates of Involvement
Principal/Senior Advisor; Environmental Site Assessment (ESA) and Preparation of Remediation Strategy;
Sydenham Pearl Brownfield; City of Brantford; Brantford, Ontario; 2012. The Sydenham Pearl Brownfield consists
of two parcels of land in downtown Brantford, both with industrial legacies dating back to the early 1900s.
CH2M HILL was retained to conduct Phase One and Two ESAs, and to prepare a Remedial Action Strategy to
revitalize the properties for potential residential development. Work included consultation with city staff, a public
meeting, and presentations to City Council. Work was completed to the satisfaction of the City, the public, and City
Council, and resulted in the approval of funds for implementation of the remedial strategy.
Senior Consultant; Wellington Block Redevelopment; Hamilton Health Sciences; Hamilton, Ontario; 2003 to
ongoing. Phase I and II ESAs, designated substance survey, risk assessment (RA) and remedial options related to
acquisition/redevelopment of a former wire/ nail manufacturing plant, asphalt plant, and rail lands under a failed
tax sale.
Project Manager; Risk Assessment for Portlands Divestiture; Public Works and Government Services Canada
(PWGSC); Port Stanley, Ontario; 2008 to Present. A Risk Assessment and supplemental investigation was
completed of sediment contamination in waterlots and soil/groundwater conditions in uplands associated with
the proposed divestiture of federal lands to a local municipality. The Risk Assessment was completed to federal
and provincial standards leading to filing of a Record of Site Condition (RSC).
Project Manager; Deloro Mine Site Cleanup; Ontario Ministry of the Environment (MOE); Belleville, Ontario;
1997 to 2010. Rehabilitation of the Deloro Mine and Smelter site (estimated $40M +) involving a risk‐based
evaluation and closure of mine wastes, smelting residues, pesticide wastes, and tailings for a facility that refined
or produced gold, cobalt, silver, stellite, and arsenic since the late 1800s. Low‐level radioactive residues are
present on the site from re‐processing of by‐products from Eldorado Nuclear in Port Hope, Ontario. CH2M HILL is
leading the Federal Environmental Assessment (EA) and Licensing Application to fulfill Canadian Nuclear Safety
Commission (CNSC) requirements.
Principal/Senior Engineer, Regional Individual Standing Offer (RISO) for Environmental Site Assessments in
Ontario, 2010 to date. Coordinated a multi‐disciplinary team for a suite of call‐ups for Phase One and Two ESAs,
sediment investigations, risk assessments, remediation options evaluations at federal sites across Ontario.
Provided senior engineering/consulting expertise and acted as the main point of contact with PWGSC for project
performance.
Project Manager/Senor Engineer; Standing Offer for UXO, Environmental, and Cultural Resources
Investigations; DCC; Former Camp Ipperwash, Ontario; 2010 to Present. Lead a multidisciplinary team
Brian Whiffin
2
conducting a suite of services UXO and, environmental and cultural investigations to quantify DND’s legacy from
previous military training exercises.
Project Manager/Senior Consultant; Several Demolition/Dismantling, Decommissioning, Waste Management
and Infrastructure Renewal Projects; Atomic Energy of Canada Ltd (AECL); Chalk River, Ontario; 2004 to 2008.
Projects include: (i) B‐204 Dismantling and Demolition, (ii) Conceptual Options Evaluation for new fuel bays at the
National Research Universal (NRU) reactor; (iii) Pathway Analysis for Bulk Materials Landfill; (iv) Conceptual Design
for a Non‐Active Landfill; (v) Sediment Remediation Feasibility Study. Also acted as the Client Service Manager and
conducted the senior review on the Stored Liquid Wastes Management Project at Chalk River.
Senior Regulatory Advisor/Senior Engineer; Faro Mine Complex Remediation and Closure Planning (FMRP)
Project; Government of Yukon (YG); Faro, Yukon; 2012 to Ongoing. CH2M HILL is supporting the Government of
Yukon, Assessment and Abandoned Mines Branch as the Project Design Team for the FMRP. In this role,
CH2M HILL is providing engineering and regulatory technical services, as well as management and planning
support. The scope of these services includes all facets of site assessment, remediation, and closure; environment
and socio‐economic assessment; and regulator permitting as needed. Work performed includes hydrogeology,
geochemistry, geotechnical engineering, hydrogeology, hydrology, biophysical assessment, and water
treatment. The project poses unique challenges in its size and complexity, requiring building a team of
multidisciplinary subject matter experts from across North America, and in its remoteness, which increases the
level of rigour required to plan and execute the work. The two project clients, YG, and Aboriginal Affairs and
Northern Development Canada (AANDC), have recognized that the Faro Mine Complex remediation and closure is
a top priority among environmental work in the Yukon and Canada; as such, CH2M HILL is providing timely,
technical, and strategic advice to achieve successful delivery. Acted as senior regulatory reviewer and advisor to
develop the regulatory approvals strategy, complete stakeholder consultation and prepare a project proposal for
a $500M capital waste management/remediation project.
Senior Project Advisor; Huron Campus Remediation; Algonquin College; Ottawa, Ontario; 1988 to 2000. The
development of a remediation strategy, investigation and subsequent $800K remediation of a former bulk
petroleum facility in Ottawa. Site cleanup was conducted in accordance with the MOE’s 1997 guideline and lead to
the issuance of an RSC.
Project Manager; Former Imico Foundry Property Use Study; City of Guelph; Guelph, Ontario; 2003 to 2004.
CH2M HILL is leading a multi‐faceted team to assist the City of Guelph in identifying viable options for
redevelopment of this Brownfield site through consideration of market demand, planning considerations,
infrastructure conditions and environmental constraints. The study will lead to a recommended redevelopment
option for the site.
Senior Advisor Peer Review; Community Based Risk Assessment (CBRA), ERA; City of Port Colborne; Port
Colborne, Ontario; 2003. Peer review of a comprehensive project to assess the level of risk related to atmospheric
deposition of metal‐containing precipitates, primarily nickel, on the natural environment.
Environmental Remediation Advisor; Harbourfront Revitalization Strategy and Secondary Plan; City of Port
Colborne; Port Colborne, Ontario; 2004 to 2004. Part of a multi‐disciplinary team formed to develop a
revitalization strategy for redevelopment of lands impacted by smelter emissions and previous industrial use.
Project Manager/Remediation Specialist; Toronto Waterfront: Portlands Preparation; Toronto Waterfront
Revitalization Corporation (TWRC); Toronto Ontario; 2002 to 2005. $60M in seed funding was allocated by three
levels of government to provide the necessary infrastructure and environmental remediation needed to attract
private sector development to Toronto’s waterfront. The subject lands comprise 1,000 acres of under‐utilized real
estate in the Port Lands and WDL bordering on the waterfront. The Corporation prepared a business plan and
development plan, and is leading implementation over the next 20 years.
Senior Consultant; Environmental Monitoring of the Meaford Tank Range; Meaford, Ontario; PWGSC; 2007 to
2008. Senior technical review of environmental monitoring, interpretation, and reporting.
1
James G. Sprenger
Principal/Senior Advisor
Education
B.Sc., Biochemistry, University of Waterloo
M.Sc. (Candidate), Occupational and Environmental Health, University of Toronto
Distinguishing Qualifications
Extensive experience conducting human health and environmental risk assessment supporting remediation
and property redevelopment
Experience assessing metals, inorganics, volatile organics, petroleum hydrocarbons, semi‐volatile organics,
and some pesticides
Extensive experience conducting environmental compliance audits for a variety of clients
Qualified Person for Risk Assessment (QPRA) (Ontario Regulation [O.Reg] 153/04, via Ontario Ministry of the
Environment [MOE])
Relevant Experience
James Sprenger has more than 20 years of experience in environmental consulting, including 18 years of human
health risk assessment (HHRA) of contaminated sites, and 12 years of environmental compliance auditing. He has
managed environmental site investigations and human health risk assessments (HHRA) related to environmental
projects, contaminated site decommissioning, and site assessment. He also has experience with industrial and mine
closure projects, providing industrial hygiene support and consultation. He has developed toxicological exposure
models and databases for HHRAs. James has experience with Canadian (Canadian Council of Ministers of the
Environment [CCME], Ontario, British Columbia, Alberta, Quebec, and Atlantic provinces) and United States
frameworks for risk assessment (New York, New Hampshire, Massachusetts) including U.S. Environmental Protection
Agency Superfund and American Society of Testing and Materials (ASTM) risk‐based corrective action tiered
framework. He has completed numerous probabilistic assessments and deterministic risk assessments (RA). James
has experience in applying risk assessment to hydrogeological problems, including the use of hydrogeological
pathways into exposure assessment models. He also has experience using risk‐based hydrogeological screening
models to understand contaminant degradation, dispersion, and advection.
James was accepted as a QPRA by the MOE in December 2004, having prepared more than five pre‐submission
forms (PSF) and contributed to many others. His current project portfolio includes eight RAs with human and
ecological aspects, as well as providing RA review, advice, and support for industrial site closure and Toronto
waterfront initiatives.
Representative Projects and Dates of Involvement
Risk Management Measures; Environmental Site Assessment (ESA) and Preparation of Remediation Strategy;
Sydenham Pearl Brownfield; City of Brantford; Brantford, Ontario; 2012. The Sydenham Pearl Brownfield
consists of two parcels of land in downtown Brantford, both with industrial legacies dating back to the early
1900s. CH2M HILL was retained to conduct Phase One and Two ESAs, and to prepare a Remedial Action Strategy
to revitalize the properties for potential residential development. Work included consultation with city staff, a
public meeting, and presentations to City Council. Work was completed to the satisfaction of the City, the public,
and City Council, and resulted in the approval of funds for implementation of the remedial strategy.
Environmental Manager/Senior RA Advisor; Former Amherstburg Manufacturing Facility, Environmental Site
Assessment, Risk Assessment, Remedial Planning, Contract Administration and Demolition Oversight;
Confidential Client, 2010 to Present. CH2M HILL was retained to provide environmental advisory and
construction management services for the decommissioning of a large abandoned chemical manufacturing
facility. Services provided have included Phase Two ESAs, Risk Assessment activities, preparation of tender
documents and tendering for facility demolition and remediation services, project administration and
construction oversight. Work is being conducted with regular consultation with the client, the public, and
James G. Sprenger
2
municipal and regulatory personnel. Onsite environmental activities have been coordinated with the demolition
of over 300,000 square feet of manufacturing space, with strict observance of health and safety protocols.
Senior Risk Assessor; Quantitative RA of Chemicals in Soil and Groundwater at Former Industrial Facility;
Hamilton Health Sciences; Hamilton, Ontario; 2004 to 2007. Conducted risk assessment screening and provided
input into field investigations to support RAs. Completed and submitted a MOE pre‐submission form and
performed a quantitative HHRA of chemicals detected in soil and groundwater. The RA was completed under
O. Reg. 153/04 framework.
Lead Risk Assessor; West Don Lands; Ontario Infrastructure and Lands Corporation (IO); Toronto, Ontario;
2010 to Present. The largest brownfield site currently under development in Ontario, this former industrial site
will encompass mixed‐use residential and commercial development, as well as a substantial parkland component,
after it serves as the Pan American Athletes’ Village (PAAV) for the 2015 Pan/Parapan American Games (Pan Am
Games). The PAAV will house over 8,000 athletes and coaching staff. This revitalization project involved an
aggressive schedule to secure the environmental approvals required in advance of infrastructure and building
construction by development partners. Site characterization, risk assessment (RA), remedial option feasibility
studies (ROFSs), remediation, and risk mitigation measures (RMMs) are key project components. CH2M HILL
Canada Limited (CH2M HILL) conducted field investigations and prepared multiple Phase One and Phase Two
environmental site assessment (ESA), ROFS, and RA reports in parallel in order to meet the development
schedule. The reports complied with Ontario Regulation (O. Reg.) 153/04 under the Environmental Protection Act,
as amended by O. Reg. 511/09, such that Records of Site Condition (RSCs) will be obtained on properties prior to
development. Currently, CH2M HILL is acting as the third‐party Ontario Ministry of the Environment (MOE)
Qualified Person (QP) to audit compliance with the Certificates of Property Use (CPUs) and RAs during the
implementation of the RMMs.
In October 2011, the WDL project was selected by the Canadian Urban Institute for the 2011 Brownie Award as
the project that best demonstrated Excellence in Project Development at the Neighbourhood Scale. The annual
Brownie Awards program recognizes leadership, innovation, and environmental sustainability in brownfield
redevelopment across Canada.
As the Human Health Risk Assessment (HHRA) Lead for the WDL project, responsible for coordinating the
completion of eight RA reports. To ensure the HHRA components of the reports are completed according to the
accelerated schedule, coordinates a team of 20 HHRA staff, and has engaged multiple stakeholders on numerous
technical issues. In addition, serves as the key RA contact for the ecological risk assessment (ERA), ESA, and Risk
Management teams, liaising with these teams to ensure the concurrent development of multiple sections of the
reports does not jeopardize report quality and harmonization.
Senior Risk Assessor; RA and RMP for Port Stanley Harbour; Public Works and Government Services Canada
(PWGSC); March 2009 to Present. Currently completing a multimedia RA (sediment, surface water, groundwater
and sediment). Tasks to date include providing direction and review of all aspects of the PSF for the MOE
submittal. A QA/QC for the RA will be completed to facilitate the filing of a record of site condition (RSC).
Senior Risk Assessor; RA and RMP for Don Valley Brickworks; City of Toronto, Ontario; September 2006 to
January 2009. As senior risk assessor and QPRA for an RA at a former brick manufacturing property, guided staff
on RA approach and reporting, development of risk management measures and review of the risk assessment
report. Reviewed construction documents to ensure risk management measures were implemented. The MOE
acknowledged the RA.
Peer‐Review; Brownfields RA for Interim Sport Fields; Waterfront Toronto; January 2006 to 2008. Provided a
review of HHRA and ecological risk assessment (ERA) of chemicals in soils and groundwater detected at a property
on the Toronto Waterfront.
Review of Brownfields RA for West Don Lands; TWRC; January 2006 to 2008. Reviewed human health and ecological
RAs of chemicals in soils and groundwater detected at a 200+‐hectare property on the Toronto Waterfront.
James G. Sprenger
3
Senior Risk Assessor; Risk Assessment at Former Epton Facility; PolyOne Canada Inc., Kitchener, Ontario;
February 2007 to Present. Provided senior review, quality assurance/quality control (QA/QC) and input for the
development of the RMP for an RA at an industrial site. Parcel 1 RA was acknowledged by the MOE; RAs for
additional parcels are being considered.
Senior Risk Assessor; Pre‐ and Post‐Closure Risk Assessments; Ontario Ministry of the Environment; Deloro,
Ontario; 2005 to 2009. Provided senior review and guidance to staff for the preparation of the pre‐ and post‐
closure RAs for the Deloro Mine Site.
1
Kurt Hansen
Qualified Person, Environmental Site Assessment
Education
M.E.S., Master of Environmental Studies, University of Waterloo
B.E.S., Honours Geography, University of Waterloo
General Arts Program, Academy of the New Church College
Professional Registrations
Professional Geoscientist: Ontario
Relevant Experience
Kurt has over 22 years’ experience in Phase One, Two, and Three environmental site assessments (ESAs),
environmental audits, site remediation programs, and field investigations involving soil and groundwater sampling
and monitoring. He is experienced in project development and implementation, including project planning and
management, site investigation, design and implementation, client/regulatory agency liaison, data analysis and
interpretation, and technical reporting. Kurt is designated as a Qualified Person for Environmental Site
Assessment (QPESA) by the Ontario Ministry of the Environment (MOE).
Representative Projects
Qualified Person; ESA and Preparation of Remediation Strategy; Sydenham Pearl Brownfield; City of Brantford;
Brantford, Ontario; 2012. The Sydenham Pearl Brownfield consists of two parcels of land in downtown Brantford,
both with industrial legacies dating back to the early 1900s. CH2M HILL was retained to conduct Phase One and
Two ESAs, and to prepare a Remedial Action Strategy to revitalize the properties for potential residential
development. Work included consultation with city staff, a public meeting, and presentations to City Council.
Work was completed to the satisfaction of the City, the public, and City Council, and resulted in the approval of
funds for implementation of the remedial strategy.
Site Assessment Lead – QPESA; West Don Lands (WDL); Ontario Infrastructure and Lands Corporation (IO);
Toronto, Ontario. The largest brownfield site currently under development in Ontario, this former industrial site
will encompass mixed‐use residential and commercial development, as well as a substantial parkland component,
after it serves as the Pan American Athletes’ Village (PAAV) for the 2015 Pan/Parapan American Games (Pan Am
Games). The PAAV will house over 8,000 athletes and coaching staff. This revitalization project involved an
aggressive schedule to secure the environmental approvals required in advance of infrastructure and building
construction by development partners. Site characterization, risk assessment (RA), remedial option feasibility
studies (ROFSs), remediation, and risk mitigation measures (RMMs) are key project components. CH2M HILL
Canada Limited (CH2M HILL) conducted field investigations and prepared multiple Phase One and Phase Two
ESAs, ROFSs, and RA reports in parallel in order to meet the development schedule. The reports complied with
Ontario Regulation (O. Reg.) 153/04 under the Environmental Protection Act, as amended by O. Reg. 511/09, such
that Records of Site Condition (RSCs) will be obtained on properties prior to development. Currently, CH2M HILL is
acting as the third‐party MOE‐Qualified Person (QP) to audit compliance with the Certificates of Property Use
(CPUs) and RAs during the implementation of the RMMs.
In October 2011, the WDL project was selected by the Canadian Urban Institute for the 2011 Brownie Award as
the project that best demonstrated Excellence in Project Development at the Neighbourhood Scale. The annual
Brownie Awards program recognizes leadership, innovation, and environmental sustainability in brownfield
redevelopment across Canada.
As QPESA for the WDL project, Kurt managed and directed field investigations and prepared four Phase One reports
and six Phase Two ESA reports for 60 blocks of the 36‐ha WDL under an accelerated schedule. The ESA team
supervised by Kurt evaluated data at approximately 290 areas of potential environmental concern (APECs) identified
through the Phase One ESAs and over 500 sample locations across the site (including more than 290 monitoring
wells). Data generated was used to build a conceptual site model (CSM) for each RSC Property to comply with post
July 1, 2011 regulatory requirements. As QPESA, Kurt led the ESA reporting and the associated site assessment
Kurt Hansen
2
summaries that were included in the RA Reports, liaised with the MOE to integrate current requirements into the
ESA reports and RSC documents, was responsible for the completion of the 13 acknowledged RSCs to date, served as
technical liaison with the RA and ROFD teams to realize efficiencies and certified that the remediation strategy was
implemented. Through this, his expertise in developing and implementing site remediation work for the purposes of
obtaining an RSC(s) with the MOE is clear. Two of the acknowledged RSCs were under O. Reg. 153/04 (before July 1,
2011) and 11 were under O. Reg. 153/04 as amended by 511/ (after July 1, 2011).
Site Assessment Lead Phase I ESA and Senior Technical Advisor; Wellington Development Block Brownfield
Redevelopment; Hamilton Health Sciences; Hamilton, Ontario; 2004 – 2007.
Project activities involved the completion of Phase I and Phase II ESAs, a designated substance and building waste
survey, risk assessment, and a remedial action plan on the Wellington Development Block located immediately west
of Hamilton General Hospital (HGH), in support of plans for the potential acquisition of the site from the City of
Hamilton. CH2M HILL prepared all demolition and remediation specifications for this project and managed the
abatement, demolition, remediation and restoration work. CH2M HILL also assisted in redevelopment options for the
various parcels of land that makeup the larger property.
As senior ESA lead, served as site assessment lead for completion of Phase I activities which included a site history
review, site inspections, interviews, an evaluation of information and reporting. The Phase I environmental site
assessment concluded that the Block has the potential for soil and groundwater contamination, with 19 potential
areas of concern noted, including metals, PCBs, asbestos‐containing materials, gasoline, diesel, and USTs.
Subsequently, provided senior technical guidance and support to subsequent phases of the project as required.
Project Manager; Updated ESA, Sediment Sampling, and Remedial Action Plan and QPESA for subsequent ESA
Update and RA; Public Works and Government Services Canada (PWGSC); Port Stanley Harbour, Ontario. Issues
include contaminated harbour sediments, soil, and groundwater (petroleum hydrocarbons [PHCs], heavy metals,
polycyclic aromatic hydrocarbons [PAHs], ammonia, and nitrate). Site strategy involves RA in conjunction with
remedial action (including phytoremediation, in situ bioremediation, and excavate/ dispose) to address “hot spot”
contamination areas; remediation criteria established during RA will be used to set remediation criteria and guide
remediation efforts. The Harbour is a multi‐tenant site with industrial/ commercial activities including fuel/hazardous
material handling/storage and vehicle maintenance. Complex environmental issues exist at the site: leaking fuel
storage tanks/pipelines and the improper storage/ handling and spills of hazardous materials; and multiple
contaminant types (PHC, heavy metals, PAHs) are present. The federally owned and operated site is considered
“environmentally sensitive” due to its proximity to Lake Erie; a risk‐based (as opposed to remediation‐based)
approach is the desired long‐term management strategy for the site. In 2008, as QPESA, worked with the technical
team to develop a data gap evaluation and supplemental investigation plan which were completed to address
provincial regulatory requirements for filing an RSC imposed as part of the transfer of lands to the municipality. In
2010, supported the public consultation program and represented the client at the information sessions. As a result
of regulatory changes coming into force in mid‐2011, and continue serve as QPESA for a Phase Two to address the
new regulatory requirements for completion of the RA and filing of RSCs on four distinct properties.
Project Manager; Environmental Due Diligence Review; Toronto Community Housing Corporation (TCHC); King
& Adelaide Sts, Toronto, Ontario; 2007. Conducted an environmental due diligence review and updated Phase I
and II ESAat 288 King Street East and 501 Adelaide Street East in Toronto, Ontario. Activities at the King and
Adelaide Streets Site included an environmental due diligence review and updated Phase I and II ESA. Based on
the ESAs’ findings, estimated the volume of subsurface materials that could require future management and
provided various cost‐effective management approaches, alongside opinions of probable implementation costs.
Subsequently, supervised and documented environmental remediation activities to address the ESAs’ findings.
Once remedial activities were complete, filed an RSC under the MOE’s O. Reg. 153/04, documenting the actions
required to facilitate the site’s redevelopment, given its more sensitive land use.
CH2M HILL has completed a number of successful ESAs and remediation projects for TCHC, including their
developments at 288 King Street East and 501 Adelaide Street East in Toronto, Ontario and the Don Mount Court
Redevelopment Project, also located in Toronto.Project Manager; Phase I ESA of Cherry Beach; Waterfront
Toronto; Toronto, Ontario. The purpose of the Phase I ESA was to review the site history and identify if potential
issues of environmental concern exist at the subject site that may warrant further investigation, and to assist in
Kurt Hansen
3
scoping an appropriate Phase II ESA if warranted. The Phase I ESA was completed in general accordance with CSA
Standard Z768‐01 so that it could be used, if required, in conjunction with other future Phase II ESA and Remedial
or Risk Assessment work to file an RSC under O. Reg. 153/04. Key project activities included background
information review, site visit, interviews, and reporting.
1
Meggen Janes
Communications Lead, Risk Management Measures, and Remedial Strategy Review
Education
M.S., Environmental Engineering, University of Guelph, Ontario
B.A.S., Geological Engineering (Geotechnical option), University of Toronto, Ontario
Professional Registrations
Professional Engineer: Ontario (1997)
Project Management Professional, 2005)
Relevant Experience
Meggen Janes has over 18 years of experience in environmental consulting, with key expertise based on
innovative and emerging technology applications. She has conducted research and development on new and
emerging technologies through bench and pilot studies and she has completed and managed property
assessments, peer reviews, compliance and environmental management systems evaluations, risk assessments,
and contaminant investigation and remediation projects at a number of public and private sector properties.
Meggen completes needs analysis for clients and evaluates requirements within the context of provincial
policies/programs and procedural framework, determining delivery options. She has applied innovative strategies
to deal with site restoration and closure by using a combination of techniques including excavation with
underpinning and sheet piling, in‐situ chemical oxidation, in‐situ and ex‐situ bioremediation, soil vapour
extraction, passive groundwater collectors, pump and treat and multi‐phase vacuum extraction. As an extension
of in‐situ environmental restoration, Meggen has designed vapour and groundwater treatment facilities for the
above‐ground treatment of contaminated material prior to discharge to the environment. She has also prepared
startup commissioning plans, and operation and maintenance manuals, for remediation systems, overseeing
operation and performance related to ongoing remediation systems.
Representative Projects and Dates of Involvement
Communications Lead; Environmental Site Assessment (ESA) and Preparation of Remediation Strategy;
Sydenham Pearl Brownfield; City of Brantford; Brantford, Ontario; 2012. The Sydenham Pearl Brownfield
consists of two parcels of land in downtown Brantford, both with industrial legacies dating back to the early
1900s. CH2M HILL was retained to conduct Phase One and Two ESAs, and to prepare a Remedial Action Strategy
to revitalize the properties for potential residential development. Work included consultation with city staff, a
public meeting, and presentations to City Council. Work was completed to the satisfaction of the City, the public,
and City Council, and resulted in the approval of funds for implementation of the remedial strategy.
Communications Lead; West Don Lands; Ontario Infrastructure and Lands Corporation (IO); Toronto, Ontario;
2010 to Present. The largest brownfield site currently under development in Ontario, this former industrial site
will encompass mixed‐use residential and commercial development, as well as a substantial parkland component.
The immediate development plan is for the majority of the site to become home to the Athletes’ Village for the
2015 Pan/Parapan American Games. This revitalization project involves an aggressive schedule to secure the
environmental approvals required in advance of infrastructure and building construction by development
partners. Site characterization, risk assessment (RA), remedial option feasibility studies (ROFSs), remediation, and
risk mitigation measures (RMMs) are key project components. CH2M HILL is conducting field investigations and
preparing multiple Phase One and Phase Two environmental site assessment (ESA), ROFS, and RA reports in
parallel in order to meet the schedule. The reports will comply with Ontario Regulation (O. Reg.) 153/04 under the
Environmental Protection Act, as amended by O. Reg. 511/09, such that Record of Site Conditions (RSCs) will be
obtained on properties prior to development.
In October 2011, the WDL project was selected by the Canadian Urban Institute for the 2011 Brownie Award as
the project that best demonstrated Excellence in Project Development at the Neighbourhood Scale. The annual
Meggen Janes
2
Brownie Awards program recognizes leadership, innovation, and environmental sustainability in brownfield
redevelopment across Canada.
As Communications lead, works with the CH2M HILL project team, IO, and related stakeholders (City of Toronto,
MOE, other government agencies, private developers, and the public) to facilitate remediation and approvals
strategies. Also ensures effective stakeholder and public communications to inform and achieve alignment with
project goals.
Project Manager; Sportsfield Site; Waterfront Toronto; Toronto, Ontario; 2006 to 2008. Project Manager/QP ESA
for multi‐stakeholder project for the development and construction of two artificial sportsfields on Toronto’s
waterfront; an environmental baseline study was completed to support an RA that incorporated risk management
measures and long term monitoring; the RA was compliant with O. Reg. 153/04 and accepted by the MOE;
stakeholder involvement was extensive through the process and approval of the remediation process from
stakeholders and MOE was obtained; an RSC was filed for the property in summer 2008.
Project Manager/Director; Community Waterfront Park Environmental Remediation; City of North Bay;
North Bay, Ontario, 2004. Project Manager/Director for cleanup of approximately 4,000 m³ of petroleum
hydrocarbon‐impacted soil at a waterfront redevelopment site; supervised soil remediation and managed an
extensive assessment of both groundwater flow and the distribution of contaminants; upgradient chlorinated
solvent contamination was identified during the work and a separate investigation was completed. The
remediation work was conducted under an accelerated time frame to meet the development schedule. The soil
remediation program was completed successfully and the groundwater contaminants and extent of impact was
characterized to assist in development and associated RA.
Project Manager; Pottersburg PCB Decommissioning Project; Ontario Ministry of the Environment (MOE);
Ontario; Ongoing. The engineering scope of this project included the development of the environmental plans to
safeguard the public and the natural environment during the removal of over 80,000 tonnes of PCB waste material
from four separate vaults. CH2M HILL then conducted the delivery of the various monitoring plans and acted as
consultant to the prime contractor during the confirmatory and Phase II sampling phases that lead to remedial
action plans for unknown conditions. CH2M HILL fees totaled over $4M.
Project Manager; Phase I ESA; Ontario Realty Corporation; 2005 to 2007. Managed Phase I ESA/Category B EA
programs conducted on several properties – one of which was the Milton County Heritage Park consisting of 69
buildings on an 80‐acre property.
Project Manager; Phase I/II Environmental Site Assessments; Multiple Sites, City of Greater Sudbury, Ontario;
2003 to 2004. Project Manager for Phase I and II environmental site assessments and designated substance
surveys on City properties to provide input into redevelopment options.
Project Manager; Phase II ESA; Canadian National; Sault Ste. Marie, Ontario; 2004. Project Manager for
investigation of soil and groundwater, hazardous materials, and designated substances at a property with multiple
areas of concern and an ongoing remediation system.
Project Manager; Phase II ESA (multiple sites) and Groundwater Monitoring Program; Hydro One Network
Services Inc.; 2000 to 2003. Project Manager for the investigation of soil and groundwater at multiple sites, which
included the evaluation of hydrogeological data to assess potential sources from areas upgradient to a site.
Project Director: Shopping Plaza Remediation; Morguard Investments Limited; GTA, Ontario; 2007 to 2008.
Project Director for development of a remedial program and implementation strategies for remediating during
plaza redevelopment; a site conceptual model was developed which contemplated the impact of shallow bedrock
and other migration pathways; site contaminants included both DNAPL and LNAPL, chlorinated solvent, and PHCs;
the remediation strategy included in‐situ reductive dechlorination for residual impacts and source removal
excavation; the strategy was planned to seamlessly integrate with development activities and has been accepted
by the development team; implementation was underway in summer 2008.
1
Dirk B. Scheurlen
Site Assessment Lead/Remediation Specialist
Education
Terrain Geology Technician Diploma, Sir Sandford Fleming College, 1989
Professional Registrations
Ontario Association of Certified Engineering Technicians and Technologists (OACETT)
Distinguishing Qualifications
Over 23 years of experience in environmental site assessment and remediation
Expertise in soil and groundwater remediation
Relevant Experience
Dirk Scheurlen has more than 23 years’ experience conducting environmental site assessments, remediation, free
product recovery and demolition. His experience includes designing and operating site remediation systems,
development of contract documents, contractor management, dispute resolution, reporting and project
management.
Representative Projects and Dates of Involvement
Site Assessment Lead; Environmental Site Assessment (ESA) and Preparation of Remediation Strategy; Sydenham
Pearl Brownfield; City of Brantford; Brantford, Ontario; 2012. The Sydenham Pearl Brownfield consists of two
parcels of land in downtown Brantford, both with industrial legacies dating back to the early 1900s. CH2M HILL
was retained to conduct Phase One and Two ESAs, and to prepare a Remedial Action Strategy to revitalize the
properties for potential residential development. Mr. Scheurlen was responsible for the development and
implementation of the Phase Two sampling and analysis plan and standard operating procedures for the intrusive
investigation.
Project Manager; Groundwater Treatment System Operation, Maintenance and Monitoring; Budcan Holdings Inc;
Erin, Ontario; 2012 to Present. Project Manager for the operation, maintenance and groundwater monitoring for
an air stripping groundwater containment and treatment system to ensure compliance with an Ontario Ministry
of the Environment (MOE) Certificate of Approval (CofA). The groundwater treatment system is being operated to
contain groundwater impacted with trichloroethylene (TCE) to prevent offsite migration in a municipality using
groundwater as a drinking water source.
Project Manager; Groundwater Remediation of TCE Plume, PolyOne Corporation; Kitchener, Ontario; 2012 to
Present. Project Manager responsible for the remediation of a TCE groundwater plume involving biostimulation
with emulsified vegetable oil and bioaugmentation with dehalococcoides (DHC microbes) to enhance the
anaerobic reductive dechlorination process at the site to facilitate degradation of TCE to non‐toxic byproducts in
accordance with an MOE CofA.
Project Manager; Wellington Development Block Brownfield Project; Hamilton Heath Sciences; Hamilton,
Ontario; January 2004 to 2007. This project was completed under an extremely compressed schedule so that HHS
could make a determination on the purchase of the Wellington Block from the City of Hamilton. The project
involved the completion of a Phase I ESA, Phase II ESA, Building Waste and Designated Substance Survey and a
Remedial Action Plan (RAP) and remedial cost estimate. A Ministry of the Environment approved Risk Assessment
(RA) was developed to remediate the site to property specific standards prior to the filing of a Record of Site
Condition (RSC). The Wellington Development Block project was the winner of the 2009 Canadian Urban Institute
Brownfield (Brownie) Award in the Category of Financing, Risk Management and Partnerships.
Field Team Coordinator; West Don Lands; Ontario Infrastructure and Lands Corporation (IO); Toronto, Ontario;
2010 to Present. The largest brownfield site currently under development in Ontario, this former industrial site
will encompass mixed‐use residential and commercial development, as well as a substantial parkland component.
Dirk B. Scheurlen
2
The immediate development plan is for the majority of the site to become home to the Athletes’ Village for the
2015 Pan/Parapan American Games. This revitalization project involves an aggressive schedule to secure the
environmental approvals required in advance of infrastructure and building construction by development
partners. Site characterization, risk assessment (RA), remedial option feasibility studies (ROFSs), remediation, and
risk mitigation measures (RMMs) are key project components. CH2M HILL is conducting field investigations and
preparing multiple Phase One and Phase Two environmental site assessment (ESA), ROFS, and RA reports in
parallel in order to meet the schedule. The reports will comply with Ontario Regulation (O. Reg.) 153/04 under the
Environmental Protection Act, as amended by O. Reg. 511/09, such that RSCs will be obtained on properties prior
to development.
In October 2011, the WDL project was selected by the Canadian Urban Institute for the 2011 Brownie Award as
the project that best demonstrated Excellence in Project Development at the Neighbourhood Scale. The annual
Brownie Awards program recognizes leadership, innovation, and environmental sustainability in brownfield
redevelopment across Canada.
As Field Team Coordinator, coordinated multiple field teams leading to MOE acceptance of Phase Two
documentation and acknowledgement of 8 RSCs. As a senior ESA team member, responsible for coordinating and
providing technical support for the preparation of 5 Phase One ESA reports, 8 Phase Two ESA reports (including
8 additional investigation/remediation reports), 2 preliminary Phase Two summary memos, and 13 RSCs for the
63‐Block WDL. The accelerated schedule and multiple stakeholder input characterizing Phase Two ESA reports
have required us to implement best practices and templates that facilitate schedule and quality compliance. The
ESA team evaluated data at approximately 195 areas of potential environmental concern (APECs) and 1,933
sample locations across the site. Data generated were being used to build the conceptual site model (CSM) for
each Phase Two grouping of Blocks, to feed information into eight RA reports, and to develop the CSMs for
supporting the filing of RSCs for the properties.
Project Task Manager; Pottersburg PCB Waste Storage Site Remediation; London Ontario; Ministry of the
Environment; 2009 to Present. Responsible for project Health and Safety, contract change orders, data
management, procurement and portions of the Phase II ESA investigation.
Project Manager; Phase I & II ESAs and UST Decommissioning at sites throughout Southern Ontario and Quebec
for Ryder Truck Rental; 2007 to 2009. The projects involved the completion of Phase I & II Environmental Site
Assessments (ESAs) for Ryder Truck Rental facilities prior to property transfers/acquisitions. Conducted
environmental investigations and remediation related to the decommissioning of USTs containing gasoline and
diesel fuel at Ryder Truck Rental facilities located in southwestern Ontario.
Project Manager; Site Remediation, 237 Barton Street East; Hamilton Health Sciences (HHS), Hamilton, Ontario;
June 2006 to 2007. The project involved soil remediation of the former Stelco Wire and Nail Works East Plant
prior to the redevelopment and expansion of the Hamilton General Hospital on the property. Responsibilities
included preparing contract documents, contract administration and oversight of the remediation contractor.
31,000 tonnes of contaminated soil was removed from the property and sent to Ministry of the Environment
(MOE) licensed landfills. Following soil remediation, Record of Site Conditions (RSC) were filed for the properties.
Project Manager; Risk Characterization and Remediation; NOVA Chemicals (Canada) Ltd.; Cambridge, Ontario;
2000 to 2007. Responsible for the operation of a groundwater collection and treatment system and groundwater
monitoring programs. Pilot testing, full‐scale design, construction, and operation of an air sparging (AS) and soil
vapour extraction (SVE) remediation system. The AS and SVE remediation program was conducted in combination
with a RA in which site‐specific remediation criteria were developed to remediate the site prior to the filing of a
RSC and transfer of the property.
Task Manager; Free Product Recovery; PolyOne; Kitchener, Ontario; 2000 to 2006. Design, construction,
subcontractor management and operation of a full‐scale SVE system at the former Epton rubber and plastics
manufacturing facility. The SVE system recovered over 28,000 litres of free phase naphtha from the water table.
Dirk B. Scheurlen
3
Following a multiphase extraction pilot test it was determined that soil vapour was the most predominant
extraction pathway primarily due to the volatility of naphtha.
Project Manager; Demolition of Former Stelco Works, 325 Wellington Street North; HHS, Hamilton, Ontario;
2005. The project involved the demolition of the 14,000 m
2
Stelco Wire and Nail Works West Plant. Responsible
for preparing contract documents, contract administration and oversight of the demolition contractor during
demolition and abatement of designated and hazardous substances. The demolition was completed on budget
and ahead of schedule.
Project Manager; Free Product Remediation; City of Hamilton/HHS; Hamilton, Ontario; 2005. The project
involved the excavation and disposal of free product containing soil and the skimming of free product from the
excavation water table at a former City works yard located at 344 Ferguson Ave. North. A total of 1,200 tonnes of
free product containing soil and 138,000 L of free product and groundwater were extracted from the subsurface
and sent offsite for disposal.
1
Krista L. Barfoot
Risk Assessor / Brownfield Redevelopment
Education
Ph.D. (Soil Science), University of Guelph, Ontario
M.Sc. (Analytical Environmental Chemistry), McMaster University, Ontario
B.Sc. Honours (Environmental Chemistry), Queen’s University, Ontario
Distinguishing Qualifications
Extensive experience conducting human health risk assessments (HHRAs) and vapour intrusion (VI)
assessments on contaminated properties in Canada and the United States, following provincial, state, and
federal guidance
Experience providing chemical, toxicological, pedological, agrological, and environmental support for various
projects in North America, South America, and the United Kingdom (UK)
Qualified Person for Risk Assessment (QPRA) (Ontario Regulation [O.Reg.] 153/04, via Ontario Ministry of the
Environment [MOE])
Relevant Experience
Krista Barfoot is a risk assessment scientist with over 13 years of experience in environmental science
investigations, including over 6 years of experience in risk assessment (RA) and (VI) assessment. She possesses the
relevant qualifications for eligibility as a QPRA under O. Reg. 153/04 of the Environmental Protection Act for a
Record of Site Condition (RSC), and is registered as such with the MOE.
Dr. Barfoot has examined aspects of both drinking water and groundwater contamination, industrial air
contamination, and soil quality degradation, and has investigative experience in all three environmental mediums
(water, air, and soil). Dr. Barfoot’s graduate studies and work have spanned the fields of chemistry, toxicology,
pedology, geology, agrology and ecology. She has completed a number of RAs and VI assessments both in Ontario
and across the United States, and has provided consulting services in the fields of agriculture and soil science.
Dr. Barfoot is part of CH2M HILL’s Environmental Services Group, and is based in the Kitchener‐Waterloo office.
Representative Projects and Dates of Involvement
Senior Technical Support; Former Amherstburg Manufacturing Facility, Environmental Site Assessment, Risk
Assessment, Remedial Planning, Contract Administration and Demolition Oversight; Confidential Client, 2010 to
Present. CH2M HILL was retained to provide environmental advisory and construction management services for
the decommissioning of a large abandoned chemical manufacturing facility. Services provided have included
Phase Two ESAs, Risk Assessment activities, preparation of tender documents and tendering for facility demolition
and remediation services, project administration and construction oversight. Work is being conducted with
regular consultation with the client, the public, and municipal and regulatory personnel. Onsite environmental
activities have been coordinated with the demolition of over 300,000 ft
2
of manufacturing space, with strict
observance of health and safety protocols. Provided senior technical support for risk assessment activities and
participated in strategic project planning.
Human Health RA; Environmental Site Assessment (ESA) and Preparation of Remediation Strategy; Sydenham
Pearl Brownfield; City of Brantford; Brantford, Ontario; 2012. The Sydenham Pearl Brownfield consists of two
parcels of land in downtown Brantford, both with industrial legacies dating back to the early 1900s. CH2M HILL
was retained to conduct Phase One and Two ESAs, and to prepare a Remedial Action Strategy to revitalize the
properties for potential residential development. Work included consultation with city staff, a public meeting, and
presentations to City Council. Work was completed to the satisfaction of the City, the public, and City Council, and
resulted in the approval of funds for implementation of the remedial strategy.
Krista L. Barfoot
2
HHRA Lead; West Don Lands; Ontario Infrastructure and Lands Corporation (IO); Toronto, Ontario; 2010 to
Present. The largest brownfield site currently under development in Ontario, this former industrial site will
encompass mixed‐use residential and commercial development, as well as a substantial parkland component,
after it serves as the Pan American Athletes’ Village (PAAV) for the 2015 Pan/Parapan American Games (Pan Am
Games). The PAAV will house over 8,000 athletes and coaching staff. This revitalization project involved an
aggressive schedule to secure the environmental approvals required in advance of infrastructure and building
construction by development partners. Site characterization, risk assessment (RA), remedial option feasibility
studies (ROFSs), remediation, and risk mitigation measures (RMMs) are key project components. CH2M HILL
Canada Limited (CH2M HILL) conducted field investigations and prepared multiple Phase One and Two ESA, ROFS,
and RA reports in parallel in order to meet the development schedule. The reports complied with Ontario
Regulation (O. Reg.) 153/04 under the Environmental Protection Act, as amended by O. Reg. 511/09, such that
Records of Site Condition (RSCs) will be obtained on properties prior to development. Currently, CH2M HILL is
acting as the third‐party Ontario Ministry of the Environment (MOE) Qualified Person (QP) to audit compliance
with the Certificates of Property Use (CPUs) and RAs during the implementation of the RMMs.
In October 2011, the WDL project was selected by the Canadian Urban Institute for the 2011 Brownie Award as
the project that best demonstrated Excellence in Project Development at the Neighbourhood Scale. The annual
Brownie Awards program recognizes leadership, innovation, and environmental sustainability in brownfield
redevelopment across Canada.
As the Human Health Risk Assessment (HHRA) Lead for the WDL project, responsible for coordinating the
completion of nine RA reports. To ensure the HHRA components of the reports are completed according to the
accelerated schedule, coordinates a team of 20 HHRA staff, and has engaged multiple stakeholders on numerous
technical issues. In addition, serves as the key RA contact for the ecological risk assessment (ERA), ESA, and Risk
Management teams, liaising with these teams to ensure the concurrent development of multiple sections of the
reports does not jeopardize report quality and harmonization.
Experience Prior to CH2M HILL
Lead Risk Assessor; RA for Multi‐Tenant Commercial Property; Confidential Client; Waterloo, Ontario; 2010.
Completed data evaluation, summary of Phase I and II Environmental Site Assessment (ESA) Reports and RA
approach document in support of completing and filing a Pre‐Submission Form (PSF) with the MOE. The PSF is
currently under MOE review.
RA Consultant; RA Evaluation for Industrial/Commercial Property; Confidential Client; Niagara Falls, Ontario;
2010. Conducted a review of Phase I and II ESA Reports, and additional investigative reports, to determine
potential for property to obtain a Record of Site Condition through the RA process. Presented findings to client,
potential buyer, and legal aid for the buyer.
Lead Risk Assessor; Development of Risk‐based Standards for Commercial Property; Confidential Client;
Hamilton, Ontario; 2009. Developed risk‐based property‐specific standards (PSSs) based on human exposure to
the site under current and future land use scenarios. The development of the PSSs was requested to aid in
securing financial support for the proposed redevelopment of the site.
Lead Risk Assessor; RA for Former Service Station; Confidential Client; Gualala, California; 2009. Developed site‐
specific human health risk‐based cleanup levels for total petroleum hydrocarbons following San Francisco Bay
Regional Water Quality Control Board and California Environmental Protection Agency (CalEPA) Guidance.
Risk Assessor; RA for 35 Regan Road; SARC Realty Holdings Limited; Brampton, Ontario; 2007 to 2009.
Conducted an RA under O. Reg. 153/04 for an RSC [including completion of a MOE PSF, identification of
Contaminants of Concern (COCs), identification of potentially complete human and ecological exposure pathways,
calculation of human health and ecological risks, development of PSSs, preparation of RA report, and responding
to MOE comments on the RA report]. The RSC was requested in relation to the sale of the property. The property
Krista L. Barfoot
3
was utilized for blow molding, and handling and blending automotive and petroleum products for packaging and
distribution. The RSC was filed in 2009.
1
Terry Lorentz
Contract Administration/Construction Oversight Lead
Education
Environmental Engineering, Post Diploma, Conestoga College, Kitchener, Ontario
B.E.S., University of Waterloo, Ontario
Distinguishing Qualifications
Environmental contractor and consultant working in senior construction management, estimating, and
business development roles
Relevant Experience
Terry has extensive experience in contract management and execution of remedial construction. He has
developed, estimated and managed over 200 projects in Canada and the United States involving building
decommissioning; aboveground and underground storage tank removal; soil excavation, removal and disposal;
hazardous waste management; liquid waste disposal; waste screening; bioremediation; soil stabilization; vapour
extraction and groundwater treatment with single project values exceeding $10M.
Representative Projects
Senior Cost Estimator; Environmental Site Assessment (ESA) and Preparation of Remediation Strategy;
Sydenham Pearl Brownfield; City of Brantford; Brantford, Ontario; 2012. The Sydenham Pearl Brownfield
consists of two parcels of land in downtown Brantford, both with industrial legacies dating back to the early
1900s. CH2M HILL was retained to conduct Phase One and Two ESAs, and to prepare a Remedial Action Strategy
to revitalize the properties for potential residential development. Work included consultation with city staff, a
public meeting, and presentations to City Council. Work was completed to the satisfaction of the City, the public,
and City Council, and resulted in the approval of funds for implementation of the remedial strategy.
Project Management, Demolition/Senior Technical Consultant, Demolition; Former Amherstburg Manufacturing
Facility, Environmental Site Assessment, Risk Assessment, Remedial Planning, Contract Administration and
Demolition Oversight; Confidential Client, 2010 to Present. CH2M HILL was retained to provide environmental
advisory and construction management services for the decommissioning of a large abandoned chemical
manufacturing facility. Services provided have included Phase Two ESAs, Risk Assessment activities, preparation of
tender documents and tendering for facility demolition and remediation services, project administration and
construction oversight. Work is being conducted with regular consultation with the client, the public, and
municipal and regulatory personnel. Onsite environmental activities have been coordinated with the demolition of
over 300,000 ft
2
of manufacturing space, with strict observance of health and safety protocols.
Technical Construction Lead; West Don Lands; Ontario Infrastructure and Lands Corporation (IO); Toronto, Ontario;
2010 to Present. The largest brownfield site currently under development in Ontario, this former industrial site will
encompass mixed‐use residential and commercial development, as well as a substantial parkland component, after it
serves as the Pan American Athletes’ Village (PAAV) for the 2015 Pan/Parapan American Games (Pan Am Games).
The PAAV will house over 8,000 athletes and coaching staff. This revitalization project involved an aggressive
schedule to secure the environmental approvals required in advance of infrastructure and building construction by
development partners. Site characterization, risk assessment (RA), remedial option feasibility studies (ROFSs),
remediation, and risk mitigation measures (RMMs) are key project components. CH2M HILL Canada Limited
(CH2M HILL) conducted field investigations and prepared multiple Phase One and Phase Two environmental site
assessment (ESA), ROFS, and RA reports in parallel in order to meet the development schedule. The reports complied
with Ontario Regulation (O. Reg.) 153/04 under the Environmental Protection Act, as amended by O. Reg. 511/09,
such that Records of Site Condition (RSCs) will be obtained on properties prior to development. Currently, CH2M HILL
is acting as the third‐party Ontario Ministry of the Environment (MOE) Qualified Person (QP) to audit compliance with
the Certificates of Property Use (CPUs) and RAs during the implementation of the RMMs.
Terry Lorentz
2
In October 2011, the WDL project was selected by the Canadian Urban Institute for the 2011 Brownie Award as
the project that best demonstrated Excellence in Project Development at the Neighbourhood Scale. The annual
Brownie Awards program recognizes leadership, innovation, and environmental sustainability in brownfield
redevelopment across Canada.
As the ROFS Lead for the WDL project, responsible for coordinating the completion of eight ROFS reports and
contributing the RMMs component of the RA document. To ensure the RMM components of the RA reports and
ROFS documents are completed according to the accelerated schedule, coordinated a team of 11 ROFS staff, and
engaged multiple stakeholders on numerous technical issues.
Senior Construction Consultant; Klondike Highway Maintenance Camp; The Government of Yukon; Dawson,
Yukon. Consulting advisor to Yukon Environment. Providing excavation, land treatment facility construction and
post‐remedial drilling support for costing, tender development and project execution.
Project Consultant; Deloro Mine Site Cleanup; Ministry of the Environment (MOE); Deloro, Ontario. Provided
comprehensive estimates of heavy construction costs and performed constructability reviews of detailed design
drawings and draft technical specifications for the Tailings Area and Industrial/Mine Area.
Senior Construction Consultant; Gitxaala Landfill Site Investigation and Remediation; Gitxaala Nation; Kitkatla, BC.
Prepared a detailed cost estimate for a large (over $7M) remediation project and provided Client with remedial
construction management throughout the works.
Estimator; Contaminated Site Remediation; Estimation of Remediation Cost, Experimental Proving Grounds,
Canadian Forces Base (CFB), Suffield, Alberta; Defence Research and Development Canada. Worked with project
team to evaluate and develop costs to conduct remediation and demilitarization activities. Remediation will be
completed in accordance with the requirements of the Federal Contaminated Sites Action Plan (FCSAP). An in‐depth
financial analysis and cash flow projections were prepared and forecasted through the remainder of the works.
Estimator; Waste Management Services and Landfill Closure; Pelee Island Waste Management System;
Pelee Island, Ontario. Prepared an engineering cost estimate for the closure of a municipal solid waste (MSW) landfill
including capping and vegetation, construction of a stormwater pond, and construction of an onsite transfer station
and site grading. Cost estimate included pricing the transportation of large equipment and materials by ferry from
the mainland to Pelee Island. Also reviewed technical specifications from a constructability aspect.
Senior Construction Consultant; Decommissioning and Remediation of an Abandoned Mine Site; Manitoba
Conservation; Gods Lake, Manitoba. In 2000, Manitoba established the Orphaned/Abandoned Mine Site
Rehabilitation Program to address public safety and environmental health concerns associated with
orphaned/abandoned mine sites. Provided consulting and cost estimate support for the remediation and
decommissioning of the Gods Lake Abandoned Mine.
Senior Construction Lead; Various Projects; Confidential Client; Sarnia, Ontario. Construction lead for a variety of
remediation projects which are part of a large remediation program at a former chemical plant/industrial facility.
Senior Construction Lead and Estimator; Various Projects; Confidential Client; Alberta. Construction lead for a
variety of remediation projects that are part of a large remediation program at a former chemical plant/industrial
facility.
Senior Construction Lead and Estimator; Various Projects; Lanxess; Sarnia, Ontario. Construction lead for a
variety of remediation projects that are part of a large remediation program at a former chemical plant/industrial
facility.
1
Andrea Wojtyniak
Environmental Design Specialist
Education
Post‐Graduate Coursework, Environmental Biology, Toxicology Option, University of Guelph, Guelph, Ontario
B.Sc., Honours Science and Business, Biology Option, Co‐Operative Education, University of Waterloo, Waterloo,
Ontario
Relevant Experience
Andrea Wojtyniak is an Environmental Design Specialist in the Environmental Services Business Group in Toronto,
Ontario. She has 6 years of experience conducting environmental science investigations, including approximately
4 years of experience in risk assessment (RA) and vapour intrusion (VI) assessment in both Canada and the United
States.
Representative Projects and Dates of Involvement
HHRA Team Member; Former Amherstburg Manufacturing Facility, Environmental Site Assessment, Risk
Assessment, Remedial Planning, Contract Administration and Demolition Oversight; Confidential Client, 2010 to
Present. CH2M HILL was retained to provide environmental advisory and construction management services for
the decommissioning of a large abandoned chemical manufacturing facility. Services provided have included
Phase Two ESAs, Risk Assessment activities, preparation of tender documents and tendering for facility demolition
and remediation services, project administration and construction oversight. Work is being conducted with
regular consultation with the client, the public, and municipal and regulatory personnel. Onsite environmental
activities have been coordinated with the demolition of over 300,000 ft
2
of manufacturing space, with strict
observance of health and safety protocols. As an HHRA Team Member, responsible for coordinating the
development and completion of the individual RA report(s). Also responsible for numerous technical aspects
related to the development of the RA, including the completion of Pre‐Submission Forms (PSFs), preparation of
technical memos identifying the building blocks and RA approach for client and regulator consideration,
identification of chemicals of concern (COCs), automation of risk calculations, conduct of indoor air and outdoor
air modelling, performance of risk calculations, preparation of supporting calculations and documentation
following MOE guidance and the MOE 2011 Rationale Document, development of Property‐Specific Standards
(PSSs), and implementation of various quality control procedures.
HHRA Team Member and Report Coordinator; West Don Lands; Ontario Infrastructure and Lands Corporation;
Toronto, Ontario; 2010 to 2011. The largest brownfield site currently under development in Ontario, this former
industrial site will encompass mixed‐use residential and commercial development, as well as a substantial
parkland component. The immediate development plan is for the majority of the site to become home to the
Athletes’ Village for the 2015 Pan/Parapan American Games. This revitalization project involves an aggressive
schedule to secure the environmental approvals required in advance of infrastructure and building construction
by development partners. Site characterization, risk assessment (RA), remedial option feasibility studies (ROFSs),
remediation, and risk mitigation measures (RMMs) are key project components. CH2M HILL is conducting field
investigations and preparing multiple Phase I and Phase II environmental site assessment (ESA), ROFS, and RA
reports in parallel in order to meet the schedule. The reports will comply with Ontario Regulation (O. Reg.) 153/04
under the Environmental Protection Act, as amended by O. Reg. 511/09, such that Record of Site Conditions
(RSCs) will be obtained on properties prior to development.
As an HHRA Team Member for the WDL project, responsible for ensuring the RA reports were completed with a
high level of quality. Specifically, served as the Technical Lead of two RA reports, and supported the development
of an additional six RA Reports. As Technical Lead, responsible for coordinating the development and completion
of the individual RA report(s). Also directly responsible for numerous technical aspects related to the
development of the RA, including the completion of Pre‐Submission Forms (PSFs), preparation of technical memos
identifying the building blocks and RA approach for client and regulator consideration, identification of chemicals
of concern (COCs) for an environmentally sensitive site using Table 1 Site Condition Standards (SCS), automation
Andrea Wojtyniak
2
of risk calculations, automation of models used to support the RAs, identification of appropriate toxicological data
for use in the RA, development of detailed justification for the use of these toxicological data, development of
toxicity profiles, conduct of indoor air and outdoor air modelling, performance of risk calculations, preparation of
supporting calculations and documentation following MOE guidance and the MOE 2009 Rationale Document,
development of Property‐Specific Standards (PSSs), and implementation of various quality control procedures.
Also liaised with the client, participating in the comment resolution process and ensuring client comments were
appropriately addressed in the final products.
Experience Prior to CH2M HILL
Risk Assessor; Confidential Client; Cambridge, Ontario; 2010. Developed and submitted Pre‐Submission Form
(PSF) to the Ontario Ministry of Environment (MOE) in accordance with O.Reg.153/04. The development of the
PSF was requested to begin the risk assessment process for the proposed sale of the site.
Risk Assessor; Confidential Client; two locations in Ohio; 2009 to 2010. Conducted two Human Health Risk
Assessments (HHRAs) for petroleum‐related impacts at two former service stations following Ohio Bureau of
Underground Storage Tank Regulations (BUSTR) guidance and models (including the use of BUSTRScreen).
Risk Assessor; Confidential Client; various locations in Washington; 2009 to 2010. Conducted HHRAs for
petroleum‐related impacts at several former service stations, in accordance with Washington Department of Ecology
Model Toxics Control Act (MTCA) guidance.
Risk Assessor; Confidential Client; various locations in California; 2007 to 2010. Conducted numerous HHRAs and
developed site‐specific human health risk‐based cleanup levels for petroleum‐related impacts in accordance with
California Regional Water Quality Control Board (RWQCB), Department of Toxic Substances (DTSC), Office of
Environmental Health Hazard Assessment (OEHHA), and California Environmental Protection Agency (CalEPA)
guidance and models (including LeadSpread and the Johnson and Ettinger Models).
Risk Assessor; Confidential Client; Ardmore, Oklahoma; 2006 to 2009. Assisted in the development of site‐
specific human health risk‐based cleanup levels for soil for a former oil refinery based on residential landuse
according to Oklahoma Department of Environmental Quality (ODEQ) guidance.
Risk Assessor; RA for 35 Regan Road; SARC Realty Holdings Limited; Brampton, Ontario; 2007 to 2009. Provided
project support for all aspects of an RA under O. Reg. 153/04, for an industrial property that had been used for
blow molding, and handling and blending automotive and petroleum products for packaging and distribution.
Project requirements included completion of an MOE PSF, identification of Contaminants of Concern (COCs),
identification of potentially complete human and ecological exposure pathways, calculation of human health and
ecological risks, development of property‐specific standards (PSSs), preparation of RA report, and responding to
MOE comments on the RA report. The record of site condition (RSC) was requested in relation to the sale of the
property, and was filed in 2009.
Risk Assessor; RA for 18 Lower Jarvis Street; Harold Gross Realty Inc. and Michael Gross Realty Ltd.; Toronto,
Ontario; 2007 to 2009. Provided project support for all aspects of an RA under O.Reg. 153/04 for a RSC. The RSC
was required as the property was planned for redevelopment to a more sensitive landuse (from
industrial/commercial to mixed residential/commercial). The RSC was filed in 2009.
Project Consultant; Risk Ranking for Energy Management Facilities; Confidential Client; Ontario; 2007.
Supported a risk ranking process through the classification of chemical, geographical, geological, and land use
data for energy management facilities across Ontario.
VI Consultant; VI Assessment of Former Dry Cleaning Site; Confidential Client; Ottawa, Ontario; 2006 to 2009.
Assessed the potential for vapour intrusion into residences and a mall impacted by the plume of a former dry
cleaning facility. The risk evaluation followed MOE 1996 and USEPA guidance.
1
Wayne Cooley
Remedial Strategy Review
Education
B.A.Sc. (Honours), Civil (Environmental) Engineering, University of Toronto, Toronto, Ontario
Diploma (Honours), Civil Engineering Technology, Ryerson Polytechnical Institute, Toronto, Ontario
Professional Registrations
Professional Engineer: Ontario (1992, No. 90331448)
Distinguishing Qualifications
Focused and detail oriented
Excellent problem solving and communication skills
Effective liaison with clients and regulatory agencies
Diverse project experience that includes landfill design/waste management, environmental site
investigation/remediation, and municipal works
Relevant Experience
Mr. Cooley is a senior engineer with over 20 years of design and management experience in environmental/
municipal engineering and construction. His primary expertise is in the area of waste management, with emphasis
on landfill permitting, design, development, operation, closure, monitoring, and reporting. Additional significant
experience consists of environmental site investigation/remediation, impervious linings, groundwater/leachate
collection, pumping systems, stormwater management, and municipal works. Mr. Cooley has extensive
experience with planning and design issues, including public consultation and approvals processes. Throughout his
career, he has been extensively involved in both environmental and municipal construction works, providing a
broad range of related services such as tender/contract administration, construction inspection and warranty
administration. Mr. Cooley has successfully managed or completed a wide range of projects for public and private
clients, and has provided effective liaison with regulatory agencies for securement of approvals.
Representative Projects
Environmental Site Investigation/Remediation
Mr. Cooley has participated in a wide range of projects involving environmental site investigations and
groundwater/soil remediation. Major projects have comprised the preparation of risk evaluation, environmental
and hydrogeologic investigation reports; detailed design of groundwater extraction and treatment systems;
remediation of an oil interceptor pond; removal of underground storage tanks; and waste characterization and
offsite disposal of hydrocarbon contaminated soils.
Development of a remedial action plan, including a field investigation program (that is, geophysics and soil
sampling/analysis) and identification/evaluation of appropriate remediation technologies, for a skeet shooting
range in Toronto, Ontario.
Detailed design of a groundwater extraction and treatment system for an industrial site in Toronto, Ontario.
Development of performance specifications and securing of contractor quotations to solidify/stabilize lagoon
sludge from a butyl‐rubber manufacturing process, so that it could be disposed of as a non‐hazardous solid
industrial waste at their proprietary landfill in Sarnia, Ontario.
Detailed design, preparation of design brief, construction inspection and tender/contract administration for a
groundwater extraction and treatment system at a commercial development site in Guelph, Ontario.
Wayne Cooley
2
Preparation of risk evaluation, environmental, and hydrogeologic site investigation reports for a commercial
development site in Guelph, Ontario.
Detailed design for remediation of an oil interceptor pond (relining with flexible geomembrane) at an
industrial site in Guelph, Ontario.
Detailed design, preparation of contract documents, construction inspection and tender/contract
administration for a groundwater collection system at an industrial site in Perth, Ontario.
Miscellaneous fieldwork and preparation of documentation with respect to the removal of underground
storage tanks and excavation, waste characterization, and offsite disposal of hydrocarbon contaminated soils
at various industrial sites in Ontario.
Development of hydraulic (that is, water level) monitoring and water/soil quality sampling programs.
Senior Technical Consultant; Kingston Dry Docks Risk Assessment; Public Works and Government Services
Canada; Kingston, Ontario; July to August 2012. Provision of senior technical advisory/review support for
conceptual design of vapour intrusion and soil gas migration mitigation components of the risk assessment.
Senior Project Engineer; Closed Non‐Hazardous Landfill; Confidential Client; Southwest Ontario; June to July
2012. Completion of a financial assurance re‐evaluation for a closed non‐hazardous solid industrial waste landfill
and a gypsum solids settling basin.
Senior Technical Consultant; York Community Centre Risk Assessment; City of Toronto; Toronto, Ontario; May
to June 2012. Provision of senior technical advisory/review support to peer review, on behalf of the City of
Toronto, the tender/construction drawings and technical specifications to ensure conformance with conceptual
design elements of the proposed vapour intrusion and soil gas migration mitigation risk assessment components.
Experience Prior to CH2M HILL
Senior Technical Consultant; Newalta Landfill; City of Hamilton; Stoney Creek, Ontario; 2010 and 2011.
Provision of senior technical advisory/review support to peer review, on behalf of the City of Hamilton, for a
landfill impact assessment (Newalta closed and active landfills) prepared for several adjacent development
properties. A follow‐up peer review on another development property adjacent the active and closed landfills was
subsequently awarded and completed.
Senior Technical Consultant; Closed Sabiston Landfill; Town of Markham; Markham, Ontario; 2009 to 2011.
Provision of senior technical advisory/review support for the water quality monitoring program and active landfill
gas collection/flaring system.
Senior Technical Consultant; Inter – Recycling Systems Landfill; Ministry of the Environment; Sarnia, Ontario;
2009 to 2011. Provision of senior technical advisory/review support for preparation of a hydrogeological
assessment, closure/post‐closure plan and remedial contingency plan (Waterloo Barrier sheet pile wall).
Senior Technical Consultant; Closed Quinte Sanitation Landfill; Ministry of the Environment; Quinte West,
Ontario; 2009 to 2011. Provision of senior technical advisory/review support for preparation of a closure/post‐
closure plan to remediate water quality, landfill gas and final cover issues.
Senior Technical Consultant and Design Manager; Kidd Mine Landfill Site “B”; Xstrata Copper Canada; Timmins,
Ontario; 2008 to 2011. Provision of senior technical advisory/review support and acted as Landfill Design Group
Lead for the environmental assessment, design, and permitting of Landfill Site “B”.
Senior Technical Consultant; New Liskeard and Haileybury Landfills; City of Temiskaming Shores; Temiskaming,
Ontario; 2009 to 2010. Provision of senior technical advisory/review support for the completion of a feasibility
study for development of a long‐term waste disposal (landfill expansion) with respect to the closed New Liskeard
and active Haileybury Landfills.
1
Janie Brenner
Cost Estimator
Education
Technologist Diploma, Terrain and Water Resource Management, Sir Sandford Fleming College
Technician Diploma, Terrain and Water Resource Management, Sir Sandford Fleming College
Professional Registrations
Canadian Certified Environmental Practitioner (CCEP), 2011
Distinguishing Qualifications
Over 8 years’ experience in the environmental industry
Relevant Experience
Janie Brenner joined the Environmental Services Business Group (ESBG) in CH2M HILL’s Kitchener, Ontario office
in 2012. She brings with her over 8 years of experience in the environmental industry, 6 years of which were spent
working as a project manager and estimator for an environmental construction firm.
Representative Projects and Dates of Involvement
Remedial Construction Estimating, Environmental Task; Former Amherstburg Manufacturing Facility,
Environmental Site Assessment, Risk Assessment, Remedial Planning, Contract Administration and Demolition
Oversight; Confidential Client, 2010 to Present. CH2M HILL was retained to provide environmental advisory and
construction management services for the decommissioning of a large abandoned chemical manufacturing
facility. Services provided have included Phase Two ESAs, Risk Assessment activities, preparation of tender
documents and tendering for facility demolition and remediation services, project administration and
construction oversight. Work is being conducted with regular consultation with the client, the public, and
municipal and regulatory personnel. Onsite environmental activities have been coordinated with the demolition
of over 300,000 ft
2
of manufacturing space, with strict observance of health and safety protocols.
Experience Prior to CH2M HILL
Lead Estimator; Deloro Mine Site; Industrial and Mine Area Cleanup Phase 1; Ontario Ministry of the
Environment (MOE); Deloro, ON; August 2011. Acted as lead estimator for the request for proposal (RFP).
Worked with a team to ensure the successful submission of a compliant proposal. Major responsibilities included
reviewing and understanding the scope of work and all associated supporting documents, procuring competitive
material and subcontractor quotes, completing a detailed costs estimate, and composing a 200 page technical
proposal. The RFP award was based on a pass or fail on the technical proposal followed by award to the lowest
bidder. Following the project award, worked with the assigned project manager and completed a comprehensive
handoff.
Lead Estimator; Victoria Park Lake Improvement; City of Kitchener; Kitchener, ON; October 2011. Acted as lead
estimator for the RFP. Worked with a team to ensure the successful submission of a compliant bid. Major
responsibilities included reviewing and understanding of the scope of work and all associated supporting
documents, procuring competitive material and subcontractor quotes, and completing a detailed costs estimate.
Due to the nature of the work, bench scale testing was completed to evaluate various solidification technologies
in preparation for the submission.
Project Manager; Aboriginal Heavy Equipment Training Program; ECO Canada and Government of Manitoba,
Mineral Resources Division; Lynn Lake, MB; November 2011. The project comprised the execution of a 3‐week
heavy equipment training program for a group of 10 Aboriginal people. Janie’s work included creating a training
curriculum, selecting candidates, and coordinating the field training activities.
Janie Brenner
2
Project Manager; Aboriginal Heavy Equipment Training Program; Manitoba Entrepreneurship, Training, and
Trade (METT), Government of Manitoba; Lynn Lake, MB; November 2011. The project comprised the execution
of a 4‐week, heavy equipment training program for a group of 12 Aboriginal people. The work included the
creating a training curriculum, selecting candidates, and coordinating the field training activities.
Lead Estimator & Project Manager; City of Barrie Landfill Reclamation and Cell 2B/2B Cell Construction; City of
Barrie; Barrie, ON; March 2010 to 2011. Acted as lead estimator and later as project manager for the first year of
the 3‐year project. The scope of work consisted of the excavation and screening of over 684,000 cubic metres (m
3
)
of municipal solid waste (MSW), the segregation of waste from fines, the placement and compaction of screen
waste, and the construction of three new engineered landfill cells.
Estimator; City of Barrie Landfill Gas Collection System Installation; City of Barrie; Barrie, ON; July 2011. Acted
as lead estimator for the successful submission of the RFP.
Project Manager; Leachate Toe Drain Installation; Waste Management Corporation; Petrolia, ON; March 2011.
Acted as project manager for the installation of a leachate toe drain in an existing industrial and municipal landfill.
The scope of work included the excavation of a 5 to 7 metre (m)‐deep trench, the placing of a drainage stone, the
installation of an 8‐inch high density polyethylene (HDPE) pipe and the management of leachate within the
work area.
Project Manager & Estimator; Interior Soil Remediation; Markham Road Apartments Ltd.; Toronto, ON;
June 2011. Acted as estimator and project manager for the remediation of hydrocarbon‐impacted soils located in
the basement of a high‐rise residential apartment building. The scope of work included the procurement of
building permits, the interior demolition of a shower and sauna room, the excavation and disposal of impacted
soil, the management of impacted groundwater, and the restoration of the site. To facilitate the work and reduce
the requirement for manual labour, a pass‐through entrance was installed in the concrete foundation wall below
ground, and heavy equipment was utilized to complete the work.
Project Manager; Trichloroethene (TCE)‐Impacted Soil Remediation; Confidential Client; Hamilton, ON;
September 2011. Oversaw the remediation of TCE‐impacted soil in Hamilton. Over 8000 tonnes of impacted soils
were excavated and 600,000 litres (L) of impacted water was treated onsite through a mobile water treatment
system. Because of the nature of the contaminants, air quality was continuously monitored and a portion of the
work was completed under supplied air.
Lead Estimator; St. Catharines Dump Site Remediation; Public Works and Government Services Canada
(PWGSC); St. Catharines, ON; January 2010. Acted as lead estimator for this request for quotation (RFQ) and
successfully submitted the winning bid. The scope of work consisted of excavating the site.
Project Manager; Cell Construction and Automotive Shredder Residue (ASR) Management; Gerdau AmeriSteel;
Whitby, ON; June 2008. Managed the construction of a landfill cell and the daily hauling, placement, and
compaction of ASR for the recycling division. Due the team’s creative thinking, the project realized significant cost
savings by using agricultural equipment instead of traditional heavy equipment.
Project Manager; Tanks Farm Demolition; Confidential Client; St. George, ON; March 2009. Managed the
demolition of six large aboveground fuel storage tanks located within a former bulk processing facility. The tanks,
which measured between 34 and 46 feet in diameter, were sheared in sections and the scrap was processed and
shipped offsite for recycling.
Project Manager; Soil Remediation; Confidential Client; Hanover, ON; November 2009. Acted as project
manager for the remediation of hydrocarbon‐impacted soil. Approximately 6,000 tonnes of impacted soils were
excavated and shipped offsite for disposal while 4,000 tonnes of clean fill was excavated and segregated onsite.
Impacted groundwater was also collected and treated onsite.
1
Ryan Manning
Contract Administration/Tender Documents
Education
B.Sc. (Eng.) (Honours), Environmental Civil Engineering, University of Guelph
Professional Registrations
Professional Engineer: Ontario (No. 100079585)
Professional Engineer: Alberta (No. 98049)
Relevant Experience
Ryan Manning joined CH2M HILL’s Environmental Business (ES) Team in the Site and Sediment Management
Business Group in 2005. He is an intermediate project engineer with more than ten years experience in
environmental investigations and remediation projects including waste management. He is experienced in the
development and coordination subsurface investigation and remediation for metals contamination, petroleum
hydrocarbon, and chlorinated solvent contamination in both the soil and groundwater systems. In addition, Ryan has
developed and managed/conducted various pump and treat and in‐situ groundwater remediation systems. He is
experienced and qualified in borehole installation, monitoring well instrumentation, groundwater development and
sampling, surface water sampling, leachate sampling, landfill gas sampling, soil sampling, waste characterization
sampling, test pit installation, confirmatory sampling, soil vapour sampling, and surveying. Ryan’s experience
includes coordination and completion of municipal landfill annual monitoring and progress programs involving
groundwater, surface water, leachate and landfill gas monitoring requirements, design and construction oversight of
leachate collection systems, landfill cell base preparations, and landfill gas collection systems.
Representative Projects and Dates of Involvement
Contract Administration; Environmental Site Assessment (ESA) and Preparation of Remediation Strategy;
Sydenham Pearl Brownfield; City of Brantford; Brantford, Ontario; 2012. The Sydenham Pearl Brownfield
consists of two parcels of land in downtown Brantford, both with industrial legacies dating back to the early
1900s. CH2M HILL was retained to conduct Phase One and Two ESAs, and to prepare a Remedial Action Strategy
to revitalize the properties for potential residential development. Work included consultation with city staff, a
public meeting, and presentations to City Council. Work was completed to the satisfaction of the City, the public,
and City Council, and resulted in the approval of funds for implementation of the remedial strategy.
Project Engineer; Former Amherstburg Manufacturing Facility, Environmental Site Assessment, Risk
Assessment, Remedial Planning, Contract Administration and Demolition Oversight; Confidential Client, 2010 to
Present. This project involves the complete demolition of decommissioning of a 300,000 ft
2
, former chemical
production facility. The facility is located in the Town of Amherstburg and is surrounded by mixed land use,
including residential and industrial. The facility was constructed near the turn of the century and as such, the
construction materials contain significant amounts of designated substances. Due to the proximity of the facility
to residential dwellings, hazard and risk mitigation measures were developed and approved by the Ontario
Ministry of the Environment to minimize the potential off site impacts resulting from demolition activities. In
addition, the Site is located within an area with designated Species at risk. Mitigation measures were evaluated
and implemented with the concurrence of the Ontario Ministry of Natural Resources in order to facilitate
completion of the works while protecting the potential species at risk receptors in the area.
Ryan is responsible for coordination of site activities, including waste identification, quantification and
classification, Hazardous Building Material Assessments, Structural Assessments, and cost forecasting, including
salvage value and demolition procedure/scheduling. Ryan prepared construction bid documents including all
technical specifications and drawings, issued addendums to the tender document, and completed tender
evaluation and tender recommendations. Ryan also developed surface water and dust monitoring and mitigation
plans in support of the demolition work and provided onsite supervision of contractors related to building
rehabilitation efforts, the construction of a new site entrance and truck scale.
Ryan Manning
2
Project Engineer; Risk Assessment for Portlands Divestiture; Public Works Government Services Canada
(PWGSC); Port Stanley, Ontario; 2008 to Present. Lead the development of a detailed cost estimate for
remediation as part of a comprehensive project involving a contaminated site investigations and risk assessment
to assess soil/groundwater conditions in uplands assessment and sediment contamination in waterlots. The
investigation was completed to facilitate the divestiture of federal lands to a local municipality. The risk
assessment was completed to federal and provincial standards leading to filing of a Record of Site Condition. Lead
the development of RAPs and order of magnitude cost estimates.
Project Engineer; Demolition of Former Industrial Facility, Reichhold Industries Limited, Burlington, Ontario;
2011 – Present. Responsible for preparation of construction bid documents including all technical specifications
and drawings. Issuing addendums to the tender document through the bid period and evaluation and tender
recommendation. Completed construction cost estimates for the demolition activities. The construction
component of this project will commenced in fall 2011 and will be completed in the summer 2012.
Construction Engineer/Inspector; Confidential Client Site; Sarnia, Ontario; September 2008 to Decmeber 2011.
Provided engineering evaluation of tenders and subcontractor selection followed by onsite supervision to provide
construction inspection and subcontractor management. Project work related to segregation of approximately
15,000 cubic metres of hazardous and non‐hazardous soil containing various VOC compounds. This excavation
was completed directly adjacent to a major U.S. – Canadian waterway. Excavated soils were either land filled or
treated at a soil treatment facility (approximately $1MM). Further remedial actions completed to date are: Zero‐
Valent Iron placement in reactive barriers for the treatment of chlorinated volatile organic compounds, pneumatic
fracturing and injection of emulsified vegetable oil in 40 locations, excavation and disposal of selected “hot‐spot”
free‐phase containing soils and phytoremediation.
Project Engineer; Contaminated Site Investigation and Remedial Action Plans; Standing Offer for Environmental
Consulting Services; DCC; DRDC Experimental Proving Grounds, Suffield, Alberta; 2009 to 2010. Scope of
services included peer review and data gap analysis of previous studies and investigations, UXO demilitarization
planning, contaminated sites investigation and assessment, remedial action planning, design and implementation
of technology evaluations and risk assessments for more than 50 APECs impacted by munitions, nuclear, biological
and chemical (NBC) agents, and environmental contamination in accordance with FCSAP. Services commissioned
to date include GIS, data management, technology reviews / feasibility studies, geophysical investigation review,
pilot field investigation and development of investigation work plans. Led the development of contaminated site
investigation work plans as well as implementation of field activities.
Project Engineer; Phase III Environmental Site Assessment, Squirrel Island, Ontario; PWGSC; 2010 to Present.
Retained by PWGSC on behalf of the Fisheries and Oceans Canada (DFO) to provide lateral and vertical delineation
of metal related contamination in association with APECs at a marine navigation light. Remedial options were
evaluated and the preferred remedial program was recommended. The results of the Phase III ESA field program
were used to update the NCSCS score for the site.
Project Engineer; Deloro Mine and Smelter Site Cleanup; Ontario Ministry of the Environment; Belleville,
Ontario; 1997 to 2010. Led the development of investigation work plans, design, specifications (based on NMS),
and contractor oversight for a pilot scale remedial action plan. Work as part of a $9.4 million contract for a
multi‐year period to develop remediation action plans for cleanup of hazardous and radioactive wastes. The scope
involved site investigation planning, intrusive (that is, test pit/ boreholes) and non‐intrusive (that is, geophysical
surveys) investigation, technology, and feasibility reviews (that is, containment, and stabilization), detailed design,
approvals (federal EA, Species at Risk, and DFO permits), health and safety plans, analytical testing, and
developing cost estimates.
431602_ES010612182309KWO
USE OR DISCLOSURE OF DATA CONTAINED ON THIS SHEET IS SUBJECT TO
THE RESTRICTION ON THE BACK OF THE TITLE PAGE OF THIS PROPOSAL.
Appendix B
Charts and Schedules
ID Task Name Duration Start Finish
1 Project Administration 500 days Mon 6/17/13 Fri 5/15/15
2 Risk Assessment 500 days Mon 6/17/13 Fri 5/15/15
3 Presubmission Forms 40 days Mon 6/17/13 Fri 8/9/13
4 MOE Review of PSFs 30 days Mon 8/12/13 Fri 9/20/13
5 Data Interpretation and Report
Preparation
50 days Mon 8/12/13 Fri 10/18/13
6 Allowance for Intrusive Work 70 days Mon 6/17/13 Fri 9/20/13
7 MOE Review of RAs 80 days Mon 10/21/13 Fri 2/7/14
8 Finalization of Draft RAs 20 days Mon 2/10/14 Fri 3/7/14
9 MOE Approval 20 days Mon 3/10/14 Fri 4/4/14
10 Remediation Report and Final RA 30 days Mon 3/9/15 Fri 4/17/15
11 Filing of RSC 20 days Mon 4/20/15 Fri 5/15/15
12 Review of Remedial Strategy 30 days Mon 4/7/14 Fri 5/16/14
13 Contact Administration, Award and
Oversight
280 days Mon 2/10/14 Fri 3/6/15
14 Prequalification of Contractors 40 days Mon 2/10/14 Fri 4/4/14
15 Preparation of Tender Documents 30 days Mon 5/19/14 Fri 6/27/14
16 Tendering and Contract Award 40 days Mon 6/30/14 Fri 8/22/14
17 Contract Oversight 7 mons Mon 8/25/14 Fri 3/6/15
18 Contingency 126 days Mon 3/9/15 Mon 8/31/15
19 Communication strategy 478 days Thu 6/20/13 Mon 4/20/15
20 Technical meeting no. 1, Kick-off
Meeting
1 day Thu 6/20/13 Thu 6/20/13
21 Technical meeting no. 2, Review
of RA
1 day Mon 10/21/13 Mon 10/21/13
22 Technical meeting no. 3, Review,
Contractor
Prequalification
1 day Thu 4/10/14 Thu 4/10/14
23 Technical meeting no. 4,
Finalization, Remedial
Strategy
1 day Mon 5/19/14 Mon 5/19/14
24 Technical meeting no. 5, Review
of Bids
1 day Mon 8/25/14 Mon 8/25/14
25 Technical meeting no. 6,
Remediation Closure
1 day Mon 3/9/15 Mon 3/9/15
26 Public meeting no. 1, Overview
Proposed Work & Schedule
1 day Thu 6/27/13 Thu 6/27/13
27 Public meeting no. 2, Remediation
Plan
1 day Tue 9/9/14 Tue 9/9/14
28 Public meeting no. 3, Remediation
Closure
1 day Thu 3/12/15 Thu 3/12/15
29 Council Meeting 1 day Mon 4/20/15 Mon 4/20/15
Project Administration
Risk Assessment
Presubmission Forms
MOE Review of PSFs
Allowance for Intrusive Work
MOE Review of RAs
Finalization of Draft RAs
MOE Approval
Remediation Report and Final RA
Filing of RSC
Review of Remedial Strategy
Contact Administration, Award and Oversight
Prequalification of Contractors
Preparation of Tender Documents
Tendering and Contract Award
8/25 3/6
Contract Oversight
Contingency
Communication strategy
6/20
10/21
4/10
5/19
8/25
3/9
6/27
9/9
3/12
Council Meeting
4/20
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
2013 2014 2015
Task Split Progress Milestone Summary Project Summary External Tasks External Milestone Deadline
Page 1
Project: Project schedule July start_r2
Date: Wed 4/10/13
Summary of Estimated Costs Revised 4/10/2013
Classification Level P
ro
je
ct
L
e
a
d
Q
u
a
li
fi
e
d
P
e
rs
o
n
(Q
P
E
S
A
)
C
o
m
m
u
n
ca
ti
o
n
s
Le
a
d
P
ri
n
ci
p
a
l/
S
e
n
io
r
A
d
v
is
o
r
S
it
e
A
ss
e
ss
m
e
n
t
Le
a
d
H
y
d
ro
g
e
o
lo
g
is
t
E
n
v
ir
o
n
m
e
n
ta
l
T
e
ch
n
ic
ia
n
P
ro
je
ct
E
n
g
in
e
e
r
P
ro
je
ct
C
h
e
m
is
t
G
IS
L
e
a
d
R
is
k
A
ss
e
ss
o
r
(I
n
t.
S
ci
e
n
ti
st
)
Ju
n
io
r
S
ci
e
n
ti
st
/
E
n
g
in
e
e
r
H
e
a
lt
h
&
S
a
fe
ty
P
u
b
s
R
e
m
e
d
ia
ti
o
n
S
tr
a
te
g
y
L
e
a
d
R
e
m
e
d
ia
l
O
p
ti
o
n
s
C
o
n
st
ru
ct
io
n
L
e
a
d
H
u
m
a
n
H
e
a
lt
h
R
is
k
A
ss
e
ss
m
e
n
t
S
e
n
io
r
R
is
k
A
ss
e
ss
m
e
n
t
A
d
v
is
o
r
E
co
lo
g
ic
a
l
R
is
k
A
ss
e
ss
o
r
T
e
n
d
e
r
D
o
cu
m
e
n
ts
/C
o
n
tr
a
ct
s
A
d
m
in
is
tr
a
ti
o
n
P
D
L
K
A
A
d
m
in
is
tr
a
ti
o
n
/A
cc
o
u
n
ti
n
g
C
o
st
E
st
im
a
to
r
Labour
Subtotal
Personnel E
d
T
a
v
e
s
K
u
rt
H
a
n
se
n
M
e
g
g
e
n
J
a
n
e
s
B
ri
a
n
W
h
if
fi
n
D
ir
k
S
ch
e
u
rl
e
n
Ji
n
lo
n
g
Z
a
n
g
Ja
m
ie
F
re
e
m
a
n
T
a
n
ia
M
cC
a
rt
h
y
A
lm
u
d
e
n
a
C
a
m
a
ch
o
A
p
ri
l
B
a
te
s
A
n
d
re
a
W
o
jt
y
n
ia
k
T
B
D
Li
sa
M
o
ff
a
t
T
B
D
W
a
y
n
e
C
o
o
le
y
D
a
v
e
F
a
rr
is
h
T
e
rr
y
L
o
re
n
tz
K
ri
st
a
B
a
rf
o
o
t
K
e
n
zi
e
Ja
m
e
s
S
p
re
n
g
e
r
Ji
m
K
ro
e
ts
ch
R
y
a
n
M
a
n
n
in
g
P
a
u
l
P
a
ss
a
le
n
t
A
id
e
e
n
H
a
m
il
to
n
T
B
D
Ja
n
ie
B
re
n
n
e
r
Allowance
Amount Description
Task Work Element Task Description
Rate ($/hour)
(March 1, 2012 to
March 1, 2013)
$
1
5
0
.0
0
$
1
5
0
.0
0
$
1
5
0
.0
0
$
1
7
5
.0
0
$
1
5
0
.0
0
$
1
2
5
.0
0
$
1
0
0
.0
0
$
1
0
0
.0
0
$
1
0
0
.0
0
$
1
0
0
.0
0
$
1
2
5
.0
0
$
1
0
0
.0
0
$
8
0
.0
0
$
7
0
.0
0
$
1
5
0
.0
0
$
1
2
5
.0
0
$
1
5
0
.0
0
$
1
7
5
.0
0
$
1
7
5
.0
0
$
1
7
5
.0
0
$
1
2
5
.0
0
$
1
5
0
.0
0
$
1
5
0
.0
0
$
7
0
.0
0
$
1
1
0
.0
0
1 Project Management Project Management 192 2 4 192
Subcontracts/POs 40 30
Meetings 40
4,000.00
Allowance for travel and other costs that may be incurred over the 2
years of the project.
Total Task Hours 272 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 2 4 222 0 500
Task Subtotal $40,800 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $300 $600 $15,540 $0 $57,240 $4,000
2 Risk Assessment ‐ 17 Sydenham Presubmission Form 7 20 20 4 4 4 2
Data Interpretation and Report Preparation 14 8 20 40 40 24 24 120 16 80 20 80 0
Allowance for Intrusive Work 8 8 40 80 20 20 16 8 40,191.00 Allowance for additional intrusive field work as may be required.
Design of RMMs 2 40 24 24 40
Finalization of Draft RA 4 4 4 8 20 8 16 20 8 10 10 10 0
Remediation Report and Final RA 8 40 1 20 8 10 40 8 10 8
Filing of RSC 4 20 4 40 8 4 4 2 2
Total Task Hours 47 80 0 1 88 56 90 180 68 70 200 0 8 40 0 0 0 120 60 92 40 0 0 0 0 1,240
Task Subtotal $7,050 $12,000 $0 $175 $13,200 $7,000 $9,000 $18,000 $6,800 $7,000 $25,000 $0 $640 $2,800 $0 $0 $0 $21,000 $10,500 $16,100 $5,000 $0 $0 $0 $0 $161,265 $40,191
3 Risk Assessment ‐ 22 Sydenham Presubmission Form 8 20 20 4 4 4 2
Data Interpretation and Report Preparation 14 8 20 40 40 24 24 120 16 80 20 80 0
Allowance for Intrusive Work 8 8 40 80 20 20 16 8 40,191.00 Allowance for additional intrusive field work as may be required.
Design of RMMs 2 40 24 24 40
Finalization or Draft RA 4 4 4 8 20 8 16 20 8 10 10 10 0
Remediation Report and Final RA 8 40 1 20 8 10 40 8 10 8
Filing of RSC 4 20 4 40 8 4 4 2 2
Total Task Hours 48 80 0 1 88 56 90 180 68 70 200 0 8 40 0 0 0 120 60 92 40 0 0 0 0 1,241
Task Subtotal $7,200 $12,000 $0 $175 $13,200 $7,000 $9,000 $18,000 $6,800 $7,000 $25,000 $0 $640 $2,800 $0 $0 $0 $21,000 $10,500 $16,100 $5,000 $0 $0 $0 $0 $161,415 $40,191
4 Revision of Remedial Strategy Allowance for Review and Revision of Remedial
Strategy
8 8 4 40 16 8 8 40 40 8 20 8,000.00 Allowance for additional field work or other costs required to finalize
the Remedial Strategy.
Total Task Hours 8 8 4 0 40 16 0 0 0 8 0 0 0 8 40 40 8 0 0 0 0 0 0 0 20 200
Task Subtotal $1,200 $1,200 $600 $0 $6,000 $2,000 $0 $0 $0 $800 $0 $0 $0 $560 $6,000 $5,000 $1,200 $0 $0 $0 $0 $0 $0 $0 $2,200 $26,760 $8,000
5 Prequalification of Contractors 4 2 4 4 2 8 80 8
Preparation of Tender Documents ($50K for all
tendering)
16 4 24 40 16 8 16 40 80 120 20
Tendering and Contract Award ‐ Environmental 8 2 4 8 20
Contract Oversight 252 252 1890 40 8 56 126 51,625.00 Assumed field costs of $150/day for vehicle, gas, cell phone, meals
to a total of 23,625 for 7months (7 months or 157.5 days). $28,000
for laboratory and other expenses.
Total Task Hours 280 0 0 8 280 0 1890 44 0 60 0 0 16 18 96 0 222 0 0 0 220 0 0 0 28 3,162
Task Subtotal $42,000 $0 $0 $1,400 $42,000 $0 $189,000 $4,400 $0 $6,000 $0 $0 $1,280 $1,260 $14,400 $0 $33,300 $0 $0 $0 $27,500 $0 $0 $0 $3,080 $365,620 $51,625
6 Communications Strategy Technical Staff Meeting #1 ‐ Kick‐off 4 4 4
100
Technical Staff Meeting #2 ‐ RA Review 6 6 6 6 100
Technical Staff Meeting #3 ‐ Contractor
Prequalification
6 6 8
100
Technical Staff Mtg #4 ‐ Finalization of Remedial
Options
6 6 6 6
100
Public Information Session #1 (RA and Remedial
Options) 250
Meeting Preparation 4 4 4 8 8 4 4
Review with Brantford 4
Attend meeting 6 6 6 6 6
Technical Staff Meeting #5 ‐ Review of Bids 6 6 100
Public Information Session #2 (Presentation of
Remediation Team) 250
Meeting Preparation 4 4 4 8 8 4 4
Review with Brantford 4
Attend meeting 6 6 6 6 6
Technical Staff Meeting #6 ‐ Remediation Closure 6 6 6 100
Public Information Session #3 (Remediation Closure) 250
Meeting Preparation 8 8 8 8 8
Review with Brantford 6
Attend meeting 6 6 6
Council Meeting 8 4 8 8 6 100
Total Task Hours 90 60 64 0 0 0 0 32 0 30 0 0 0 0 26 0 22 0 16 0 0 0 0 0 8 348
Task Subtotal $13,500 $9,000 $9,600 $0 $0 $0 $0 $3,200 $0 $3,000 $0 $0 $0 $0 $3,900 $0 $3,300 $0 $2,800 $0 $0 $0 $0 $0 $880 $49,180 $1,450
Total Hours ‐ All Tasks 745 228 68 10 496 128 2070 436 136 238 400 0 32 106 162 40 252 240 136 184 300 2 4 222 56 6,691
Total Cost ‐ All Tasks $111,750 $34,200 $10,200 $1,750 $74,400 $16,000 $207,000 $43,600 $13,600 $23,800 $50,000 $0 $2,560 $7,420 $24,300 $5,000 $37,800 $42,000 $23,800 $32,200 $37,500 $300 $600 $15,540 $6,160 $821,480 $145,457
Total Costs (Labour and Cost Allowances, excluding taxes) $966,937
Contract Administration and Contract
Oversight
Summary of Estimated Costs
Expense Allowances
RFP 12‐04 Enviornmental Consulting Services Required to Complete a Remediation Strategy
for the Sydenham Pearl Brownfield Site ‐ Labour Summary
Page 1 of 1