Semester Project–Developing a Project Risk Management Plan (500 marks)
As part of the semester project, students will
develop a set of project risk management planning documents
to be discussed in detail in the first face-to-face session. Main tasks to be accomplished are:
1. Students will select a hypothetical project or draw from a current work project and develop a project charter for the chosen project (Milestone 1; submission deadline 02/18/2020 at 11:59 pm; 50 marks)
2. Create risk management documents based upon templates, techniques, and examples provided in the PMI Practice standard for project risk management:
1. Risk Identification, Risk Register and Stakeholder List (Milestone 2; submission deadline 03/10/2020 at 11:59 pm; 50 marks)
2. Qualitative and Quantitative Risk Analysis Report (Milestone 3; submission deadline 04/07/2020 at 11:59 pm; 100 marks)
3. Risk management plan (cumulative) (Milestone 4; submission deadline 05/05/2020 at 11:59 pm; 300 marks)
Your final submission is a cumulative submission in which you combine the outputs from milestones 1, 2, and 3. This submission is the risk management plan for your selected project. It must consist of the following two parts:
1. Part 1 (presentation (submit as a separate file)):
1. Describe the general approach to managing risk on your project (one slide)
2. Define specific approaches, tools, and data sources that were used to perform the risk management on the project (one slide)
3. Risk categories used and risks identified (one slide)
4. Stakeholder summary–identification and risk appetite (one slide)
5. Result of qualitative risk analysis (one slide)
6. Result of quantitative risk analysis (one slide)
7. Risk responses planned for the project (one slide)
8. Strategies for implementing risk responses and monitoring risks (one slide)
9. Summary and conclusions (one slide)
2. Part 2 (PDF (submit as a separate file))
1. Outputs from Milestones 1, 2 and 3 after incorporating comments from the instructors and any other changes/improvements
Rubric
Semester Project Milestone 4 Rubric
Semester Project Milestone 4 Rubric | ||
Criteria |
Ratings |
Pts |
This criterion is linked to a Learning OutcomePresentation content and analysis |
200.0 to >175.0 pts Above expectations 175.0 to >140.0 pts Meets expectations 140.0 to > 100.0 pts Provides most of the required components 100.0 to >0 pts Below expectations |
200.0 pts |
This criterion is linked to a Learning OutcomeFinalized Outputs from Milestones 1, 2 and 3 |
100.0 to >85.0 pts Above expectations 85.0 to >70.0 pts Meets expectations 70.0 to >50.0 pts Provides most components 50.0 to >0 pts Below expectations |
100.0 pts |
Total Points: 300.0 |
Previous
Semester Project–Developing a Project Risk Management Plan (500 marks)
As part of the semester project, students will
develop a set of project risk management planning documents
to be discussed in detail in the first face-to-face session. Main tasks to be accomplished are:
1. Students will select a hypothetical project or draw from a current work project and develop a project charter for the chosen project (Milestone 1; submission deadline 02/18/2020 at 11:59 pm; 50 marks)
2. Create risk management documents based upon templates, techniques, and examples provided in the PMI Practice standard for project risk management:
1. Risk Identification, Risk Register and Stakeholder List (Milestone 2; submission deadline 03/10/2020 at 11:59 pm; 50 marks)
2. Qualitative and Quantitative Risk Analysis Report (Milestone 3; submission deadline 04/14/2020 at 11:59 pm; 100 marks)
3. Risk management plan (cumulative) (Milestone 4; submission deadline 05/05/2020 at 11:59 pm; 300 marks)
For milestone 3, you are required to use the risk register and stakeholder list to perform Qualitative and Quantitative Risk Analysis for your selected project. Follow the steps provided below:
· Use the Probability and Impact Matrix to perform a qualitative risk analysis
· Select one of the quantitative risk analysis techniques (Decision Tree Analysis, Expected Monetary Value, Fault Tree Analysis, Monte Carlo Simulation, or System Dynamics) and perform the analysis using the selected technique
· Summarize your results and compile analysis from step 1 and 2. Make sure to include important assumptions you made while carrying out the analysis.
Please see Chapter 11, Section 11.3 and 11.4 of the PMBOK Guide and Chapters 6 and 7 of the Practice standard for project risk management.
Rubric
Semester Project Milestone 3 Rubric
Semester Project Milestone 3 Rubric | ||||
Criteria |
Ratings |
Pts |
||
This criterion is linked to a Learning OutcomeQualitative Risk Analysis |
40.0 to >34.0 pts Analysis above expectations 34.0 to >28.0 pts Analysis meets expectations 28.0 to >16.0 pts Analysis provides most of the required components 16.0 to >0 pts Analysis below expectations |
40.0 pts |
||
This criterion is linked to a Learning OutcomeQuantitative Risk Analysis |
||||
This criterion is linked to a Learning OutcomeSummary of results |
20.0 to >15.0 pts Excellent summary 15.0 to >10.0 pts Good summary 10.0 to >8.0 pts Fair summary 8.0 to >0 pts Summary below expectations |
20.0 pts |
||
Total Points: 100.0 |
Previous
Next
Plan Risk Management
MGMT 767 Risk Management (Lecture 2)
February 18, 2020
Weekly Objectives
• Define the inputs, tools and techniques, output of plan risk management
process
• Analyze the project and tailor the risk management activities to the project
• Identify and address barriers to project risk management
Project Risk Management Processes
• The process of defining how to conduct risk management activities for a
project
Plan Risk Management
• The process of identifying individual project risks as well as sources of overall project risk, and documenting
their characteristicsIdentify Risks
• The process of prioritizing individual project risks for further analysis or action by assessing their probability
of occurrence and impact as well as other characteristicsPerform Qualitative Risk Analysis
• The process of numerically analyzing the combined effect of identified individual project risks and other
sources of uncertainty on overall project objectivesPerform Quantitative Risk Analysis
• The process of developing options, selecting strategies, and agreeing on actions to address overall project
risk exposure, as well as to treat individual project risksPlan Risk Responses
• The process of implementing agreed-upon risk response plansImplement Risk Responses
• The process of monitoring the implementation of agreed-upon risk response plans, tracking identified risks,
identifying and analyzing new risks, and evaluating risk process effectiveness throughout the project
Monitor Risks
Why Do Projects Fail?
• 75% of projects fail:
• They are actually impossible
• They are over-constrained (or under-resourced)
• They are not competently managed
Project Success versus Project Management Success
Key Ideas for Project Risk Planning
• Project selection affects risk management and depends on it
• Project risk management builds on the foundation provided by
project definition and planning
• A project risk plan summarizes your risk management approach
Project Selection is Important
• Optimism bias
• Limited resources
• Priorities misaligned
• Funding issues
• Unrealistic schedule
• Limited organizational capabilities
When Planning for Risk Management
• Pay attention to factors that are:
• Above the Project Level
• At the Project Level
Project Management Processes
Initiating
Process
Planning
Process
Executing
Process
Closing
Process
Monitoring and Controlling
Process
Project
Start
Project
End
Plan Risk
Responses
Perform
Quantitative
Risk Analysis
Perform
Qualitative
Risk Analysis
Identify Risks
Plan Risk
Management
Monitor Risks
Plan Risk Management
• How to conduct risk management activities for a project
• Ensures that the degree, type, and visibility of risk management are
proportionate to both risks and the importance of the project to the
organization and other stakeholders
• Performed once or at predefined points in the project
• Early in the project
• If risk management plan requires modifications
• Major phase changes
• Changes to scope etc.
Data Flow
Source: PMBOK 6th edition
Input 1: Project Charter
• Authorizes the project
• High-level project description
• Overall projects risk
• Key stakeholder list
• High-level requirements
Input 2: Project Management Plan
• How the project will be executed, monitored, controlled, and closed
• Subsidiary management plans—10 knowledge areas
• Baselines-scope
• Additional components—change management
• Project Methodology
Input 3: Project Documents
• Stakeholder register
• Details of project’s stakeholders
• Roles of all listed stakeholders
• Stakeholders’ attitudes toward risk
• Risk thresholds
• Roles and responsibilities
Input 4: Enterprise Environmental Factors
• Internal EEFs
• Culture, structure and governance
• External EEFs
• Market related issues
• Social and cultural issues
Input 5: Organizational Process Assets
• Organizational risk policy
• Risk categories—RBS
• Common definitions of risk concepts and terms
• Risk statement formats (e.g., PERIL Database)
• Templates for risk management plan, risk register, and risk report
• Roles and responsibilities
• Authority levels for decision making
• Lessons learned database
Tools and Techniques
• Expert judgement
• Data analysis
•
Stakeholder analysis
• Meetings
Stakeholder analysis
Source: https://www.fin.gov.nt.ca/sites/fin/files/stakeholder_register x
Stakeholder analysis
Output
Plan Risk
Management
Risk Management
Plan
Project
Management Plan
How risk management activities will be structured and performed
Risk Management Plan
Risk
Management
Plan
Risk Strategy—general approach to managing risk
Methodology—approaches, tools and data sources
Roles and Responsibilities—lead, support and team members
Funding—identifies funds for PRM
Timing—when and how often the processes will be performed
Risk Categories—grouping of individual risks
Stakeholder Risk Appetite—risk appetite of key stakeholders
Definition of Risk Probability and Impacts—scale to be used for the project
Probability and Impact Matrix—prioritization of risks
Reporting Format—risk reports
Tracking—documents used to track risk activities
Key Focus of Risk Management Plan
Risk Breakdown Structure
Definitions of Probability and Impacts
Probability and Impact Matrix with Scoring
Summary
• Relationship among Project Risk Management, project management and the management processes of the rest of the
organization
• Separate budget in terms of resources, cost, and time for Project Risk Management
• Cost of responding to risks themselves should be included appropriately in the project budget
• Guidelines and rules for escalating risk-related information to management and other stakeholders
• How to maintain effective communication with the stakeholders to track any changes in stakeholders’ attitudes towards
risk
• Sharing of a common understanding of all terms used to describe the risks, and other critical values and thresholds
• Define subjective scale for qualitative analysis
• Define key numerical values for quantitative analysis
• Template for risk register
• Participation of stakeholders
• Roles and responsibilities
Wrap up and plan for next two
weeks
Quiz 1
• Format (online on Canvas)
• Topics covered (all materials covered till Module 5)
• Date and time (Tuesday, February 25, 2020, 6:30 pm to 9:00 pm)
• Duration (50 minutes)
• Other issues
Weeks 5 and 6
• Identify Risks: risk breakdown structure, risk register
• Discussion posts 5 and 6
• Online Quiz 1 (Week 5)
• Questions
Sources
• Kendrick, T. (2015). Identifying and managing project risk (3rd ed.). New York, NY: AMACOM. ISBN-13:
9780814436080
• Project Management Institute, Inc. [PMI]. (2009). Practice standard for project risk management. Newtown
Square, PA: Project Management Institute. ISBN-13: 9781933890388
• Project Management Institute (PMI). (2017). A guide to the project management body of knowledge
(PMBOK Guide®) (6th ed.). Newtown Square, PA: Project Management Institute. ISBN-13: 9781628251845
Thank you for downloading this
AMACOM eBook.
Sign up for our newsletter, AMACOM BookAlert, and
receive special offers, access to free chapter downloads, and
info on the latest new releases from AMACOM, the book
publishing division of American Management Association
International.
To sign up visit our website: www.amacombooks.org
http://www.amacombooks.org
Identifying
and
Managing
Project Risk
Identifying
and
Managing
Project Risk
Essential Tools for Failure-Proofing Your Project
Third Edition
Tom Kendrick, PMP
American Management Association
New York • Atlanta • Brussels • Chicago • Mexico City • San Francisco
Shanghai • Tokyo • Toronto • Washington, D. C.
Bulk discounts available. For details visit:
www.amacombooks.org/go/specialsales
Or contact special sales:
Phone: 800-250-5308
Email: specialsls@amanet.org
View all the AMACOM titles at: www.amacombooks.org
American Management Association: www.amanet.org
This publication is designed to provide accurate and authoritative information in regard to the subject
matter covered. It is sold with the understanding that the publisher is not engaged in rendering legal,
accounting, or other professional service. If legal advice or other expert assistance is required, the
services of a competent professional person should be sought.
Library of Congress Cataloging-in-Publication Data
Kendrick, Tom.
Identifying and managing project risk : essential tools for failure-proofing your project / Tom
Kendrick. — Third edition.
pages cm
Includes bibliographical references and index.
ISBN 978-0-8144-3608-0 (hardcover)
ISBN 0-8144-3608-0 (hardcover)
ISBN 978-0-8144-3609-7 (ebook)
ISBN 0-8144-3609-9 (ebook)
1. Risk management. 2. Project management. I. Title.
HD61.K46 2015
658.4’04—dc23 2014039980
“PMI” and the PMI logo are service and trademarks of the Project Management Institute, Inc., which
are registered in the United States of America and other nations; “PMP” and the PMP logo are
certification marks of the Project Management Institute, Inc., which are registered in the United States
of America and other nations; “PMBOK,” “PM Network,” and “PMI Today” are trademarks of the
Project Management Institute, Inc., which are registered in the United States of America and other
nations; “. . . building professionalism in project management . . .” is a trade and service mark of the
Project Management Institute, Inc., which is registered in the United States of America and other
nations; and the Project Management Journal logo is a trademark of the Project Management Institute,
Inc.
PMI did not participate in the development of this publication and has not reviewed the content for
accuracy. PMI does not endorse or otherwise sponsor this publication and makes no warranty,
guarantee, or representation, expressed or implied, as to its accuracy or content. PMI does not have any
financial interest in this publication and has not contributed any financial resources.
Additionally, PMI makes no warranty, guarantee, or representation, express or implied, that the
successful completion of any activity or program, or the use of any product or publication, designed to
http://www.amacombooks.org/go/specialsales
http://specialsls@amanet.org
http://www.amacombooks.org
http://www.amanet.org
prepare candidates for the PMP® Certification Examination, will result in the completion or
satisfaction of any PMP® Certification eligibility requirement or standard.
©2015 Tom Kendrick.
All rights reserved.
Printed in the United States of America.
This publication may not be reproduced, stored in a retrieval system, or transmitted in whole or in part,
in any form or by any means, electronic, mechanical, photocopying, recording, or otherwise, without
the prior written permission of AMACOM, a division of American Management Association, 1601
Broadway, New York, NY 10019.
The scanning, uploading, or distribution of this book via the Internet or any other means without the
express permission of the publisher is illegal and punishable by law. Please purchase only authorized
electronic editions of this work and do not participate in or encourage piracy of copyrighted materials,
electronically or otherwise. Your support of the author’s rights is appreciated.
About AMA
American Management Association (www.amanet.org) is a world leader in talent development,
advancing the skills of individuals to drive business success. Our mission is to support the goals of
individuals and organizations through a complete range of products and services, including classroom
and virtual seminars, webcasts, webinars, podcasts, conferences, corporate and government solutions,
business books, and research. AMA’s approach to improving performance combines experiential
learning—learning through doing—with opportunities for ongoing professional growth at every step of
one’s career journey.
Printing number
10 9 8 7 6 5 4 3 2 1
http://www.amanet.org
Contents
Acknowledgments
Introduction
CHAPTER 1: Why Project Risk Management?
The Doomed Project • Risk • Opportunities and Risks • Benefits of
Project Risk Management • Costs of Project Risk Management • The
Project Risk Management Process • Anatomy of a Failed Project: The
First Panama Canal Project
CHAPTER 2: Planning for Risk Management
Project Selection • Overall Project Planning Processes • Defining Risk
Management for the Project • Risk Management Infrastructure for the
Organization • The PERIL Database • A Second Panama Canal
Project: Sponsorship and Initiation (1902–1904)
CHAPTER 3: Identifying Project Scope Risk
Sources of Scope Risk • Defining Deliverables • High-Level Risk
Assessment Tools • Setting Limits • Work Breakdown Structure •
Other Scope-Related Risks • Documenting the Risks • Panama Canal:
Setting the Objective (1905–1906)
CHAPTER 4: Identifying Project Schedule Risk
Sources of Schedule Risk • Activity Definition • Estimating Activity
Duration • Activity Sequencing • Documenting the Risks • Panama
Canal: Planning (1905–1907)
CHAPTER 5: Identifying Project Resource Risk
Sources of Resource Risk • Resource Planning • Staff Acquisition •
Outsourcing • Effort Estimates Adjusted for Risk • Cost Estimates,
Budgets, and Risk • Documenting the Risks • Panama Canal:
Resources (1905–1907)
CHAPTER 6: Managing Project Constraints and Documenting Risks
Analyzing Constraints • Managing Opportunities • Scope Modification •
Resource Modification • Schedule Modification • Assessing Options
and Updating Plans • Seeking Missing Risks • Creating a Risk
Register • Panama Canal: Improving the Plan (1906)
CHAPTER 7: Quantifying and Analyzing Activity Risks
Qualitative and Quantitative Risk Analysis • Probability and Impact •
Qualitative Risk Assessment • Quantitative Risk Assessment •
Panama Canal: Risks (1906–1914)
CHAPTER 8: Managing Activity Risks
Root Cause Analysis • Categories of Risk • Selecting Risks to Address
• Risk Response Planning • Dealing with Risk Causes • Implementing
Preventative Ideas • Dealing with Risk Effects • Documenting Your
Risk Plans and Risk Owners • Managing a Specific Risk • Bow Tie
Analysis for Documenting Risk Responses • Panama Canal: Risk
Plans (1906–1914)
CHAPTER 9: Quantifying and Analyzing Project Risk
Project-Level Risk • Aggregating Risk Responses • Project Modeling
and Simulations • Integrated Schedule/Cost Assessment • System
Analysis • Critical Chain Considerations • Questionnaires and Surveys
• Analysis of Scale • Project Appraisal • Scenario Analysis • Project
Metrics • Financial Metrics • Panama Canal: Overall Risks (1907)
CHAPTER 10: Managing Project Risk
Project Documentation Requirements • Project Start-Up • Selecting
and Implementing Project Metrics • Establishing Reserves and
Managing for Contingency • Project Baseline Negotiation • Project
Plan Validation • Specification Change Control • Panama Canal:
Adjusting the Objective (1907)
CHAPTER 11: Monitoring and Controlling Risky Projects
Don’t Panic • Applying the Plan • Project Monitoring • Collecting
Project Status • Metrics and Trend Analysis • Responding to Issues •
Communication and Risk Reporting • Project Archive • Managing Risk
Reserves • Project Reviews and Risk Reassessment • Taking Over a
Troubled Project • Panama Canal: Risk-Based Replanning (1908)
CHAPTER 12: Closing Projects
Project Closure • Project Retrospective Analysis • Panama Canal:
Completion (1914)
CHAPTER 13: Program, Portfolio, and Enterprise Risk Management
Project Risk Management in Context • Program Risk Management •
Portfolio Risk Management • Enterprise Risk Management • Panama
Canal: Over the Years
CHAPTER 14: Conclusion
Choosing to Act • Managing Your Risks • Panama Canal: The Twenty-
First Century
APPENDIX: Selected Detail from the PERIL Database
Scope Risks • Schedule Risks • Resource Risks
Index
About the Author
Free Sample Chapter from The AMA Handbook of Project Management,
Fourth Edition by Paul C. Dinsmore, PMP, and Jeannette Cabanis-
Brewin
Acknowledgments
The third edition of this book rests on more decades of project work
than the earlier editions, as well as many hours of discussion about project
management and project risk (including more than a little good-humored
disagreement). It is also the consequence of many presentations and
workshops on project risk management. Project work described in this book
includes projects I have led at Hewlett-Packard, DuPont, and elsewhere, in
addition to other projects done by colleagues, friends, and workshop
participants from an enormous diversity of project environments. The large
number of project situations that serve as the foundation of this book ensures
that it is aligned with the real world and that it contains ideas that are
practical and effective—not just based on interesting theories.
It is not possible to specifically acknowledge all of the people who
have contributed useful content about projects and risk found in this book,
but I need to single out a few. High among these are my colleagues from the
HP Project Management Initiative team, where I spent more than a decade.
These folks served as a boundless source of wisdom and good examples, and
they were always quick to point out anything I said that was nonsense.
Although all have now moved on, we remain close as friends, as critics, and
as associates. From this group, I am particularly indebted to Richard
Simonds, who diligently reads most of what I write and complains
surprisingly little. I also owe big debts to Terry Ash, Richard Bauhaus, Ron
Benton, Wolfgang Blickle, Charlie Elman, Randy Englund. Denis Lambert,
John Lamy, Patrick Neal, Patrick Schmid, Ted Slater, and Ashok Waran.
I also need to acknowledge others who contributed to this book,
particularly John Kennedy, who ensured that anything I said about statistics
was within defendable confidence limits, and Peter de Jager, who bears many
Y2K risk management scars.
I am also grateful for support, guidance, and constructive criticism
helping to “advance the state of the art” within the project management
RiskSIG, especially Chuck Bosler, Karel de Bakker, Craig Peterson, David
Hulett, David Hillson, Esteri Hinman, Pedro Ribeiro, and Janice Preston.
Finally, my largest debt of gratitude in this endeavor goes to my wife,
Barbara, who encouraged this project, supported it, and read many versions
of the manuscript (including the boring parts). She provided the book with
most of its clarity and a good deal of its logical structure. If the book proves
useful to you, it is largely due to her efforts.
While others have contributed significantly to the content of this book,
any errors, omissions, or other problems are strictly my own. Should you run
into any, let me know.
I also appreciate all the feedback and support from project risk
management facilitators and participants, which have been enormously
helpful in creating this third edition of Identifying and Managing Project
Risk. If you are using this book to conduct training or university classes and
are interested in supplemental materials, please feel free to contact me.
Tom Kendrick
San Carlos, California
tkendrick@FailureProofProjects.com
http://tkendrick@FailureProofProjects.com
Introduction
Your mission, Jim, should you decide to accept it …
So began every episode of the classic TV series Mission: Impossible,
and what followed chronicled the execution of that week’s impossible
mission. The missions were seldom literally impossible, though; careful
planning, staffing, and use of the (seemingly unlimited) budget resulted in a
satisfactory conclusion just before the deadline—the final commercial.
Today’s projects should also probably arrive on a tape that “will self-
destruct in five seconds.” Compared with project work done in the past,
current projects are more time constrained, pose greater technical challenges,
and rarely seem to have enough resources. All of this leads to increased
project risk—culminating too often in the “impossible project.”
As a leader of complex projects, you need to know that techniques
exist to better deal with risk in projects like yours. Used effectively, these
processes will help you recognize and manage potential problems. Often,
they can make the difference between a project that is possible and one that is
impossible. This is what Identifying and Managing Project Risk is about.
Throughout this book, examples from modern projects show how to apply the
ideas presented to meet the challenges you face. This is not a book of
theories; it is based on data collected in the recent past from hundreds of
complex projects worldwide. A database filled with this information, the
Project Experience Risk Information Library (PERIL), forms much of the
foundation for this book. These examples are used to identify sources of risk,
and they demonstrate practical responses that do not always resort to brute
force.
The structure of the book also reflects the changes adopted in the most
recent edition of the Guide to the Project Management Body of Knowledge
(PMBOK® Guide) from the Project Management Institute (PMI®, the
professional society for project managers). The Risk section of the PMBOK®
Guide is one of the key areas tested on the Project Management Professional
(PMP®) certification examination administered by PMI. This book is also
consistent with the PMI® Practice Standard for Project Risk Management
and the topics relevant to the PMI Risk Management Professional (PMI-
RMP®) Certification.
The first half of the book addresses risk identification, which relies
heavily on thorough project definition and planning. The initial six chapters
show the value of these activities in uncovering sources of risk. The
remainder of the book covers the assessment and management of risk, at the
detail (activity) level as well as at the project level and above. These chapters
cover methods for assessing identified risks, establishing an overall risk plan
for the project, making project adjustments, ongoing risk tracking, project
closure, and the relationship between project risk management and program,
portfolio, and enterprise risk management.
It is especially easy on modern projects to convince yourself that there
is little to be learned from the past and that established ideas and techniques
“no longer apply to my project.” Tempting though it is to wear these
hindsight blinders, wise project managers realize that their chances of success
are always improved when they take full advantage of what has gone before.
Neither project management in general nor risk management in particular is
all that new. Broad principles and techniques for both have been successfully
used for more than a century. Even though many lessons can be learned from
current projects (as the PERIL database illustrates), there is also much to be
absorbed from earlier work.
As a graphic reminder of this connection, each chapter in this book
concludes with a short description of how some of the principles discussed
relate to a very large historical project: the construction of the Panama Canal.
Taking a moment every so often to consider this remarkable feat of
engineering reinforces the importance of good project management practices
—and may provide some topical relief from what can be occasionally dry
subject matter.
Risk in projects comes from many sources, including two that are
generally left out of even the better books on the subject: (1) the inadequate
application (or even discouragement) of project management practices and
(2) the all too common situation of wildly aggressive project objectives that
are established without the backing of any realistic plan. These risks are
related because only through adequate understanding of the work can you
detect whether objectives are impossible, and only by using the information
you develop can you hope to do anything about it.
Identifying and Managing Project Risk is intended to help leaders of
today’s complex projects (and their managers) successfully deliver on their
commitments. Whether you develop products, provide services, create
information technology solutions, or deal with complexity in other types of
projects, you will find easy-to-follow, practical guidance to improve your
management of project risk, along with effective practices for aligning your
projects with reality. You will learn how to succeed with seemingly
impossible projects by reducing your risks with minimal incremental effort.
Chapter
1
Why Project Risk Management?
Those who cannot remember the past
are condemned to repeat it.
—GEORGE SANTAYANA
Far too many of today’s projects retrace the shortcomings and errors of
earlier work. Projects that successfully avoid such pitfalls are often viewed as
“lucky,” but there is usually more to it than that.
The Doomed Project
All projects involve risk. There is always at least some level of
uncertainty in a project’s outcome, regardless of what the Microsoft Project
Gantt chart on the wall seems to imply. Modern projects are particularly
risky, for a number of reasons. First, they are complex and highly varied.
These projects have unique aspects and objectives that significantly differ
from previous work, and the environment for complex projects evolves
quickly. In fact, the very opportunities that give rise to today’s projects
contain significant uncertainty, increasing the differences from one project to
the next. In addition, modern projects are frequently “lean,” challenged to
work with minimal funding, staff, and equipment. To make matters worse,
there is a pervasive expectation that, however fast the last project may have
been, the next one should be even quicker. The number and severity of risks
on these projects continue to grow. To avoid a project doomed to failure, you
must consistently use the best practices available.
Good project practices come from experience. Experience,
unfortunately, generally comes from bad project management. We can learn
what not to do by doing it and then dealing with the consequences.
Fortunately, we can also benefit from experience even when it is not our own.
The foundation of this book is the experiences of others—a large collection
of mostly plausible ideas that did not work out as well as hoped.
Projects that succeed generally do so because their leaders do two
things well. First, leaders recognize that much of the work on any project,
even the highest of high-tech projects, is not new. For this work, the notes,
records, and lessons learned on earlier projects can be a road map for
identifying, and in many cases avoiding, many potential problems. Second,
they plan project work thoroughly, especially the portions that require
innovation, in order to understand the challenges ahead and to anticipate
many of the risks.
Effective project risk management relies on both of these ideas. By
looking backward, past failures may be avoided, and by looking forward via
project planning, many future problems can be minimized or eliminated.
Risk
In projects, a risk can be almost any uncertain event associated with the
work. Not all risks are equally important, though. Project leaders must focus
on risks that can materially affect project objectives, or “uncertainty that
matters.” There are many ways to characterize risk. One of the simplest, from
the insurance industry, is:
Loss multiplied by likelihood
Risk is the product of these two factors: the expected consequences of
an event and the probability that the event might occur. All risks have these
two related but distinctly different components. Employing this concept, risk
may be characterized in aggregate for a large population of events (macro
risk), or it may be considered on an event-by-event basis (micro risk).
Both characterizations are useful for risk management, but which of
these is more applicable differs depending on the situation. In most fields,
risk is primarily managed in the aggregate, that is, in the macro sense. As
examples, insurance companies sell a large number of policies, commercial
banks make many loans, gambling casinos and lotteries attract crowds of
players, and managers of mutual funds hold large portfolios of investments.
The literature of risk management for these fields (which is extensive) tends
to focus on large-scale risk management, with secondary treatment for
managing single-event risks.
As a simple example, consider throwing two fair, six-sided dice. In
advance, the outcome of the event is unknown, but through analysis,
experimenting, or guessing, you can develop some expectations. The only
possible outcomes for the sum of the faces of the two dice are the integers
between 2 and 12. One way to establish expectations is to figure out the
number of possible ways there are to reach each of these totals. (For example,
the total 4 can occur in three ways from two dice: 1 + 3, 2 + 2, and 3 + 1.)
Arranging this analysis in a histogram results in Figure 1-1. Because each of
the 36 possible combinations is equally likely, this histogram can be used to
predict the relative probability for each possible total. Using this model, you
can predict the average sum over many tosses to be 7.
Figure 1-1. Histogram of Sums from Two Dice
If you throw the dice many times, the empirical data collected (which
is another method for establishing the probabilities) will generally resemble
the theoretical histogram. However, because the events are random, it is
extraordinarily unlikely that your experiments rolling dice will ever precisely
match the theory. What will emerge, though, is that the average sum
generated in large populations (100 or more throws) will be close to the
expected average of 7, and the shape of the histogram will also be similar to
the predicted theoretical distribution. Risk analysis in the macro sense takes
notice of the population mean of 7, and casino games of chance played with
dice are designed by “the house” to exploit this fact. On the other hand, risk
in the micro sense, noting the range of possible outcomes, dominates the
analysis for casino visitors, who may play such games only once; the risk
associated with a single event—their next throw of the dice—is what matters
to them.
For projects, risk management in the large sense is useful to the
organization where many projects are undertaken. But from the perspective
of the leader of a single project, there is only the one project. Risk
management for the enterprise or for a portfolio of projects is mostly about
risk in the aggregate (a topic explored in Chapter 13). Project risk
management focuses mainly on risk in the small sense, and this is the
dominant topic of this book.
Macro Risk Management
In the literature of the insurance and finance industries, risk is
described and managed using statistical tools: data collection, sampling, and
data analysis. In these fields, a large population of individual examples is
collected and aggregated, and statistics for loss and likelihood can be
calculated. Even though the individual cases in the population may vary
widely, the average loss-times-likelihood tends to be fairly predictable and
stable over time. When large numbers of data points from the population at
various levels of loss have been collected, the population can be characterized
using distributions and histograms, similar to the plot in Figure 1-2. In this
case, each “loss” result that falls into a defined range is counted, and the
number of observations in each range is plotted against the ranges to show a
histogram of the overall results.
Figure 1-2. Histogram of Population Data
Various statistics and methods are used to study such populations, but
the population mean is the main measure for risk in them. The mean
represents the typical loss—the total of all the losses divided by the number
of data points. The uncertainty, or the amount of spread for the data on each
side of the mean, also matters, but the mean sufficiently characterizes the
population for most decisions.
In fields such as these, risk is managed mostly in the macro sense,
using a large population to forecast the mean. This information may be used
to set interest rates for loans, premiums for insurance policies, and
expectations for stock portfolios. Because there are many loans, investments,
and insurance policies, the overall expectations depend on the average result.
It does not matter so much how large or small the extremes are; as long as the
average results remain consistent with the business objectives, risk is
managed by allowing the high and low values to balance each other,
providing a stable and predictable overall result.
Project risk management in this macro sense can be useful at the
project portfolio and enterprise levels. If all the projects undertaken are
considered together, performance primarily depends on the results of the
“average” project. Some projects will fail and others may achieve spectacular
results, but the aggregate performance is what matters to the business’s
bottom line. Chapter 13 explores managing risk at these levels and the
relationship of portfolio and enterprise risk management to project risk
management.
Micro Risk Management
Passive measurement, even in the fields that manage risk using large
populations, is never the whole job. Studying averages is necessary, but it is
never sufficient. Managing risk also involves taking action to influence the
outcomes.
In the world of gambling, which is filled with students of risk on both
sides of the table, knowing the odds in each game is a good starting point.
Both parties also know that if they can shift the odds, they will be more
successful. Casinos shift the game in roulette by adding zeros to the wheel
but not including them in the calculation of the payoffs. In casino games
using cards such as blackjack, casino owners employ the dealers, knowing
that the dealer has a statistical advantage. In blackjack, the players may also
shift the odds by paying attention and counting the cards, but establishments
minimize this advantage through frequent shuffling of the decks and barring
known card counters from play. There are even more effective methods for
shifting the odds in games of chance, but most are not legal; tactics like
stacking decks of cards and loading dice are frowned upon. Fortunately, in
project risk management, shifting the odds is not only completely fair, it is an
excellent idea.
Managing risk in this small sense considers each case separately—
every investment in a portfolio, every individual bank loan, every insurance
policy, and, in the case of projects, every exposure faced by the current
project. In all of these cases, standards and criteria are used to minimize the
possibility of large individual variances above the mean, and actions are
taken to move the expected result. Screening criteria are applied at the bank
to avoid making loans to borrowers who appear to be poor credit risks.
(Disregarding these standards by deviating from this policy and offering so-
called subprime mortgages was responsible for much of the disastrous 2008
worldwide economic downturn.) Insurers either raise the price of coverage or
refuse to sell insurance to people who seem statistically more likely to
generate claims. Insurance firms also use tactics aimed at reducing the
frequency or severity of the events, such as auto safety campaigns. Managers
of mutual funds work to influence the boards of directors of companies
whose stocks are held by the fund. All these tactics work to shift the odds—
actively managing risk in the small sense.
For projects, risk management is almost entirely similar to these
examples, focusing on aspects of each project individually. Thorough
screening of projects at the overall business level attempts to select only the
best opportunities. It would be excellent risk management to pick out and
terminate (or avoid altogether) the projects that will ultimately fail—if only it
were that easy. As David Packard noted many years ago, “Half the projects at
Hewlett-Packard are a waste of time and money. If I knew which half, I
would cancel them.”
Project risk management—risk management in the small sense—works
to improve the chances for each individual project. The leader of a project has
no large population, only the single project; there will be only one outcome.
In most other fields, risk management is primarily concerned with the mean
values of large numbers of independent events. For project risk management,
however, what generally matters most is predictability—managing the
variation expected in the result for this project.
For a given project, you can never know the precise outcome in
advance, but through review of data from earlier work and project planning,
you can improve your predictions of the potential results that you can expect.
Through analysis and planning, you can better understand the odds and take
action to change them. The goals of risk management for a single project are
to establish a credible plan consistent with business objectives and then to
minimize the range of possible outcomes, particularly adverse outcomes.
One type of “loss” for a project may be measured in time. The
distributions in Figure 1-3 compare timing expectations graphically for two
similar projects. These plots are different from what was shown in Figure 1-
2. In the previous case, the plot was based on empirical measurements of a
large number of actual historical cases. The plots in Figure 1-3 are
projections of what might happen for these two projects, based on
assumptions and data for each. These histograms are speculative and require
you to pretend that you will execute the project many times, with varying
results. Developing this sort of risk characterization for projects is explored
in Chapter 9, which discusses quantifying and analyzing project risk. For the
present, assume that the two projects have expectations as displayed in the
two distributions.
Figure 1-3. Possible Outcomes for Two Projects
For these two projects, the average (or mean) duration is the same, but
the range of expected durations for Project A is much larger. Project B has a
much narrower spread (the statistical variance, or standard deviation), and so
it will be more likely to be completed close to the expected duration. The
larger range of possible durations for Project A represents higher risk, even
though it also includes a small possibility of an outcome even shorter than
that expected for Project B. Project risk increases with the level of
uncertainty, both negative and positive.
Project risk management uses the two fundamental parameters of risk
—likelihood and loss—just as any other area of risk management does.
Likelihood is generally characterized as probability and may be estimated in
several ways for project events (though often by guessing, so it can be quite
imprecise). For projects, loss is generally referred to as impact, and it is based
on the consequences to the project if the risk does occur. Impact is usually
measured in time (as in the examples in Figure 1-3) or cost, particularly for
quantitative risk assessment. Other risk impacts include increased effort,
issues with stated deliverable requirements, and a wide range of other more
qualitative consequences that are not easily measured, such as team
productivity, conflict, and impact on other projects or other operations.
Applying these concepts to project risk is covered in Chapter 7.
Managing project risk depends on the project team understanding the
sources of variation in projects and then working to minimize threats and to
maximize opportunities wherever it is feasible. Because no project is likely to
be repeated enough times to develop distributions like those in Figure 1-3
using measured, empirical data, project risk analyses rely heavily on
projections and range estimates.
Opportunities and Risks
The topic of opportunities arises frequently when discussing risk. Both
topics are complex, and there is no question that they are interrelated. In the
project environment, there are at least three types of opportunity. The first
relates to choices made concerning the specifications and other aspects of the
expected project deliverable. The second type of opportunity that projects
deal with relates to decisions made in planning and executing the work,
generally involving trade-offs. A third type of opportunity involves
uncertainties regarding project activities having a range of outcomes that may
either be adverse or beneficial to the project (similar to the duration estimates
in Figure 1-3). All three of these meanings for opportunity relate to risk, and
each is covered in some detail in this book.
To a great degree, project risk management is necessitated by the first
kind of project opportunity. Projects are by definition unique undertakings, so
the results they are expected to deliver inevitably involve unknowns. The
business case for most projects rests on the assumption that the value of the
outcome will significantly exceed the project’s cost. Sometimes there are
good reasons to accept the starting assumptions regarding performance,
deadlines, budgets, and other project parameters. In most cases, though, the
initial project assumptions are based more on wishful thinking than on
reliable, analytical analysis. One consequence of this is a high correlation
between risk and reward for projects in general. Significant benefits generally
involve significant risk, and the more substantial we expect the returns from a
project to be, the more potential issues we are likely to encounter in achieving
them. This type of project opportunity is based on the choice of objectives
and constraints. The more steeply that one tilts the playing field by imposing
aggressive, so-called stretch goals, the more significant risks there will be and
the less likely it will be that the project will achieve its goals. Chapters 3
through 5 explore identifying risks associated with choices regarding project
constraints and objectives.
A second aspect of project opportunity management also involves
choices, this time in planning the work. Most projects find that initial plans
fall short of timing, cost, or other stated objectives. In an attempt to meet
aspirational goals, project leaders work to optimize the workflow by adopting
alternatives that compress plans, save money, or use other trade-offs to better
conform to what their key stakeholders have requested. Even when tactics are
found that can effectively address a critical constraint (such as an aggressive
deadline), the changes usually involve trade-offs (for example, higher costs
or diminished scope), increased risk, and new project failure modes. Analysis
of such self-inflicted risks that emerge from managing project constraints is
explored in Chapter 6.
The third type of project opportunity involves beneficial uncertainties
associated with planned activities, and managing these is central to project
risk management. Because of the aggressive objectives set at the outset of
most projects, uncertainties concerning the work tend to skew heavily toward
adverse consequences. (When best-case scenarios are used in setting project
baselines, all the uncertainty is shifted to the downside.) Nonetheless, there
may be at least a few potentially beneficial uncertainties in your projects.
Chapter 6 explores uncovering such “positive risks,” and techniques for
managing them are addressed in Chapter 8.
Benefits of Project Risk Management
Is it even possible to manage risk? This fundamental question is
unfortunately not trivial because uncertainty is intrinsic to project work,
regardless of how we approach it. If by “manage risk” we mean completely
removing all risks and uncertainty, for projects this is not possible. We can
manage project risk, however, if we mean understanding significant sources
of risk and taking prudent actions (such as the tactics outlined earlier and
throughout the second half of this book) to minimize failure modes and
increase our chances of project success.
Because our ability to manage risk is at best only partially effective,
it’s fair to ask a second question: Should we bother to try to manage risk? As
with any business decision, the answer has to do with cost and benefits.
Developing a project plan with thorough risk analysis unquestionably
involves effort, which may seem like unnecessary overhead to many project
stakeholders and even to some project leaders. Project risk management
yields many benefits, though. Particularly for complex projects, they
generally far outweigh the costs. A summary of the benefits of project risk
management follow, and each is amplified later in this book. Specific project
risk management costs are outlined in the following section.
Lower Costs and Less Chaos
Adequate risk analysis lowers both the overall cost and the frustration
caused by avoidable problems. The amount of rework and unforeseen late
project effort is reduced. Knowledge of the root causes of potentially severe
project problems enables project leaders and teams to work in ways that
avoid these problems. Dealing with the causes of risk also minimizes
firefighting and chaos during projects, much of which is focused on the short
term and deals primarily with symptoms rather than with the intrinsic
underlying problems.
Project Justification
Project risk management is undertaken primarily to improve the
chances of projects achieving their objectives. Although there are never any
guarantees, broader awareness of common failure modes and ideas that make
projects more robust can significantly improve the odds for success. Effective
project risk management either provides a credible foundation showing that a
given project is possible or shows that the project is infeasible and ought to
be avoided, aborted, or at least modified. Risk analysis may also uncover
opportunities to improve projects and increase project value.
Project Priority and Management Support
Support from managers and other project stakeholders and
commitment from the project team are more easily won when projects are
based on thorough, understandable information. High-risk projects may begin
with a lower priority, and this may be out of line with the overall benefits
expected when it is completed. (Remember, high risk often aligns with high
reward.) You can raise your project’s priority by documenting its value. You
also may be able to increase it by generating a thorough risk plan, displaying
your competence and good preparation for possible problems. Whenever you
are successful in improving the priority of your project, you significantly
reduce project risk—by opening doors, reducing obstacles, obtaining needed
resources, and shortening queues for services.
Project Portfolio Management
Achieving and maintaining an appropriate mix of ongoing projects for
an organization depends on risk data. The ideal project portfolio includes
both lower- and higher-risk (and return) projects in proportions that are
consistent with the business objectives. The process of project portfolio
management and its relationship to project risk are covered in Chapter 13.
Fine-Tuning Plans to Reduce Risk
Risk analysis uncovers weaknesses in a project plan and triggers
changes, new activities, and resource shifts that temper project risk. Risk
analysis at the project level may also reveal needed shifts in overall project
structure or basic assumptions.
Establishing Management Reserve
Risk analysis demonstrates the uncertainty of project outcomes and is
useful in justifying reserves for schedule and/or resources. It’s more
appropriate to define a window of time (or budget) instead of a single-point
objective for risky projects. It is fine to set project targets on expected
estimates (the “most likely” versions of the plans), but project commitments
for high-risk projects are best established with less aggressive goals,
reflecting the risks. The target and committed objectives set a range for
acceptable project results and visibly communicate the uncertainty. For
example, the target schedule for a risky project might be 12 months, but the
committed schedule, reflecting potential problems, may be set at 14 months.
Completion within (or before) this range defines a successful project; only if
the project takes more than 14 months will it be considered a failure. Project
risk assessment data provides both the rationale and the magnitude for the
required reserve. More on this is found in Chapter 10.
Project Communication and Control
Project communication is most effective when there is a solid, credible
plan. Risk assessments also build awareness of project exposures for the
project team, showing when, where, and how painful the problems could be.
This causes people to work in ways that avoid project difficulties. Risk data
can also be useful in negotiations with project sponsors. Using information
about the likelihood and consequences of potential problems gives project
leaders more influence in defining objectives, determining budgets, obtaining
staff, setting deadlines, and negotiating project changes.
Costs of Project Risk Management
Project risk management has many potential benefits, but it isn’t free.
Managing risk entails work, and this requires investment in both time and
effort (cost). Done effectively, though, the incremental contribution for
project risk management can be very modest. Risk identification is best done
as part of overall planning, listing risks as you proceed through the process
whenever you encounter an unknown, possible worst-case, or other potential
problem. Analysis of risks also need not be a major undertaking, especially if
the processes are well established and straightforward to use. Responding to
key risks is similarly not typically a great deal of extra work, and in fact a lot
of this falls under the category of “doing the job of a project leader.”
(Criticism after the fact for risk situations that you fail to adequately prepare
for and manage usually centers more on your overall competence than on
your expertise as a risk manager.)
Determining how much effort is warranted and what specific risk
management tactics to adopt involves judgment, as well as balancing the
trade-offs between more thorough analysis and expected additional benefits.
You will find some tactics that can assist you in justifying an increase in
process application and maturity in Chapter 2.
The Project Risk Management Process
The overall structure of this book mirrors the information in the Guide
to the Project Management Body of Knowledge (or PMBOK® Guide). This
guide from the Project Management Institute (PMI) is widely used as a
comprehensive summary of project management processes and principles.
The PMBOK® Guide has ten Project Management Knowledge Areas:
• Project Integration Management
• Project Scope Management
• Project Time Management
• Project Cost Management
• Project Quality Management
• Project Human Resource Management
• Project Communications Management
• Project Risk Management
• Project Procurement Management
• Project Stakeholder Management
Of these areas, Project Risk Management is the most central to this
book, but all ten of these topics are strongly related.
The PMBOK® Guide is also built around five Process Groups:
Initiating, Planning, Executing, Monitoring and Controlling, and Closing. In
the PMBOK® Guide, the processes are related as shown in Figure 1-4. The
six topics for Project Risk Management are included in two of these groups:
the Planning Processes group and the Monitoring and Controlling Processes
group.
In this book, the first of the six topics, “Plan Risk Management,” is
discussed in Chapter 2, which also explores the relationship between project
initiation and project risk management. “Identify Risks” is covered in
Chapters 3 through 6, on scope risk, schedule risk, resource risk, and
managing project constraints. The analysis and management of project risk is
covered first at a detailed level and then for projects as a whole. (This is a
distinction not explicit in the PMBOK® Guide, which addresses project-level
risk only superficially.) The next two topics, “Perform Qualitative Risk
Analysis” and “Perform Quantitative Risk Analysis,” relate to risk
assessment. Risk assessment is covered on two levels: for activity risks in
Chapter 7 and for overall project risk in Chapter 9. “Plan Risk Responses” is
also discussed twice: in Chapter 8 for activities and in Chapter 10 for the
project as a whole. “Control Risks” is the topic of Chapter 11. The relation
between risk management and project closing processes is covered in Chapter
12.
As in the PMBOK® Guide, the majority of the book aligns with project
planning, but the material here goes beyond the coverage in the PMBOK®
Guide to focus on the how-to of effective risk management from the
practitioner’s standpoint. There is particular emphasis on ideas and tools that
work well and that can be easily adapted to complex projects. All risk
management topics in the PMBOK® Guide are included here, for people who
may be using this book to prepare to sit for the Project Management
Professional (PMP®), Risk Management Professional (RMP®), or other
certification tests.
Figure 1-4. PMI PMBOK ® Guide Links Among Process Groups
Anatomy of a Failed Project: The First Panama Canal
Project
Risk management is never just about looking forward. Heeding the
lessons learned on projects of all types—even some distant examples—can
help you avoid problems on new projects. One such example, illustrating that
people have been making similar mistakes for a long, long time, is the initial
effort by the French to construct a canal across Panama. Although this project
is far from recent, it offers many lessons in managing risk that remain
valuable to this day.
The construction of the Panama Canal roughly 100 years ago faced
unprecedented technical challenges and was the risky, high-tech project of its
day. There were no earlier similar projects of its scale to learn from, and
much of the engineering required extensive innovation. It was, for its time,
breathtakingly expensive. The Panama Canal represents the single largest
project investment anywhere on earth prior to the late twentieth century. The
construction effort stretched over several decades, required a series of project
leaders, and provides a wealth of project management examples, both
positive and disastrous. (Examples cited throughout this book are drawn from
a number of sources, but by far the best single source is The Path Between
the Seas: The Creation of the Panama Canal, 1870–1914, by David
McCullough.)
The story of the Panama Canal is especially instructive because it is
actually the story of two projects that straddled the emergence of modern
project management in the early twentieth century. The first project failed for
many reasons, but lack of good project and risk management played a huge
part. The second succeeded largely because of the rigorous and disciplined
application of good project practices. The Panama Canal projects illustrate
many of the points made in this book, and they demonstrate important
concepts applicable to current projects.
First, successful project management practices are not new. They are
well established and have worked effectively for over a century. Modern
project management was developed in the late 1800s to deal with the
increasingly enormous civil engineering projects of that era all over the world
—the bridges, the transcontinental railroads, the dams, and other massive
projects made possible by Machine Age technology. Many basic lessons
learned on earlier projects can be usefully applied to your high-tech projects
today.
Second, tools for managing projects have evolved significantly, but the
fundamental principles have changed little. Henry Gantt, who developed the
chart that bears his name, contributed to the planning of many projects. He
did all of this with a ruler and a straightedge. Never in his whole life did he
fire up Microsoft Project—not even once. Having the very newest tool may or
may not help your project, but understanding why management tools are
important and how best to use them will always serve you well.
Finally, the systematic application of good methods leads to successful
outcomes in projects of all types. All projects are fundamentally dependent
on people, and human beings are not very different today than we were
hundreds, or even thousands, of years ago. To motivate people and enhance
performance on your project team, you can look to what has worked before
because, by and large, it still does.
The building of the Panama Canal was not an infeasible project; it was,
after all, ultimately completed. However, the initial undertaking was certainly
premature. The first canal project, begun in the late 1800s, entailed massive
risk. Negligible investment in project management contributed significantly
to the decision to go forward in the first place and directly resulted in major
project problems and its ultimate failure.
Although there was speculation far earlier, the first serious
investigation of a canal in Central America was in the mid-1800s. Estimates
were that such a canal would provide US$48 million a year in shipping
savings and might be built for less than US$100 million. Further study on-site
was less optimistic, but in 1850 construction of a railroad across the Isthmus
of Panama started. The railroad was ultimately completed, but the US$1.5
million, two-year project swelled to US$8 million before it was finished,
three years late in 1855. After a slow start, the railroad did prove to be a
financial success, but its construction problems foreshadowed the canal
efforts to come.
A few years later on the other side of the world, the Suez Canal was
completed and opened in 1869. This project was sponsored and led
successfully from Paris by Ferdinand de Lesseps. This triumph earned him
the nickname “The Great Engineer,” although he was actually a diplomat by
training, not an engineer at all. He had no technical background and only
modest skills as an administrator. However, he had completed a project many
thought to be impossible and was now world famous. The Suez project was a
huge financial success, and de Lesseps and his financial backers were eager
to take on new challenges.
Examining the world map, de Lesseps decided that a canal at Panama
would be his next triumph, so in the late 1870s a French syndicate negotiated
the necessary agreements in Bogota, Colombia. (Panama was then the
northernmost part of Colombia.) They were granted rights to build and
operate a canal in exchange for a small percentage of the revenue to be
generated over 99 years.
Although it might seem curious today that these canal construction
projects so far from France originated there, in the late 1800s Paris was the
center of the engineering universe. The best schools in the world were there,
and many engineering giants of the day lived in Paris, including Gustav Eiffel
(then planning his tower). Such complex engineering projects could hardly
have arisen anywhere else.
The process of defining the Panama project started promisingly
enough. In 1879, Ferdinand de Lesseps sponsored an International Congress
to study the feasibility of a canal connecting the Atlantic and Pacific oceans
through Central America. Over a hundred delegates gathered in Paris from a
large number of nations, though most of the delegates were French. A
number of routes were considered, and canals through Nicaragua and Panama
both were recommended as possibilities. Construction ideas, including a
realistic lock-and-dam concept (somewhat similar to the canal that was
ultimately built), were also proposed. In the end, though, the Congress voted
to support a sea-level canal project at Panama, even though nearly all the
engineers present thought the idea infeasible and voted against it. Not
listening to technical people is a perilous way to start a project. The Panama
Canal was neither the first nor the last project to suffer self-inflicted problems
arising from insufficient technical input.
Planning for the project was also a low priority. De Lesseps paid little
attention to technical problems. He believed need would result in innovation
as it had at Suez, and the future would take care of itself. He valued his own
opinions and ignored the views of those who disagreed with him, even
recognized authorities. An inveterate optimist, he was convinced, based only
on self-confidence, that he could not fail. These attitudes are not conducive to
good risk management; few things are more dangerous to a project than an
overly optimistic project leader. His primary risk management strategy seems
to have been hoping for the best.
The broad objective de Lesseps set for his Compagnie Universal du
Canal Interoceanique was to build a sea-level canal in 12 years, to open in
1892. He raised US$60 million from investors through public offerings—a
lot of money but still less than one-third of the initial engineering cost
estimate of more than US$200 million. In addition to this financial shortfall,
there was little detailed planning done before work actually commenced, and
most of that was done at the 1879 meeting in Paris. Even on the visits that de
Lesseps made to Panama and New York to build support for the project, he
failed to engage technical experts.
Eventually the engineers traveled to Panama, and digging started in
1882. Quickly, estimates of the volume of excavation required started to rise,
to 120 million cubic meters—almost triple the estimates that were used for
the decisions in 1879. As the magnitude of the effort rose, de Lesseps made
no public changes to his cost estimates or to the completion date.
Management of risks on the project, inadequate at the start, improved
little in the early stages of execution. There were many problems. Panama is
in the tropics, and torrential rains for much of the year created floods that
impeded the digging and made the work dangerous. The frequent rains turned
Panama’s clay into a flowing, sticky sludge that bogged down work, and the
moist, tropical salt air combined with the viscous mud to destroy all
machinery. There was also the issue of elevation. The continental divide in
Panama is not too high by North or South American standards, but it does
rise to more than 130 meters. For a canal to cross Central America, it would
be necessary to dig a trench more than 15 kilometers long to this depth, an
unprecedented amount of excavation. Digging the remainder of the 80-
kilometer transit across the isthmus was nearly as daunting.
Adequate funding for the work was also a problem because only a
portion of the money that de Lesseps raised was allocated to construction
(most of the money went for publicity, including a impressive periodic Canal
Bulletin, used to build interest and support). Worst of all, diseases, especially
malaria and yellow fever, were lethal to many workers not native to the
tropics, who died by the hundreds. As work progressed, the engineers,
already dubious, increasingly believed the plan to dig a sea-level canal was
doomed.
Intense interest in the project and a steady stream of new workers kept
work going, and the Canal Bulletin reported good progress (regardless of
what was actually happening). As the project progressed, there were changes.
Several years into the project, in 1885, the cost estimates were finally raised,
and investors provided new funds that quadrupled the project budget to
US$240 million. The expected opening of the canal was delayed
“somewhat,” but no specific date was offered. Claims were made at this time
that the canal was half dug, but the truth was probably closer to 15 percent.
Information on the project was far from trustworthy.
In 1887, costs were again revised upward, exceeding US$330 million.
The additional money was borrowed, as de Lesseps could find no new
investors. Following years of struggle and frustration, the engineers finally
won the debate over construction of a canal at sea level. Plans were shifted to
construct dams on the rivers near each coast to create an enormous artificial
lake that would serve as much of the transit. Sets of locks would be needed to
bring ships up to, and down from, the constructed lake. Although this would
slow the transit of ships somewhat, it significantly reduced the necessary
excavation.
Even with these changes, problems continued to mount, and by 1889
more revisions and even more money were needed. After repeated failures to
raise funding, de Lesseps liquidated the Compagnie Universal du Canal
Interoceanique and shut the project down. This collapse caused complete
financial losses for all the investors. By 1892, scandals were rampant, and the
bad press and blame spread far and wide. Soon the lawyers and courts of
France were busy dealing with the project’s aftermath.
The French do not seem to have done a formal postproject analysis, but
looking at the project in retrospect reveals over a decade of work, more than
US$300 million spent, lots of digging, and no canal. Following the years of
effort, the site was ugly and an ecological mess. The cost of this project also
included at least 20,000 lives lost (many workers who came to Panama died
so soon after their arrival that their deaths were never recorded; some
estimates of the death toll run as high as 25,000). Directly as a result of this
project failure, the French government fell in 1892, ending one of the
messiest and most costly project failures in history.
The leader of this project did not fare well in the wake of the disaster.
Ferdinand de Lesseps was not technical, and he was misguided in his beliefs
that equipment and medicines would appear when needed. He also
chronically reported more progress than was real (through either poor
analysis or deception; the records are not clear enough to tell). Shortly
thereafter, he died a broken man, in poverty. Had he never undertaken the
project at Panama, he would have been remembered as the heroic builder of
the Suez Canal. Instead, his name is primarily linked to the failure at Panama.
Perhaps the one positive outcome from all this was clear evidence that
building a sea-level canal at Panama was all but impossible because of rains,
flooding, geology, and other challenges. These problems persist to this day
even with current technology.
Although it is not possible ever to know whether a canal at Panama
could have been constructed in the 1880s, better project and risk management
practices, widely available at the time, would have helped substantially.
Setting a more appropriate initial objective, or at least modifying it sooner,
would have improved the likelihood of success. Honest, more frequent
communication—the foundation of well-run projects—would almost
certainly have either forced these changes or led to the earlier abandonment
of the work, saving thousands of lives and a great deal of money.
Chapter
2
Planning for Risk Management
You can observe a lot just by watching.
—YOGI BERRA
Planning for risk involves paying attention. When we don’t watch,
projects fail.
How many? One frequently quoted statistic is 75 percent. The primary
source for this assertion goes back to a study done in 1994 by the Standish
Group and documented in “The CHAOS Report.” There are reasons to be
skeptical of this number, starting with the fact that if three of four projects
actually did fail, there would probably be a lot fewer projects. What the
Standish Group actually said in its study was that about a quarter of projects
in the sample were cancelled before delivering a result. In addition to this,
roughly half of the projects were “challenged,” producing a deliverable but
doing it late, over budget, or both. The remaining quarter of the projects they
viewed as successful.
Although the Standish Group has done further research over the years
obtaining similar results, the actual picture for projects is probably not quite
so bleak. The Standish Group studied only large IT projects, those with
budgets of more than US$2 million. In addition, the survey information did
not come from the project leaders but was reported by the executives in the
organizations where the projects were undertaken. Larger projects are more
prone to fail, and US$2 million is a big IT project (especially in 1994). The
source of the data also raises a question about what was being compared to
what. Were the projects in fact troubled, or were they doomed from the start
by unrealistic expectations that were never validated? Whatever the true
numbers for failed projects are, however, too many fail unnecessarily, and
better risk management can help.
Although unanticipated so-called acts of God doom some projects,
most fail for one of three reasons:
• They are actually impossible.
• They are overconstrained (“challenged” in the Standish Group
model).
• They are not competently managed.
A project is impossible when its objective lies beyond the technical
capabilities currently available. “Design an antigravity device” is an example.
Other projects are entirely possible, but not with the time and resources
available. “Rewrite all the corporate accounting software so that it can use a
different database package in two weeks using two part-time university
students” is an overconstrained project. Unfortunately, projects also fail
despite having a feasible deliverable and plausible time and budget
expectations. These projects fail because of poor project management—
simply because too little thought is put into the work to produce useful
results.
Risk and project planning enable you to distinguish among and deal
with all three of these situations. For projects that are demonstrably beyond
the state of the art, planning and other analysis data generally provide
sufficient information to terminate the project or at least to redirect the
objective (buy a helicopter, for example, instead of developing the antigravity
device). Chapter 3, on identifying project scope risks, discusses these
situations. For projects with unrealistic timing, resource, or other constraints,
risk and planning data provide you with a compelling basis for project
negotiation, resulting in a more plausible objective (or, in some cases, the
conclusion that a realistic project lacks business justification). Chapters 4, 5,
and 6, on schedule, resource, and other risk identification, discuss issues
common for overconstrained projects. Dealing with “challenged” projects by
negotiating a realistic project baseline is covered in Chapter 10.
The third situation, a credible project that fails because of faulty
execution, is definitely avoidable. Through adequate attention to project and
risk planning, these projects can succeed. Well-planned projects begin
quickly, limiting unproductive chaos. Rework and defects are minimized, and
people remain busy performing activities that efficiently move the project
forward. A solid foundation of project analysis also reveals problems that
might lead to failure and prepares the project team for their prompt
resolution. In addition to making project execution more efficient, risk
planning also provides insight for faster, better project decisions. Although
changes are required to succeed with the first two types of projects mentioned
earlier, this third type depends only on you, your project team, and the
application of the solid project management concepts in this book. The last
half of this book, Chapters 7 through 13, specifically addresses these projects.
Project Selection
Project risk is a significant factor even before there is a project.
Projects begin as a result of an organization’s business decision to create
something new or change something old. Projects are a large portion of the
overall work done in organizations these days, and at any given time there are
always many more attractive project ideas than can be funded or adequately
staffed. Assumptions about embryonic projects may be wildly unrealistic,
compounding the challenges. The process for choosing projects both creates
project risk and relies on project risk analysis, so the processes for project
selection and project risk management are tightly linked. Selecting and
maintaining an appropriate list of active projects requires project portfolio
management.
Project selection affects project risk in a number of ways. Poor project
portfolio management exacerbates a number of common project risks:
• Excessively rosy expectations for project results and benefits
• Too many projects competing for limited resources
• Project priorities that are misaligned with overall strategies
• Inadequately funded projects
• Unrealistic project deadlines
• Optimistic estimates of organizational capabilities
Project risk management data is also a critical input to the project
selection process. Project portfolio management uses project risk assessment
as a key criterion for determining which projects to put into planning at any
given time. Without high-quality risk data and credible estimates for
candidate projects, excessive numbers of projects, many unrealistic, will be
undertaken and many of them will fail. Chapter 13 explores the topic of
project portfolio risk management in detail.
Overall Project Planning Processes
The project selection process is a major source of risk for all projects,
but the overall project management approach is even more significant. When
projects are undertaken in organizations lacking adequate project
management processes, risks will be unknown and probably unacceptably
high. Without adequate analysis of projects, no one has much idea of what
“going right” looks like, so it is not possible to identify and manage the risks
—the things that may go wrong. The project management processes provide
the magnifying glass you need to inspect your project to discover its possible
failure modes.
Regular review of the overall methods and processes used to manage
projects is an essential foundation for good risk management. If project
information and control is sufficient across the organization and most of the
projects undertaken are successful, then your processes are working well. For
many high-tech projects, though, this is not the case. The methods used for
managing project work are too informal, and they lack adequate structure.
Exactly what process you choose matters less than that you are using one. If
elaborate, formal, PMBOK®-inspired heavyweight project management
works for you, great. If agile, lightweight, adaptive methodologies provide
what you need, that’s fine too. The important requirement for risk
management is that you adopt and use an effective project management
process.
For too many modern projects, there is indifference or even hostility to
planning. This occurs for a number of reasons, and it originates in
organizations at several levels. At the project level, other types of work may
carry higher priority, or planning may be viewed as a waste of time. Above
the project level, project management processes may appear to be
unnecessary overhead, or they may be discouraged to deprive project teams
of data that could be used to win arguments with their managers. Whatever
the rationalizations used, there can be little risk management without
planning. Without at least a basic plan, most of the potential problems and
failure modes for your project will remain undetected.
The next several pages provide support for the investment in project
processes. If you need, or if your management needs, convincing that project
management is worthwhile, read on. If project planning and related
management processes are adequate in your organization, skip ahead.
At the Project Level
A number of reasons are frequently cited by project leaders for
avoiding project planning. Some projects are not thoroughly planned because
the changes are so frequent that planning seems futile. Quite a few leaders
know that project management methodology is beneficial, but with their
limited time they feel they must do only “real work.” An increasingly
common reason offered is the belief that in these days of Internet time,
thinking and planning are no longer affordable luxuries. There is a response
for each of these assertions.
Inevitable project change is a poor reason not to plan. In fact, frequent
change is one of the most damaging risk factors, and managing this risk
requires good project information. Project teams that have solid planning data
are better able to resist inappropriate change, rejecting or deferring proposed
changes based on the consequences demonstrated using the project plan.
When changes are necessary, it is easier to continue the work by modifying
an existing plan than by starting over in a vacuum. In addition, many high-
tech project changes directly result from faulty project assumptions that
persist because of inadequate or incomplete planning data. Better
understanding leads to a clearer definition of project deliverables and fewer
reasons for change.
The time required to plan is also not a valid reason to avoid project
management processes. Although it is universally true that no project has
enough time, the belief that there is no time to plan is difficult to understand.
All the work in any project must always be planned. There is a choice as to
whether planning will be primarily done in focused early-project or periodic
iterative exercises or by identifying the work to be done one activity at a
time, day by day, throughout the project. All necessary analysis must be done
by someone, eventually. An ad hoc approach requires comparable, if not
more, overall effort, and it carries a number of disadvantages. First, there can
be few, if any, meaningful metrics, and tracking project progress will at best
be guesswork. Second, most project risks, even those easily identified, come
as unexpected surprises when they occur. Early, more thorough planning
provides other advantages, and it is always preferable to have project
information sooner rather than later. Why not invest in planning when the
benefits are greatest?
Assertions about Internet time are also difficult to accept. Projects that
must execute as quickly as possible need more, not less, project planning.
Delivering a result with value requires sequencing the work for efficiency
and ensuring that the activities undertaken are truly necessary and of high
priority. On fast-track projects, there is no time for rework, excessive defect
correction, or unnecessary activity. Project planning, particularly on time-
constrained projects, is real work.
Above the Project Level
Projects are undertaken based on the assumption that whatever the
project produces will have value, but there is often little consideration of the
type and amount of process that projects need. Especially in high-tech
environments, little to no formal project management is mandated, and often
it is even discouraged.
If the current standards and project management practices are minimal
in your organization, it will be to your benefit to improve them. There are
two possible ways to do this. Your best option is to convince the managers
and other stakeholders that more formal project definition, planning, and
tracking will deliver overall value to the business. When this is successful, all
projects benefit. For situations where this is unsuccessful, a second option is
to adopt greater formalism just for your current project. It may even be
necessary to do this in secret, to avoid criticism and comments like, “Why are
you wasting time with all that planning stuff? Why aren’t you working?”
In organizations where expenses and overhead are tightly controlled, it
can be difficult to convince managers to adopt greater project formalism.
Building a case for this takes time and requires metrics and examples, and
you may find that some upper-level managers are highly resistant even to
credible data. The benefits are substantial, though, so it is well worth trying;
anything you can do to build support for effective project processes over time
will help.
If you have credible, local data demonstrating the value of project
management or the costs associated with inadequate process, assemble it.
Most organizations that have such data also have good processes. If you have
a problem that is related to inadequate project management, it is likely that
you will also not have a great deal of information to draw from. For projects
lacking a structured methodology, few metrics are established for the work,
so mounting a compelling case for project management processes using your
own data may be difficult.
Typical metrics that may be useful in supporting your case relate to
achieving specifications, managing budgets, meeting schedules, and
delivering business value. Project processes directly impact the first three, but
may only indirectly influence the last one. The ultimate value of a project
deliverable is determined by a large number of factors, many that are external
to the project and probably out of your control. Business value data may be
the best information you have available, though, so make effective use of
what you can find.
Even if you can find or create only modest evidence that better project
management processes will be beneficial, it is not hopeless. Other approaches
may suffice, such as using anecdotal information, models, and case studies.
Determining which approaches to use depends on your situation. There
is a wide continuum of beliefs about project management among upper-level
managers. Some managers favor project management naturally. These folks
will require little or no convincing, and any approach you use is likely to
succeed. Other managers are highly skeptical about project processes and will
focus heavily on the visible costs (which are unquestionably real) while
doubting the benefits. The best approach in this case is to gather local data,
lots of it, that shows as clearly as possible how high the costs of not using
better processes are. Trying to convince an extreme skeptic that project
management is a good investment may ultimately prove to be a waste of
time, for both of you. Good risk management in such an environment will be
up to you, and you may need to do it below the radar.
Fortunately, most managers are somewhere in the middle, neither true
believers in project management nor chronic process adversaries. The
greatest potential for process improvement is with this ambivalent group.
Using anecdotal information, models, case studies, and other information can
be effective.
Anecdotal information. Building a case for more project process with
stories depends on outlining the benefits and costs and on showing there is a
net benefit. Project management lore is filled with stated benefits, among
them:
• Better communication
• Less rework
• Lowered costs, reduced time
• Earlier identification of gaps and inadequate specifications
• Fewer surprises
• Less chaos and firefighting
Finding situations that show where project management delivered on
these or where the lack of process created a related problem should not be
hard.
Project management has its costs, some direct and some more subtle,
and you will need to address these. One obvious cost is the overhead it
represents: meetings, documentation, effort invested in project management
activities. Another is the initial (and ongoing) cost of establishing good
practices in an organization, such as training, job aids, and new process
documentation. Do some assessment of the investment required and
summarize the results.
There is a more subtle cost to managers in organizations that set high
project management standards: the shift that occurs in the balance of power in
an organization. Without project management processes, all the power in an
organization is in the hands of management; all negotiations tend to be
resolved using political and emotional tactics. Having little or no data, project
teams are fairly easily backed into whatever corners their management
chooses. With data, the discussion shifts and negotiations are based on
realistic data. Even if you choose not to directly address this cost, be aware of
it in your discussions.
Answering the question, “Is project management worth it?” using
anecdotal information depends on whether the benefits can be credibly shown
to outweigh the costs. Your case will be most effective if you find the best
examples you can, using projects from environments as similar to yours as
possible.
Models. Another possible approach for establishing the value of
process relies on logical models. The need for process increases with scale
and complexity, and managing projects is no exception. Scaling projects may
be done in a variety of ways, but one common technique segregates them into
three categories: small, medium, and large.
Small projects are universal; everyone does them. There is usually no
particular process or formality applied, and more often than not these simple
projects are successful. Nike-style (“Just Do It”) project management is good
enough, and although there may well be any number of slightly better ways
to approach the work (apparent in hindsight, more often than not), the
penalties associated with simply diving into the work are modest enough that
it doesn’t matter much. Project management processes are rarely applied with
any rigor, even by project management zealots, because the overhead
involved may double the work required for the project.
Medium-size projects last longer and are more complex. The benefits
of thinking about the work, at least a little, are obvious to most people. At a
minimum, there is a to-do list. Rolling up your sleeves and beginning work
with no advance thought often costs significant additional time and money.
As the to-do list spills over a single page, project management processes start
to look useful. At what exact level of complexity this occurs has a lot to do
with experience, background, and individual disposition. Many midsize
projects succeed, but the possibility of falling short of some key goal (or
complete project failure) is increasing.
For large projects, the case for project management should never really
be in doubt. Beyond a certain scale, all projects with no process for managing
the work will fail to meet at least some part of the stated objective. For the
largest of projects, success rates are low even with program management and
systems engineering processes in addition to thorough project management
practices.
For projects of different sizes, the costs of execution with and without
well established project management practices will vary. Figure 2-1 shows
the cost of a best-effort, or brute-force, approach to a project contrasted with
a more proactive project management approach. The assumption for this
graph is that costs will vary linearly with project scale if project management
is applied, and they will vary geometrically with scale if it is not. This figure,
though not based on empirical data, is solidly rooted in a large amount of
anecdotal information.
Figure 2-1. Cost Benefit for Project Management
The figure has no units because the point at which the crossover occurs
(in total project size and cost) is highly situational. If project size is measured
in effort-months, a common metric, a typical crossover might be between 1
and 4 total effort-months.
One motivation for adopting agile, iterative methods on complex
project undertakings is to convert larger, longer projects into a succession of
shorter ones—making the work more straightforward to plan and manage.
Wherever the crossover point is, the cost benefit is minor near this
point and negative below it. For these smaller projects, project management
is a net cost or of small financial benefit. (Cost may not be the only, or even
the most important, consideration, though. Project management
methodologies may also be employed for other reasons, such as to meet legal
requirements, to manage risk better, or to improve coordination among
independent projects.)
A model similar to this, especially if it is accompanied by project
success and failure data, can be a compelling argument for adopting better
project management practices.
Case studies. To offset the costs of project management, you need to
establish measurable (or at least plausible) benefits. Many studies and cases
have been developed over the years to assess this, including the one
summarized in Figure 2-2. The data in this particular study was collected
over a three-year period from more than 200 projects at Hewlett-Packard. For
every project included, all schedule changes were noted and characterized.
All changes attributed to the same root cause were aggregated, and the
summations were sorted for the Pareto diagram in the figure, displaying the
magnitude of the change on the vertical axis and the root causes along the
horizontal axis.
Figure 2-2. Schedule Change Pareto Diagram
Additional project effort—hundreds of engineer-months—was
associated with the most common root causes. The codes for the root causes,
sorted by severity, were:
1. Unforeseen technical problems
2. Poor estimation of effort/top-down schedules
3. Poor product/system design or integration problems
4. Changing product definition
5. Other
6. Unforeseen activities/too many unrelated activities
7. Understaffed or resources not on time
8. Software development system/process problems
9. Related project slip (also internal vendor slip)
10. Insufficient support from service areas
11. Hardware development system/process problems
12. Financial constraints (tooling, capital, prototypes)
13. Project placed on hold
A. Acceleration
Not every one of these root causes directly correlates with project
management principles, but most of them clearly do. The largest one is
unforeseen technical problems, many of which were likely due to insufficient
planning. The second, faulty estimation, is also a project management factor.
Although better project management would not have eliminated all these
slippages, it surely would have reduced them. The top two reasons in the
study by themselves represent an average of roughly five unanticipated
engineer-months per project; reducing this by half would have saved
thousands of dollars per project. Similar conclusions may be drawn from the
analysis of the Project Experience Risk Information Library (PERIL)
database later in this chapter and elsewhere in this book.
Case study data such as in these examples, particularly if it directly
relates to the sort of project work you do, can be compelling. You likely have
access to data similar to this, or could estimate it, for rework, firefighting,
crisis management, missing work, and the cost of defects on recent projects.
Other reasons for project management. One of the principal
motivators in organizations that adopt project principles is the reduction of
uncertainty. Most technical people hate risk and will go to great lengths to
avoid it. One manager who strongly supports project management practices
uses the metaphor of going down the rapids of a white-water river. Without
project management, you are down in the water—you have no visibility, it is
cold, it is hard to breathe, and your head is hitting lots of rocks. With project
management, you are up on a raft. It is still a wild ride, but you can see a few
dozen feet ahead and steer around the worst obstacles. You can breathe more
easily, you are not freezing and are not so wet, and you have some
confidence that you will survive the trip. In this manager’s group, minimizing
uncertainty is important and planning was never optional.
Another motivator is a desire (or requirement) to become more process
oriented. Current standards and legal requirements for enterprise risk
management in the United States and worldwide make adoption of formal
processes for risk management obligatory. (The direct connection of this to
project risk management is explored in Chapter 13.) In firms that provide
solutions to customers, using a defined methodology is a competitive
advantage that can help win business. In some organizations, evidence of
process maturity is deemed important, so they aspire to standards for higher
maturity set by organizations such as the Software Engineering Institute. In
other instances, specific process requirements may be tied to the work, as
with many government contracts, as well as in the financial, biotech,
pharmaceutical, and other highly regulated industries. In all these cases,
project management is mandatory, at least to some extent, whether the
individuals and managers involved think it is a good idea or not.
The Project Management Methodology
Project risk management depends on thorough, sustained application of
effective project management principles. The precise nature of the project
management methodology can vary widely, but management of risk is most
successful when consistent processes are adopted by the organization as a
whole because there will be more useful data to work with and more durable
support for the ongoing effort required. If you need to manage risk better on
your project and it proves impossible to gain support for more effective
project management principles broadly, at least resolve to apply them to your
projects, with sufficient rigor to develop the information you need to manage
risk.
Defining Risk Management for the Project
Beyond basic project planning, risk management also involves specific
planning for risk. Risk planning begins by reviewing the initial project
assumptions. Project charters, data sheets, or other documents used to initiate
a project often include information concerning risk, as well as goals, staffing
assumptions, and other information. Any risk information included in these
early project descriptions is worth noting; sometimes projects believed to be
risky are described as such, or there may be other evidence of project risk.
Projects thought to be low risk may involve assumptions leading to
unrealistically low staffing and funding. Take note of any differences in your
perception of project risk and the stated (or implied) risks perceived by the
project sponsors. Risk planning builds on a foundation that is consistent with
the overall assumptions and project objectives. In particular, work to
understand the expectations of the project stakeholders, and adopt an
approach to risk management appropriate to your environment.
Stakeholder Risk Tolerance and Quantification
Organizations in different businesses deal with risk in their own ways.
Start-ups and speculative endeavors such as oil exploration must have a high
tolerance for risk; many projects undertaken are expected to fail, but these are
compensated for by a small number that are extremely successful. More
conservative organizations, such as governments and enterprises that provide
solutions to customers for a fee, are generally risk averse and expect
consistent success but more modest returns on each project. Organizational
risk tolerance is reflected in the organizational policies, one example of
which might be a preestablished prohibition on pursuing fixed-price contract
projects.
In addition, the stakeholders of the project may have strong individual
opinions on project risk. Although some stakeholders may seek risks (and the
associated opportunities), others may be risk tolerant, and still others may
wish to avoid risks through actions that minimize extreme outcomes.
Technical contributors tend to prefer low risk. One often repeated example of
stakeholder risk preference is attributed to the NASA astronauts, who
observed that they were perched on the launch pad atop hundreds of systems,
each constructed by the lowest bidder. Risk tolerance often depends on where
you are sitting.
Work to characterize the appetite for risk for your key stakeholders,
especially your sponsor. In your interactions with them, ask questions to
uncover clues to their risk tolerance, such as:
• Worst case, how much overall would they be willing to invest?
• What is the minimum result that they would find acceptable?
• What are the most significant concerns they have about the project?
Risk Management Strategy
Integrate what you learn about your stakeholder’s risk tolerance into
your overall project planning. If your key project stakeholders prefer to avoid
risks, integrate processes for clearly defining requirements, detailed schedules
with precise estimates, and quantitative analysis of uncertainties and worst
cases. Include a thorough risk analysis in your planning documents, and plan
for periodic reviews to update it as your project proceeds.
Even if your project is highly speculative, novel, or revolutionary,
incorporate risk identification into all your planning processes and provide
for adequate analysis of any significant risks you uncover. Tolerance for risks
is not a license to take them; your goal after all is to run a successful project
that delivers good value.
Planning Data
Project planning information supports risk management. As you define
the project scope and create planning documents, such as a project work
breakdown structure or an iteration-based release plan, you will uncover
potential project risks. Other planning processes also support your efforts in
uncovering risk. Specific ideas for using planning processes to identify risks
are explored in Chapters 3 through 6.
Risk Processes and Tools
A major theme of this book is that risk management is not something
that a project leader does a bit of toward the end of project planning, if you
have time. Risk permeates all projects, so risk identification processes work
best when they are integrated with project planning and related processes. In
addition to contributing to projects that are more likely to be successful, this
approach offers two additional benefits. By focusing on risks as a
fundamental part of project management, you will find more risks and
minimize unknowns. You will also expend less effort overall, because
managing risks will become a small part of work that you are doing anyway,
instead of an additional piece of planning (and effort that may appear to some
as unnecessary overhead).
Risk identification is a fundamental part of defining and analyzing
scope, schedules, costs, and other project plans. As you develop planning
documents, be alert to unknowns—work where you lack expertise, uncertain
estimates, analysis depending on incomplete or unreliable-looking data, and
other knowledge gaps. Show error bars around quantitative estimates in order
to display uncertainty and highlight worst cases. Collect specific information
about gaps, holes, and potential problems as you progress, and list them with
other risks that your project may encounter. Chapters 3 through 6 will explore
doing this in detail.
Review (or create) a format for your project risk register, which you
will build on the foundation of risks identified for your project. Ensure that it
includes the information you will need to analyze, prioritize, and respond to
risks. You will find guidance on this in Chapter 8. Also plan to keep key
current risks visible throughout your project using a technique such as a
shared top-ten risk list.
Overall risk assessment can be enhanced using tools that provide
Monte Carlo risk simulations based on statistical modeling techniques.
Chapter 9 explores the selection and use of such software tools.
In general, as you set up processes and tools that you will employ for
tracking, communicating, and managing your project, ensure that they are
consistent with your efforts to monitor and manage risks.
Priorities and Risk Assessment Criteria
Use your discussions with your sponsor’s and stakeholders’ risk
tolerance data to determine how many categories you plan to use in assessing
risks (such as high, moderate, and low), and ensure that your descriptions for
them are consistent with organizational practices and your stakeholders’ risk
attitudes. Establish descriptions for each of the categories that you will use
for qualitative risk assessment. For example, set ranges and develop
definitions for high impact, low probability, and any other categories you will
use in prioritizing risks.
Risk Breakdown Structures, Templates, Statistics, and
Metrics
Risk management is easier and more thorough when you have access to
predefined templates for planning, project information gathering, and risk
assessment. For projects of a given type, a preestablished hierarchy
describing typical categories of risk, called a risk breakdown structure (RBS),
can be a useful starting point. A very general RBS that can be a good starting
point will be used to organize and discuss risk data in the PERIL database,
which will be discussed later in this chapter and throughout the book.
Templates that are preloaded with information common to most
projects make planning faster and decrease the likelihood that necessary work
will be overlooked. Consistent templates created for use with project
scheduling applications organizationwide make sharing information easier
and improve communication. If such templates exist, use them. If there are
none, create and share proposed versions of common documents with others
who do similar project work, and begin to establish standards.
What you collect and measure is also central to risk management.
Define thresholds for project parameters you will monitor during the project
for schedule slippage, overall cost control, deliverable performance, and any
other quantitative status data you plan to collect. Determine in advance what
actions will be triggered whenever your project data fails to meet the defined
thresholds. Setting ranges and limits is a major topic in Chapter 7, and
examples of metrics useful for risk management are covered in Chapter 9.
Project Data Archives
Long-term risk management requires a solid base of historical data.
Archived project data supports project estimating, quantitative project risk
analysis, and project tracking and control. Creating a shared repository of
project metrics, experiences, and risks can provide trend data valuable for
process improvement in general and especially for better risk management.
Using project data to improve project risk management will be addressed in
Chapter 12.
Risk Management Plan
For small projects, risk planning may be informal, but for large,
complex projects, you will be wise to develop and publish a written risk
management plan. A risk management plan includes information on
stakeholders, planning processes, project tools, and metrics, and it states the
standards and objectives for risk management on your project. Although
much of the information in a risk plan can be developed generally for all
projects in an organization, each specific project has at least some unique risk
elements.
A risk plan usually starts by summarizing your risk management
approach and including your risk management planning information, as just
discussed. In your risk plan, list the methodologies and processes that you
will use, and define the roles of the people who will be responsible for them.
Also include definitions and standards you plan to use with any risk
management tools, the frequency and agenda for periodic risk reviews,
formats for risk management reports, and risk-related requirements for
project status collection and other tracking.
In addition, for major projects and programs, define any significant
activities for risk identification, analysis, control, and review, and secure the
staffing and funding to support these efforts. Incorporate any budgets
dedicated to risk analysis, contingency planning, and risk monitoring into
your plans.
Another aspect of risk planning is ensuring that risk management plans
include adequate attention to uncertainties that represent project
opportunities. Uncertainty in projects can swing both ways, and some
activities and other work may go better than expected. Allocate at least some
of your risk management efforts to consider project aspects that may result in
better outcomes, along with your work in managing potential threats.
Managing uncertain project opportunities is discussed in more detail in
Chapter 6.
Risk Management Infrastructure for the Organization
Risk management at the project level is much more effective in
organizations that take risk seriously. Take full advantage of any assistance
that is available for this. If there is little structured support for managing risk
in your organization, encourage the sharing of effective risk practices and
data among your peers and managers. The discussion here briefly covers
several organizational aspects of project risk management. Chapter 13
explores program, portfolio, and enterprise risk management in more detail.
Education and Coaching
If workshops, classes, or other formal development offerings on risk
management are available in your organization, participate in them. If there
are none, propose bringing in consultants or educators to facilitate sessions
aimed at building skills to improve your process maturity and to do a more
thorough job of finding and dealing with project risks.
If formal education seems to not be an option, at least organize periodic
informal gatherings of your peer project leaders to network and share
experiences. Brown-bag lunchtime or similar gatherings can be a very
effective tactic for exchanging ideas, learning about risks and tactics for
managing them, and generally sharing practices that are effective in your
environment.
If your organization has a project management office (PMO) or a
similar centralized function dedicated to supporting project management
efforts, work with the staff when setting up networking sessions, and
encourage them to provide help, formally through consulting and similar
interactions, as well as informally.
Whether or not you have access to a PMO or other formal project
resources, seek out the advice of seasoned project professionals in your
organization who manage difficult projects with little apparent difficulty.
Establishing mentoring relationships between novice and experienced project
managers is a good way to improve overall project process maturity
throughout an organization.
Process Review and Improvement
After each project, conduct a retrospective analysis to capture lessons
learned, recognize effective practices, and identify processes you need to
improve. Use the opportunity to collect information on risks that occurred
and what, in hindsight, you could have done differently to avoid or better
manage the situation. Focus at least some of your postproject analysis on
your risk management processes, and modify them to remedy deficiencies
before the next project. Share your findings and process updates with your
peer project leaders, and review reports from other completed projects to
benefit from what they have learned.
Communication and Archives
During, and especially following, each project, document what you
uncover about risks identified, experiences (both effective and ineffective) in
managing them, and practices that you find useful in managing risks. Archive
your documents and provide access to your information to other project
leaders, your PMO or other support teams, key stakeholders, and others who
might benefit from the information.
One very useful method for gaining a better overall understanding of
organizational challenges and risks is to offer to facilitate project meetings
(such as start-up workshops, project reviews, and postproject retrospectives)
for other project leaders. In addition to seeing what other projects similar to
yours are facing, you will also free up the other leaders to participate more
fully in their meetings. You will also build up goodwill and can ask the other
leaders to return the favor and facilitate your meetings. Increasing the
perspectives engaged in project analysis will uncover more risks, build a
more thorough understanding of organizational challenges, and provide a
basis for more cohesive processes and better overall risk management.
Managing Organizational Biases
In most organizations, several types of bias will interfere with effective
risk management. These include, but are hardly limited to, denial, optimism,
recent experiences, poor understanding of probability and randomness, and
faulty information. At the organization level, you can minimize bias, but
because much of it is hardwired in the human brain it cannot be eliminated.
The most pervasive organizational source of bias affecting risk
management is denial. No one wants to encounter risks, so most stakeholders
put on their blinders and pretend that there are no risks when initiating
projects. Analysis of return on investment generally assumes that all value
and benefits will be maximized and that costs will be unencumbered with any
difficulties or unforeseen obstacles. In some organizations, this assumption is
so pervasive that sponsors and management actively discourage the
identification and reporting of risks, characterizing those who mention them
as having bad attitudes and poor performance. All projects have risks. Denial
does not make them disappear; it just makes them more damaging and bigger
surprises.
Optimism, recent experience, and understanding of probability also
make managing risk more difficult. Most types of risk are, in fact, fairly
unlikely. It may appear safe to ignore risks that do not happen very often, or
at least to characterize them as extremely improbable. It is human nature to
underestimate the chances of encountering unlikely events with unfavorable
outcomes (like most project risks) and to overestimate the occurrence of
unlikely events with beneficial outcomes. People often discount risks of a
type that have not happened lately (or may not have happened yet). We tend
to have short memories, and wishful thinking may lead us to think that
something that has not happened for a while will not recur. We may also
assume that a risk that has low probability that did occur recently will not
happen again for a while (or if it does, it will happen to someone else). At the
organization level, a broader base of risk data makes most of these mistakes
less likely. Optimism in the face of visible data showing otherwise is hard to
justify. Also, across an organization even risks that occur seldom will
happen, making them hard to ignore. The human brain is never very good at
thinking about probabilities, but even here an organization can invest in
education to help people do a better job in managing uncertainty.
Overall, the cause of managing project risks is biased in most
organizations by a lack of useful information. The more an organization
invests in collecting, organizing, and understanding the data they have, the
less “ignorance” bias they will encounter. The next section, as well as much
of the rest of this book, looks at typical risks encountered in actual projects.
Data like this also provides a foundation to help with managing bias in the
risk management process. The topic of bias will be addressed in more detail
in Chapter 7, where precision and bias in risk assessment are key topics.
The PERIL Database
Good project management is based on experience. Fortunately, the
experience and pain need not all be personal. You may also learn from the
experience of others, avoiding the aggravation of seeing everything firsthand.
The Project Experience Risk Information Library (PERIL) database provides
a step in that direction.
For more than two decades, in conducting workshops and classes on
project risk management, I have been collecting anonymous data from
hundreds of project leaders on their past project problems. Their descriptions
included both what went wrong and the amount of impact it had on their
projects. I have compiled this data in the PERIL database, which serves as a
foundation for this book. The database describes a wide spectrum of things
that have gone wrong with past projects, and it provides a sobering
perspective on what future projects will face. The size of the PERIL database
has grown with each edition of this book, and it now includes slightly more
than 1,000 cases.
Some project risks are easy to identify because they are associated with
familiar work. Other project risks are more difficult to uncover because they
arise from new, unusual, or otherwise unique requirements. The PERIL
database is valuable in helping to identify at least some of these otherwise
invisible risks. In addition, the PERIL database summarizes the magnitude of
the consequences associated with key types of project risk. Realistic impact
information can effectively counteract the generally optimistic assessments
typically used for project risks. Although some of the specific cases in the
PERIL database relate only to certain types of projects or may be unlikely to
recur, some close approximation of these situations will be applicable to most
projects.
Sources for the PERIL Database
The information in the PERIL database comes primarily from
participants in classes and workshops on project risk management,
representing a wide range of project types. Slightly under half the projects are
product development projects, having tangible deliverables. The remainder
are information technology, customer solution, or process improvement
projects. The projects in the PERIL database are worldwide, with a majority
from the Americas (primarily the United States, Canada, and Mexico). The
rest of the cases are from Asia (mostly Singapore and India) and from Europe
and the Middle East (from about a dozen countries, but largely from
Germany and the United Kingdom). As with most modern projects, whatever
their type or location, the projects in the PERIL database share a strong
dependence on new or relatively new technology. The majority of these
projects also involve software development. Both longer and shorter projects
are represented here, but the typical project in the database has a planned
duration of between six months and one year. Although some large programs
are in PERIL, typical staffing on these projects was rarely more than about 20
people.
The raw project numbers in the PERIL database are presented in the
following table.
Although the PERIL database represents many projects and their risks,
it is far from comprehensive even with 1,000 examples. The database
contains only a small fraction of the many thousands of projects undertaken
by the project leaders from whom it was collected, and it does not even
represent all the problems encountered on the projects that are included.
Because of this, analysis of the data in the PERIL database is more
suggestive than definitive of potential project risks. Despite this, the overall
analysis of the current data corroborates the conclusions reached from the
earlier, smaller databases, and the overall patterns have held up.
Also, as with any data based on nonrandom samples, there are
inevitable sources of bias. The database contains a bias for major project risks
because the project leaders were asked to provide information on significant
problems. Trivial problems are excluded from the data by design. There is
also potential bias because each case was self-reported. Although all the
information included is anonymous, some embarrassing details or impact
assessment may well have been omitted or minimized. In addition, nearly all
of the information was reported by people who were interested enough in
project and risk management to invest their time participating in a class or
workshop for skilled practitioners, so they are at least modestly skilled in
project management. This probably means that problems related to poor
project management will be underrepresented.
Even considering these various limitations and biases, the PERIL
database illuminates a wide range of risks typical of today’s projects. It is
filled with constructive (and stable) patterns, and the biggest source of bias—
a focus on only major problems—accurately mirrors accepted strategies for
risk management. Nonetheless, before blindly extending the following
analysis to any particular situation, be aware that your mileage may vary.
Measuring Impact in the PERIL Database
The problem situations that make up the PERIL database resulted in a
wide range of adverse consequences, including forced overtime, significant
overspending, scope reductions, and a long list of other undesirable outcomes
that can be difficult to compare quantitatively. Although such an extensive
assortment of misery may be fascinating, it is difficult to pummel into a
structure for meaningful analysis. Because of this, I chose to normalize all the
quantitative data in the database using only one consistent measure of impact:
time, measured in weeks of project slippage. This tactic makes sense in light
of today’s obsession with meeting deadlines, and it was an easy choice
because by far the most prevalent serious impact reported in the data was
deadline slip. Focusing on time is also appropriate because among the project
triple constraints of scope, time, and cost, time is the only one that’s
completely out of our control—when it’s gone, it’s gone.
For cases where the impact reported was primarily something other
than time, I either worked with the project leader to estimate an equivalent
project slippage or excluded the case from the database. For example, when a
project met its deadline through the use of substantial overtime, we estimated
the slippage equivalent to working all those nights, weekends, and holidays.
If a project found it necessary to make significant cuts to the project scope,
we estimated the additional duration that would have been required to deliver
the original scope. Where such transformations are included in the PERIL
database, we were consistently conservative in estimating the adjustments.
To better reflect the reality of typical projects, the time data in the
PERIL database also excludes extremes. In keeping with the theme of focus
on major risk, projects that reported a time slippage of less than a week were
not included. On the assumption that there are probably better ways to handle
projects that overshoot their deadlines by six months or more, the cases
included that reported longer slips are all capped at 26 weeks. This prevents a
single case or two from inordinately skewing the analysis, while retaining the
root causes of the problems. Because of their enormous and disruptive
potential impact, these and other high-impact cases will receive more detailed
attention later in this book.
The average impact for all records was roughly seven weeks,
representing almost a 20 percent slip for a typical nine-month project. The
averages by project type were consistently close to the average for all of the
data, with product development projects averaging a bit more than seven
weeks and IT and solution projects slightly less than seven weeks. By region,
projects in the Americas averaged slightly more than seven weeks. Projects in
Asia and in Europe and the Middle East were slightly less, but still more than
six weeks of slippage. This data by region and project type includes average
impact, in weeks.
Risk Causes in the PERIL Database
Although the consequences of the risks in the PERIL database are
consistently reported in terms of time, the risk causes were varied and
abundant. One approach to organizing this sort of data uses a risk breakdown
structure (RBS) to categorize risks based on risk type. The categories and
subcategories I have used to structure the database form an example of an
RBS. Each reported problem in the database is characterized in the hierarchy
based on its principal root cause. The top level of the hierarchy is organized
similarly to the first half of this book, that is, around the project triple
constraints of scope, schedule (time), and resource (cost). The database
subdivides these types of risks based on further breakdown of the root causes
of the risks. For most of the risks, determining the principal root cause was
fairly straightforward. For others, the problem reported was a result of several
factors, but in each case the risk was assigned to the project parameter that
appeared to be the most significant.
Across the board, risks related to scope issues were dominant. They
were both the most frequent and, on average, the most damaging. Resource-
related risks were next most numerous, followed by schedule risks. Both of
these categories were about equally harmful and somewhat less consequential
than the scope risks. The typical slippage for risks within each major type
was about six to eight weeks.
The total impact of all the risks is a bit more than 7,000 weeks—almost
140 years—of slippage. A Pareto chart summarizing total impact by category
is shown in Figure 2-3.
Figure 2-3. Total Project Impact by Root Cause Category
Within each of these three categories, the data is further subdivided
based on root cause categories, using the definitions in the table on the next
page.
A Pareto of the cumulative impact data is shown in Figure 2-4. By far
the largest source of slippage in this Pareto chart is scope change; it is more
than twice as large as the next subcategory. As depressing as all this data is,
however, the top five subcategories here are all aspects that are at least
partially within the purview of the project leader. This suggests that more
focus on the things that you can control as a project leader can significantly
reduce the number and magnitude of unpleasant surprises you’ll encounter
during your projects. This idea, along with further decomposition of these
risk root cause categories, is explored in the next three chapters, with scope
risks discussed in Chapter 3, schedule risks in Chapter 4, and resource risks
in Chapter 5.
Big Risks
Most books on project risk management spend a lot of time on theory
and statistics. Past editions of this book departed from that tradition by
focusing instead on what actually happens to real projects, using the PERIL
database as the foundation. The point was to illuminate significant sources of
actual project risk, with specific suggestions about what to do about the most
serious problems—high-impact risks that might be called “black swans.”
Figure 2-4. Total Project Impact by Subcategory
Referring to such risks as black swans has been popularized of late by
the writings of Nassim Nicholas Taleb. The original notion of a black swan
started in Europe before there was much knowledge about the rest of the
world. In the study of logic, the statement “All swans are white” was used as
the example of something that was incontrovertibly true. Because all the
swans observed in Europe were white, a black swan was considered to be
impossible. It came as something of a shock when a species of black swans
was later discovered in Australia. This realization gave rise to the
metaphorical use of the term “black swan” to describe something erroneously
believed to be impossible.
Taleb’s primary subject matter (discussed in depth in his 2001 book,
Fooled by Randomness) is financial risk, but his concept of a black swan as a
“large-impact, hard-to-predict, rare event” is nonetheless also applicable to
project risk management. It is a mistake to consider a situation to be
impossible merely because it happens rarely or has not happened yet. Project
leaders are often biased to discount major project risks because they estimate
them to have extremely low probabilities, as mentioned earlier in this chapter.
Whether we recognize them or not, these risks do occur—the PERIL
database is full of them—and the severity of problems they cause means that
it is foolish to ignore them.
In the next three chapters, we will heighten the visibility of these
project-destroying black swans by singling out the most severe 20 percent of
the risks in the PERIL database—the slightly more than 200 cases
representing the greatest schedule slippage. The definition of a “large-impact,
hard-to-predict, rare event” is a useful starting point, but as the database
shows, these most damaging risks are not as rare as might be thought, and
they are not necessarily difficult to predict for project managers who are
aware of them as possibilities.
A bit more than half of the black swans are scope risks. Schedule and
resource risks are fewer, each constituting roughly a quarter of the total.
These risks caused projects to slip at least three months, and they account for
over half of the total damage in the PERIL database, almost 3,800 weeks of
accumulated slip. The next three chapters will dig into the details of these
risks, with the goal of improving your chances of identifying them in future
projects. In the second half of the book, we will explore response tactics for
dealing with these and other significant project risks.
Key Ideas for Project Risk Planning
• Project selection affects risk management and depends on it.
• Project risk management builds on the foundation provided by
your project definition and planning.
• A project risk plan summarizes your risk management
approach.
A Second Panama Canal Project: Sponsorship and
Initiation (1902–1904)
A man, a plan, a canal. Panama.
—FAMOUS PALINDROME
Successful projects are often not the first attempt to do something.
Often, there is a recognized opportunity that triggers a project. If the first
attempted project fails, it discourages people for a time. Soon, however, if the
opportunity remains attractive enough, another project will begin, building on
the work and the experiences of the first one. A canal at Panama remained an
attractive opportunity. When Theodore Roosevelt became president in 1901,
he decided to make the successful completion of a Central American canal
part of his presidential legacy. (And so it is. He is the “man” in the famous
palindrome.)
As much as the earlier French project failed because of lapses in
project management, the U.S. project ultimately succeeded as a direct result
of applying good project principles. In fact, the work of Fred Taylor, Henry
Gantt, and other management consultants of the time was advancing in the
early twentieth century and strongly influenced work on the new canal
project in Panama. The results of better project and risk management on this
second project will unfold throughout the remainder of this book.
Unlike the initial attempt to build a canal, the U.S. effort was not a
commercial venture. Maintaining separate U.S. navies on the East and West
coasts had become increasingly costly. Consolidation into a single larger
navy required easy transit between the Atlantic and Pacific, so Theodore
Roosevelt saw the Panama Canal as a strategic military project, not a
commercial one. The U.S. venture considered several routes, but as the
French had done, they settled on Panama.
Theodore Roosevelt was a more typical project sponsor than Ferdinand
de Lesseps. He delegated the management of the project to others. His
greatest direct contribution to the project was in “engineering” the
independence of Panama from Colombia. (This “revolution” was
accomplished by a pair of gunboats, one at Colon on the Gulf of Mexico and
another at Panama City on the Pacific. Without the firing of a single shot,
Roosevelt created the independent nation of Panama in 1902. Repercussions
of this U.S. foreign policy decision persist in Central America, more than a
century later.) To get the project started quickly, Roosevelt also moved to
acquire the assets of the Nouvelle Compagnie (which was of some value to
shareholders of the original company, but not much).
“I took the isthmus!” Roosevelt said. He then went to the U.S.
Congress to get approval to go forward with the building of the canal.
Following all this activity and the public support it generated, Congress had
little choice but to support the project. Although the specifics for the project
were still vague, the intention of the United States was clear: to build a canal
at Panama capable of transporting even the largest U.S. warships and to build
it as quickly as was practical.
Insight into Roosevelt’s thinking concerning the project is found in this
quote from 1899, two years before his presidency:
Far better it is to dare mighty things, to win glorious
triumphs, even though checkered by failure, than to take
rank with those poor spirits who neither enjoy much nor
suffer much, because they live in the gray twilight that
knows not victory nor defeat.
Project sponsors often aspire to “dare mighty things.” They are much
more risk tolerant than most project leaders and teams. Good risk
management planning serves to balance the process of setting project
objectives, so we undertake projects that are not only worthwhile and
challenging but also possible.
Chapter
3
Identifying Project Scope Risk
“Well begun is half done.”
—ARISTOTLE
Although beginning well will never actually complete half of a project,
beginning poorly will lead to disappointment, rework, stress, and potential
failure. A great deal of project risk can be discovered at the earliest stages of
project work, when defining the scope of the project.
For risks associated with the elements of the project management triple
constraint (scope, schedule, and resources), scope risk will generally be
considered first. Of the three types of projects that will fail—those that are
beyond your capabilities, those that are overconstrained, and those that are
ineffectively executed—the first type is the most significant because this type
of project is literally impossible. Identification of scope risks will reveal
either that your project is feasible or that it lies beyond the state of your art.
Early decisions to shift the scope or abandon the project are essential on
projects with significant scope risks.
There is a lack of consensus in project management circles on a precise
definition of “scope.” Broad definitions use scope to refer to everything in the
project, and narrow definitions limit project scope to focus on project
deliverables. For the purposes of this chapter, project scope here will be
consistent with the Guide to the Project Management Body of Knowledge
(PMBOK® Guide). The type of scope risk considered here relates primarily
to the project output(s). Other types of project risk will be explored in later
chapters.
Sources of Scope Risk
Scope risks are most numerous in the Project Experience Risk
Information Library (PERIL) database, representing more than 40 percent of
the data. Even more important, risks related to scope accounted for close to
half of the total schedule impact. The two broad categories of scope risk in
PERIL relate to changes and defects. By far the most damage was due to
poorly managed change (three-quarters of the overall scope impact and more
than a third of all the impact in the entire database), but all the scope risks
represented significant exposure for these projects. Even though some of the
risk situations, particularly in the category of defects, were legitimately
“unknown” risks, quite a few of the problems could have been identified in
advance and managed as risks. The two major root cause categories for scope
risk are separated into more detailed subcategories.
Scope changes due to gaps were the most frequent, but scope creep
changes were the most damaging on average. A Pareto chart of overall
impact by type of risk is summarized in Figure 3-1, and a more detailed
analysis follows.
Change Risks
Change happens. Few if any projects end with the original scope intact.
Managing scope risk related to change relies on minimizing the loose ends of
requirements at project initiation and having (and using) a robust process for
controlling changes throughout a project. In the PERIL database, there are
three categories of scope change risks: scope gaps, scope creep, and scope
dependencies.
Figure 3-1. Total Project Impact by Scope Root Cause Subcategories
Scope creep was the most damaging type of change risk, resulting in an
average schedule slip of well over eight weeks. Scope gaps were only slightly
less damaging, but not by much, and were also both more common and had
greater total impact. Just these two subcategories by themselves represent
over a third of all the reported impact in the PERIL database.
Scope gaps. These gaps are the result of committing to a project before
the project requirements are complete. When legitimate needs are uncovered
later in the project, change is unavoidable. Some of the overlooked
requirements were a consequence of the novelty of the project, and some
were because customers, managers, team members, or other project
stakeholders were not available (or not consulted) at project initiation.
Although some of the scope gaps are probably unavoidable, in most of the
cases these gaps were due to incomplete or rushed analysis. A more thorough
scope definition and project work breakdown would have revealed the
missing or poorly defined portions of the project scope.
Scope creep. This type of change plagues all projects, especially
complex projects. New opportunities, interesting ideas, undiscovered
alternatives, and a wealth of other information emerges as the project
progresses, providing a perpetual temptation to redefine the project and to
make it “better.” Some project change of this sort may be justified using
clear-eyed business analysis, but too many of these non-mandatory changes
sneak into projects because the consequences are either never analyzed or
drastically underestimated. To make matters worse, the purported benefits of
the change are often unrealistically overestimated. In retrospect, much of
scope creep delivers little added value. In some particularly severe cases, the
changes in scope delay the project so much that the ultimate deliverable has
no value at all because the need is no longer pressing or it has been met by
other means. Scope creep represents unanticipated additional investment of
time and money because it requires new effort, and it also results in redoing
work already completed. Scope creep is most damaging when entirely new
requirements are piled on as the project runs. Such additions not only make
projects more costly and more difficult to manage, they also can significantly
delay delivery of the originally expected benefits. Managing scope creep
requires an initial requirements definition process that thoroughly considers
potential alternatives, as well as an effective process for managing
specification changes throughout a project.
Scope creep can come from any direction, but one of the most insidious
is from inside the project. Every day a project progresses, you learn
something new, so it’s inevitable that you will see things that were not
apparent earlier. This can lead to well-intentioned proposals by someone on
the project team to “improve” the deliverable. Sometimes, scope creep of this
sort happens with no warning or visibility until too late, within a portion of
the project where the shift seems harmless. Only after the change is made do
the real and sometimes catastrophic unintended consequences emerge.
Particularly on larger, more complicated projects, all changes deserve a
thorough analysis and public discussion, with a particularly skeptical analysis
of all alleged benefits. Both scope creep and scope gaps are universal and
pervasive issues for modern projects.
Scope dependencies. These are due to external factors that affect the
project and are the third category of change risk. (Dependency risks that are
primarily due to timing rather than requirements issues are characterized as
schedule risks in the database.) Though less frequent in the PERIL database,
compared with other scope change risks, scope dependencies represented an
average slippage of well over a month. Admittedly, some of the cases in the
database involved situations that no amount of realistic analysis would have
uncovered in advance. Most examples, though, were a result of factors that
should not have come as complete surprises. Although legal and regulatory
changes do sometimes happen without notice, a little research will generally
provide advance warning. Projects also depend on infrastructure stability, and
the periodic review of installation and maintenance schedules will reveal
plans for new versions of application software, databases,
telecommunications, hardware upgrades, or other changes that the project
may need to anticipate and accommodate.
Defect Risks
Complex projects rely on many things to work as expected.
Unfortunately, new things do not always operate as promised or as required.
Even normally reliable things may break down or fail to perform as desired in
a novel application. Defects represent about a third of the scope risks and
about one-seventh of all the risks in the PERIL database. The three categories
of defect risks are software, hardware, and integration.
Software problems and hardware failures. These were the most
common types of defect risk in the PERIL database, approximately equal in
frequency. As to impact, software defects averaged well over seven weeks of
delay, and hardware problems were a bit under seven weeks. In several cases,
the root cause was new, untried technology that lacked needed functionality
or reliability. In other cases, a component created by the project (such as a
custom integrated circuit, a board, or a software module) did not work
initially and had to be fixed. In still other cases, critical purchased
components delivered to the project failed and had to be replaced. Nearly all
of these risks are visible, at least as possibilities, through adequate analysis
and planning.
Some hardware and software functional failures were related to quality
or performance shortfalls. Hardware may be too slow, require too much
power, or emit excessive electromagnetic interference. Software may be too
difficult to operate, have inadequate throughput, or fail to work in specific
circumstances. As with other defects, the definition, planning, and analysis of
project work will help in anticipating many of these potential performance
issues.
Integration defects. These constituted the third type of defect risk in
the PERIL database. These defects related to system problems above the
component level. Although they were not as numerous in the database, they
were quite damaging. Integration defects caused an average of about seven
weeks of project slip. For large programs, work is typically decomposed into
smaller, related subprojects that can progress in parallel. Successful
integration of the deliverables from each of the subprojects into a single
system deliverable requires not only that each of the components delivered
operates as specified but also that the combination of all these parts functions
as a system. All computer users are familiar with this failure mode. Whenever
all the software in use fails to play nicely together, our systems lock up,
crash, or report some exotic “illegal operation.” Integration risks, though
relatively less common than other defect risks in the PERIL database, are
particularly problematic because they generally occur on the verge of the
project deadline and are never easy to diagnose and correct. Again, thorough
analysis relying on disciplines such as software architecture and systems
engineering can ensure the timely identification and management of possible
integration risks.
Black Swans
Based on schedule impact, the worst 20 percent of the risks from each
category in the PERIL database—black swans—deserve more detailed
attention. We’ll explore these “large-impact, hard-to-predict, rare events” in
this section. Each of the black swan risks resulted in at least three months of
schedule slip, so each certainly qualifies as having a large impact. Black swan
risks are rare; the PERIL database has an intentional bias in favor of the most
serious risks, which are (or at least we hope are) not risks we expect to see
frequently. The purpose of this section and similar discussions in Chapters 4
and 5 is to make some of these black swans more visible and easier to
predict.
Of the most damaging 206 risks in the PERIL database, 107—just over
half—were scope risks. In the database as a whole, black swans accounted
for slightly more than half of the total risk impact. The top scope risks
exceeded this with nearly 60 percent of the aggregate scope risk impact. The
details are presented in the following table:
Not surprisingly, the black swan scope risks were dominated by change
risk, with over three-quarters of the risks in terms of impact. When major
change risks occur, their effects are painful. Black swan defect risks were
somewhat less damaging, but as with change risks, more than half of the
impact was a result of the worst risks reported.
Eighty-two black swan scope risks were associated with change,
dominated by scope gaps (with a total of 47). Most of the cases involved
ready-shoot-aim tactics—beginning work before understanding what was
needed. Some of the scope gap risks were:
• Team failed to engage the critical power users early enough.
• Project manager thought the solution was only one task, but there
were four.
• Incomplete design was a result of not considering the particular
country needs.
• Lack of consensus on the specifications resulted in later
modifications.
• Survey tasks were assigned to several people in different countries,
and each assumed others would complete the work.
• Development plans failed to include all of the 23 required
applications.
• Seventy-five percent of the requirements were unknown initially to
the project staff.
• Scope for the project was never signed off by upper management.
• A midproject review turned up numerous regulations that were not
implemented.
Most of the rest of the black swans attributable to change risk involved
scope creep. Among these 32 risks were:
• The contract specified state-of-the-art retrofit materials, and
interpretation of this changed several times over two years.
• New technology was introduced late and with insufficient analysis.
• The project team agreed to new requirements midproject, some of
which were not even possible.
• Volume requirements were increased late in the project, requiring
extensive rework.
• Engineering never stopped adding bells and whistles to the graphical
user interface.
• Extension of scope to include Japanese users was poorly managed
and controlled.
• System was expanded to include two more cities for political reasons.
• Application was changed for prospective Chinese customer (who in
the end did not buy).
Three black swan change risks were caused by external dependencies,
including the mandated use of a new technology and shifts in import
requirements from Homeland Security.
There were fewer black swans in the scope defect categories (25 in
total). Software defects caused 14, hardware issues resulted in ten more, and
one was a consequence of poor integration planning. Some of the worst scope
defect risks included:
• Printer project failed to meet print quality goals, requiring redesign.
• Hardware failed near the end of a three-month final test, resulting in
refabrication and retest.
• Defect was discovered only after delivery to the customer.
• The software had 20 major defects and 80 other problems that
prevented timely closure.
• Tests revealed a significant flaw, deferring release to the next
quarterly update.
Identifying scope risks similar to these examples can expose many
potential problems. Reviewing these examples and the additional scope risks
from the PERIL database listed in the end-of-book Appendix can be a good
starting point for uncovering possible scope-related problems on your next
project.
Defining Deliverables
Scoping gaps were the top category of risk in the PERIL database.
Defining deliverables thoroughly is a powerful tool for uncovering these
potential project risks. The process for specifying deliverables for a project
varies greatly depending on the type and scale of the project.
For small projects, informal methods can work well, but for most
projects, adopting a more rigorous approach is where good project risk
management begins. For most projects, defining the deliverables is the initial
opportunity for the project leader and team to begin uncovering risks.
Whatever the process, the goal of deliverable definition is developing
specific, written requirements that are clear, unambiguous, and agreed to by
all project stakeholders and contributors. Some projects do this thoroughly at
the start and anticipate only small, easily managed changes as the work
proceeds. Projects using agile methods do scoping provisionally using a
disciplined process to set specific, prioritized scoping requirements and then
to manage periodic adjustments using feedback generated after delivery of
each iteration’s results. In all cases, initial stakeholder agreement on initial
requirements is essential to managing scope.
A good, thorough process for defining project deliverables begins with
identifying the people who should participate, including everyone who needs
to agree. Project scope risk increases when key project stakeholders are not
involved in the project early enough. Many scope gaps become visible only
late in the project when these people finally get involved. Whenever it is not
possible to work with the specific people who will later be part of the project
team, locate and work with people who are available and who can represent
all the needed perspectives and functional areas. If you need to, call in favors,
beg, plead, or do whatever you need to do to get the right people involved.
Deliverable definition includes all of your core project team, but it
rarely ends there. You will also need others from outside your team, from
other functions such as marketing, finance, sales, and support. You are also
likely to need input from people who may even be outside your organization
—from customers, users, other related project teams, and potential
subcontractors. Consider the project over its entire development life cycle.
Think about who will be involved with all stages of design, development,
manufacturing or assembly, testing, documentation, marketing, sales,
installation, distribution, support, and other aspects of the work.
Even when the right people are available and involved early in the
initial project definition activities, it is difficult to be thorough. The answers
for many questions may not yet be available, and some of your data may be
ranges or even guesses. Specifics concerning new methods or technologies
add more uncertainty. Three useful techniques for dealing with scope risk are
using a documented definition process, developing a straw man definition
document, and adopting a rigorous evolutionary methodology.
Requirements Management
Processes for defining deliverables vary depending on the nature of the
project. For product development projects, the following guidelines are a
typical starting point for requirements management. By reviewing such a list
and documenting both what you know and don’t know, you set the
foundation for project scope and begin to identify the activities for your
project plan necessary to fill in the gaps.
Topics for a typical deliverable definition process are:
1. Alignment with business strategy: How does this project contribute
to stated high-level business objectives?
2. User and customer needs: Has the project team captured the
ultimate end user requirements that must be met by the deliverable?
3. Compliance: Has the team identified all relevant regulatory,
environmental, and manufacturing requirements, as well as any
relevant industry standards?
4. Competition: Has the team identified both current and projected
alternatives to the proposed deliverable, including not undertaking the
project?
5. Positioning: Is there a clear and compelling benefit-oriented project
objective that supports the business case for the project?
6. Decision criteria: Does this project team have an agreed-upon
hierarchy of measurable priorities for cost, time, and scope?
7. Delivery: Are logistical requirements understood and manageable?
These include, but are not limited to, sales, distribution, installation,
sign-off, and support.
8. Sponsorship: Does the management hierarchy collectively support
the project, and will they provide timely decisions and ongoing
resources?
9. Resources: Does the project have, and will it continue to have, the
staffing and funding needed to meet the project goals within the
allotted time?
10. Technical risk: Has the team assessed the overall level of risk it is
taking? Are technical and other exposures well documented?
(This list traces back to the 1972 SAPPHO Project at the University of
Sussex, England.)
Although this list is hardly exhaustive, examining each criterion and
documenting the information you already have provides solid initial data for
scoping and assists you in seeing what is missing. Determining the degree to
which you understand each element (on a scale ranging from “Clueless” on
one extreme to “Omniscient” on the other) reveals the biggest gaps. Although
some level of uncertainty is inevitable, this analysis clarifies where the
exposures are and helps you and the project sponsor decide whether the level
of risk is inappropriately high. The last item on the list, technical risk, is most
central to scope risk identification. High-level project risk assessment
techniques are discussed in detail later in this chapter.
As the requirements come into focus, compile a written list. A list will
not only provide a dependable, common source of data for subsequent project
planning, it also will give you a basis for identifying aspects that are in
conflict, generating useful stakeholder feedback, and allow you to prioritize
and quantify what you are taking on.
Straw Man Definition Document
Most books on project management prattle on about identifying and
documenting all the known project requirements. This is much easier said
than done in the real world. It can be nearly impossible to get users and
stakeholders of complex projects to cooperate with this strategy. When too
little about a project is clear, many people see only two options: accept the
risks associated with incomplete definition (including inevitable scope creep),
or abandon the project. Between these, however, lies a third option. Instead
of simply accepting a lack of data, the project team can create a straw man
definition, generating a plausible list of specific requirements. These
requirements may come from earlier projects, assumptions, or guesses, or
they can come from your team’s concept of a potential solution to the
problem that the project is expected to solve. Any definition constructed this
way is certain to be inaccurate and incomplete, but formalizing requirements
leads to one of two beneficial results.
The first possibility is that these made-up requirements will be
accepted and approved, giving you a solid basis for planning. Once sign-off
has occurred, anything that is not quite right or deemed incomplete can still
be changed, but only through a disciplined project change process. (Some
contracting firms get quite rich using this technique. They win business by
quoting fixed fees that are below the cost of delivering all the stated
requirements, knowing full well that there will be changes. They then make
their profits by charging for the inevitable changes as they occur, generating
large incremental project billings.) Even for projects where the sponsors and
project team are in the same organization, the sign-off process gives the
project team a great deal of leverage when changes are proposed later in the
project. (This whole process brings to mind the old riddle: How do you make
a statue of an elephant? Answer: You get an enormous chunk of marble and
chip off anything that does not look like an elephant.)
The second possible outcome is a flood of criticism, corrections, edits,
and “improvements.” Where most people are intimidated by a blank piece of
paper or an open-ended question, everyone, deep down, is a born critic. Once
a straw man requirements document is created, the project leader can
circulate it far and wide as “pretty close, but not exactly right yet.” Using
such a document to gather comments (and providing big, red pens to get
things rolling) is an excellent way to generate scoping information, though it
may be humbling to the original authors. Embarrassing or not, it is far better
to identify scoping issues early than to discover that you missed something
during acceptance testing at the end.
Agile and Iterative Methods
When the scope gaps are extremely large, a third approach to scope
definition may be more productive. Agile (or evolutionary, or cyclic)
methodologies are increasingly employed for software and related types of
development, where the ultimate deliverables are truly novel, intangible, and
cannot be specified with much certainty. Rather than defining a system as a
whole, these more organic approaches define the problem to be addressed
and set out general overall objectives. These goals are laid out in a sequence
of incremental stages, each producing a functional deliverable. Software
development projects have employed these step-by-step techniques for
decades, with increasingly wide application since the creation of the Agile
Manifesto in 2001. Such techniques are effective for innovative development
projects undertaken by small project teams who have ready access to their
end users. The system deliverables released at the end of each development
cycle adds additional value and functionality, and each iteration brings the
project closer to its final destination. As the work continues, specific scope is
defined for the next cycle or two using user feedback from testing of the
previous cycle’s deliverables. Typical development iterations vary from
about two to six weeks, depending on the specific methodology (Scrum, the
most prevalent, mandates 30 days). Deliverables for future cycles are defined
only in general terms, allowing scoping to evolve utilizing user evaluations
and other data collected along the way for course corrections.
Although this approach can be an effective technique for managing
revolutionary projects where definition is not initially possible, it may
encourage scope creep. It can also result in so-called gold plating, that is,
delivering additional functionality because it’s possible, not because it’s
necessary.
Evolutionary methodologies may also carry higher costs than other
project approaches. Whenever a project can define project deliverables with
good precision early using a more traditional “waterfall” approach, it will
result in a faster, less costly project. By avoiding a meandering definition
process and eliminating the need to deliver to users every cycle and then
evaluate their feedback, comparative costs for more traditionally run projects
may be as little as a third, and timelines can be cut in half. From a risk
standpoint, evolutionary methodologies focus primarily on scope risk,
starting the project with no certain end date or budget. Without disciplined
management, such projects might never end.
Risk management on such multicycle projects requires frequent
reevaluation of the current risks as well as carefully focused scope
management. To manage overall risk using agile methodologies, establish
firm limits for both time and money, not only for the project as a whole but
also for checkpoints no more than a few months apart. Also, set stringent
standards for value delivered whenever setting or adjusting scope in each
succeeding iteration.
Current thinking on evolutionary software development includes a
number of methodologies described as agile, adaptive, or lightweight. These
methods adopt more robust scope control and incorporate project
management practices intended to avoid the license-to-hack nature of some of
the earlier evolutionary development models. Extreme programming (XP) is
a good example of this. XP is intended for use on relatively small software
development projects by project teams collocated with their users. It adopts
effective project management principles for estimating, managing scope,
setting acceptance criteria, planning, and communicating. XP puts pressure
on the users to determine the overall scope initially, and, based on this, the
project team determines the effort required for the work. Short development
cycles are used to implement the deliverable incrementally, as prioritized by
the users, but the amount of scope (which is carved up into “stories”)
delivered in each cycle is determined exclusively by the programmers. XP
allows revision of scope as the project runs, but only as a zero-sum game—
any additions cause something to be removed (or at least deferred until later).
XP also rigorously avoids scope creep within each cycle.
Scope Documentation
However you go about defining requirements, once they are defined,
you need to document them. Managing scope risk requires a scope definition
that clearly defines both what you expect to accomplish and what you intend
to exclude. One problematic type of scope definition characterizes project
requirements as “musts” and “wants.” Although it may be fine to have some
flexibility during early project analysis, carrying uncertainty into
development work exacerbates scope risk. Retaining a list of want-to-have
features remains common on many high-tech projects, making planning
chaotic and estimates inexact, and ultimately results in late (often expensive)
scope changes. From a risk management standpoint, the is/is-not technique is
far superior to musts-and-wants. The “is” list is equivalent to the musts, but
the “is-not” list serves to limit scope. Determining what is not in the project
specification is never easy, but if you fail to do it early, many scope risks will
remain hidden behind a moving target. An “is-not” list does not cover every
possible thing the project might include. It is generally a list of completely
plausible, desirable features that could be included and that in fact might well
be in scope for some future project—just not this one.
The is/is-not technique is particularly important for projects that have a
fixed deadline and limited resources because it defines a boundary for scope
consistent with the timing and budget limits. It is always preferable to deliver
the minimum requirements on time than to carry superfluous scoping
objectives that either make you miss your deadline or must be dropped near
the end of the project. As you document your project scope, establish limits
that define what the project will not include in order to minimize scope creep.
There are dozens of formats for a document that defines scope. In
product development, it may be a reference specification or a product data
sheet. In a custom solution project (and for many other types of projects), it
may be a key portion of the project proposal. For information technology
projects, it may be part of the project charter document. In other types of
projects, it may be included in a statement of work or a plan of record. For
agile software methodologies, it may be a brief summary on a Web page or a
collection of index cards tacked to a wall or forms taped to a whiteboard.
Whatever it may be called or be a part of, an effective definition for project
requirements must be in writing. Specific information typically includes:
• A description of the project: What are you doing?
• Project purpose: Why are you doing it?
• Measurable acceptance and completion criteria: What does “done”
look like?
• Planned project start
• Expected deadline and any other timing constraints
• Cost expectations (at least a rough order of magnitude) and budget
constraints
• Intended customer(s) or users
• What the project will and will not include (is/is-not)
• Dependencies (both internal and external)
• Staffing requirements (in terms of skills and experience)
• High-level risks
• Technology required
• Hardware, software, or other infrastructure required
• Detailed requirements, outlining functionality, usability, reliability,
performance, supportability, and any other significant issues
• Other data customary and appropriate to your project
The third item on the list, acceptance criteria, is particularly important
for identifying defect risks. When the requirements to be used at the end of
the project are unclear or not defined, there is little chance that you will avoid
problems, rework, and late project delay. The key for identifying scope risk is
to capture what you know and, even more important, to recognize what you
still need to find out.
High-Level Risk Assessment Tools
Some level of project risk assessment is central to project initiation.
Even though there may be little concrete information for such an early
assessment of risk, several techniques provide useful insight into project risk
even in the beginning stages. These tools are:
• Risk framework
• Risk complexity index
• Risk assessment grid
The first two are useful in any project that creates a tangible, physical
deliverable through technical development processes. The third is appropriate
for projects that have less tangible results, such as software modules, new
processes, commercial applications, network architectures, or Internet service
offerings. These tools all start with answering the same question: How much
experience do you have with the work the project requires? How the tools use
this information differs, and each builds on the assessment of technical risk in
different directions. These tools are not mutually exclusive; depending on the
type of project, more than one of them may provide insight into overall risk.
Although any of these tools may be used at the start of a project to get
an indication of project risk, none of the three is precise. The purpose of each
is to provide information about the relative risk of a new project. Each of
these three techniques is quick, though, and can provide insight into project
risk early in a new project. None of the three is foolproof, but the results
provide as good a basis as you are likely to have for deciding whether to go
beyond initial investigation into further project work. (You may also use
these three tools to reassess project risk later in the project. Chapter 9
discusses reusing these three tools, as well as several additional project risk
analysis methods that rely on planning details to refine overall project risk
assessment.)
Risk Framework
This is the simplest of the three high-level techniques. To assess risk,
consider the following three project factors:
• Technology (the work)
• Marketing (the user)
• Manufacturing (the production and delivery)
For each of these factors, assess the amount of change required by the
project. For technology, does the project use only well-understood methods
and skills, or are new skills required (or might they need to be developed)?
For marketing, will the deliverable be used by someone (or by a class of
users) you know well, or does this project address a need for someone
unknown to you? For manufacturing, consider what is required to provide the
intended end user with your project deliverable: Are there any unresolved or
changing manufacturing or delivery channel issues?
For each factor, the assessment is binary: Change is either trivial
(small) or significant (large). Assess conservatively; if the change required
seems somewhere between these choices, it is safest to assume that it will be
significant.
Nearly all projects will require significant change to at least one of
these three factors. Projects representing no (or little) change may not even be
worth doing. Some projects, however, may require large changes in two or
even all three factors. For complex projects, changes correlate with risk. The
more change inherent in a project and the more types of change, the higher
the risk will be.
In general, if your project has significant changes in only one factor, it
probably has an acceptable, manageable level of risk. Evolutionary-type
projects, where existing products or solutions are upgraded, leveraged, or
improved, often fall into this category. If your project changes two factors
simultaneously, it has higher relative risk, and the management decision to
proceed, even into further investigation and planning, ought to reflect this.
Projects that develop new platforms intended as the foundation of future
project work frequently depend on new methods for both technical
development and manufacturing. For projects in this category, balance the
higher risks against the potential benefits.
If your project requires large shifts in all three categories, the risks are
the greatest of all. Many, if not most, projects in this risk category are
unsuccessful. Projects representing this much change are revolutionary and
are justified by the substantial financial or other benefits that will result from
successful completion. Often the risks seem so great—or so unknowable—
that a truly revolutionary project requires the backing of a high-level sponsor
with a vision.
A commonly heard story around Hewlett-Packard from the early 1970s
involves a proposed project pitched to Bill Hewlett, the more technical of the
two HP founders. The team presented a mock-up of a handheld device
capable of scientific calculations with ten significant digits of accuracy. The
model was made out of wood, but it had all the buttons labeled and was
weighted to feel like the completed device. Bill Hewlett examined the
functions and display, lifted the device, slipped it in his shirt pocket, and
smiled. The HP-35 calculator represented massive change in all three factors:
The market was unknown, manufacturing for it was unlike anything HP had
done before, and it was debatable whether the electronics could even be
developed on the small number of chips that could be crammed into such a
tiny device. The HP-35 was developed primarily because Bill Hewlett wanted
one. It was ultimately a hugely successful product, selling more units in a
month than had been forecasted for the entire year, and yielding a spectacular
profit. The HP-35 also fundamentally changed the direction of the calculator
market worldwide, and it destroyed the market for slide rules and mechanical
computing devices forever.
This story is known because the project was successful. Similar stories
surround many other revolutionary products, like the Apple Macintosh, the
Yahoo (and then Google) search engine, and home video cassette recorders.
Stories about the risky projects that fail (or fall far short of their objectives)
are harder to uncover; most people and companies would prefer to forget
them. The percentage of revolutionary ideas that crash and burn, based on the
rate of Silicon Valley start-up company failures, is historically around 90
percent. The higher risks of such projects should always be justified by
substantial benefits and a strong, clear vision.
Risk Complexity Index
The risk complexity index is the second technique for assessing project
risk. As in the risk framework tool, technology is the starting point. This tool
looks more deeply at the technology being employed, separating it into three
parts and assigning to each an assessment of difficulty. In addition to the
technical complexity, the index looks at another source of project risk: the
risk arising from larger project teams, or scale. The following formula
combines these four factors:
Index = (Technology + Architecture + System) × Scale
For this index, Technology is defined as the basis for development
used on the project. Architecture refers to high-level functional components
and any external interfaces, and System is the internal software and hardware
that will be used in the product. Assess each of these three against your
experience and capabilities, assigning each a value from 0 to 5:
• 0: Only existing technology required
• 1: Minor extensions to existing technology needed in a few areas
• 2: Significant extensions to existing technology needed in a few areas
• 3: Almost certainly possible, but innovation needed in some areas
• 4: Probably feasible, but innovation required in many areas
• 5: Completely new, technological feasibility in doubt
The three technology factors will generally correlate, but some
variation is common. Add these three factors, to a sum between 0 and 15.
For Scale, assign a value based on the number of people (including all
full-time contributors, both internal and external) expected on the project:
• 0.8: Up to 12 people
• 2.4: 13 to 40 people
• 4.3: 41 to 100 people
• 6.6: More than 100 people
The calculation for the index yields a result between 0 and 99. Projects
with an index below 20 are generally low-risk projects with durations of well
under a year. Projects assessed between 20 and 40 are medium risk. These
projects are more likely to get into trouble, and often take a year or longer.
Most projects with an index above 40 are high risk, finishing long past their
stated deadline, if they are completed at all.
Risk Assessment Grid
The first two high-level risk tools are appropriate for hardware
deliverables. Projects with intangible deliverables may not easily fit these
models, so the risk assessment grid can be a better approach for early risk
assessment.
This technique examines three project factors, similar to the risk
framework. Assessment here is based on two choices for each factor, and
technology is again the first. The other factors are different, and here the
three factors carry different weights. The factors, in order of priority, are
Technology, Structure, and Size.
The highest weight factor, Technology, is based on required change,
and it is rated either low or high, depending on whether the project team has
experience using the required technology and whether it is well established in
situations similar to the current project.
Structure is also rated either low or high, based on factors such as solid
formal specifications, project sponsorship, and organizational practices
appropriate to the project. Structure is rated low when there are significant
unknowns in staffing, responsibilities, infrastructure issues, objectives, or
decision processes. Good up-front definition indicates high structure.
Size is similar to the Scale factor in the risk complexity index. A
project is rated either large or small. For this tool, size is not an absolute
assessment. It is measured relative to the size of teams that the project leader
has successfully led in the past. Teams that are as little as 20 percent larger
than the size a project leader has successfully led should be considered large.
Other considerations in assessing size are the expected length of the project,
the overall budget for the project, and the number of separate locations where
project work will be performed.
After you have assessed each of the three factors, the project will fall
into one of the sections of the grid, A through H (see Figure 3-2). Projects in
the right column are the most risky; those to the left will be more easily
managed.
Beyond risk assessment, these tools may also guide early project risk
management, indicating ways to lower project risk by using alternative
technologies, making changes to staffing, decomposing longer projects into a
sequence of shorter ones with less aggressive or incremental goals, or
improving the proposed structure. Use of these and other techniques to
manage project risk is the topic of Chapter 10.
Figure 3-2. Risk Assessment Grid
Setting Limits
Although many scope risks come from specifics of the deliverable and
the overall technology, scope risk also arises from failure to establish firm,
early limits for the project.
In workshops on risk management, I demonstrate another aspect of
scope risk using an exercise that begins with a single U.S. dollar bill. I show
it to the group, setting two rules:
• The dollar bill will go to the highest bidder, who will pay the amount
bid. All bids must be for a real amount—no fractional cents. The first
bid must be at least a penny, and each succeeding bid must be higher
than earlier bids. (This is the same as with any auction.)
• The second-highest bidder also pays the amount he or she bid (the bid
just prior to the winning bid), but gets nothing in return. (This is
unlike a normal auction.)
As the auctioneer, I start by asking if anyone wants to buy the dollar
for one cent. Following the first bid, I solicit a second low bid, “Does anyone
think the dollar is worth five cents?” After two low bids are made, the auction
is off and running. The bidding is allowed to proceed to (and nearly always
past) $1.00, until it ends. If $1.00 is bid and things slow down, a reminder to
the person who has the next highest bid that he or she will spend almost one
dollar to buy nothing usually gets things moving again. The auction ends
when no new bids are made. The two final bids nearly always total well over
$2.00.
By now everything is quite exciting. Someone has bought a dollar for
more than a dollar. A second person has nothing to show for a bid almost as
high. To calm things down, I put the dollar away, explain that this is a lesson
in risk management (not a swindle), and apologize to people who seem upset.
So what does the dollar auction have to do with risk management? This
game’s outcome is similar to what happens when a project that comes up
against its deadline (or budget), creeps past it, and just keeps going. “But we
are so close. It’s almost done. We can’t stop now!” The auction effectively
models any case where people have, or think they have, too much invested in
an undertaking to quit.
Dollar auction losses can be minimized by anticipating the possibility
of an uncompensated investment, setting limits in advance, and then
enforcing them. Rationally, the dollar auction has an expected return of half a
dollar (the total return, one dollar, spread between the two final bidders). If
each participant set a bid limit of 50 cents, the auctioneer would always lose.
For projects, clearly defining limits and then monitoring intermediate results
will provide an early indication of trouble. Project metrics, such as earned
value (described in Chapter 9), are useful in minimizing unproductive
investments by detecting project overrun early enough to abort or modify
questionable projects. Defining project scope with sufficient detail and limits
is essential for risk management.
Work Breakdown Structure
Scope definition reveals some risks, but scope planning digs deeper
into the project and uncovers even more. Product definition documents, scope
statements, and other written materials provide the basis for decomposing of
project work into increasingly finer detail, so it can be understood, delegated,
estimated, and tracked. The process used to do this—to create the project
work breakdown structure (WBS)—reveals potential defect risks.
One common approach to developing a WBS starts at the scope or
objective statement and proceeds to carve the project into smaller parts,
working top-down from the overall project concept. The decomposition of
work that is well understood is straightforward and quickly done. Whenever
it is confusing or difficult to decompose project work into smaller, more
manageable pieces, there is scope risk. Whenever any part of your project
resists breakdown, it reveals a lack of understanding, which is inherently
risky.
Work Packages
The ultimate goal of the WBS process is to describe the entire project
in small pieces, sometimes called work packages. Each work package should
be deliverable oriented and have a clearly defined output. General guidelines
for the size of the work represented by the work packages at the lowest level
of a WBS are usually stated in terms of duration (e.g., between two and 20
workdays) or effort (no more than roughly 80 person-hours). When
breakdown to this level of granularity is difficult, it is generally because of
gaps in project understanding. These gaps either need to be resolved as part
of project scoping or captured as scope risks. (The relationship between
processes for estimation and risk are explored in Chapters 4 and 5.)
Work defined at the lowest level of a WBS may also be called
activities, tasks, or something else, but what matters most is that you know
how to complete it. Note as risks all cases where you cannot decompose the
work into pieces that you understand and that are within the guidelines.
Aggregation
A WBS is a hierarchy and a useful method for detecting missing work.
The principle of aggregation for a WBS ensures that the defined work at each
level plausibly includes everything needed at the summary level above it. If
the listed items under a higher-level work package do not represent its
complete to-do list, your WBS is incomplete. Either complete it by adding
the missing work to the WBS, or note the WBS gaps as project scope risks.
Any work in the WBS that you cannot adequately describe contributes to
your growing accumulation of identified risks.
Parts of a project WBS that resist easy decomposition are rarely visible
until you systematically seek them out. The WBS development process
provides a tool for separating the parts of the project that you understand
from those that you do not. Before proceeding into a project with significant
unknowns, you also must identify these risks and determine whether the
worst-case costs or other consequences are justified.
Ownership
Some project work is difficult to break into smaller parts for a number
of reasons, but a frequent factor is a lack of experience with the work
required. This is a common sort of risk discovered in developing a WBS,
revealed through the delegation of ownership. A key objective in completing
the project WBS is the delegation of each lowest-level work package (or
whatever you may choose to call it) to someone who will own that part of the
project. Delegation and ownership are well established in management theory
as motivators, and they also contribute to team development and broader
project understanding.
Delegation is most effective when it’s voluntary. It is fairly common
on projects to allow people to assume ownership of project activities in the
WBS by signing up for them, at least on the first pass. Although there is
generally some conflict over activities that more than one person wants,
sorting this out by balancing the workload, selecting the more experienced
person, or using some other logical decision process usually works. But when
the opposite occurs—when no one wants to be the owner—it reveals project
risk. Activities without volunteers are risky, but you may need to do some
digging to find out why. There are a number of common root causes,
including the one already discussed: No one understands the work well.
Perhaps no one currently on the project has developed key skills that the
work requires, or the work is technically so uncertain that no one believes it
can be done at all. Or the work may be feasible, but no one believes that it
can be completed in the “roughly two weeks” expected for activities defined
at the lowest level of the WBS. In other cases, the description of deliverables
may be so fuzzy that no one wants to take them on.
There are many other possible reasons, and these are also risks. Of
these, a lack of time is usually the most common. If everyone on the project
is already working beyond full capacity on other work and other projects, no
one will volunteer. Another possible cause might be that the activity requires
working with people no one likes. If the required working relationships are
expected to be difficult or unpleasant, no one will volunteer, and successful
completion of the work is uncertain. Some activities may depend on outside
support or require external inputs that the project team is skeptical about. Few
people willingly assume responsibility for work that is likely to fail because
of issues beyond their control.
In addition, the work itself might be the problem. Even easy work can
be risky, if people see it as thankless or unnecessary. All projects have at
least some required work that no one likes to do. It may involve
documentation or some other dull, routine part of the work. If done
successfully, no one notices; this is simply expected. If something goes
wrong, though, it draws a lot of attention. The activity owner has managed to
turn an easy part of the project into a disaster, and he or she will at least get
yelled at. Most people avoid these activities.
Another situation is the unnecessary activity. Projects are full of these
too, at least from the perspective of the team. Life cycle, phase gate, and
project methodologies place requirements on projects that seem to be (and in
some cases, may actually be) unnecessary overhead. Other project work may
be scheduled primarily because it is part of a planning template or because
“That’s the way we always do it.” If the work is actually not needed, good
project managers work to eliminate it.
To the project risk list, add clear descriptions of each risk identified
while developing the WBS, including your best understanding of the root
cause for each. These risks may emerge from difficulties in developing the
WBS to an appropriate level of detail or in finding willing owners for the
lowest-level activities. A typical risk listed might be, “The project requires
conversion of an existing database to a new platform, and no one on the
current project staff has the needed experience.”
WBS Size
Project risk correlates with size; when projects get too large, risk
becomes overwhelming. Scope risk rises with complexity, and one measure
of complexity is the size of the WBS. Once you have decomposed the project
work, count the number of items at the lowest level. When the number
exceeds about 200, project risk is high.
The more separate bits of work that a single project leader must
understand, the more likely it becomes that something crucial to the project
will be missed. As the volume of work and project complexity expand, the
tools and practices of basic project management become more and more
inadequate.
At high levels of complexity, the overall effort is best managed in one
of two ways: as a series of shorter projects in sequence delivering what is
required in stages or as a program made up of a collection of smaller projects.
In both cases, the process of decomposing the total project into sequential or
parallel parts starts with a decomposition very like a WBS. In the case of
sequential execution, the process may involve agile methods such as those
discussed previously in this chapter. For programs involving teams working
in parallel, the resulting decomposition creates a number of projects. Each
project will be managed by a separate project leader using project
management principles, and the overall effort will be the responsibility of a
program manager. Project risk is managed by the project leaders, and overall
program risk is the responsibility of the program leader. The relationship
between managing project and program risk is discussed in Chapter 13.
When excessively lengthy or complex projects are left as the
responsibility of a single project leader to plan, manage risk, and execute, the
probability of successful completion is low.
Other Scope-Related Risks
Not all scope risks are strictly within the practice of project
management. Examples are market risk and confidentiality risk. These risks
are related, and although they may not show up in all projects, they are fairly
common. Ignoring these risks is inappropriate and dangerous.
A business balance sheet has two sides: assets and liabilities. Project
management primarily focuses on liabilities, the expense and execution side,
using measures related to the triple constraint of scope/schedule/resources.
Market and confidentiality risks tend to be on the asset, or value, side of the
business ledger, where project techniques and teams are involved indirectly,
if at all. Project management is primarily about delivering what you have
been asked to deliver, but this does not always equate to “success” in the
marketplace. Although it is obvious that “on time, on budget, within scope”
will not necessarily make a project an unqualified success, managing these
aspects alone is a big job and is really about all that a project leader should
reasonably be held responsible for. The primary owners for market and
confidentiality risks may not even be active project contributors, although
many kinds of complex projects now engage cross-functional business teams
—making these risks more central to the project. In any case, the risks are
real, and they relate to scope. Unless identified and managed, they can result
in project failure.
Market Risk
This first type of risk is about getting the definition wrong. Market risk
can relate to features, timing, cost, or almost any facet of the deliverable.
When development efforts are lengthy, the problem to be solved may change,
go away, or be better addressed by an emerging new technology. A
satisfactory deliverable may be brought to market a week after an essentially
identical offering from a competitor. Even when a project produces exactly
what was requested by a sponsor or economic buyer, it may be rejected by
the intended end user. Sometimes the people responsible for promoting and
selling a good product do not (or cannot) follow through. Many paths can
lead to deliverables that meet the specifications and that are delivered on time
and on budget yet are never used or fall short of expectations.
The longer and the more complicated the project is, the greater the
market risk will tend to be. Project leaders contribute to the management of
these risks through active, continuing participation in any market research
and customer interaction and by frequently communicating with all the
stakeholders surrounding the project who will be involved with deployment
of the deliverable.
Some of the techniques already discussed can help in managing this. A
thorough process for deliverable definition probes for many of the sources of
market risk, and the high-level risk tools outlined previously also provide
opportunities to understand the environment surrounding the project.
In addition, ongoing contact with the intended users, through
interviews, surveys, market research, and other techniques, will help to
uncover problems and shifts in the assumptions the project is based on. Agile
methodologies employ ongoing user involvement in the definition of short,
sequential project cycles, minimizing the “wrong” deliverable risk greatly for
project teams working closely with their end users.
If the project is developing a product that will compete with similar
offerings from competitors, ongoing competitive analysis to predict what
others are planning can be useful (but, of course, competitors will not make
this straightforward or easy—confidentiality risks are addressed next).
Responsibility for such ongoing effort may be fully within the project, but if
it is not, the project team should still review what is learned and, if necessary,
encourage the marketing staff (or other stakeholders) to keep the information
current.
The project team should always probe beyond the specific
requirements (the stated need) to understand where the specifications come
from (the real need). Understanding what is actually needed is generally
much more important than simply understanding what was requested, and it
is a key part of opportunity management. The early use of models,
prototypes, mock-ups, and other simulations of the deliverable will help you
find out whether the requested specifications are in fact likely to provide what
is needed. Short cycles of development with periodic releases of meaningful
functionality (and value) throughout the project also minimize this category
of risk. Standards, testing requirements, and acceptance criteria need to be
established in clear, specific terms and periodically reviewed with those who
will certify the deliverable.
Confidentiality Risk
A second type of risk that is generally not exclusively in the hands of
the project team relates to secrecy. Although some projects are done in an
open and relatively unconstrained environment, confidentiality is crucial to
many high-tech projects, particularly long ones. If information about the
project is made public, its value could decrease or even vanish. Better funded
competitors with more staff might learn of what you are working on and
build it first, making your work irrelevant. Of course, managing this risk well
will potentially increase the market risk because you will be less free to
gather information from end users. The use of prototypes, models, mock-ups,
or even detailed descriptions can provide data to competitors that you want to
keep in the dark. On some projects, the need for secrecy may also be a
specific contractual obligation, as with government projects. Even if the
deliverable is not a secret, you may be using techniques or methodologies
that are proprietary competitive advantages, and loss of this sort of
intellectual property also represents a confidentiality risk.
Within the project team, several techniques may help. Some projects
work on a need-to-know basis and provide to team members only the
information required to do their current work. Although this will usually hurt
teamwork and motivation and may even lead to substandard results (people
will optimize only for what they know, not for the overall project), it is one
way to protect confidential information.
Emphasizing the importance of confidentiality also helps. Periodically
reinforce the need for confidentiality with all team members, especially with
contractors or other outsiders. Be specific about the requirements for
confidentiality in contract terms when you bring in outside help, and make
sure all nondisclosure terms and conditions are clearly understood. Any
external market research or customer contact also requires effective
nondisclosure agreements, again with enough discussion to make the need for
secrecy clear.
In addition to all this, project documents and other communication
must be appropriately marked “confidential” (or according to the
requirements set by your organization). Restrict distribution of project
information, particularly electronic versions, to people who need it and who
understand and agree with the reasons for secrecy. Protect information stored
on computer networks or in the cloud with passwords that are changed
frequently enough to limit unauthorized access. Use legal protections such as
copyrights and patents as appropriate to establish the ownership of
intellectual property. (Deciding when to patent intellectual property can be
tricky. On the one hand, they protect your work. On the other hand, they are
public and may reveal what you are working on to competitors.)
Although the confidentiality risks are partially the responsibility of the
project team, many lapses are well out of their control. Managers, sponsors,
marketing staffs, and favorite customers are the sources for many leaks.
Project management tools principally address execution of the work, not
secrecy. Effective project management relies heavily on good, frequent
communication, so projects with substantial confidentiality requirements can
be difficult and even frustrating to lead. Managing confidentiality risk
requires discipline, frequent reminders of the need for secrecy to all involved
(especially those involved indirectly), limiting the number of people
involved, and more than a little luck.
Documenting the Risks
As the requirements, scope definition documents, WBS, and other
project data start to take shape, you can begin to develop a list of specific
issues, concerns, and risks related to the scope and deliverables of the project.
When the definitions are complete, review the risk list and inspect it for
missing or unclear information. If some portion of the project scope seems
likely to change, note this as well. Typical scope risks involve performance,
reliability, untested methods or technology, or combinations of deliverable
requirements that are beyond your experiences. Make clear why each item
listed is an exposure for the project; cite any relevant specifications and
measures that go beyond those successfully achieved in the past in the risk
description, using explicitly quantified criteria. An example might be, “The
system delivered must execute at twice the fastest speed achieved in the prior
generation.”
Sources of specific scope risks include:
• Requirements that seem likely to change
• Mandatory use of new technology
• Requirements to invent or discover new capabilities
• Unfamiliar or untried development tools or methods
• Extreme reliability or quality requirements
• External sourcing for a key subcomponent or tool
• Incomplete or poorly defined acceptance tests or criteria
• Technical complexity
• Conflicting or inconsistent specifications
• Incomplete product definition
• Large WBS
Using the processes for scope planning and definition will reveal many
specific technical and other potential risks. List these risks for your project,
with information about causes and consequences. The list of risks will
expand throughout the project planning process. Your risk list will serve as
your foundation for a risk register, which you will use to analyze and manage
project risk.
Key Ideas for Identifying Scope Risks
• Clearly define all project deliverables, and note challenges.
• Set limits on the project based on the value of the deliverables.
• Decompose all project work into small pieces, and identify
work not well understood.
• Assign ownership for all project work, and probe for reasons
behind any reluctance.
• Note risk arising from expected project duration or complexity.
Panama Canal: Setting the Objective (1905–1906)
One of the principal differences between the earlier unsuccessful
attempt to build the Panama Canal and the later project was the application of
good project management practices. However, the second project had a shaky
beginning. It was conceived as a military project and funded by the U.S.
government, so the scope and objectives for the revived Panama Canal
project should have been clear, even at the start. They were not.
The initial manager for the project as work commenced in 1904 was
John Findlay Wallace, formerly the general manager of the Illinois Central
Railroad. Wallace was visionary; he did a lot of investigating and
experimenting, but he accomplished little in Panama. His background
included no similar project experience. In addition to his other difficulties, he
could do almost nothing without the consent of a seven-man commission set
up back in the United States, a commission that rarely agreed on anything.
Also, nearly every decision, regardless of size, required massive amounts of
paperwork. A year later, in 1905, US$128 million had been spent, but still
there was no final plan, and most of the workers were still waiting for
something to do. The project had in most ways picked up just where the
earlier French project had left off, problems and all. Even after a year, it was
still not clear whether the canal would be at sea level or constructed with
locks and dams. In 1905, mired in red tape, Wallace announced the canal was
a mistake, and he resigned.
John Wallace was promptly replaced by John Stevens. Stevens was
also from the railroad business, but his experience was on the building side,
not the operating side. He built a reputation as one of the best engineers in the
United States by constructing railroads throughout the Pacific frontier. Before
appointing Stevens, Theodore Roosevelt eliminated the problematic seven-
man commission, and he significantly reduced the red tape, complications,
and delay. As chief engineer, Stevens, unlike Wallace, effectively had full
control of the work. Arriving in Panama, Stevens took stock and immediately
stopped all work on the canal, stating, “I was determined to prepare well
before construction, regardless of clamor of criticism. I am confident that if
this policy is adhered to, the future will show its wisdom.” And so it did.
With the arrival of John Stevens, managing project scope became the
highest priority. He directed all his initial efforts at preparation for the work.
He built dormitories for workers to live in, dining halls to feed them,
warehouses for equipment and materials, and other infrastructure for the
project. The doctor responsible for the health of the workers on the project,
William Crawford Gorgas, had been trying for over a year to gain support
from John Wallace for measures needed to deal with the mosquitoes, by then
known to spread both yellow fever and malaria. Stevens quickly gave this
work his full support, and Dr. Gorgas proceeded to eradicate these diseases.
Yellow fever was conquered in Panama just six months after Dr. Gorgas
received Stevens’s support, and he made good progress combating malaria as
well.
Under the guidance of Stevens, all the work was defined and planned
employing well-established, modern project management principles. He said,
“Intelligent management must be based on exact knowledge of facts.
Guesswork will not do.” He did not talk much, but he asked lots of questions.
People commented, “He turned me inside out and shook out the last drop of
information.” His meticulous documentation served as the basis for work
throughout the project.
Stevens also determined exactly how the canal should be built, to the
smallest detail. The objective for the project was ultimately set in 1907
according to his recommendations: The United States would build an 80-
kilometer (50-mile) lock-and-dam canal at Panama connecting the Atlantic
and Pacific oceans, with a budget of US$375 million, to open in 1915. With
the scope defined, the path forward became clear.
Chapter
4
Identifying Project Schedule Risk
Work expands so as to fill the time available for its completion.
—C. NORTHCOTE PARKINSON, PARKINSON’S LAW
Although Parkinson’s observation was not backed up with any
empirical data, its truth is rarely questioned. It seems particularly appropriate
for today’s complex projects because, in addition to all the obvious reasons
that people have for using up the time available to complete their work, on
modern projects there is an additional reason. Most people who are drawn to
these complex projects are analytical, and they like to be precise, accurate,
and thorough. If there is time available to attempt to make something perfect,
most engineers will try.
Projects, however, are rarely about perfection. They are about
pragmatism, delivering a result that is “good enough.” Practicality is not
particularly motivating, and it is rarely much fun, so complicated projects
often diverge from the direct path and out into the weeds. Thoroughly
identifying schedule risks requires awareness of this and disciplined use of
project management planning tools to create appropriate schedules that avoid
overengineering.
In the previous chapter, we considered factors that can make projects
literally impossible. In this chapter and in Chapter 5 concerning resource
risks, our focus is on constraints—factors that transform otherwise reasonable
projects into ones that are doomed to fail. Project processes for scheduling
and resource planning provide a fertile source for discovery of project risks
that arise from these constraints.
Sources of Schedule Risk
Schedule risk cases make up slightly less than 30 percent of the records
in the PERIL database. These risks have an average impact of over six weeks,
about equal to resource risks, and they represent nearly a quarter of the
overall impact in the PERIL database. Schedule risks fall into three
categories: delays, estimates, and dependencies. Delay risks were most
numerous; these are defined as schedule slips due to factors that are at least
nominally under the control of the project. Estimate risks were on average the
most damaging of the schedule risks; these are cases of inadequate durations
allocated to project activities. Schedule dependency risks, also significant,
relate to project slippage due to factors outside the project. (These
dependencies all relate to timing; dependency problems primarily caused by
deliverable requirements are grouped with the scope change risks.) Each root
cause category is further divided into subcategories, as summarized in the
following table:
The overall impact of these schedule risk subcategories is summarized
in Figure 4-1. The subcategory with the largest total impact was estimating
novel work, with waiting for a needed component not far behind.
Figure 4-1. Total Project Impact by Schedule Root Cause
Subcategories
Delay Risks
Delay risks represent over half of the schedule risks and about one-
seventh of all the risks in the PERIL database. Impact from delays had the
lowest average of any other subcategory in the database, but it was still well
over one month. Types of delay risk in the PERIL database include parts,
information, hardware, and decisions.
Parts that were required to complete the project deliverable were the
most frequently reported source of delay, with an average schedule impact of
over five weeks. Delivery and availability problems were common sources
for this delay, but quite a few issues also involved international shipping,
including customs, paperwork, and related concerns. Delays also resulted
from parts that arrived on time but were found to be defective. The time
required to replace or repair components that did not work properly represent
significant sources of project slip.
Information needed by the project represented more than 20 percent of
the cases in the delay category. These were also the most damaging on
average, representing an average of more than six weeks of project slip.
Some of the information delay was due to time differences between parts of
distributed global teams. Regularly losing one or more days due to
communication time lags and misunderstandings was common. In other
cases, access to information was inadequate, or delivery of needed reports
was interrupted.
Nearly a fifth of the delay risks were caused by late hardware that was
needed to perform project work, including systems and other equipment.
Risks in this subcategory averaged about a month of delay.
Slow decisions also caused project slippage. Roughly one-sixth of the
delay examples were due to managers or other stakeholders who did not act
as quickly as necessary to keep the project on schedule. Sometimes the cause
was poor access to the decision makers or their lack of interest in the project.
For other projects, delays were the result of extended debates, discussions, or
indecision. Projects facing these issues lost over five weeks on average while
waiting for a response to a project request.
Potential delay risks may be difficult to anticipate, and many of them
legitimately appear to be unknown risks. Thorough analysis of the input
requirements at each stage of the project plan, however, will highlight many
of them.
Estimating Risks
Of all the types of schedule risk found in projects, estimating is the
most visible. When you ask project managers what their biggest difficulties
are, estimating is high on, if not at the top of, the list. Despite this, the
number of incidents in the PERIL database is not too large, about 8 percent of
the records, and only about a quarter of the total schedule risks. The average
impact of the estimating risks is only slightly above that of the PERIL
database as a whole, at just under two months of slippage. One frequently
cited issue with estimating in complex projects is the relatively rapid change
in the work. The standard advice is that good estimates rely on history, but
when the environment is in constant flux, history may not seem all that useful
(more on this later in the chapter). The estimating risk subcategories relate to
learning curves, judgment, and imposed deadlines.
Learning curve issues were the most common type of estimating risk.
Their impact was well above the average for the database, in excess of nine
weeks. The quality of the estimates when new technology or new people (or
even worse, both) are involved is not good. The portions of project work that
require staff to do things they have never done before are always risky, and
although thorough analysis of the work can show which parts of the project
plan are most exposed, precise estimating is difficult.
Judgment in estimating was the next most common estimating problem
in the PERIL database. For most of these cases, the estimates were simply
overoptimistic—one of the most common sources of project bias. Some of
these estimates were too short by a factor of three or four. Dealing with this
source of estimating risk requires thorough planning, with appropriate
understanding and decomposition of the work, so that the effort and steps
required are known. It also requires good record keeping. Metrics and project
data archives are invaluable in creating future estimates that are more
consistent with reality than past estimates were (even for projects where
things change rapidly). Having some data always beats having to guess.
Another powerful tool in revealing and combating optimistic estimates is
worst-case analysis. The answer to the question “What might go wrong?”
will not only reveal something about the likely duration, it will also uncover
new potential sources of risk.
Imposed deadlines were the third subcategory of estimating risks.
These inaccurate estimates cause close to two months of slippage, and their
root cause lies outside the project. Modern projects frequently have
aggressive deadlines set by stakeholders in advance, with little or no input
from the project team. Even when the project plan shows the deadline to be
unrealistic, these unattainable timing objectives are often retained. Such
projects are doomed from the start.
Dependency Risks
Dependency risks were about a fifth of the schedule risks. The impact
from schedule dependency risks is about equal to the average for the PERIL
database as a whole, averaging just over seven weeks of slip per incident.
There are three dependency risk subcategories: other projects, infrastructure
factors, and legal issues.
Other projects with shared dependencies not only were the most
numerous of the dependency risks, they also are quite damaging, with an
average of nearly eight weeks. In larger projects (often classified as
programs), a number of smaller projects interact and are linked by
interdependencies. In addition to providing one another with information and
deliverables that meet well-defined specifications (which is a scope risk
exposure), each project within a larger program must also synchronize the
timing of schedule dependencies to avoid being slowed down by (or slowing
down) other projects. Managing all these connections is difficult in complex
programs, and the amount of damage increases with time; many of these risks
in the PERIL database were noticed only near the end of the projects. Even
for the interfaces that were defined in advance, delay was fairly common due
to the uncertainty in each project and the high likelihood that at least one of
the interconnected projects would encounter some sort of difficulty. With so
many possible failure modes, it is all but certain that something will go
wrong. Analysis of the connections and interfaces between projects is a key
aspect of program management, and many of the risks faced by the projects
become visible through interface management techniques (detailed in Chapter
13).
Infrastructure dependencies also interfered with project schedules in
the PERIL database. The frequency of these problems was somewhat lower
than those due to project interdependencies, but their impact was less on
average, at less than six weeks. These situations included interruption of
technical services, such as computer systems or networks required by the
project, and inadequate access to resources such as help desks, system
support, and people who understood older but necessary applications. Several
projects were delayed by maintenance outages that were unknown to the
project team, even though they had been scheduled in advance.
Legal and regulatory dependencies were also problematic. Though the
number of cases was well under 20 percent of the dependency risks, the
average impact was highest for this subcategory, in excess of nine weeks.
Legal and paperwork requirements for international shipments can cause
problems when they change abruptly. Monitoring for planned or possible
changes to laws and mandatory standards can forewarn of many potential
regulatory problems.
Black Swans
In this book we have been referring to the worst 20 percent of the risks
in the PERIL database as black swans. These “large-impact, hard-to-predict,
rare events” caused at least three months of schedule slip, and just under one-
quarter (46 of these most damaging 206 risks) were schedule risks. As with
the black swans as a whole, the most severe of the schedule risks account for
one-half of the total measured impact. The details are summarized in the
following table.
As can be seen in the table, the black swan schedule risks were
distributed relatively evenly. There were 19 estimating risks, with 11 related
to learning curve issues. About two-thirds of the learning curve risk impact
was caused by cases such as these:
• The team in Germany lacked expertise needed for testing in a key
intermediate step.
• New development team members were hired regardless of their lack
of business knowledge.
• Ramp-up required 40 new test engineers.
• Neophyte project staff lacked system expertise.
There were five cases of major project slippage due to estimating
judgment, all related to excessively optimistic assessment of project work.
Three black swan risks were caused by imposed deadlines. Most were
due to unrealistic commitments made “to win the business” or otherwise
without project team input.
Schedule delays in the PERIL database accounted for another 15 black
swans. Six of these significant risks were due to delayed parts. A couple of
examples were as follows:
• A component ordered was too long for international shipment, so it
was cut and shipped in pieces. What arrived was useful only as raw
material and replacing it was expensive.
• Insufficient amount of test material was sent to the contract lab.
Five more long delays were caused by late information, including
these:
• Merging of multiple standards was needed to support reorganization.
The lack of a consistent definition delayed project data conversion.
• An old application that had to be updated lacked documentation, and
finding original code took weeks.
Three of the black swan risks were due to tardy decision making,
halting projects while waiting for stakeholder consensus to develop. One
black swan was hardware related, caused by a shipment of required servers
that got stuck in customs.
There were also 12 black swan dependency risks. Seven black swan
risks were associated with programs in the PERIL database, including these
examples:
• The manager of a related project allowed stakeholders to make
frequent scope changes, causing ripple effects and delay.
• Interdependencies in complex programs were detected late.
• Firmware needed for a key project component was dropped by
another project.
There were also three significant infrastructure examples, involving
situations such as an unexpected operating environment upgrade that resulted
in lots of rework and significant overhead.
Also, two projects encountered regulatory delay due to situations such
as an unexpected recertification and a newly required verification study.
Additional examples of schedule risks from the PERIL database may
be found in the Appendix to this book.
Activity Definition
Building a project schedule starts with defining project work at an
appropriate level of decomposition. When working with small parts of the
project, the estimating and sequencing of work in a project are easier and
therefore less risky. Although the entire project may be big, complicated, and
confusing, the principle of divide and conquer allows for independent
consideration of each little piece of work and lets the project team bring order
out of chaos. The starting point for schedule development (as well as for
resource planning) is the project work breakdown structure (WBS), discussed
in Chapter 3. If the work described at the lowest level of your WBS is
consistent with the guidelines of 2 to 20 days duration or 80 hours of effort,
the lowest-level items may be used as a solid foundation for scheduling. If
your WBS decomposition is not yet to that level of granularity, hidden risks
and questionable estimates will remain until you have done further analysis
and decomposition. Managing risk depends on knowing what “going right”
looks like, so it’s best to work with small, self-contained, deliverable-oriented
bits of your project that you can competently estimate, schedule, and monitor.
The lowest level of the WBS hierarchy is the basis for developing a
schedule, but the terminology used varies. Some call the items work
packages, scheduling tools often use the term tasks, and agile software
methodologies such as XP refer to stories. In “Project Time Management,”
the PMBOK® Guide refers to these pieces of work as activities, so that is the
term used here.
Creating a project schedule requires both duration estimating and
activity sequencing. Which of these planning tasks you undertake first is
largely a matter of personal preference. The PMBOK® Guide shows these
two processes in parallel, which is realistic. Both estimating and activity
sequencing are iterative processes, and there is a good deal of interaction
between the two when building a project plan. If starting to sequence project
activities prior to estimating them seems more natural for your projects, use
the material in this chapter in that order. What is essential for risk
management is that you do both thoroughly because each reveals unique
schedule risks.
Estimating Activity Duration
Estimating risk provides a substantial number of the entries in the
PERIL database and represented the highest average impact, at nearly two
months. A good estimating process is a powerful tool for identifying this type
of schedule risk. When the estimates that are precise can be separated from
those that are uncertain, the risky parts of the project are more visible. When
estimates are top-down or based on guesses, the exposures in the project plan
remain hidden. Quite a few failed projects are a consequence of inaccurate
estimates.
In the dictionary, an estimate is “a rough or approximate calculation.”
Projects require approximations of both time and cost. The focus of this
section is on the risks associated with time estimates. All project estimates
are related, though, and a number of concepts introduced here will be
expanded in Chapter 5 and used there to identify resource risks through the
processes of estimating effort and cost. Estimates of varying accuracy are
derived throughout a project, from the “rough-order-of-magnitude” estimates
used to initiate projects to the more precise estimates that are refined as the
project runs that will be used to control and execute project work. Single-
point estimates imply accuracy that is rarely justified in complex projects.
Estimates that make risk visible are therefore stated as ranges, or with a
percentage (plus or minus) to indicate the precision, or by using a probability
distribution for expected possibilities.
Estimation Pitfalls
Estimating project work is challenging, and most project leaders will
admit that they don’t do it as well as they would like. Understanding the
factors that make accurate project estimating difficult provides insight into
sources of project risk and helps us to improve future estimates. Four key
impediments to estimating well are:
1. Avoidance
2. Optimism
3. Lack of information
4. Granularity
Probably the most significant problem with estimating is that people
who work on most projects do not like to estimate, and they avoid doing it.
The appeal of complex projects is the work—designing, programming,
engineering, building, and other activities that the analytical people on these
projects like to do. People avoid estimating (and planning in general) because
it is seen as overhead, or boring “administrivia.” Estimates are done quickly
and only grudgingly. Most technical people have little estimating experience
or training in estimating, so their skill level is low. Few people like doing
things they do poorly. To make matters worse, because the estimates
provided are so often inaccurate, most of the feedback they get is negative. It
is human nature to avoid activities that are likely to result in criticism and
perhaps punishment.
Too much optimism is another enemy of good estimates. In the PERIL
database, the most common causes for poor estimating are learning curves
and judgment, both of which may be symptoms of the very common human
bias for optimism. Estimates that are too short create many additional project
problems, including severe increases in late-project work and deadline
slippage. Optimistic estimates are often based on best-case scenario analysis
(each activity is scheduled assuming that nothing goes wrong), assumptions
about the amount of time that people will have available to do project work,
and overconfidence in the talent and speed of the project team. The third kind
of estimating risk in the PERIL database is top-down deadline pressure.
When sponsors and stakeholders are inappropriately optimistic, they impose
unrealistic time constraints on the project, forcing the project team to create
estimates and schedules based on the time available instead of the reality of
the work.
A third issue is a lack of information. Initial project estimates are the
product of early analysis, when the amount and quality of available project
information are still low. Often, scope definition is still changing and
incomplete, and significant portions of the work are poorly understood when
these estimates are made. Compounding this, on most modern projects there
is little (sometimes no) historical information to use in estimating, and no
defined estimating processes are used. The estimating method used far too
often is guessing.
A fourth factor contributing to poor estimates is the granularity of the
work. Early estimates are often done for projects based on descriptions of the
work and the deliverables and are lacking much detail. Estimates are
chronically inaccurate when they are based on high-level project deliverables
without details or acceptance criteria. The quality of estimates for long-
duration project activities is also poor. Guidelines for project activities at the
lowest level of the WBS—roughly two weeks’ duration, or 80 hours of effort
—enable better estimating. When the activity duration extends beyond a
month, duration assessments tend to be wildly inaccurate.
To recap, metrics, well-defined estimating procedures, clear scoping,
disciplined planning, and periodic review of the project are all instrumental in
improving estimates and decreasing estimation risk.
Estimation Techniques
Most of the estimating risks in the PERIL database are categorized as
judgment and learning curve problems. The projects affected by these risks
all had significant delays due to unrealistically short estimates. Many projects
failed to account properly for the increasing complexity or new technologies
in their work. Other projects chronically underestimated the time for shipping
and other commonplace project dependencies. Better processes and more
attention to performance data will help to identify many of these risks, if not
eliminate them.
Effective estimating techniques all rely on history. The best predictor
for work duration (or effort) on a project will be a past measurement made
when doing the same (or similar) work done earlier. All effective estimating
processes either use historical data directly or rely on history as a foundation.
Sources of appropriate data are essential to estimating well and reducing
estimation risk. Good estimating is based on:
• Historical data
• Experts and expert judgment
• Experience-based rules and parametric formulas
• Relative size or scale assessment
• Delphi group estimating
• Further decomposition
For cases where none of these methods are effective, there will be
estimating risk.
Historical data. The simplest estimating technique is to look up the
answer. The most useful historical information, for projects of all types, is
solid empirical data, collected with discipline and care during earlier work.
Unfortunately for most project leaders, such project metric databases may be
rare for today’s projects, and useful information may be sparse. Potential
sources of information on activity effort and duration for projects can be
found by reviewing data from:
• Postproject analysis and lessons-learned reports
• Personal notes and status reports from recent projects
• Notes from team members
• Published technical data (either inside your organization or public)
• Reference materials and engineering or other standards
• The Web (offering data of wildly varying reliability)
Anecdotal historical information is often plentiful. Discuss the project
with others and probe their memories. Written historical data tends to be
more reliable, but anecdotal information is easier to get. Memories may not
be as trustworthy, but any historical information can serve as a good starting
point for preliminary estimating, especially if the data is recent, relevant, and
credible.
A lack of documented history is a problem that is easy to fix.
Measurement and productivity analysis are essential to the ongoing
management of estimation risk, so resolve to begin or to continue collecting
actual activity data at least for your own projects. Metrics useful for risk
management are covered in detail in Chapter 9.
Experts. Historical information need not be personal to be useful.
Even when no one on the project has relevant experience or data, there may
be others, outside your project, who do. Look to peers, managers, and
technical talent elsewhere in your organization. Seek out the opinions of
colleagues in professional societies who do similar work for other companies.
Outside consultants in technical or management fields may have useful
information that they will share for a fee. Even quotations and proposals from
service suppliers may contain useful data that you can use for estimating
project work.
Rules and formulas. When a type of work is repeated often, the data
collected over time may evolve into useful formulas for duration or for effort.
These formulas may be informal rules of thumb providing approximate
estimates that relate to measurable aspects of activity output, or they may be
elaborate, precise (or at least precise-looking) analytical equations derived by
regression analysis using data from past projects. One often referenced
parametric formula in the software development world is the Constructive
Cost Model (COCOMO), initially introduced several decades ago by Barry
Boehm at TRW, with refinements over the years based on work at the
University of Southern California, among many others. If your organization
supports such size-based estimation methods, use them, and contribute data
from your projects to improve their accuracy and keep them current.
Relative size or scale assessment. Parametric estimating techniques
such as COCOMO use quantitative metrics to derive estimates of duration
and cost, but size-based estimates can be useful even if they are based on
more qualitative assessments. For small projects (or the short iterations used
for agile management), so-called T-Shirt estimation techniques can be useful
for planning. Activities are defined and then sorted into categories such as
small, medium, large, or extra large. Within the categories, defined work can
be compared and some adjustments made for work that does not appear
sufficiently similar. Relative estimating works best when standards are
defined (for example, “small” equals one to three person-days) and the team
has sufficient experience with the technique to ensure reasonable correlation
between the number of activities in each category that can be completed in a
month (or some other fixed amount of time). Relative size estimating can also
be a low-anxiety way to introduce analytical estimating methods.
Delphi estimates. What individuals can’t tell you, groups sometimes
can. The Delphi process uses inputs from several people (a minimum of four
or five) to establish numerical estimate ranges and to stimulate discussion.
This method relies on the fact that, although no one person may be able to
confidently provide reliable estimates, a population of stakeholders can
frequently provide a realistic prediction (as well as range information useful
in assessing uncertainty). Delphi is a group-intelligence process to tap into
anecdotal historical data that would otherwise remain hidden, and because it
is collaborative, it contributes to group buy-in, ownership, and motivation.
Further decomposition. Another approach you can use when you lack
historical data is to create some. Begin by breaking the activity to be
estimated into even smaller pieces of work, and choose a representative
portion. Perform this part of the work and measure the duration (or effort)
required to complete it. Extrapolate from the actual measurements of the
portion of the work to estimate the whole activity. Some activities can also be
better estimated if thought of as small projects, with phases such as
investigation, analysis, development, documentation, and testing.
For activity estimates where none of these methods prove useful, you
will face estimating risk.
The Overall Estimating Process
Good project estimating requires many inputs, starting with a
comprehensive list of project activities. Another is a resource plan,
information about the people and other resources available to the project. The
resource plan is part of the “Project Resource Management” segment of the
PMBOK® Guide and is a major topic in Chapter 5. One key reason for the
resource information was mentioned in Chapter 3: You need to know the
owners for activities at the lowest level of the project WBS. The activity
owner is generally responsible for initial activity duration estimates. Whether
the owner is the only contributor, or leads a team, or serves as a liaison to
another group where the work will be done, work estimates are ultimately the
owner’s responsibility.
Accurate estimates require clear, specific information about each
activity. Document any constraints on activity durations or project
assumptions that might affect the estimates. Activities with more than one
deliverable may be easier to manage and have less risk if they are broken
down further, creating new, smaller activities for each deliverable.
Acceptance criteria and unambiguous, measurable requirements also
contribute to accurate estimates. If specifications are unclear, clarify them or
note the project risks.
There are three distinct types of project estimates:
1. Duration estimates, measured in active work time (usually
workdays)
2. Effort estimates, measured using a combination of people and time
(person-days or something similar)
3. Calendar estimates, measured in elapsed time (calendar days)
Each type of estimate has its place in the planning process. Duration
estimates are used as input to computer scheduling tools and for schedule
analysis. Effort estimates are based on resource analysis and relate to project
costs. Calendar duration estimates underpin project deadlines and support
accurate tracking. Project planning requires all three estimate types, and
either starts with duration estimates or effort estimates. The other estimates
follow, ultimately generating calendar estimates that are used to ascertain the
project timeline. Whatever estimating sequence you prefer, good planning
and risk management depends on estimates derived from bottom-up project
analysis. Avoid so-called pegged-date, or arbitrary, politically specified
estimates. Building a plan with unrealistic estimates creates risk and
undermines your ability to negotiate necessary project changes.
Some project leaders prefer to derive duration estimates first and then
develop the effort estimates when other planning data, such as activity
sequencing information, is available. Effort estimates may then be used to
validate and adjust the duration estimates. This process is summarized in
Figure 4-2. You may prefer to begin with effort estimating, but whatever
sequence you employ must consider the same issues, factors, and risks.
Figure 4-2. Estimation Process
Project-specific factors and duration estimates. As mentioned,
project estimating methods (including guessing) start with information
derived in some way from history and experience. Beginning with the best
available historical data for each activity, develop duration estimates. Use
project-specific information to adjust these initial assessments, based on
differences between the current project and earlier work. Project-specific
factors include:
• Clarity of the project specifications
• Likelihood of significant specification change
• New resource requirements
• Longer overall project duration
• Unusual technical complexity
• New required technology
• Extreme requirements for reliability
• Geographic separation and cultural diversity on the project team
• Infrastructure and environment differences
• Training requirements
Every lowest-level activity in your WBS requires a duration estimate,
measured in workdays (or some suitable units). In addition to providing input
for adjusting historical data, these project-specific factors may also reveal
significant project risks. If so, list them.
The estimates themselves may also reveal risks. Any activities with
uncertain estimates are risky. However, lack of confidence in an estimate is a
symptom of risk, not the risk itself. Whenever any of your project estimates
seem untrustworthy, probe for why, and note the root cause as the risk. Two
common sources of low-confidence estimates are lack of experience with the
work and activities that may have several different outcomes, such as an
investigation.
Resource factors and effort estimates. Duration estimates, combined
with project information on people and teams, provide the basis for effort
estimates. Initial resource plans provide information on resource factors, such
as:
• The amount of time each day that each team member has for project
work
• The number of people contributing to each activity
• The skills, experience, and productivity of each team member
• Training and mentoring requirements
• Nonproject responsibilities for each person
• Communication lags and other consequences of distributed teams
• Expected turnover or attrition of staff during the project
• The number and duration of project (and other) meetings
• The amount of project communication and reporting
• Travel requirements
• The number of required people not yet assigned to the project
The first factor on the list, the number of project hours in a day, is a
common cause of underestimation. Not every hour that people work is
available for project activities. Meetings, communication (both formal and
informal), breaks, meals, and other interruptions take time. Even the common
assumption of five to six hours per day for project activities may be
significantly higher than the reality available to many projects. Productivity is
also a source of variation, and for individual team members it can vary
wildly. Any estimates of effort or duration made in advance of assigning the
specific people who will do the work are risky. These and other resource-
related risks will be discussed in greater detail in Chapter 5.
By considering the effort required by each activity in light of the
resource factors, you can determine activity effort in person-hours (or
contributor-days or some other combination of staffing and time).
Nonproject factors and calendar estimates. The final stage of
estimation is to translate duration estimates into calendar estimates. To
translate workday duration estimates into elapsed-time estimates, you need to
account for all the days that are not available for project work. Computer
scheduling tools simplify this process; many of the following factors can be
entered into the calendar database, allowing the software to do the
calculations. Some nonproject factors include:
• Holidays
• Weekends
• Vacations and other paid time off
• Other projects
• Other nonproject work
• Lengthy nonproject meetings
• Equipment downtime
• Interruptions and shutdowns
• Scheduled medical leave
Calendar estimates account for all the days between the start and end of
each activity. Specific dates for each activity are derived by combining
duration estimates, nonproject factors, and the activity sequencing
information that we discuss later in this chapter. One particular risk common
for global projects is a result of differences in scheduled time off for
geographically separate parts of the project team. Frequent loss of some of
the project team to various national and religious holidays is disruptive
enough, but all too often these interruptions come as a surprise to the project
leader, who may not be aware of all the relevant holidays.
Applying Estimating Techniques
Figure 4-3 summarizes estimation techniques that are applicable in
various situations. For each project activity, the team either has experience or
not. For the type of work involved, relevant metrics will either exist or not.
Highest estimating risk is found in the worst-case, lower-right
quadrant: no experience and no data. This case is far from unusual; on
complex projects, it may be true for a number of activities you need to
estimate. The most frequently used estimating methods involve guessing,
sometimes with arcane rules, and in this situation a guess may be your best
option. You can also consider alternatives such as getting someone who has
experience to consult on your project or even replanning the work to use an
approach where your team does have experience.
Only slightly better than this is the case where you have no experience
but you have found some external information. Estimates based on someone
else’s measurements are better than nothing, but unless your project is similar
to the project for which the measurements were made, the data may not be
relevant. In either of these cases, when a project activity requires work for
which you lack experience, estimation risk is high, and the potential
inaccuracy of activity duration estimates belongs on your project risk list.
Figure 4-3. Estimating Techniques
The upper-right quadrant is for activities that have been done before
but for which no data exists. Although this should not happen, it is fairly
common on modern projects. Thorough analysis and estimating methods
such as Delphi may provide adequate estimates, but the results of these
processes still contain estimation risk. Over time, more disciplined data
collection can help you better manage these risks.
The best case is the upper-left quadrant. The existence of both
experience and measurements should provide credible, reliable estimates for
project activities. Eventually, proactive risk management and disciplined
application of other project processes will move many, if not most, activities
here, even on high-tech projects.
Another significant source of estimation risk arises from the people
who are assigned to do the work. “Good” estimates need to be believable,
which means that they are derived from data and methods that make sense.
This is a good foundation, but even the best estimating techniques yield
unreliable estimates if they lack the project team buy-in. To be accurate,
estimates must also be believed. No matter how much data goes into creating
estimates, if the people who will do the work do not agree with them, they are
risky. Good estimates are both believable and believed.
Duration Estimates Adjusted for Uncertainty
All the techniques just discussed generate deterministic, single-point
estimates for project activities. This type of estimate implies a precision that
is far from reality. To better deal with uncertainty and risk, the Program
Evaluation and Review Technique (PERT) methodology was developed in
the late 1950s by the U.S. military. The earliest forms of PERT used three-
point range estimates for each activity: an optimistic estimate, a most likely
estimate, and a pessimistic estimate. (PERT may be used for both time and
cost analysis. This discussion focuses on time analysis. PERT for cost
estimates will be explored in Chapter 5.) Traditionally, PERT mapped a bell-
type distribution that could skew toward either the optimistic or pessimistic
estimate, usually with a Beta distribution such as the one in Figure 4-4. The
three estimates defined the range and peak of the distribution as in the figure,
and an “expected” activity duration (the 50 percent point for the curve) could
be derived using the formula:
where: te is the calculated expected duration
(the mean)
to is the optimistic duration (the best
case)
tm is the most likely duration (the peak of
the distribution)
tp is the pessimistic duration (the worst
case)
In addition to the expected estimate, PERT is also used to
quantitatively assess estimation risk. For PERT, the range of possible
outcomes allows you to approximate the standard deviation (σ) for each
activity duration estimate, where:
Figure 4-4. Duration Estimates for PERT Analysis
The theory behind PERT was a step in the right direction, but in
practice PERT analysis may be problematic. The three most common issues
people have with PERT are the time and effort required for the analysis, data
quality, and misuse of the information.
PERT requires more data—three estimates. This requires more time to
collect, enter, and analyze. The collection process is annoying to the project
team, and the three estimates are not easily integrated using common project
management tools. Because of this, the cost of PERT analysis may exceed
the apparent value of the results.
Also, as discussed, the quality of even one estimate can be suspect. The
accuracy of the two additional estimates is usually worse. Definitions of
optimistic and pessimistic can be inconsistent, arbitrary, and confusing.
PERT initially defined the range limits as “1 percent tails.” It was suggested
that people imagine doing an activity 100 times and select estimates so that
only once would the duration fall below the optimistic estimate and only once
would it lie above the pessimistic estimate. For most activities, these
estimates were generally wild guesses, or fixed plus/minus percentages.
Because of this, PERT is often the victim of garbage-in/garbage-out.
Probably the biggest reason that PERT is not more widely used is the
potential for misuse of the information involved. Many organizations
experiment with PERT for a time before this issue surfaces, but it eventually
does. Everything starts out well. Project teams do their best to figure out what
the three estimates might be for each activity, using difficult-to-understand
definitions involving Beta distributions and 1 percent tails (or 5 or 10 percent
tails—there are many variants). Project PERT analysis proceeds for a time,
and some insight into project uncertainty begins to emerge. This continues
until some bright midlevel manager notices the optimistic estimates. Because
the project teams have at least implied that these estimates are not actually
impossible, managers begin to insist that schedules be based only on these
most aggressive estimates, which are used to define the project deadlines.
The statistical underpinnings of PERT predict that such schedules have
essentially no chance of success, and experience invariably proves that the
prediction is correct. If any interest in PERT remains after this, the battered
project teams, acting in self-defense, start to use different definitions for
optimistic estimates.
Although PERT methodology can be troublesome, especially in its
traditional form, three-point estimates can be useful. Optimistic estimate
analysis is an important tool for exploring project opportunities, and in
Chapter 6 we will discuss using this best-case analysis to explore project
opportunities.
Even more important, pessimistic (or worst-case) estimates are a
particularly fertile source of project risk information. After collecting activity
estimates, investigate worst cases using questions such as:
• What might go wrong?
• What are the likely consequences should any issues arise?
• Is the staff involved experienced in this area?
• Have we had problems with this kind of work before?
• Does this activity depend on inputs, resources, or other factors we
don’t control?
• Are there aspects of this work that we don’t understand well?
• If you were betting money on the estimates, would they change?
The responses to these and related probing questions will provide two
pieces of important project risk data. The potential consequences you
uncover, including slippage, additional costs, and other information, will be
useful for later project risk assessment. Even more revealing, the sources or
root causes of any potential slip (or other significant impact) are project risks
that belong on your risk list.
Schedule impact information can also be used for a simplified variation
on PERT that provides insight into schedule risk. This analysis uses the initial
activity estimates for both the optimistic and most likely PERT estimates,
which Parkinson’s Law, the quotation that opened this chapter, predicts
anyway. The worst-case information that you collect on any activity duration
provides data for your pessimistic estimates. The distribution this implies will
be essentially triangular and similar to what is shown in Figure 4-5. The
formula approximating the expected duration is te = (5tm + tp)/6.
Figure 4-5. PERT-Like Estimating
Although PERT techniques such as three-point estimating relate to
activity estimating, PERT analysis and more sophisticated simulation
techniques are really tools for project risk assessment. This use of PERT and
related tools is explored in detail in Chapters 7 and 9.
Activity Sequencing
Additional scheduling risks become visible as you develop your project
schedule by combining sequencing information with the activity estimates.
Activity sequencing requires you to determine the dependencies for each
project activity, and these linkages reveal many potential sources of project
delay. Delay and other dependency risks were responsible for most of the
scheduling risks in the PERIL database.
One effective method for minimizing schedule risk related to
sequencing is to break long, complex projects into a series of much shorter
ones. This principle is fundamental to agile (evolutionary, cyclic) software
development methodologies. If the cycles are sufficiently short—about four
weeks is a common cycle in methodologies such as Scrum—the
dependencies either become irrelevant or are sufficiently simple that
managing them is trivial. For the most part, Scrum ignores task dependencies
except as special cases within each sprint, or iteration cycle. The same
principle applies generally; the shorter the overall arc of a project is, the
fewer complications and risks there will be arising from activity
dependencies.
In more complex projects, many possible types of dependencies may
connect project activities, but most are linked by finish-to-start relationships
—once one activity or a collection of activities is complete, other project
activities can begin. Occasionally, some activities might need to be
synchronized by either starting or finishing at the same time, and the logic of
project work may also depend on interruptions and lags of various kinds.
Although project plans may include some of these more exotic dependencies,
the majority of the dependencies in a typical project network are finish-to-
start linkages, and it is these sequential-activity dependencies that are most
likely to cause work flow problems and delays.
Discovering risks arising from schedule dependencies requires all
project activities be linked both to predecessor and to successor activities.
Schedule development requires a logical network of project activities (and
milestones) that has no gaps. Establish a logical flow of work for your project
so that each project activity, without exception, has a continuous path
backward to your initial project milestone and a continuous path forward to
the final project deadline. Project analysis and risk identification will be
incomplete (and possibly worthless) if there are gaps or dangling
connections. For project planning using a computer tool, avoid the use of
features such as must-start-on and must-end-on pegged-date logic. The
software will generate a Gantt chart that looks a lot like a project plan, but
you will not be able to perform schedule analysis, do proper project tracking,
or effectively identify schedule risk.
Critical Path Methodology
Critical path methodology (CPM) analysis combines duration estimates
with dependency information to calculate the minimum project duration. For
larger projects, the analysis is best done using a computer scheduling tool.
Once all your activities, duration estimates, and dependencies are entered into
the database of a scheduling tool, the software automatically analyzes the
project network. The set (or sets) of activities that make up the longest
sequence is the project critical path, which is generally highlighted using an
appropriately scary red color. Each of the red activities carries schedule risk
because if it exceeds its duration estimate, everything that follows in the
project will also slip, including the project deadline.
CPM also calculates float, or slack, for noncritical activities, revealing
any flexibility available. If the float is small, even though a given activity
might be colored a soothing blue, it’s also risky. Even project activities that
have a large amount of float can be risky when their worst-case estimates
exceed the calculated float. The other noncritical activities, those with
significant float and reliable-looking estimates, are also relevant to risk
management. They may represent replanning opportunities for keeping your
project on track.
Computer scheduling tools make it is easy to do what-if analysis and
reveal risky activities in addition to those on the project critical path. The first
step is to make a copy of the database for the project (so you can manipulate
the copy to identify additional schedule risks and leave your initial schedule
intact). By deleting all the critical activities in your copy (relinking any
resulting broken dependencies as you go), you can see what the resulting
project looks like and generate a list of the next tier of risky activities to
watch out for.
It’s even more illuminating to replace all your initial estimates with
worst-case estimates to see what happens. When you do this one activity at a
time, you discover how sensitive the overall project is to each potential
problem. If you enter all of your worst-case estimates, you get a version of
the plan that shows a far longer schedule than is probable, but the end point
displays just how bad things might get should everything go wrong. (And
remember, your analysis is based only on known risks; if there are significant
unknown project risks, even your worst-case schedule may be optimistic.)
In reality, every activity in the project represents at least a low level of
schedule risk. Any piece of work in the plan could be the one that causes
your project to fail. CPM analysis is a useful technique for determining which
schedule risks belong on your risk list.
Multiple Critical Paths and Timing Uncertainty
Projects can and often do have more than one critical path. Multiple
critical paths further increase schedule risk. To see why, consider the simple
network in Figure 4-6. Both paths A-D-J and C-H-L are marked as critical,
and for this analysis we will assume “expected” durations where the
probability of an activity finishing early (or on time) is the same as the
chance of the activity finishing late. For a project with a single critical path,
the project as a whole has identical probabilities—50/50. (This assumes all
events and activities are independent—more on this later.) What can we say
about the project in Figure 4-6, with two critical paths?
Figure 4-6. Project with Two Critical Paths
The expectation for each path being on time or early is the same as for
the activities, 50 percent, but there are two paths. If the risks associated with
the two paths are independent, the matrix in Figure 4-7 shows the
probabilities for each possible outcome. The project has only one chance in
four of finishing early or on time because this requires both paths to be early
or on time, which is expected 25 percent of the time.
The situation gets worse with more than two critical paths. With three
critical paths, the chances fall to one in eight, and this fraction shrinks by a
factor of two with each additional critical path. The more potential failure
modes there are, the more likely it is that the project will be late. Although
this picture is bleak, most complex projects face even higher risk. Few
projects are planned using estimates that are equally likely to be slightly early
or slightly late. Aggressive estimates are common on modern projects for all
the reasons discussed earlier in the chapter, including optimism bias, lack of
experience, and political pressure. If the estimates are actually 10 percent
likely to be early or on time and 90 percent likely to be late, a matrix similar
to Figure 4-7 for two critical paths will calculate only a 1 percent chance of
success.
In addition, this analysis assumes statistical independence for all
events. Although the assumption of independence may be valid for some
project work, on most projects the work is all done by the same small team of
people, and much of the work is interrelated. Assuming that the outcome of a
given activity will have no effect on succeeding activities is unrealistic.
Project problems tend to cascade, and there is often significant positive
correlation between project activities. The upshot of all this is that schedule
risk and timing uncertainty increase significantly with multiple parallel
failure modes.
Figure 4-7. Result Matrix for a Project with Two Critical Paths
Scheduling Risky Work
The timing of activities may also increase project risk. Whenever an
activity has high uncertainty, it is human nature to schedule it to start late in
the project. If an activity requires the invention of something new or if the
specifics of the work are far from obvious, you may be tempted to defer the
work until later in the project, reasoning that the delay might give you a
chance to figure it out. Also, scheduling risky work toward the end of your
project will allow you to write at least a few weekly status reports that are not
filled with bad news about troubled activities.
Tempting though this is, it is a bad idea. Deferring riskier activities
until late in the project can lead to both increased project risk and cost. By
scheduling risky activities earlier, you can learn faster and frequently with
less effort, whether there are any showstoppers—activities that make your
whole project impossible. When you discover the problems earlier, project
decision makers have more options, including shifting the objective, using
the time still available to seek alternate ways to proceed with the project, or
even abandoning the work altogether. If a risky activity is deferred until late
in the project, changes may be impossible or much more costly, and there
will be little or no time left to seek another approach. Perhaps the worst case
of all is discovering that the project is not feasible and canceling it after
months (or even years) of effort have elapsed. When risky work is scheduled
earlier, a decision to cancel can be made after spending only a small portion
of the project budget instead of nearly all of it. In addition to being a waste of
time and money, late cancellation is demotivating for the project team and
will make it difficult to find enthusiastic staff for future projects.
Schedule Path Convergence
Another project risk is due to what is called fan-in. Most places in a
project network that have a large number of predecessor dependencies are
milestones, but any point of convergence in a project network represents
schedule risk. Because project work stops at a milestone or activity whenever
any of the preceding activities are incomplete, each additional path represents
an additional failure mode and increases the probability of delay. Milestones,
phase exits, stage gates, and other life cycle checkpoints are often delayed in
large programs because of a single missing requirement. Even when all the
other work is satisfactorily done, the project halts until the final predecessor
dependency is completed.
The largest fan-in exposure for many projects is the final milestone,
which usually has a large number of predecessor activities. Even in the
simple project network in Figure 4-6, there are three predecessor
dependencies for the finish milestone.
Interfaces
Dependency risks outside the project are also substantially represented
in the PERIL database. Dependencies of all kinds may represent schedule
risks, but interfaces—dependencies that connect one or more projects—are
particularly problematic; the impact of these risks was among the highest for
all schedule risks in the PERIL database, averaging almost eight weeks per
project. Connections between projects are most common for projects that are
part of a larger program. As each project team plans its work, dependencies
on other projects are discovered and must be planned and managed.
Dependencies that are wholly within a project carry schedule risk, but
interfaces are even riskier. For a schedule interconnection, each project
contains only half of the linkage, either the predecessor or the successor
activity. The deliverables can be components, services, information, software,
or almost anything that one project creates that is required as an input by
another project. The project that expects to receive the deliverable potentially
faces both schedule and scope risk. If the handoff is late, the dependent
project could slip. Even when it is on time, if the deliverable is not
acceptable, the project (and the whole program) may be in trouble. Interfaces
are particularly important to identify and manage because of the limited
visibility of progress across separately managed projects.
The process for managing these interfaces and the risks related to them
is best managed at the program level, and it is described in Chapter 13 in the
section on program risk management.
Interface management requires agreement and commitments in writing
between each involved project, and even then it’s risky. Add each interface
dependency for your project to your list of project risks.
Planning Horizon
Yet another source of schedule risk relates to project duration. When
you drive an automobile at night on a dark road with no illumination other
than your headlights, you can see only a limited distance ahead. The reach of
the headlights is several hundred meters, so you must stay alert and
frequently reexamine the road ahead to see things as they come into view.
Projects also have visibility constraints. Projects vary a good deal in
how much accurate planning is possible, but all project planning has a limit.
For some projects, planning even three months in advance is difficult. Agile
methods provide one method for dealing with highly volatile project
environments. For other projects, the planning horizon might be longer, but
project planning in general is rarely accurate more than six months or so into
the future. Uncertainty inherent in work planned too far in advance is a
source of significant schedule risk on any long-duration project. Make
specific note of any unusual, novel, or unstaffed activities more than three
months away. Regularly schedule explicit activities in the project plan to
review estimates, risks, assumptions, and other project data. Risk
management relies on periodic recommendations for project plan adjustments
based on the results of these reviews.
Project reviews are most useful at natural project transitions. The most
common of these are major project milestones, such as at the end of a life
cycle phase, a development iteration, a stage gate, or a checkpoint. It is also
useful to conduct a review after any significant change to the project
objective, whenever key contributors leave or are added to the project team,
or following business reorganizations. At a minimum, schedule reviews for
longer projects at least every three to six months. A process for project
review is detailed in Chapter 11.
Documenting the Risks
Schedule risks become visible throughout the planning and scheduling
processes. The specific instances discussed in this chapter are all project
risks:
• Long-duration activities
• Significant worst-case (or pessimistic PERT) estimates
• High uncertainty estimates
• Overly optimistic estimates
• All critical path (and near critical path) activities
• Multiple critical paths
• Convergence points in the logical network
• External dependencies and interfaces
• Deadlines beyond the planning horizon
• Cross-functional and subcontracted work
Augment the list of project scope risks, adding each schedule risk
identified with a clear description of the risk situation. The list of risks
continues to expand throughout the project planning process and serves as the
foundation for project risk analysis and management.
Key Ideas for Identifying Schedule Risks
• Determine the root causes of all uncertain estimates.
• Identify all estimates not based on historical data.
• Note dependencies that pose delay risks, including all
interfaces.
• Identify risky activities and schedule them early in the project.
• Ascertain risks associated with multiple critical (or near critical)
paths.
• Recognize the riskiest dependencies at fan-in points in the
project schedule.
• Note risks associated with lengthy projects.
Panama Canal: Planning (1905–1907)
Early in his work in Panama, John Stevens spent virtually all his time
among the workers, asking questions. His single-minded pursuit was
thorough project planning. Stevens put all he learned into his plans,
establishing the foundation he required to get the project moving forward.
The primary tool for construction was one Stevens was familiar with:
the railroad. He recognized that digging enormous trenches was only part of
the job. Excavated soil had to be moved out of the cut in central Panama
where someday ships would pass, and it had to be deposited near the coasts to
construct the required massive earthen dams. In the rain forests of Panama at
the turn of the twentieth century, the railroad was not only the best way to do
this, it was the only practical way. Much of the planning that Stevens did
centered on using the railroad as a tool, and by early in 1906, he had
documented exactly how this was to be done. When excavation resumed, his
elaborate, “ingeniously elastic” use of the railroad enabled progress at a
vigorous pace, and it continued virtually nonstop until the work was
complete.
Once Stevens had broken the work down into smaller, easily
understood activities, the canal project began to look possible. Each part of
the job was now understood to be something that had been done, somewhere,
before. It became a matter of getting it all done, one activity at a time.
For all his talents and capabilities, John Stevens never considered
himself fully qualified to manage the entire project. His experience was with
surveying and building railroads. The canal project involved construction of
massive concrete locks (like enormous bathtubs with doors on each end) that
would raise ships nearly 30 meters from sea level and lower them back again
—12 structures in all. The project also required a great deal of knowledge of
hydraulics; moving enormous amounts of water quickly was essential to
efficient canal operation. Stevens had no experience with either of these types
of engineering. These gaps in his background, coupled with his dislike of the
hot, humid climate and the omnipresent (and still dangerous) insects, led him
to resign as chief engineer after two years, in 1907.
This did not sit well with Theodore Roosevelt. Losing such a
competent project leader was a huge risk to the schedule. Both of his project
leaders had now resigned before completing his most important project, and
Roosevelt was determined that this would not happen again. To replace John
Stevens, Roosevelt chose George Washington Goethals, an immensely
qualified engineer. Goethals had been seriously considered for the job twice
previously and was ideally qualified to complete the Panama Canal. He had
built a number of similar, smaller projects, and he had a great deal of
experience with nearly all the work required at Panama.
Theodore Roosevelt wanted more than competence, however. For this
project, he wanted “men who will stay on the job until I get tired of having
them there, or until I say they may abandon it.” He was safe in his choice of a
new chief engineer and project leader: George Goethals was a major (soon to
be lieutenant colonel) in the U.S. Army Corps of Engineers, and if he tried to
resign, he could be court-martialed and sent to jail.
Chapter
5
Identifying Project Resource Risk
If you want a track team to win the high jump,
you find one person who can jump seven feet,
not several people who can jump six feet.
—FREDERICK TERMAN,
STANFORD UNIVERSITY DEAN AND PROFESSOR OF ENGINEERING
Fred Terman is probably best known as the father of Silicon Valley. He
encouraged Bill Hewlett and Dave Packard, the Varian brothers, and
hundreds of others to start businesses near Stanford University, just south of
San Francisco. Starting in the 1930s, alarmed at the paucity of job
opportunities in the area, he helped his students start companies, set up the
Stanford Industrial Park, and generally was responsible for the establishment
of the world’s largest high-tech center. He was good at identifying and
nurturing technical talent, and he understood how critical it is in any
undertaking.
A lack of technical skills or access to appropriate staff is a large source
of project risk for complex projects. Risk management on these projects
requires careful assessment of the skills needed and the commitment of
capable staff.
Sources of Resource Risk
Resource risks are the next most numerous and damaging after scope
risks. They represent a bit more than 30 percent of the records in the PERIL
database. Resource risks represent more than a quarter of the overall impact
in the PERIL database, and they had an average impact of over six weeks,
about the same as schedule risks. There are three categories of resource risk:
people, outsourcing, and money. People risks arise within the project team.
Outsourcing risks are a consequence of using people and services outside the
project team for critical project work. The third category, money, is the rarest
risk subcategory for the PERIL database, as few of the problems reported
were primarily about funding. Money, however, has the highest average
impact and the effect of insufficient project funding has substantial impact on
projects in many other ways. The root causes of people and outsourcing risk
are further characterized by type, shown in the following summary:
A Pareto chart of overall impact by type of risk is in Figure 5-1.
Although risks related to internal staffing dominate the listed resource risk
subcategories, both outsourcing and money risks are included in the top three.
People Risks
Risks related to people represent the most numerous resource risks,
constituting nearly 20 percent of the entire database and over half of the
resource category. People risks are subdivided into five subcategories:
Figure 5-1. Total Project Impact by Resource Root Cause
Subcategories
1. Loss: Permanent staff member loss to the project due to resignation,
promotion, reassignment, health, or other reasons
2. Temporary loss: Short-term staff loss due to illness, hot site, support
priorities, or other reasons
3. Queuing: Slip due to other commitments for needed resources or
expertise
4. Late start: Staff not available at project start; often because of the
late finish of previous projects
5. Motivation: Loss of team cohesion and interest, typical of long
projects
Loss of staff permanently had by far the highest overall category
impact, and an average slip of seven weeks. Permanent staff loss represented
about one-third of the people risks. The reasons for permanent staff loss
included resignations, promotions, reassignments to other work or different
projects, and staffing cutbacks. Discovering these risks in advance is difficult,
but good record keeping and trend analysis are useful in setting realistic
project expectations.
Temporary loss of project staff was the next most common people-
related risk, with roughly another quarter of the total. Its overall impact was
lower than for permanent staff loss, causing an average slip of just under four
weeks. A typical reason for short-term staff loss was a customer problem (a
so-called hot site) related to the deliverable from an earlier project. Other
reasons for short-term staff loss included illness, travel problems, and
organizational reorganizations.
Queuing problems represented about another quarter of the people-
related risks in the PERIL database. The average schedule impact due to
queuing was four weeks. Most organizations optimize operations by
investing the bare minimum in specialized (and expensive) expertise, and in
costly facilities and equipment. This leads to a potential scarcity of these
individuals or facilities and to contention for access between projects. Most
projects rely on at least some special expertise that is shared with other
projects, such as system architects needed at the start, testing personnel
needed at the end, and other specialists needed throughout the project. If an
expert happens to be free when a project is ready for the work to start, there is
no problem, but if he or she has five other projects queued up already when
your project needs attention, you will come to a screeching halt while you
wait in line. Queuing analysis is well understood, and it is relevant to a wide
variety of manufacturing, engineering, computer networks, and many other
business systems. Any system subject to queues requires some excess
capacity to maximize throughput. Optimizing organizational resources
needed for projects based only on cost drives out necessary capacity and
results in project delay.
Late starts when key staff are unavailable at the beginning of a project
also caused a good deal of project delay. Although only about 10 percent of
the people-related resource risks, their average impact was well over six
weeks. Staff joining the project late had a number of root causes, but the most
common was a situation aptly described by one project leader as the rolling
sledgehammer. Whenever a prior project is late, some, perhaps even all, of
the staff for the new project are still busy working to get it done. As a
consequence, any following project gets a slow and ragged start, with key
people beginning their contributions to the new project only when they can
break free of the earlier one. Even when these people become available, there
may be additional delay because the staff members coming from a late
project are often burned out from the stress and long hours typical of an
overdue project. The rolling sledgehammer creates a cycle that self-
perpetuates and is hard to break. Each late project causes the projects that
follow also to be late.
Motivation issues were the smallest subcategory, at only a bit more
than 5 percent of the people-related resource risks. However, these risks had
an average impact in excess of nine weeks, among the highest for any of the
subcategories in the PERIL database. Motivation issues are generally a
consequence of diminishing interest on long-duration projects or of
interpersonal conflicts.
Thorough planning and credible scheduling of the work well in
advance will reveal some of the most serious potential exposures regarding
people. Histogram analysis of resource requirements may also provide insight
into staffing exposures that a project will face, but unless analysis of project
resources is credibly integrated with comprehensive resource data for other
projects and all the nonproject demands within the business, the results may
not provide sufficient insight. Aligning staffing capacity with project
requirements requires ongoing attention. One significant root cause for
understaffed projects is little or no use of project planning information to
make or revise project selection decisions at the organizational level,
triggering the too-many-projects problem. (Managing such portfolio risks is
explored in Chapter 13.) Retrospective analysis of projects over time is also
an effective way to detect and measure the consequences of inadequate
staffing, especially for chronic problems.
Outsourcing Risks
Outsourcing risks account for nearly one-third of the resource risks.
Although the frequency in the PERIL database is lower than for people risks,
the impact of outsourcing risk was higher, in excess of six weeks. Risks
related to outsourcing are separated into two subcategories: late or poor
outputs and delayed start.
Late or poor output from outsource partners is a problem that is well
represented in the PERIL database. The growth of outsourcing in the recent
past has been driven primarily by a desire to save money, and often it does.
There is a trade-off, though, between this and predictability. Work done at a
distance is out of sight, and problems that might easily be detected with
efforts within the organization may not surface as an issue until it is too late.
More than 80 percent of the outsourcing risks involved receiving a late or
unsatisfactory deliverable from an external supplier, and the average impact
for these incidents was well over six weeks. These delays result from many
of the same root causes as other people risks—turnover, queuing problems,
staff availability, and other issues—but a precise cause may not be known.
Receiving anything the project needs late is a risk, but these cases are
compounded by the added element of surprise; the problem may be invisible
until the day of the default (after weeks of reports saying, “Things are going
just fine . . .”), when it is too late to do much about it. Lateness was often
exacerbated in cases in the PERIL database because work that did not meet
specifications caused further delay while the work was redone correctly by
the project team.
Delayed starts are also fairly common with outsourced work, causing
about a fifth of the outsourcing problems. Before any external work can
begin, contracts must be negotiated, approved, and signed. All these steps are
time-consuming. Beginning a new, complex relationship with people outside
your organization can require more time than expected. For projects with
particularly unusual needs, just finding an appropriate supplier may cause
significant delays. The average impact from these delayed starts in the
database was just over five weeks.
Outsourcing risks can be detected through planning processes, and by
careful analysis and thorough understanding of all contract terms. Both the
project team and the outsourcing partner must understand the terms and
conditions of the contract, especially the scope of work and timing
requirements.
Money Risks
The third category of resource risks was rare in the PERIL database,
representing a little more than 10 percent of the resource risks and roughly 4
percent of the whole. It is significant, however, because when funding is a
problem, it is often a big problem. The average impact was the highest for
any subcategory, at well over ten weeks. Insufficient funding can
significantly stretch out the duration of a project, and it is a contributing root
cause in many other subcategories (people turnover due to layoffs and
outsourcing of work primarily motivated by cost cutting, as examples).
Black Swans
In this book we have been referring to the worst 20 percent of the risks
in the PERIL database as black swans. These “large-impact, hard-to-predict,
rare events” caused at least three months of schedule slip, and 53 of these
most damaging 206 risks, a bit more than a quarter, were resource risks. As
with the black swans as a whole, the most severe of the resource risks
account for about half of the total measured impact. The details are given in
the table on the next page.
As can be seen in the table, the black swan resource risks were
distributed unevenly. The motivation and money categories represent a much
higher portion of the total, with several categories near the average of 50
percent, and several of the people-related risk categories much lower.
Not surprisingly, money issues were a substantial portion of the black
swan resource risks. Fifteen cases, almost a third of the risks reported in this
category, were in this group. Nearly all involved either underfunded projects
or severe cutbacks in budgets, including such situations as:
• Subject-matter experts were let go to save money.
• Due to a layoff, no writer was immediately available, so approval was
delayed.
• Project was cut back, delayed fixes cost a lot of money, and needed
resources were assigned to other work.
• Project budget was restricted to the bare minimum estimated.
• There were large funding cutbacks (66 percent of project team).
There were also 17 outsourcing black swan risks. Sixteen were due to
late or poor output, with these among them:
• A key supplier was purchased by another company and reorganized.
Project was forced to find a new supplier.
• Research and development were outsourced, but the relationship was
not managed well, and all work ultimately had to be redone.
• Contract manufacturer failed to deliver on time.
• Changes were agreed to, but the supplier shipped late and
deliverables did not work.
• Components were delayed, and contractors were committed to other
work and were able to work only part time.
There was also a black swan outsourcing risk due to a delayed start
when settling the terms of the agreement and negotiating the contracts took
months, causing the project to begin late.
There were 21 additional black swan people risks. This category had
the largest total number of these severe risks, but it also represented a smaller
proportion of the impact.
Permanent staff loss also caused a lot of pain and led the list of black
swan people risks with nine. Here are a few examples:
• Expert medical specialist was no longer available.
• Product owner having unique knowledge left the company.
• Manager quit his job because of his mother’s illness.
Although the four black swan risks associated with motivation were
less than half of all the motivation risks, they accounted for nearly three-
quarters of the impact from this subcategory. These risks were:
• Management mandated the project but never got team buy-in.
• Programmers were volunteers, and ultimately all of them quit.
• Staff got along poorly and frequently quarreled.
• The product manager disliked the project manager.
There were also three black swan project risks due to queuing, causing
projects to be slowed by a lack of access to specific resources, for example:
• Key decisions were stalled when no system architect was available.
• Several projects shared only one subject-matter expert.
There were three more major people risks caused by late staffing
availability. All were due to people who were trapped on a delayed prior
project.
Temporary loss of people caused only two black swan risks. Most
temporary staff loss situations in the PERIL database were resolved in a lot
less than three months.
You will find additional examples of resource risks listed in the
Appendix.
Resource Planning
Resource planning is a useful tool for anticipating many of the people,
outsourcing, and money risks. Inputs to the resource planning process include
the project work breakdown structure (WBS), scope definition, activity
descriptions, duration estimates, and the project schedule. Resource
requirements planning can be done in a number of ways, using manual
methods, histogram analysis, or computer tools.
Resource Requirements
Based on the preliminary schedule and assumptions about each project
activity, you will need to determine the skills and staffing required for each
activity. It is increasingly common, even for relatively small projects, to use a
computer scheduling tool for this. For all project work, identify staff by
name. Although preliminary resource planning can start using functions or
roles, effort estimates done without staffing information are imprecise, and
there is significant resource risk until the project staff is named and
committed. Identify as a risk any work depending on staff members who
cannot be named during project planning.
For the project as a whole, also identify all holidays, scheduled time
off, significant nonproject meetings, and other time that will not be available
to the project. Do this for each person as well, and identify any scheduling
differences for different regions, countries, and companies involved in the
project. A computer scheduling tool is a good place to store calendar
information, such as holidays, vacations, and any other important dates. If
you do use a computer tool, enter all the calendar data into the database
before you begin resource analysis.
You also need to determine the amount of effort available from each
contributor. Even for full-time contributors, it is difficult to get more than
five to six hours of project activity work per day, and part-time staff will
contribute much less.
Particularly for project activities that are already identified as potential
risks, such as those on the critical path, determine the total effort required and
verify who will do the necessary work. Knowing the resources your project
will need and how this compares with what is available is central to
identifying and managing project risk.
Whether you do this analysis manually by inspection of the project
plans, through a tabular or spreadsheet approach, or by using resource
analysis functionality in project management software, your goal will be to
detect resource shortfalls that could hurt your project. Work to uncover any
resource over- and undercommitments. Even if you use a computer tool—and
there are many—remember that a scheduling tool is primarily a database with
specialized output reports. The quality of the information the tool provides
can never be any better than the quality of the data that you put in. You and
the project team must still do the thinking; a computer cannot plan your
project or identify its risks.
Histogram Analysis Using Computer Tools
For more complicated projects, graphical resource analysis is useful.
Resource histograms can be used to show graphically where project staffing
is inadequate on an individual-by-individual or an overall project basis. The
graphical format provides a visible way to identify places in the preliminary
schedule where project staffing fails to support the planned workflow, as
shown in Figure 5-2. In this case, the effort profile for a project team member
expected to contribute to all these activities shows that this person must work
a double shift where the activities overlap.
Figure 5-2. Histogram Analysis for an Individual
The benefits of entering resource data into a computer scheduling tool
include:
• Identifying resource overcommitment risks
• Improving the precision of the schedule
• Building compelling evidence for negotiating budgets and schedules
• Focusing more attention on project estimates
These benefits require some investment on your part. Histogram
analysis adds complexity to the planning process, and it increases the effort
for both planning and tracking. In your resource analysis, allocate sufficient
time for this in your overall project workload.
Be particularly wary of assumptions that contribute to project risk, such
as the dependability of committed start dates for project contributors. Both
late starts and queuing delays were significant sources of risk in the PERIL
database.
Resource shortfalls are not limited to staffing. Early in your project,
assess your project infrastructure: the equipment, software, and any other
project assets. If required computers, software applications, test gear,
instruments, communications and networking equipment, or other available
hardware elements are not adequate or up-to-date, plan to replace, upgrade, or
augment them. The effort and money to do this tend to be easiest to obtain
during the planning and start-up phases of a new project. Also, getting
familiar with new hardware and software is less disruptive early than it will
be in the middle of the project, when it could disrupt high-priority project
activities.
Staff Acquisition
Histograms and other project analysis are necessary but rarely
sufficient to determine whether the project has the staffing and skills required
to do the work. Particularly for the riskiest project activities, revalidate both
the skills needed and your effort estimates.
Skill Requirements
Through project scope definition and preliminary planning, identify
specific skills and other needs required by your project. Your initial project
staffing will often include adequate coverage for some or even most of these,
but on many projects there are substantial gaps. These gaps will remain
project resource risks until they can be resolved.
Specific skills that are not available on the project team might be
acquired by negotiating for additional staff or through training or mentoring.
In some cases, the needed skills can be added through outsourcing. These
options are most possible when the need is made known early and supported
with credible planning data. You may also be able to replan the parts of the
project that require unavailable skills to use other methods that require only
skills already available on the project team. If there are knowledge gaps that
can be filled through training, schedule the training early in the project.
Postponing training until just before you need it increases two risks: that the
time or money required for it will no longer be available and that the ramp-up
time to competence may exceed what you planned. (Learning curve issues
were a major source of schedule risk in the PERIL database.) Building new
skills can also be a powerful motivator and team builder—both of which can
reduce risk for any project.
The ultimate goal of staff acquisition is to ensure that all project
activities are aligned with specific individuals who are competent and can be
counted on to get the work done. Two significant resource risks related to
staff acquisition are unnamed staff members and contributors with unique
skills. Every identified staffing need on your project roster that remains
blank, identified only with a function or marked “to be hired,” is a risk. Even
if these people are later named, their productivity may not be consistent with
your estimates and assumptions. It is also possible that the names will still be
missing even after work is scheduled to begin—and some staffing
requirements may never be filled. Plans based on unassigned staffing are
unreliable, and every project staffing requirement that lacks a credible
commitment by an actual person is a project risk.
Unique skills also pose a problem. When project work can be assigned
to one of several competent contributors, there is a good chance that it will be
done adequately and on schedule. When only a single person knows how to
do the work, the project faces risk. A necessary person may not be available
to the project when needed for many reasons, including illness, resignation,
injury, or reassignment to other higher-priority work. There are no
alternatives for the project when this happens; work on a key part of the
project will halt. Whenever a key part of your project depends on access to a
single specific individual, note it as a risk.
Revisiting Estimates
As noted in Chapter 4, resource planning and activity estimating are
interrelated. As the staffing plan for the project comes together, additional
resource risks become apparent through a review of the assumptions you used
for estimating. Project resource risks are usually the most severe for activities
that are most likely to impact the project schedule—activities that are on the
critical path, or have little float, or have worst-case estimates that could put
them on the critical path. Reviewing the effort estimates for these and other
project activities reveals resource risks related to staff ability, staff
availability, and the project environment.
Staff ability. Individual productivity varies a great deal, so it matters
who will be involved with each project activity. Even for very simple tasks,
there can be very great differences in performance. Cooks often encounter the
requirement for “one onion, chopped.” The amount of time this task will take
depends greatly on the person undertaking it. For a home cook, it might take
two or three minutes (assuming that the majority of the chopping is restricted
to the onion). A trained professional chef, as watchers of television cooking
shows know, dispatches this task in seconds. On the other extreme one finds
the perfectionist, who could make an evening out of ensuring that each
fragment of onion is identical in size and shape.
Productivity measurements for “knowledge” work of most kinds show
a similar wide spectrum. Research on productivity shows that people who are
among the best at what they do typically work two to three times as fast as
the average, and they are more than ten times as productive as the slowest. In
addition to being faster, the best performers also make fewer errors and do
much less rework.
Differences due to variations in productivity are frequently a source of
inaccurate project estimates. Project leaders often plan the project using data
from their own experience, and then delegate the work to others who may not
be as skilled or as fast as they are (or think they are). When there are
historical metrics that draw on a large population, you can accurately predict
how fast an average person will be able to accomplish similar work. If your
project contributors are significantly more (or less) productive than the
average, your effort and duration estimates will be accurate only if they are
adjusted accordingly. When you do not know who will be involved in the
work, risks can be significant.
Staff availability. No one can ever actually work on project activities
full time. Even within the project, every project contributor has commitments
that are above and beyond the scheduled project work, for example
communication activities. Further, some team members will inevitably be
responsible for significant work outside the project. Studying computer and
medical electronics firms, Wheelwright and Clark (in Revolutionizing
Product Development) reported the effect of assigning work on parallel
projects to engineers. For engineers assigned to a single project or two
projects, about 70 percent of the time spent went into project activities,
roughly equivalent to the often quoted five or six hours of project work per
day. With three and more projects, useful time plummets precipitously. An
engineer with five projects deals with so much overhead that only 30 percent
of the time remains for project activities. Not all projects are equal, so when
you are faced with this situation, find out how your overcommitted
contributors prioritize their activities. Ask each part-time contributor about
both the importance and the urgency of the work on your project. Both
matter, but it’s a lack of urgency that will hurt your project the most. When
contributors see your project’s work as low priority, it is a risk. If you are
unable to adjust the attitude, you may even need to consider alternative
resources or other methods to do the project work.
The too-many-projects problem takes a heavy toll on project progress,
and estimates of duration or effort that fail to account for the impact of
competing priorities can be absurdly optimistic.
Project environment. The project environment is yet another factor
that has an impact on the quality of project estimates. Noise, interruptions,
the workspace, and other factors may erode productivity significantly. When
people can work undistracted, a lot gets done.
This is not typical, though. Frequent disturbances are commonplace,
particularly with work done in an open-office environment. The background
noise level, nearby conversations, colleagues who drop by to chat, and other
interruptions are actually much more disruptive than generally assumed in
project estimates. People can’t shift from one activity to a different one
instantaneously. Studies of knowledge workers indicate that it takes 20
minutes, typically, for the human brain to come back to full concentration
following an interruption as short as a few seconds. A contributor who gets
several telephone calls, a few tweets, or quick questions from a peer every
hour cannot accomplish much.
Once the staffing for your project is set, consider all these factors,
particularly the talent, proportion of time dedicated to your project, and the
effect of the environment on the estimates in your project plan. Make
adjustments as necessary, identify the resource risks, and add them to your
project risk list.
Outsourcing
Outsourcing was a significant source of resource risk in the PERIL
database, causing an average project slip of nearly seven weeks. Better
management of outsourcing and procurement can uncover many of these
problems in advance. (The focus of this section is, consistent with the
PMBOK® Guide, from the perspective of the project leader who acquires
services using procurement processes. Risks associated with managing fee-
for-service projects on a contract basis largely parallel those for projects in
general.)
Not all project staffing needs can be met with internal people. More
and more work on modern projects is done using outside services. It is
increasingly difficult (and expensive) to maintain competence in all the fields
of expertise that might be required, especially for skills needed only
infrequently. A growing need for specialization underlies the trend toward
increased dependence on project contributors outside the organization. Other
reasons for this trend are attempts to lower costs and a desire in many
organizations to reduce the amount of permanent staff.
Procurement Process
In the PMBOK® Guide, “Project Procurement Management” has four
components:
1. Plan procurements
2. Conduct procurements
3. Control procurements
4. Close procurements
The first two of these provide significant opportunities for risk
identification. Outsourcing project work is most successful when appropriate
legal and other documentation is detailed and incorporated into project
planning. The risks of outsourced work can be minimized by clearly defining
responsibilities, requirements, and evaluation criteria, both in the initial
request and in the ultimate contract. Doing this effectively can be difficult,
and it generally takes more effort and specificity than might ordinarily be
applied to project planning.
Specific risks permeate all aspects of the procurement process, starting
before any work directly related to outsourcing formally starts. The process
generally begins with the identification of any requirements that the project
expects to have difficulty meeting with the existing staff. Procurement
planning involves investigation of possible options and requires a make-or-
buy analysis to determine whether there are any reasons why using outside
services may be undesirable or inappropriate. From the perspective of project
risk, delegating work to dedicated staff whenever possible is almost always
preferable. Communication, visibility, continuity, motivation, and project
control are all easier and better for in-house work. Other reasons to avoid
outsourcing may include higher costs, potential loss of confidential
information, an ongoing significant need to maintain core skills (on future
projects or for required support), and lack of confidence in the available
service providers. Some outsourcing decisions are made because all the
current staff is busy and no one is available to do necessary project work.
These decisions seem to be based on the erroneous assumption that project
outsourcing can be done successfully with no effort. Ignoring the substantial
effort required to find, evaluate, negotiate and contract with, routinely
communicate with, monitor, and pay a supplier is a serious risk.
Even though it may be desirable to avoid outsourcing, project realities
may require it. Whenever the make-or-buy decision comes out buy, there will
be risks to manage.
The next step in the outsourcing process is to develop a request for
proposal (RFP), also known as request for bid, invitation to bid, and request
for quotation. In organizations that regularly outsource project work, there are
usually standard forms and procedures to be used, so the steps in assembling,
distributing, and later analyzing the RFP responses are generally not up to the
project team. This is fortunate because using well-established processes,
preprinted forms, and professionals in your organization who do this work
regularly are all essential to minimizing risk. If you lack templates and
processes for this, consult colleagues who are experienced with outsourcing
and borrow theirs, customizing as necessary. Outsourcing is one aspect of
project management where figuring things out as you proceed will waste a lot
of time and money and result in significant project risk.
Risk management also requires that at least one member of the project
team be involved with planning and contracting for outside services, so that
the interests of the project are represented throughout the procurement
process.
Ensure that each RFP includes a clear, unambiguous definition of the
scope of work involved, including the terms and conditions for evaluation
and payment. Although it is always risky for any project work to remain
poorly defined, outsourced work deserves particular attention. Inadequate
definition of outsourced work leads to all the usual project problems, but it
may result in even more schedule and resource risk. Problems with
outsourced deliverables often surface late in the project with no advance
warning (generally, following a long series of “we are doing just fine” status
reports) and frequently will delay the project deadline, This outcome was
evident in the PERIL database, where delivery of a late or inadequate
deliverable led to more than a month and a half of average project slippage.
There can also be significant increased cost due to required changes and late-
project expedited work. Minimize outsourcing risks through the scrupulous
definition of all deliverables involved, including all measurements and
performance criteria you will use for their evaluation.
As part of procurement planning, establish the criteria that you will use
to evaluate each response. Determine what is most important to your project,
and ensure that these aspects are clearly spelled out in the RFP, with
guidance for the responders on how to supply the required information.
Because the specific work on modern projects tends to evolve and change
quickly, there is a good chance that well-established criteria for selecting
suppliers will, sooner or later, be out-of-date. In light of your emerging
planning data for the project, review the proposed criteria to validate that they
are still appropriate. If the list of criteria used in the past seems in need of
updating, do it before sending out the RFP. Establish priorities and relative
weights for each evaluation criterion, as well as how you will assess the
responses you receive. Communicating your priorities and expectations
clearly in the RFP will help responders to self-qualify (or self-disqualify)
themselves and will better provide the data you need to make a sound
outsourcing decision.
Relevant experience is also important in avoiding outsourcing risk. In
the RFP, request specifics from responders on similar prior efforts that were
successful, and ask for contact information so that you can follow up and
verify. Even for work that is novel, ask for reference information from
potential suppliers that will at least allow you to investigate past working
relationships. Although it may be difficult to get useful reference information,
it is always prudent to request it.
Once you have established the specifics of the work to be outsourced,
as well as the processes and documents you plan to use, the next step is to
find potential suppliers and encourage them to respond. One of the biggest
risks in this step is failure to contact enough suppliers. For some project
work, networking and informal communications may be sufficient, but
sending the RFP to lists of known suppliers, putting information on public
Web sites, and even advertising may be useful in letting potential responders
know of your needs. If too few responses are generated, the quality and cost
of the choices available may not serve the project well.
Bringing the RFP process to closure is also a substantial source of risk.
There are potential risks in decision making, negotiation, and the contracting
process.
Decision-making risks include not doing adequate analysis to assess
each potential supplier and making a selection based on something other than
the needs of the project.
Inadequate analysis can be a significant source of risk. It is fairly
common for the decisions on outsourcing to coincide with many other project
activities, and writing and getting responses to an RFP often takes more time
than anticipated. As a result, you may be left with little time to evaluate the
proposals on their technical merit. Judging proposals by weight, appearance,
or some other superficial criteria may save time but is not likely to result in
the best selection. Thoroughly evaluating and comparing multiple complex
proposals takes time and effort. Before you make a decision, spend the time
necessary to ensure a thorough evaluation. It’s like the old saying, “Act in
haste; repent at leisure”—except in your case you will be repenting when you
are very busy.
Another potential risk in the selection process is pressure from outside
your project to make a choice for reasons unrelated to your project.
Influences from other parts of the organization may come to bear during the
decision process—to favor friends, to avoid some suppliers, to align with
strategic partners of some other internal group, or to use a global (or a local)
supplier. Because the decision will normally be signed and approved by
someone higher in the organization, sometimes the project team may not
even be aware of these factors until late in the process. Documenting the
process and validating your criteria for supplier selection with your
management can reduce this problem, but the use of outside suppliers not
selected by the project team represents significant and sometimes disastrous
project risk.
Overall, you must diligently stay on top of the process to ensure that
the selections made for each RFP are as consistent with your project
requirements as possible.
After selecting a supplier, the next step is negotiating to finalize the
details of the work and finances. After a selection is made, the balance of
power begins to shift from the purchaser to the supplier, raising additional
risks. Once the work begins, the project will be dependent on the supplier for
crucial, time-sensitive project deliverables. The supplier is primarily
dependent on the project for money, which in the short run is neither crucial
nor urgent. To a lesser extent, suppliers are also dependent on future
recommendations from you (which can provide leverage for ongoing risk
management), but from the supplier’s perspective, the relationship is mainly
based on cash.
Effective and thorough negotiation is the last opportunity for the
project to identify (and manage) risks without high potential costs. All
relevant details of the work and deliverables need to be discussed and clearly
understood, so the ultimate contract will unambiguously contain a scope of
work that both parties see the same way. Details concerning tests,
inspections, prototypes, and other interim deliverables must also be clarified.
Specifics concerning partial and final payments, as well as the process and
cost for any required changes or modifications, are also essential aspects of
the negotiation process. Failure to conduct thorough, principled negotiation
with a future supplier is a potential source of massive risk. Shortening a
negotiation process to save time is never a good idea.
Because the primary consideration on the supplier side is financial, the
best tactic for risk management in negotiation is to strongly align payments
with the achievement of specific results. Payment for time, effort, or other
less tangible criteria may allow suppliers to bill the project even while failing
to produce what your project requires. When negotiating the work and
payment terms, the least risky option for you as the purchaser is to establish a
payment-for-result contract.
Outsourcing risk can also be lowered by negotiating contract terms that
align with specific project goals. Although a contract must include
consequences for supplier nonperformance, such as nonpayment, legal action,
or other remedies, these terms do little to ensure project success. Whenever a
supplier fails to perform, your project will still be in trouble. Lack of a key
deliverable will lead to project failure, so it is also useful to negotiate terms
that more directly support your project objectives. If there is value in getting
work done early, incentive payments are worth considering. If specific
additional costs are associated with late delivery, establish penalties that
reduce payments proportionate to the delay. For some projects, more
complex financial arrangements than the simple fee-for-result may be
appropriate, applying percentages of favorable variances in time or cost that
will benefit the supplier and portions of unfavorable ones that will reduce
their fees. Negotiating terms that more directly support the project objectives
and involve suppliers more deeply in the project may significantly reduce
outsourcing risks.
If, despite your best efforts, the negotiation process results in terms that
represent potential project problems, note these as risks. In extreme cases,
you may want to reconsider your selection decision or even the decision to
outsource the project work at all.
Once you have consensus on the terms and conditions for the work,
you must finalize the contract. All agreed-upon terms must be documented in
a signed contract and put into force. One effective way to minimize risk is to
use a well-established, preprinted contract format to document the
relationship. This should include all of the information that a complete,
prudent contract must contain, so that the chances of leaving out something
critical, such as protection of confidential information or proprietary
intellectual property, will be reduced. For this reason, you can reduce project
risk by using a standard contract form with no significant modifications or
deletions. In addition, using standard formats will reduce the time and effort
needed for contract approval. In large companies, contracts varying from the
standard may take an additional month (or even more) for review, approval,
and processing. Adding data to a contract is also generally a poor idea, with
one big exception. Every contract needs to include a clear, unambiguous
definition of the scope of work that specifies measurable deliverables and
payment terms. A good contract also provides an explicit description of the
process to be used if any changes are necessary.
One other source of risk in contracting is also fairly common for
today’s projects. The statement of work must be clear not only in defining the
results expected but also in specifying who will be responsible. It turns out
that this is quite a challenge for engineers and other analytical people. Most
engineering and other technical writing is filled with passive-voice sentences,
such as, “It is important that the device be tested using an input voltage
varying between 105 and 250 volts AC, down to a temperature of minus 40
degrees Celsius.” In a contract, there is no place for the passive voice. If the
responsible party is not clearly specified, the sentence has no legal meaning.
It fails to make clear who will do the testing and what, if any, consequences
there may be, should the testing fail. To minimize risks in contracts, write
requirements in the active voice, spelling out all responsibilities in clear terms
and by name.
Finally, when setting up a contract, minimize the resource risk by
establishing a not-to-exceed limitation to avoid runaway costs. Set this limit
somewhat higher than the expected cost in order to provide some reserve for
changes and unforeseen problems, but not a great deal higher. Many complex
projects provide a reserve of about 10 percent to handle small adjustments. If
problems or changes arise that require more than this, they will trigger review
of the project, which is prudent risk management.
Procurement Risks
A variety of other risks arise from outsourcing. One of the largest is
unanticipated cost, even if the work seems to be thoroughly defined.
Unforeseen aspects of the work, which are never possible to eliminate
completely, may trigger expensive change fees.
Continuity and turnover of contract staff are also risks. Although
people who work for another company may be loyal to your project and stay
with it through to the end, the probabilities are lower than for the permanent
staff on your project. Particularly with longer projects, turnover and
retraining can represent major risks.
Outsourcing may also increase the likelihood of turnover and
demotivation of your permanent staff. If it becomes standard procedure to
outsource all the new, bleeding-edge project work, your permanent staff gets
stuck doing the same old things, project after project, never learning anything
new. It becomes harder to motivate and hold onto people who have no
opportunity for personal development.
There may also be hidden effort for the project due to outsourcing, not
visible in the plan. Someone must maintain the relationship, communicate
regularly, deal with payments and other paperwork, and carry the other
overhead of outsourcing. Although this may all run smoothly, if there are any
problems it can become a major time sink. The time and effort this overhead
requires are routinely overlooked or underestimated, and much, perhaps all,
of this will likely fall on you.
Finally, the nature of work at a distance requires significant additional
effort. Getting useful status information is a lot of work. You will not get
responses to initial requests every time, and verifying what is reported may
be difficult. You can expect to provide much more information than you
receive, and interpreting what you do get can be difficult. Even if the
information is timely, it may not be completely accurate, and you may get
little or no advance warning for project problems. Working to establish and
maintain a solid working relationship with outsourcing partners can be a
major undertaking, but it is prudent risk management.
Effort Estimates Adjusted for Risk
Once you have validated the effort estimates for each activity in the
project WBS, you can calculate the effort required in each project phase and
total project effort. The “shape” of projects generally remains consistent over
time, so the percentages of effort for each project phase derived from your
planning process ought to be consistent with the measured results from earlier
projects. Whatever the names and contents of the actual project phases, any
significant deviation in the current plan compared with historical norms is
good reason for skepticism. It’s also evidence of risk; any plan that shows a
lower percentage of effort in a given project phase than is typical has
probably failed to identify some of the necessary activities or underestimated
them.
Published industry norms may be useful, but the best information to
use for comparison is local. How projects run in different environments
varies a great deal, even for projects using a common life cycle or
methodology. Historical data from peers can be helpful, but data directly
from projects that you have run is better. The disciplined collection of project
metrics is essential for accurate estimation, sound planning, and effective risk
management. If you have personal data, use it. If you lack data from past
projects, this is yet another good reason to start collecting it.
Not all project phases are as accurately planned as others because some
project work is more familiar and receives more attention. The middle phases
of most project life cycles contain most of the work that defines “what we
do.” Programmers program; hardware engineers build things; tech writers
write; and in general, people do what it says on their business card. Whatever
the “middle” phases are called (development, implementation, execution, and
so forth), it is during this portion of the work where project contributors use
the skills in which they have the most background and experience. These
phases of project work are generally planned in detail, and activity estimates
are often quite accurate. The phases that are earlier (such as investigation,
planning, analysis, and proposal generation) and later (test, rollout,
integration, and ramp-up) are generally less accurate. Using the life cycle
norm data and assuming the development portion of the plan is fairly
accurate, it is possible to detect whether project work may be missing or
underestimated in the other phases. If this analysis shows inadequate effort
allocated to the early (or late) phases based on historical profiles for effort, it
is a good idea to find out why.
Effort profiles for projects also vary with project size. By mapping the
data from a large number of projects with various life cycles into a simple,
generic life cycle, a significant trend emerges. The simplified project life
cycle in Figure 5-3 is far less detailed than any you are likely to use, but all
life cycles and methodologies define phases or stages that map into these
three broad categories:
1. Thinking: This consists of all the initial work on a project, such as
planning, analysis, investigation, charter establishment, initial design,
proposal generation, requirements analysis, specification, and
preparation for the business decision to commit to the project.
2. Doing: The work that generally defines the project, including
development, is where the team rolls up their sleeves and digs into the
creation of the project deliverable.
3. Checking: This phase includes testing the results created by the
project, searching for defects in the deliverable(s), correcting
problems and omissions, approvals and sign-offs, and project closure.
As projects increase in size and complexity, the amount of work grows
rapidly. Project effort tends to expand geometrically as projects increase in
time, staffing, specifications, or other parameters. In addition to this overall
rise in effort, the effort spent in each phase of the project, as a percentage,
shifts. As projects become larger, longer, and more complex, the percentage
of total project effort increases for both early front-end project work and for
back-end activities at the end of the project. The graphical summary in Figure
5-3 shows this shift, based on data from a wide range of projects.
Small projects (shorter than six months, with most of the work done by
a small collocated team) spend nearly all their effort in doing—creating the
deliverable. Medium projects (six to 12 months long, with more than one
team of people contributing) might spend about half of their effort in other
work. Projects that are still larger (one year or longer, with several distributed
or global teams) will spend only about a third of the total effort developing
project deliverables. This rise in effort both in the early and late stages of
project work stems from the increased amount of information and
coordination required, as well as the significantly larger number of possible
(and therefore statistically expected) failure modes in these more difficult
projects. Fixing defects in complex systems requires a lot of time and effort.
Software consultant Fred Brooks (author of The Mythical Man-Month) states
that a typical software project is one-third analysis, one-sixth coding, and
one-half testing.
Figure 5-3. Effort by Project Phase
All this bears on project risk for at least two reasons. The first is
chronic underestimation of late project effort. If a complex project is planned
with the expectation that 10 percent of the effort will be in up-front work,
followed by 80 percent in development, the final phase will rarely be the
expected 10 percent. It will balloon to another 80 percent (or more). This is a
primary cause of the all-too-common late project work bulge. Many entirely
possible projects fail to meet their deadline (or fail altogether) due to
underinvestment in early analysis and planning.
The second reason that life cycle norms are valuable is found in the
symmetry of Figure 5-3. The total effort required for a project tends to be
lower when the initial and final phases of the work are roughly in balance. If
the life cycle norms for typical projects reveal that little effort is invested up
front and a massive (generally unexpected) amount of effort is necessary at
the end, then all projects are taking longer and costing more than necessary.
Most projects that fail or are late because of end-of-project problems would
benefit greatly from additional up-front work and planning. As an alternative
to this, you might also benefit by breaking lengthy projects into a sequence of
shorter, less ambitious undertakings requiring less overhead or by adopting
agile methods.
Cost Estimates, Budgets, and Risk
Inadequate overall funding was a major problem for nearly all the
projects in the PERIL database with money risks, causing well over 10 weeks
of average slippage. Total project expense is generally dominated by staffing
and outsourcing costs, but they also include estimates for equipment,
services, travel, communications, and other project needs. Uncertainty can
originate from any of these sources.
Cost Estimates Adjusted for Uncertainty
PERT (Program Evaluation and Review Technique) is one way to
explicitly analyze cost risk. Chapter 4 discussed using PERT for time, based
on three-point duration estimates for each activity (an optimistic estimate, a
most likely estimate, and a pessimistic estimate). This range information
could be used to calculate the expected estimate, which would lie at the
midpoint of the distribution. PERT for cost also employs the same three
estimates to derive an expected cost for each activity, using essentially the
same formula:
where ce is the “expected” cost
co is the “optimistic” (lowest realistic) cost
cm is the “most likely” cost
cp is the “pessimistic” (highest realistic) cost
As with PERT for time, the standard deviation (σ) is estimated to be
(cp − co)/6. A distribution showing this graphically is in Figure 5-4.
Figure 5-4. Cost Estimates for PERT Analysis
Cost-based PERT estimates are generally done in monetary units
(pesos, rupees, euros), but they may also be evaluated in effort (person-hours,
engineer-days) instead of, or in addition to, the financial estimates.
Whether for time or cost, PERT concepts are useful in gathering risk
information about project activities, particularly when considering the worst-
case (pessimistic) estimates. Use of PERT and three-point estimates for
project risk management goes well beyond adjusting cost and duration
estimates for uncertainty and will be explored in detail in Chapters 7 and 9.
Staffing and Outsourcing Costs
Staffing costs can be calculated using the activity effort estimates,
based on your histograms, spreadsheets, or other resource planning
information. Using standard hourly rates for the project staff and your effort
estimates, you can convert effort into project costs. For longer projects, you
may also need to consider factors such as salary changes and the effect of
inflation. Consider three-point effort estimates and worst-case analysis when
assessing the credibility of all cost estimates.
Estimate any outsourcing costs using the contracts negotiated for the
services, working with figures about halfway between the baseline contract
fees and the not-to-exceed amounts.
Equipment and Software Costs
The best time on a project to request new equipment or to upgrade
older hardware, systems, and applications for a project is at the outset. You
should assess the project’s needs and research the available options. Inspect
all equipment and software applications already in place to determine any
opportunities for replacement or upgrade. Document the project’s needs and
assemble a proposal including all potential purchases. As discussed earlier in
the chapter, proposing the purchase and installation of new equipment at the
start of the project has two benefits: getting approval from management when
it is most likely and allowing for installation when there is little other project
work to conflict with it. Propose purchasing the best equipment available, so
that if the purchase is approved, you will be able to work as fast and
efficiently as possible. If you propose the best options and only some of the
budget is approved, you still may be able to find alternative hardware or
systems that will enable you to complete your project. Estimate the overall
project equipment expense by summing the cost of any approved proposals
with other expected hardware and software costs.
Travel
The best time to request travel money for your project is also at the
beginning; midproject travel requests are often refused. As you plan the
project work, determine when travel will be necessary and decide who will be
involved. Travel planned and approved in advance is easier to arrange, less
costly, and less disruptive for the project and the team members than last-
minute emergency trips. Request and justify face-to-face meetings with
distant team members, getting team members from each site together at the
project start and, for longer projects, at least every six months thereafter. Also
budget for appropriate travel to interact with users, customers, and other
stakeholders.
There are no guarantees that travel requested at the beginning of the
project will be approved or that it might not be cut back later. If you do not
estimate and request travel funds early, however, the probability of approval
may be zero.
Other Costs
Communication is essential on all projects, and when managing
distributed teams, it can be quite costly. High-quality video- (and even audio-
) conferencing technology may require up-front investments as well as usage
fees. Schedule and budget for frequent status meetings, using the most
appropriate technology you can find.
Projects that include team members outside a single company may
need to budget for setup and maintenance of a secure public-domain Web site
outside corporate firewalls for project information that will be available to
everyone. Other services such as shipping, couriers, and photocopying may
also represent significant expenses for your project.
Cost Budgeting
Cost budgeting is the accumulation of all the cost estimates for the
project. For most of today’s projects, the majority of the cost is for people,
either permanent staff or workers under some kind of contract. The project
cost baseline also includes estimated expenses for equipment, software and
services, travel, communications, and other requirements. Whenever your
preliminary project budget analysis exceeds the project cost objectives, the
difference represents a significant project risk. Unless you are able to devise a
credible lower-cost plan or negotiate a larger project budget, your project
may prove to be impossible because of inadequate resources.
Documenting the Risks
Resource risks become visible throughout the planning and scheduling
processes. Resource risks discussed in this chapter include:
• Activities with unknown staffing
• Understaffed activities
• Activities with uncertain costs or high worst-case (or pessimistic
PERT) estimates
• Work that is outsourced
• Contract risks
• Activities requiring a unique resource
• Part-time team members
• Remote team members
• Impact of the work environment
• Budget requirements that exceed the project objectives
Add each specific risk discovered to the list of scope and schedule
risks, with a clear description of the risk situation. This growing risk list
provides the foundation for project risk analysis and management.
Key Ideas for Identifying Resource Risks
• Identify all required skills you need for which you lack named,
committed staffing.
• Determine all situations in the project plan where people or
other resources are overcommitted.
• Find all activities with insufficient resources.
• Identify uncertain activity effort and cost estimates.
• Note outsourcing risks.
• Gain funding approval early for needed training, equipment
purchases, and travel.
• Ascertain all expected project costs.
Panama Canal: Resources (1905–1907)
Project resource risk arises primarily from people factors, as
demonstrated in the PERIL database, and this was certainly true on the
Panama Canal project. Based on the experiences of the French during the first
attempt, John Stevens realized project success required a healthy, productive,
motivated workforce. For his project, money was never an issue, but
retaining people to do difficult and dangerous work in the hot, humid tropics
certainly was. Stevens invested heavily, through Dr. Gorgas, in insect control
and other public health measures. He also built an infrastructure at Panama
that supported the productive, efficient progress he required. At the time of
his departure from the project, Stevens had established a well-fed, well-
equipped, well-housed, well-organized workforce with an excellent plan of
attack.
This boosted productivity, but George Goethals realized that success
also relied on continuity and motivation. He wanted loyalty not to him but to
the project. The work was important, and Goethals used any opportunity he
had to point this out. He worked hard to keep the workers engaged, and much
of what he did remains good resource management practice today.
Goethals took a number of important steps to build morale. He started a
weekly newspaper, the Canal Record. The paper gave an accurate, up-to-date
picture of progress, unlike the Canal Bulletin periodically issued during the
French project. In many ways, it served as the project’s status report, making
note of significant accomplishments and naming those involved in order to
build morale. The paper also provided feedback on productivity. Publishing
these statistics led to healthy rivalries, as workers strove to better last week’s
record for various types of work, so they could see their names in print.
It was crucial, Goethals believed, to recognize and reward service.
Medals were struck at the Philadelphia Mint, using metal salvaged from the
abandoned French equipment. Everyone who worked on the project for at
least two years was publicly recognized and presented with a medal in a
formal ceremony. People wore these proudly. In a documentary made many
years after the project, Robert Dill, a former canal worker interviewed at age
104, was still wearing his medal, number 6726.
Goethals also sponsored weekly open-door sessions on Sundays when
anyone could come with their questions. Some weeks over a hundred people
would come to see him. If he could quickly answer a question or solve a
problem, he did it then. If a request or suggestion was not something that
would work, he explained why. If there were any open questions or issues, he
committed to getting an answer, and he followed up. Goethals treated
workers like humans, not brutes, and this engendered fierce loyalty.
Although all this contributed to ensuring a loyal, motivated, productive
workforce, the most significant morale builder came early on, from the
project sponsor. In 1906, Theodore Roosevelt sailed to Panama to visit his
project. His trip was without precedent; never before had a sitting U.S.
president left the country. The results of the trip were so noteworthy that one
newspaper at the time conjectured that someday, a president “might
undertake European journeys.”
Roosevelt chose to travel in the rainy season, and the conditions in
Panama were dreadful. This hardly slowed him down at all; he was in the
swamps, walking the railroad ties, charging up the slopes, even operating one
of the huge, 97-ton Bucyrus steam shovels. He went everywhere the workers
were. The reporters who came along were exhausted, but the workers were
hugely excited and motivated.
On Roosevelt’s return to Washington, so much was written about the
magnitude and importance of the project that interest and support for the
canal spread quickly throughout the United States. People believed, “With
Teddy Roosevelt, anything is possible.”
Chapter
6
Managing Project Constraints and
Documenting Risks
A good plan, violently executed right now, is better
than the perfect plan executed next week.
—GENERAL GEORGE S. PATTON
Reviewing a plan to detect problems and make improvements generally
ought to be a brief exercise done toward the end of initial project planning.
This chapter is not about the obsessive application of every single project
management practice in an endless quest for the flawless plan (sometimes
called analysis-paralysis). The topic here is realistic, commonsense project
analysis. The principal objective of reviewing the plan is to quickly find
defects and omissions, deal with unmet constraints, and seek an improved
plan. You are not after a perfect plan, just the best one possible using what
you currently know about your project.
This part of the planning process relates to risk management in several
ways, but two aspects are particularly important. First, the process of
replanning to deal with constraints will nearly always create project risk—
self-inflicted risk—because minimizing one parameter of a project often
leads to more pressure on other aspects of the work, creating additional
exposures, failure modes, and potential problems. These new risks result
from trade-offs made by the project team, and they need to be recognized,
documented, and added to the project risk list. A second type of project risk
is that of not taking on the “right” project. All projects have alternatives, and
examining at least some of these options is key to opportunity management,
also discussed in this chapter.
Analyzing Constraints
As you proceed through preliminary project definition and planning, a
coherent picture of your project starts to emerge. Although your project plan
is still incomplete at this point, it begins to provide insight into whether the
project objective is possible. Often, it reveals the unpleasant fact that the
project (at least as defined to that point) is impossible or at least
overconstrained; the result of your bottom-up plan leaves at least part of the
project objective unmet. Your preliminary analysis might reveal a schedule
that extends beyond the deadline, resource requirements that exceed initial
budgets, or other significant issues. Your planning process reveals just how
much trouble you are in.
Failure of the preliminary plan to meet the overall project objective is
not the only issue that emerges at this stage of planning. Above and beyond
the high-level constraints, most projects also have other constraints that you
must manage. Timing requirements for intermediate documents, prototypes,
and other midproject deliverables may mandate fixed-date milestones within
the project plan. The profile of available resources may be interrupted at
specific times by the business cycle, by holidays and vacations, or by higher-
priority projects. In addition, projects undertaken in lean organizations
(where keeping everyone busy all the time in the name of efficiency is a top
priority) will frequently run into a queue when access to a critical, unique
resource is required. Delays for contract approvals, management sign-off, and
other decisions are common. Identifying and managing risks from these other
constraints is also part of risk management on high-tech projects.
Your primary goal in managing project constraints is to remove or at
least minimize the differences between the project objective and your project
plan, in terms of scope, schedule, and resources. The standard triangle
diagram, shown in Figure 6-1, for examining project trade-offs is one way to
show these differences. The plan, represented by the gray triangle, is quite a
bit larger than the objective, shown as the black triangle.
For this project, the initial plan suggests that the deliverable is probably
feasible, so this project is not literally impossible: Its scope is within your
capabilities. However, as shown, the project will require both more time and
more resources (people, money, etc.) than requested in the project objective,
so based on the current plan, it is not feasible because of its constraints. For
projects where the scope is plausible, the situation in Figure 6-1 is fairly
common. Bottom-up project planning begins with a work breakdown
structure (WBS) that is consistent with the desired scope, but the initial
schedule and resource plans fall wherever the WBS leads them—often at
significant variance with the project objective.
Figure 6-1. Objective Versus Plan
For some projects, the objective is firm, based on hard limits that
cannot be modified. For other projects, the objective may be based on softer
constraints, goals that are desirable but not absolutely necessary. Each project
is unique, so determining how to approach trade-off analysis for your project
requires you to understand what the constraints and priorities are, as well as
how they were determined. In the simplest form, project priorities boil down
to the old saying, “Good, fast, cheap: Pick two.” Every project requires at
least one degree of freedom. Because of this, it is unrealistic to nail down all
aspects of a project prior to completing a thorough analysis of the required
work.
Any of the three parameters could be the most flexible, but for
planning purposes, one of them must be unconstrained. Although you can get
a deliverable out of a project quickly and cheaply, it may fail to meet the
need. This lesson was illustrated several times in the late 1990s by NASA on
several failed Mars missions, working under the mantra “Faster, Better,
Cheaper.” Similarly, excellent results are often possible in short time frames,
but the cost of this compression is high and may not be justified by the result
(crashing project activities in the project schedule is covered later in this
chapter). You may even be able to deliver good results at low cost in projects
where time is not limited (though this scenario could result in the analysis-
paralysis already mentioned).
A slightly more sophisticated analysis rests on prioritizing the triple
constraint. Rank-ordering scope, schedule, and resources shows which of the
three is most important for your project. A simple three-by-three grid is often
used for this, as in Figure 6-2.
The project priorities shown here are common for high-tech projects
because timing dominates more and more of the work. In contract work,
deadlines with financial penalties are often looming. In product development,
pressure from competitors, trade show schedules, and other real constraints
on timing are often at issue. Even in application development, delivery often
must synchronize with fiscal accounting periods. In all these cases, schedule
is the dominant priority, and failure to meet the project deadline will have
significant, possibly dire consequences. Schedule is the parameter such
projects constrain.
In Figure 6-2, the second priority is resources. This is also common
because the desire to minimize resources and execute as efficiently as
possible is a key goal for many projects. In fact, many projects face
significant limits on competent, available staff. In the time frame of many
complex projects, the number of available people who are familiar with new
or evolving technologies and methods is fixed and can increase only
gradually over time through training, mentoring, and other methods for
hauling people up the learning curve. Projects such as this strive to optimize
their resources.
The largest degree of freedom for the project in Figure 6-2 is for scope,
indicating that some aspects or specifications may be set in the objective that,
although desirable, may not be absolutely required. The project will accept
small changes to the deliverable, particularly if not making the changes
would require more time, more resources, or both. This prioritization is one
of six possibilities, and good examples for each of the other five are easily
imagined. Though all prioritizations are possible, today’s projects frequently
converge on schedule/resources/ scope, as in Figure 6-2.
For the example in Figure 6-1, the initial plan failed to meet the
deadline and was also over budget. Doing some what-if analysis, you may
discover a way to use a top-notch group of consultants (with a credible track
record) to perform more work in parallel, shortening the overall project. This
approach will not be inexpensive; it makes the budget problem even bigger
and results in the shift shown in Figure 6-3. In this figure, the schedule has
been compressed, bringing it in line with the objective, but the resources
required for the project, which already exceeded the objective, are even
farther out of line with the project expectations.
Figure 6-2. Project Priority Matrix
Figure 6-3. Plan Trade-Offs
For projects whose resources are the lowest priority, this tactic may be
a good alternative. For projects with the priorities in Figure 6-2, however, this
is not likely to be the best plan. It may be better to reevaluate the
specifications and propose a plan that achieves its deadline within budget but
falls slightly short on scope. Some projects may find that some of the
requested requirements are not actually needed. Other projects may propose
delivering the most valuable functionality on time and delivering the rest in a
follow-on project somewhat later. The analysis for such a scope reduction
might result in a shift similar to that shown in Figure 6-4.
Figure 6-4. Seeking the “Best” Plan
In this case, changes proposed to the initial plan affect all three of the
project parameters, with the most significant difference between the objective
and the plan being a small reduction in the feature set for the deliverable.
The overall objectives of the plan review and what-if analysis are to
discover the options available as alternatives to the initial plan and to see
whether it might be desirable, or even necessary, to revisit the project
objective and change the project definition. This triangle model allows trade-
offs to be explored in the project “state space,” seeking plan alternatives that
could be realistic, feasible projects. For particularly ill-conceived projects, the
analysis may fail to turn up any options close to the original objective. For
such projects, you need to negotiate a major change to the objective, abandon
the project, or at least think about updating your résumé.
In most cases, though, reasonable alternatives for your project are not
difficult to find. Start your analysis of the project plan with the parameter that
has the lowest priority and explore possible changes related to that aspect of
the project. These modifications are generally the easiest to negotiate, so it
makes sense to focus first on that side of the triangle. For most projects, you
will also want to examine alternatives for the other two parameters. The
upcoming sections describe using this what-if technique for exploring project
opportunities and then for options related to scope, resources, and schedule
(following the prioritization in Figure 6-2).
Managing Opportunities
When your preliminary plan falls short of the project objective, it could
seem inappropriate to revisit opportunities because doing so would likely
make things worse. There are a number of good reasons for exploring these
project options, though, and they relate directly to risk management. Whereas
risk management seeks to understand what might go badly in a project,
opportunity management looks for what might go better. In particular,
opportunity management asks what similar but superior projects might be
possible. Realizing halfway through the work that you could have achieved a
more valuable result is not useful. It’s too late at that point on most projects
to do anything about it. As discussed in Chapter 1, projects are driven by
opportunity, and many times the sponsors, stakeholders, and others who
conceive them may not be in the best position to see them. In the course of
planning, the project team will frequently discover new technologies,
methods, or other possibilities that would result in a superior project.
Adopting a better opportunity in such a case might also result in a more
interesting, more motivating project that can enhance teamwork and provide
development opportunities valued by contributors. Mostly, however, it helps
to ensure that you are not working on the wrong project. As with risks, a
good starting point for opportunity management is the triple constraint of
scope, schedule, and resources.
Scope
Deliverables for high-tech projects are set using two kinds of input,
user/market demand and technological possibilities. Most project work relies
primarily on the first. The sponsors, economic buyers, managers, and others
who get projects started are generally doing so to meet a need, solve a
problem, or respond to some specific request. Although this may be
sufficient, the requested deliverables in high-tech projects can fall well short
of what is possible. Technology moves fairly quickly, so user requests may
represent continued use of an older technology even after emerging new ideas
and approaches are available. If you were collecting specifications for a
project deliverable from people sitting on a river bank washing their clothes
with two large stones, their requirements would probably involve developing
lighter rocks. The concept of a washing machine might not occur to them if
the technology is not part of their experience. Similarly, the project team may
be able to see possibilities based on technology unknown to the users that
would solve the problem or meet the need much more effectively than the
original request. Opportunity management is about merging a deep
understanding of user needs with the technical capabilities available to create
the best deliverable—not necessarily the one initially envisioned. A what-if
project with a slightly longer schedule and higher budget compared with the
original objective, but with a superior deliverable such as depicted in Figure
6-5, may be a much better project alternative.
Scope opportunity management often requires a counterproposal to the
original objective and may involve negotiation. Some project leaders actively
avoid this sort of confrontation, viewing it as unpleasant and usually
unproductive. This is unfortunate because this process represents one of the
real sources of power and influence that the project leader has. There is an
old saying, “If you are going to lose an argument, change the subject.”
Proposing an alternative that is demonstrably superior to the requested
deliverable can effectively change the subject, avoiding an otherwise doomed
project by substituting a better, more realistic one.
The main motivation for opportunity management, however, is to
increase the business value of the project. There are a number of ways to
approach this. Surveying the current state of relevant and closely related
technologies is a typical starting point. It may be that a new generation of
hardware is available that could effectively be used. New technologies or
methods may provide greater speed or reliability. Emerging standards may
have application to your work, which could extend the possible uses of the
deliverable both in the current project and for future applications. It might be
possible to develop a deliverable with capabilities that solve a whole class of
problems instead of the single one that triggered the project. Conversely, it
may be possible to break up an ambitious project into shorter stages,
developing something that provides tangible value (perhaps most of what is
actually needed) for a fraction of the time and cost that the entire project
would require.
Figure 6-5. An Opportunistic Plan
Resources
Explore options for efficiency or schedule reduction through the use of
additional, more highly skilled, or outside contributors. If improvements to
your tools, systems, or other aspects of your infrastructure will help
performance, propose changes. Gain access to and use the best available
facilities and methods for communications. Bringing distributed teams
together and arranging other face-to-face collaborations may significantly
boost progress and teamwork. If so, obtain funding for the necessary travel. If
additional training for contributors will help the project, schedule it.
If some team members have underallocated time during parts of the
project, consider replanning to more effectively use the effort available
(although this will reduce resource reserve and increase potential failure
modes).
Schedule
Schedule opportunities include revising the schedule to exploit float,
revising logical dependencies, devising ways to exploit the optimistic end of
a three-point estimate range, and crashing activities. Seek valid shortcuts and
better, newer methods for the work. Although each of these can reduce the
schedule, each also tends to increase risk. These concepts are discussed in the
section on schedule modifications.
Some project leaders list opportunities with risks and assess them
together using the processes outlined in Chapter 7. Although opportunities
and risks are related, they are not exactly opposites. Most people equate risks
with threats, and the choice of whether to manage them or not is primarily the
responsibility of the project team. Unmanaged risks that do occur are
unquestionably going to be seen as the responsibility of the team.
Opportunities are not symmetric with risks. Many opportunities, as
discussed in Chapter 1, are adopted as choices and embedded in the
assumptions as part of the project initiation process. These opportunities are
fundamental to the business case for projects, and, as we have seen, are the
source for many risks, particularly scope-related risks. New opportunities
uncovered during planning may originate with the project team, but adopting
them, particularly if they involve significant scope or other changes to the
overall objectives, is never a project team decision. Proposals are needed
before consideration, and a commitment to modify the project deliverable
will require stakeholder approval.
The consequences represented by risks and opportunities are not really
symmetric either. It’s often said, “Success has many fathers, while failure is
an orphan.” Whenever things work out better than expected, everyone takes
credit—especially the managers. When things go badly, the project team will
be left standing alone.
Opportunities that significantly change the project require sponsor
support, and acceptance of them is nearly always more complex than the risk
assessment process described in Chapter 7. Opportunities that do not
represent substantial shifts to the overall project objective (including much of
what follows in this chapter) mostly fall into the category of good project
planning. Some of the opportunities and alternative plans you consider may
reduce project risk, while others may increase it. Note the consequences on
your risk list for any plan alternatives you seriously consider.
Scope Modification
Proposed changes to the project deliverable may be easily accepted,
absolutely nonnegotiable, or anything in between. This depends on the
project, the sponsors and users, and the type and magnitude of the change.
Whatever the circumstances, a conscientious project team will spend at least
a little time examining the effect on the project of adjusting the project
deliverable. This what-if exercise helps your team understand the work better
and provides you with valuable information for decision making.
To meet project constraints, many projects will end up trimming scope.
Before deciding what features or aspects of the project deliverable to drop or
change, determine which requirements are absolute must-have features and
which are lower priorities. There are several techniques for prioritizing
requirements. The simplest is to list the requirements and sort them into a
sequence where the most essential ones are at the top of the list and the least
important ones fall to the bottom. Is/is-not analysis, described in Chapter 3, is
another possible starting point. You will need to revisit the list of items on the
“is” list to validate that each requirement is in fact essential. Determining
what portions of scope can be demoted to the “is-not” list effectively limits
scope. This is particularly useful for projects that have hard limits on timing
and budget; the is/is-not technique establishes a firm boundary for scope that
is consistent with the other limits.
The purpose of the exercise, however you approach it, is to capture and
document the specifications that you must deliver, separating them from the
portions of the requested deliverable that are desirable but not absolutely
necessary. Accepting small decreases in reliability or performance may cause
a significant reduction in project time and cost, and such trade-offs may result
in a project that better meets its overall objectives.
Dropping project scope requirements is far easier when done early.
Late changes are often painful and expensive, consuming effort that would
have been unnecessary had the change been made earlier. Freezing scope
early does not mean that project scope will never shift; it just means that any
modifications will be subject to analysis and change control before being
accepted. Determining the lowest-value features and requirements allows you
to intelligently determine what to exclude (either permanently or as part of a
follow-on project).
Resource Modification
Revisiting the resource plan can also lead to an overall plan that better
fits the objective. Alternative approaches to staffing, cross-training,
outsourcing, and other elements of the resource plan are all potentially useful
tactics.
Resource Analysis
For some projects, there may be ways to get work done faster without
increasing the overall required resources. One possibility is to rearrange the
work assignments to use available staffing more fully and effectively.
Schedules may be too long because of nonproject commitments. If the
external work can be postponed or eliminated, it could have a significant
impact on your schedule. You may also be able to find ways to improve the
effectiveness of the project team by simply asking individuals what they need
to work faster. Many people get more work done through telecommuting,
working at times when they are more efficient, or being in a different work
environment. Unless you ask, these possibilities will remain hidden.
You may even be able to minimize distractions and noise during some
or most of the project by moving work off-site, collocating the team in a
closed-off area, or relocating to space that is out of normal foot traffic areas.
One project team I worked with attributed much of their on-schedule
performance to their location in a trailer (while new buildings were being
completed). It was quiet there, and no one dropped by to visit.
Training Additional Staff
Another tactic that can potentially help the schedule as well as mitigate
a source of project risk is mentoring and cross-training. Project timelines are
often longer than theoretically necessary on high-tech projects because only
one person knows how to do some part of the work. These activities must be
scheduled in sequence, queued up for the expert. Work can speed up if others
on the staff have an interest in this area of expertise and can be trained to take
on activities in parallel. Of course, people new to a discipline will rarely work
as fast as experienced staff. Duration estimates for activities assigned to them
will generally be longer, due to training requirements and lower work
efficiency. Activities assigned to the current expert will also take somewhat
longer because of the required mentoring. Nevertheless, the benefits to the
schedule in getting the work done concurrently can be substantial. In
addition, the project risk profile will improve because the project will no
longer be dependent on a single person. If the expert becomes unavailable to
your project (because of illness, higher-priority work, resignation, or any
other reason), your project will not grind to a halt but can continue (although
more slowly) using the newly trained staff.
Staffing Alternatives
For projects where schedule is much more important than budget,
subcontracting work to outside service providers might speed things up,
providing that a larger staff can work in parallel on activities that are
currently planned in sequence. If the project priority is high, more staff from
within the organization may also be an option. Some projects cannot run as
quickly as theoretically possible because the experience and talent available
on the original project team is low, so it is useful to explore the possibility of
finding staff who are more productive or who do not require any training
before taking on project activities. Additional resources of other types, such
as faster computers, newer equipment for test and other work, or systems to
automate manual activities, can also potentially help to compress the project.
New work methods require training and practice but nonetheless may save
time. All these options will raise the resource cost of the project, but for some
projects this trade-off may be justified.
Schedule Modification
Reexamining the schedule also provides alternative projects. Some
ideas to consider include using float, revising activity dependencies, and
crashing the schedule.
Using Float
One simple approach for shortening your project involves reducing the
amount of float on noncritical activities. Float is derived from the critical path
analysis of the schedule (discussed in Chapter 4), and it measures how much
an activity can slip without impact on the project deadline.
To shorten your project using float, shift some of the work on critical
path activities to staff assigned to noncritical activities. These staffing shifts
will cause changes to noncritical activities (such as delaying the start,
interrupting the activity, or reducing productivity), but as long as the
activities retain some float, the additional effort on the critical activities can
shorten the project. Bear in mind that this sort of schedule compression
comes with a price. Using all (or nearly all) of the float for an activity
increases project risk and creates new failure modes.
Revising Activity Dependencies
A second, more elaborate idea involves revising activity dependencies.
Here, the schedule is shortened by rearranging or redefining the work. The
simplest possibility is to inspect the dependencies linking critical path
activities, looking for opportunities to shorten the schedule using a more
compact logical work flow.
If revising activity sequences is ineffective, you can reexamine the
activities and brainstorm alternate ways to approach longer activities on the
critical path by using a different breakdown or a completely new approach.
This second method often involves breaking critical path activities down
further to create smaller activities that can be executed in parallel, as shown
in Figure 6-6.
Figure 6-6. Converting Activities to Parallel Execution
This concept has a variety of names, including concurrent engineering,
fast-tracking, and simultaneous development. For parallel execution to be
effective, there are at least two requirements. First, you need to allow
integration time in the estimates for the parallel activities or define a new
activity (as in Figure 6-5) during which all the separately developed
components are assembled. The second requirement is often less visible but it
is even more important. Detailed up-front analysis is essential to ensure that
the integration works. All the connections, interfaces, and relationships
between the independently developed activity deliverables must be defined
and thoroughly documented. Whatever this work is called—architecting,
systems engineering, or something else—doing it well will be the difference
between components that mesh properly and integration efforts that fail.
When the system decomposition is done poorly, integration activities can
consume all the time you expected to save—and more. Even worse, it may
utterly fail, resulting in components that are completely unusable. Before
committing to a plan that uses independent parallel development, explicitly
identify when and by whom this analysis will be done, and note the
integration risks on your project risk list.
Another approach for schedule compression through revising activity
dependencies involves overlap of the work. In the plan, there may be finish-
to-start dependencies on the critical path that can be converted to start-to-start
dependencies with lags.
In Figure 6-7, the preliminary project plan includes a design activity
scheduled for three weeks, followed by a coding activity scheduled for four
weeks. After thinking about it, the project team may decide that it would be
possible to begin coding after only two weeks of design because there will be
enough information to start programming for some of the modules at that
point, and staffing will be available to get going. Although it may seem that
converting a finish-to-start dependency to start-to-start dependency with an
overlap of a week would save that week on the schedule, this is overly
optimistic. There is an increased likelihood of rework or discovery of
something unexpected in the final week of design, so when you elect to make
this sort of change, increase your duration estimates for any activities that
you choose to begin early (in this case, about two days have been added to
the coding activity), and also explicitly note the new risk.
Figure 6-7. Modifying Activity Dependencies
Optimistic Estimates
Most best-case estimates are based on wishful thinking, and few will
actually happen on most projects due to Parkinson’s Law and other factors.
Some, however, will be based on effective ideas for working more efficiently
or productively, and represent ways to credibly shorten the schedule. If there
are ways to modify the approach taken, the project environment, or other
factors that would support shortening a duration estimate, incorporate the
changes for your project. Whenever compressing a schedule using best-case
analysis data, however, be aware that this is a choice that may have
unintended consequences and that it does carry at least some risk because you
can never completely wipe out the worst-case scenarios.
Crashing the Schedule
An additional scheduling technique, common on projects with extreme
schedule pressure, is crashing. In this sense, crashing means applying
additional resources to gain speed—as in a crash program. Not all activities
can be crashed. It is not possible to crash activities when one person must do
all the work, when activities cannot be partitioned, or when you do not
control activity time constraints. A good example of an uncrashable activity
is sailing a ship from New York to London. With one ship, it takes five days.
With five ships, it still takes five days.
Even when crashing helps, it adds both additional cost and new risks to
projects. If an activity is efficiently executed by a team of three people, a
team of six will rarely be able to do it in half the time. Involving more people
requires extra communication, overhead, and complexity, so resources and
time never trade off linearly. This has been observed and documented for all
types of projects for a long time, but the best discussion of this for high-tech
projects remains The Mythical Man-Month by Fred Brooks. Brooks covers in
detail how people get in each other’s way and how inefficiencies grow as the
number of people working on a project increases. As productivity drops,
project risk increases because of the larger staff, potential confusion, work
methods, and general complexity.
For all this, when time is critical to your project, these trade-offs may
be justified. Crashing a project schedule requires you to locate the activities
that can be shortened and to estimate the related impact of compression,
particularly on the project budget. Experienced project leaders usually have a
good sense of how to do project work efficiently, so initial plans are
generally built using assumptions for staffing and work methods that
minimize effort and cost. For any given activity, though, other combinations
of staffing and duration may be possible. One person working alone on an
activity might take a long time; two working together could take quite a bit
less. Adding more people will, for some activities, continue to reduce the
activity duration even more. Eventually, though, you reach a point of
diminishing returns, where adding more staff makes a negligible difference in
the activity duration. At that point, a curve describing the relationship
between staffing and time has a bend in it, giving it an L-shape, similar to the
curve in Figure 6-8.
Figure 6-8. Trade-Off Between Effort and Time
For any given activity, there is also a minimum possible duration; no
amount of additional staffing, money, or other tactics will allow you to do the
work in less time.
Because the initial estimates tend to be near the bend in the curve
(where the cost is minimized), shortening projects by crashing can be quite
expensive. Strategies for compressing projects by crashing begin by seeking a
number of ideas, more than may be needed to meet the project deadline.
Examine the schedule for activities that could be crashed, expedited, or
otherwise changed in ways that could shorten the project, initially focusing
on the critical path(s). Ideas for each activity can then be considered in turn
and assessed for both effectiveness and cost.
If the next priority after schedule is cost, you will first adopt the
strategies that have the least impact to the project budget. This will require
you to estimate the cost penalty for each idea. The usual way to do this is to
calculate the cost per time (usually per day) associated with the schedule
reduction. For example, one idea might be to shorten a development activity,
initially estimated to take 15 workdays and consume $4,000 of effort. You
believe that this could be reduced to 11 days, saving four, if you bring in an
outside contractor to help for a week at a rate of $6,000. Both the initial and
compressed approaches to this activity are indicated in Figure 6-9, and the
slope of the dotted line connecting them, $1,500 per day, defines the cost
penalty for schedule compression.
Figure 6-9. Estimates for Crashed Activity
Ideas for schedule compression can come from a variety of sources.
The project team can brainstorm, you can consult peers or experts, or you can
research what similar past projects did when they ran into trouble and were
forced to work faster. In addition to providing a potentially rich source of
ideas, project recovery information may offer data on costs and describe the
work that will be required.
Typical methods that may prove effective in shortening project activity
durations (for a price) include:
• Adding staff
• Paying for overtime
• Hiring outside staff to help or outsourcing whole project activities
• Paying to expedite shipping or other services
• Upgrading or replacing slower equipment
• Spreading work over more shifts
For each crashable activity idea you develop, estimate the total cost
involved and assess the cost penalty—the expense for each day of schedule
improvement—so that you can arrange the ideas from least costly to most
expensive per day. Starting with the least costly strategies, make schedule
changes affecting critical activities and note the cost of the additional
resources. For each modification considered, check that the change does in
fact provide a schedule improvement, and monitor for noncritical path
activities that become critical. You can continue the process, crashing
activities until it is no longer necessary or is not possible.
Any schedule compression ideas that you do not use can be held in
reserve as possible contingency plans for your project. (Contingency
planning is discussed in detail in Chapter 8.) An alternative to adopting
tactics for shortening the project based on cost takes this concept an
additional step. Ideas for crashing can be useful as contingency plans only if
they relate to future portions of the project. To maximize the potential utility
of any crashing tactics you have developed, you might choose to apply them
based on timing. If you start with the ideas that shorten the project by acting
on the earliest activities, any leftover tactics will remain available as
contingency plans. Although this will generally cost more, it will result in a
more resilient plan.
Before leaving the topic of schedule changes, it’s worth noting that a
compressed schedule has a lot more failure modes and will generate a good
deal more stress on the project. The trade-offs between time and cost and
between time and scope are visible throughout the process of managing
project constraints. The trade-off between time and risk is more subtle but
nonetheless real. At the conclusion of this process, document any changes
you made and list all the new risks introduced to your project plan, including
the new critical and near critical paths. Also be aware of the increased overall
project risk contributed by the added complexity and stress.
Assessing Options and Updating Plans
After investigating possible scope, resource, and schedule changes, you
have the information you need to assess your options and seek the plan that
best meets the project objective. Your analysis may result in a credible
project plan (including a detailed project schedule, resource plan, and
description of major project deliverables) that supports the project objective
and any other significant constraints. If so, your next step is risk analysis.
If the best plan you can develop is still far from the objective, it is
evidence that you have an overconstrained project. In such a case, use your
what-if analysis of scope, schedule, and resource combinations and develop
at least two additional plans that achieve slightly different project objectives,
such as:
• Fewer resources needed but longer schedule or reduced scope
• Increased scope (with higher demonstrable value) but more time or
resources required
• Shorter schedule but more resources needed (or scope reduced)
For each option, document the relative advantages and risks. These
alternative plans can be used in discussions and negotiations. (Negotiating
project objective changes is a key topic of Chapter 10.)
Incorporate any plan changes that you are empowered to make into
your preliminary schedule and other project documents. If you developed
alternative plans, document them as well, with any proposed changes or
opportunities that would require higher-level approval.
Seeking Missing Risks
Although you have collected risk data throughout the planning of
project work, your risk list remains incomplete. Review your scope
definition, preliminary schedule, and resource plan, using the ideas in
Chapters 3 through 5, looking for risks you may have missed. You may also
want to review the selected risks from the PERIL database listed in the
Appendix to further stimulate discovery of project risks. There are also a
number of additional methods for detecting potential problems and risks.
Brainstorming
One powerful risk discovery process is brainstorming. With the project
team, review the risk list that you have already constructed. Work together to
brainstorm additional potential project problems. Examine the methods and
processes you intend to use and consider any aspects that are new or that will
be particularly difficult. Think about risk that would arise as a consequence
of any organizational changes that are rumored or seem likely. Finally, focus
on outside factors that might have an impact on your project, such as natural
disasters, weather, government or legal changes, and actions of competitors.
Also, plan to spend at least some of your time focusing on uncertain events
that could have a beneficial effect on your project—opportunities that might
make your work easier.
Capture every idea without comment, questions, or criticism. Stimulate
people to think of new risks triggered by the thoughts of others. List every
risk that is mentioned, even those you think you can do nothing about. Keep
the brainstorming going, striving to hear from every member of the project
team, until the flow of ideas seems at an end. Conclude the process by
restating any risks that are unclear, combining or eliminating redundant risks.
Add all the new risks to the project risk list.
Retrospective Analysis
Another technique for finding risks in a new project is retrospective
analysis of earlier projects. The old adage that “Lightning never strikes twice
in the same place” is demonstrably false; lightning strikes the same spot
hundreds of times, always the highest place with the best electrical
connection to the ground. (If this were not the case, lightning rods would not
work.) On projects, the analogous statement “That can never happen again” is
equally untrue. Risks tend to recur in project after project, unless you deal
with the source of chronic problems by doing things differently to avoid
them. Postproject analyses from earlier work (in the form of project
retrospectives, lessons learned, postmortems, or close-out reports) are a rich
source of risk information.
These reports generally contain two types of data useful for risk
management: effective practices worth repeating and areas where
improvement is warranted. In the area of good practices, seek specific ideas
from what was done well, practices to repeat or extend, and specific
significant accomplishments. Examine your plan to see whether you are
incorporating opportunities to take full advantage of known good practices.
In the realm of things that did not go well, review previous project data for
problems, assumptions, poor estimates, actual versus planned beginnings and
ends of major activities, the complexity of activities undertaken, the number
of changes proposed and accepted, sources of delay, and other issues.
Identify any aspects that impacted progress, and list as risks any that may
affect your current work as planned.
Scenario Analysis
Additional risks may come to light through scenario analysis. Discuss
situations expected along the project timeline, step by step, asking questions
such as, “What might go wrong here?” and “What will be keeping me up at
night during this portion of the work?” You can close your eyes and “play a
movie in your head” to gain insight into the project’s work and the problems
it may be exposed to. Techniques familiar to software development
organizations, such as inspections and structured walk-throughs, may also be
applied to the project plan to reveal weaknesses, omissions, and risks.
Assumptions Analysis
Also related to scenario analysis is review of your assumptions. As you
think through project scenarios, review the project assumptions to uncover
any that might change. As you proceed through your project planning,
assumptions analysis can reveal where initial expectations may no longer be
valid or could result in possible project failure modes.
SWOT Analysis
A similar approach to scenario analysis is Strengths, Weaknesses,
Opportunities, and Threats (SWOT) analysis. For many projects, particularly
those involving delivering solutions, these aspects are examined early in the
project. As the project planning process approaches closure, you should
revisit both the identified weaknesses and threats for the project to ensure that
any that are not adequately addressed in your planning are noted as risks.
Expert Interviews
Risk discovery sources outside your project can also be useful. Expert
interviews both inside and outside your organization can be a potentially rich
source of information on risks that your project may encounter. Utilizing the
experiences and perspectives of others is a potent technique for identifying
and managing risks.
Root Cause Analysis
Root cause analysis, or cause-and-effect, exercises are powerful tools
for risk discovery. Risk management requires knowledge of the root causes
that lead to project problems. There are a number of effective techniques for
discovering the sources of problems, and although they are most often
applied retrospectively, they can also be used to examine future problems.
These techniques include failure mode and effect analysis, fishbone
diagrams, root cause analysis, K-J analysis, or other varieties of cause-and-
effect analysis. Using these processes to look for potential risks begins by
stating an outcome the project intends to avoid—such as losing a key
resource, delay in getting an important input, or significant increases in the
cost of some portion of the project. The next step is to challenge the project
team to work backward to uncover plausible sources that could cause the
problem. In addition to uncovering specific risks that might not otherwise be
detected, this exercise will often raise the perception of how probable certain
problems are likely to be. Before the sources of trouble are articulated, most
projects look fairly straightforward. After documenting the things that can
contribute to project difficulty, you have a much more realistic view of the
work, balancing the sometimes excessive optimism that is common early in a
new project. Further discussion of root cause analysis as a tool for managing
risks is in Chapter 8.
Bow Tie Analysis
Like root cause exploration, bow tie analysis facilitates discovery of
antecedents to project problems. Bow tie analysis is often used to help
provide a clear picture for catastrophic failure modes involving public health
and safety. The overall process incorporates both sides of the risk picture—
what comes before it and what follows it. Bow tie analysis is named for the
overall shape of a typical diagram, as shown in Figure 6-10.
Figure 6-10. Generic Bow Tie Diagram
The Fault Tree portion on the left side of the diagram is the most
relevant to risk identification. It focuses on the causes of known risks, and,
like root cause fishbone diagrams, it provides insight into the underlying
sources of potential project problems.
Bow tie analysis is a robust technique for documenting not only risks
but also the actions that are planned to both prevent and to recover from
them. You will find an example and more details on using this technique for
risk response planning in Chapter 8.
Value Analysis and ROI Risk
Projects are undertaken based on a belief that investing in them will be
justified by the benefits generated. Spend at least some time during your
planning on investigating the assumptions that support the expected value
your project will represent. Consider potential problems that might
undermine the business case, such as scoping shortfalls, delays, competitor
actions or other external changes, and other eventualities. Add any significant
exposures you uncover to your risk list.
Other Risks and Risk Breakdown Structure Analysis
Finally, sort the items included on your risk list using categories based
on a risk breakdown structure. Many organizations have defined detailed
hierarchies of risks. If you have one that is relevant for your project, use it. If
you lack one, the generic structure of the PERIL database with its
subcategories for scope, schedule, and resources can provide a good starting
point.
Review what you have listed, paying particular attention to any
categories of risk where your list has few or no entries. Add any risks to your
list that arise from this examination. Also focus your review on identifying
uncertainties in risk categories that fall outside your overall planning
processes and control, such as those involving safety, legal, environmental,
market shifts, and other factors outside project management.
Creating a Risk Register
Risk management depends on making risks visible and documenting
them. Every time you uncover a risk, write it down. For each listed risk,
check that the description is clear, including a summary of the consequences.
Use a consistent format to describe each risk, such as: “If [cause], [risk] could
occur, resulting in [consequence].” For example, “If our lead designer Sara
leaves, we will have insufficient experienced staff to complete the design,
resulting in a delay of at least four weeks.”
Once you have listed and clearly defined all the risks you have
identified, start to assemble a risk register to support the next steps of
analysis and assessment. Your risk register may be a table, spreadsheet,
database, or even a specialized risk tracking application. Completeness
matters more than the specific format you choose, so ensure that your risk
register provides space for entering (at least):
• A clear risk description
• Probability assessment
• Impact estimate
• Overall rating
• Impact description, including when the risk would most likely occur
• Risk owner
• Triggers or other indicators that signal risk occurrence
• Response summary
• Contingency or recovery summary
Create your project risk register by organizing your risk list and adding
these and other relevant details.
Key Ideas for Constraint Management and Risk Discovery
• Minimize differences between project plans and objectives.
• Understand and clearly document project priorities.
• Explore project opportunities.
• Use priorities to identify project alternatives.
• Identify and explicitly remove unnecessary project scope.
• Determine risks and costs of proposed plan revisions.
• Minimize unknown risk through brainstorming, analysis, and
research.
• Thoroughly document known project risks.
Panama Canal: Improving the Plan (1906)
Many projects, viewed in retrospect, failed because they could not
manage the work within mandated constraints. In reviving the Panama Canal
project, a great deal of effort went into rethinking the approach to the work,
to avoid the most significant issues that plagued the earlier project.
For projects of all types, it is beneficial to invest effort early,
investigating whether there are better, faster, more efficient ways to do what
is required. New technologies, methodologies, and approaches are born this
way. Several key innovations were introduced in the U.S. canal project.
Avoiding schedule and cost problems required changes to the equipment used
and the methods employed to accomplish the work.
On the equipment side, twentieth-century technology made possible the
huge, powerful steam shovels that gave the U.S. effort a big advantage over
the earlier project. New technology also provided equipment suitable for use
in the warm, damp, machine-destroying environment of Panama.
As important as the hardware was, however, the way the equipment
was used made an even bigger difference. John Stevens, as a railroad
engineer, saw the canal project as a railroad problem. To him, the canal was
“the greatest of all triumphs in American railroad engineering.” To keep the
huge shovels digging continuously, Stevens developed a system so that
shovel loads could be dropped onto railroad flatcars that ran along track
adjacent to the shovels. The flatcars circulated in large loops out to the dams
and other places where these loads could be deposited. Once there, huge
fixed scoops (similar to the fronts of enormous snowplows) cleaned off the
flatcars for their return to the shovels, with no need to stop or pause at any
point for this enormous conveyor belt. Using this arrangement and the much
larger steam shovels, the U.S. project was soon excavating more in one day
than the earlier French project had accomplished in a month.
This system would have been sufficient for the project if the shovels
had been simply digging deep holes in one place, but they were not. As the
digging proceeded, the shovels had to move, and so did the railroad tracks
that carried the flatcars. For this, John Stevens developed an elaborate, elastic
method for moving the track, providing a constant, steady stream of empty
flatcars flowing by the steam shovels. With his system, 12 men could move
almost 2 kilometers of track in a single day. Using conventional track-laying
methods, 600 men would have had difficulty equaling this performance. As
the construction continued, excavation in the Culebra Cut widened and
deepened, so these methods were used at multiple levels. Each level had its
own railroad loop, shovels, and crews. The total track moved in one year
approached 2,000 kilometers. Without these innovations, the canal project
would have taken years longer to complete and cost far more, and it might
well have been abandoned before completion, like the earlier project.
Chapter
7
Quantifying and Analyzing Activity Risks
When you know a thing, to hold that you know it,
and when you do not know a thing, to allow that
you do not know it—this is knowledge.
—CONFUCIUS
Project planning processes serve several purposes, but probably the
most important for risk management is to differentiate the parts of the work
that are well understood, and therefore less risky, from the parts where you
are clueless. Often, what separates an impossible project from a possible one
is isolating the most difficult work early, so it receives the attention and effort
required to deal with it. Risk assessment techniques are central to gaining an
understanding of what is most uncertain about a project, and they are the
foundation for managing risk. The focus of this chapter is analysis and
prioritization of the specific project risks listed in your project risk register.
Analysis of overall project risk will be addressed in Chapter 9.
Qualitative and Quantitative Risk Analysis
Risk analysis strives for deeper understanding of potential project
problems. Techniques for doing this are based on either qualitative
information (used to prioritize risks) or quantitative risk estimates (used to
measure them).
Uses for Qualitative Assessment
Qualitative techniques are easier to apply and generally require less
effort. Qualitative assessment considers ranges for probability and categories
of impact when analyzing loss-times-likelihood. Qualitative methods are not
precise, but they do provide a way to incorporate consideration of risk
consequences that cannot be easily measured. Qualitative risk assessment is
generally the basis for rank-ordering risks, allowing you to select the most
significant ones to manage using the techniques discussed in Chapter 8.
Uses for Quantitative Assessment
Quantitative methods strive for greater precision, and they can reveal
more about each risk. These methods require more work, but quantitative
analysis also provides insight into the absolute magnitude of risk impacts and
supplies the data necessary for sizing schedule and/or budget reserves on
risky projects.
Precision and Bias
Although the dichotomy between quantitative and qualitative risk
analysis is explicit in the PMBOK® Guide, analysis methods fall into a
continuum of possibilities. They range from qualitative assessment using a
small number of categories, through methods that use progressively more and
finer distinctions, to the extreme of determining specific quantitative data for
each risk. If the primary goal of risk analysis is to prioritize risks to determine
which ones are important enough to warrant further analysis and response,
the easiest qualitative assessment methods generally suffice. If you need to
assess project-level risk with maximum precision, then you will also need to
employ quantitative assessment methods (although the nature of the data
available—much of it based on guesswork—will generally put a rather
modest limit on your accuracy).
Accurately estimating and assessing risks is challenging even for the
most experienced project professionals. Difficulty with the precise
assessment of risks suffers from all the factors that make any project
estimating difficult: lack of relevant experience, a paucity of useful data, and
bias. In addition to optimism bias, which results in underestimation for both
probability and impact assessment, other biases are also in play, including
recency bias (“That hasn’t happened lately”) and judgment bias (because
people tend to cherry-pick the data they pay attention to).
Bias is a significant issue for project risk management and may even
result in failure to list significant risks to which we choose to be blind (such
as the black swans that are assumed will never happen). Effective risk
management depends on understanding these and other sources of bias, and
on working to overcome them throughout the risk identification and
assessment processes.
Probability and Impact
Both qualitative and quantitative assessment methods have the same
foundation. Both rest on the simple formula discussed in Chapter 1: loss
multiplied by likelihood. The realm of likelihood is statistics and probability.
Loss in projects is measured in impact: time, money, and other project
factors, including some that may be difficult to quantify. These two
parameters characterize risk, either qualitatively using categories or
quantitatively using estimates.
Risk Probability
All project risks involve uncertainty. The likelihood, or probability, of
any specific risk will always be somewhere between zero (occurrence
impossible) and one (occurrence inevitable). Qualitative risk assessment
methods divide the choices into probability ranges and require project team
members to assign each risk to one of the defined ranges. Quantitative risk
assessment assigns each risk a specific fraction between zero and one (or
between 0 and 100 percent).
Risk probability must always fall between zero and one, but picking a
credible value is hard. There are only three ways to estimate probabilities. For
some situations, such as flipping coins and throwing dice, you can construct a
mathematical model and calculate an expected probability. In other
situations, a simple model does not exist, but many historical events may be
similar. In these cases statistical analysis of empirical data may be used to
calculate probabilities. Actuaries estimate probabilities this way for the
insurance industry. In all other cases, probability estimates are based on
guesses. For complex events that seldom or perhaps never occur, you can
neither calculate nor measure to determine a probability. Ideas such as
referencing analogous situations, scenario analysis, and gut feel come into
play. For most project risks, probabilities tend to be guesses based on not
much objective data, so they are inexact.
In fact, assessing likelihood in general is problematic because of a
number of issues. One of the most fundamental is that the human brain is not
equipped to deal well with the concept of probabilities. Part of this comes
through in our optimism bias. We tend to see desirable outcomes as much
more likely than they actually are. (“This lottery ticket is sure to win.”)
Conversely, we estimate undesirable outcomes to be far less likely. (“That
risk could never happen.”) Another bias concerns recency, a tendency to base
predictions on only the immediate past. Instead of thinking in terms of
randomness and probability, we tend to discount both risks that have not
happened lately (“We are on a ‘lucky streak’ that will continue.”) and risks
that have (“Well, we had that unlikely problem on the last project, so it can’t
occur again for a while.”) Randomness does not follow patterns and rules.
The likelihood of flipping heads is always 50 percent, even after a run of
heads (or tails). Judgment bias is also a large impediment, particularly when
dealing with small percentages. It is common to think in terms of likely and
unlikely, without much consideration of degree. The inability to think clearly
about relative probability leads to lumping risks together that have
significantly different likelihoods. Effective probability assessment requires
us to manage our biases and to remain wary of them.
Assessing probability with qualitative methods requires less precision
because it does not require specific numerical values. Qualitative assessment
divides the complete range of possibilities into two or more nonoverlapping
ranges of probability. The simplest qualitative assessment uses two ranges:
more likely than not (0.5 to 1) and less likely than not (0 to 0.4999). Project
teams may be able to pick one of these choices for each risk with little
difficulty, but the coarse granularity of the analysis makes prioritizing
significant risks for further attention fairly arbitrary.
A more common method for qualitative assessment uses three ranges,
assigning a value of high, medium, or low to each risk. The definitions for
these categories vary, but these are typical:
• High: 50 percent or higher (likely)
• Medium: Between 10 and 50 percent (unlikely)
• Low: 10 percent or lower (very unlikely)
These three levels of probability are generally easy to determine for
project risks without much debate, and the resulting characterization of risk
allows you to discriminate adequately between likely and unlikely risks. It
can help people who are managing their biases (and muddled thinking about
chance) to align these categories with events for which people have
experience. High probability is similar to the flipping of a two-sided coin
(heads or tails). Medium probability is about the same as rolling a specific
number using a six-sided die (or perhaps having your birthday fall on a
Saturday in a given year). Low probability might be likened to rolling snake
eyes (a pair of ones) or box cars (a pair of sixes) using a pair of six-sided
dice. Whatever you can do to help people better associate risks with realistic
probability range will improve your analysis.
Qualitative probability assessment may also use four, five, or even
more categories. These methods tend to use linear ranges for the
probabilities: quartiles for four, quintiles for five, and so forth. (The names
assigned to five categories are typically: very high, high, moderate, low, and
very low.) The more ranges there are, the better the characterization of risk, at
least in theory. More ranges make it harder for the project team to achieve
consensus, though, and people may perceive little meaningful difference
between some of the intermediate categories. The apparent additional
precision that comes from more categories may mask bias and imply
unwarranted accuracy.
The logical extension of this continues through increasingly
quantitative assessments using integer percentages (100 categories) to
continuous estimates allowing fractional percentages. Although it may look
like the accuracy is improved, the process for determining numerical
probabilities can require a lot of overhead, and you must remember that most
probability estimates are at least partly based on guesses, with little or no
objective data. The illusion of precision can be a source of risk in itself;
making subjective information look objective can result in unjustified
confidence and questionable decisions.
Depending on the project, the quality of available data, and the planned
uses of the risk data, there are a number of ways to estimate probability. For
qualitative assessment methods using five or fewer categories, experience,
polling, interviewing, and rough analysis of the risk situation may be
sufficient. Describing events that people have some experience with (games
of chance using dice or playing cards can be effective) and aligning them
with probability categories may enhance the quality of your assessments. For
cases where people are unsure, probe with worst-case questions (“Could this
sort of thing happen once a year?”) and select the category based on what
people consider the upper range of what is possible.
For quantitative methods, a solid base of historical performance data is
always the best data source, as it provides an empirical foundation for
probability assessment and is less subject to bias. Estimating probabilities
using methods such as the Delphi technique (mentioned in Chapter 4) or
computer modeling (discussed later in this chapter) and employing
knowledgeable experts (who may have access to more data than you do) can
also potentially improve the quality of quantitative probabilities.
Measurement-based probabilities, when available, serve an additional
purpose in project risk management: trend analysis. In hardware projects,
statistics for component failure support decisions to retain or replace
suppliers for future projects. If custom circuit boards, specialized integrated
circuits, or other hardware components are routinely required on projects,
quarter-by-quarter or year-by-year data across a number of projects will
provide the fraction of components that are not accepted, and provide data on
whether process changes are warranted to improve the yields and success
rates. Managing risk over the long term relies heavily on metrics, discussed
in Chapter 9.
Risk Impact
The loss, or project impact, for an individual risk is more complicated
to define than the probability. Although the minimum is again zero, both the
units and the maximum value for impact vary with the risk. The impact of a
given risk may be relatively easy to ascertain and have a single, predictable
value, or it may be best expressed as a distribution or histogram of
possibilities. Qualitative risk assessment methods for impact again divide the
choices into ranges. The project team assigns each risk to one of the ranges,
based on the magnitude of the risk consequences. For quantitative risk
assessment, impact may be estimated using units such as days of project slip,
money, or some other suitable measure.
Qualitative impact assessment assigns each risk to one of two or more
nonoverlapping options that include all the possible risk consequences. A
two-option version uses categories such as low severity and high severity,
with suitable definitions of these terms related to how the risk affects the
project objective. As with probability analysis, the usefulness of only two
categories is limited.
There will be better discrimination using three ranges, where each risk
is assigned a value of high, medium, or low. There are many ways to define
the three categories, but one useful technique relates each to the project
objective and plan as follows:
• High: Project objective is at risk (mandatory change to one or more
of scope, schedule, or resources).
• Medium: Project objectives can be met, but significant replanning
will be required.
• Low: No major plan changes; the risk is an inconvenience, or it will
be handled through overtime or other minor adjustments.
These three levels of project impact are not difficult to assess for most
risks and provide useful data for sequencing risks according to severity.
Other methods use additional categories, and some partition impact
further into specific project factors, related to schedule, cost, and scope or
other parameters. Impact measurement is open-ended; there is no theoretical
maximum for any of these factors (in a literally impossible project, both time
and cost may be considered infinite). Because the scale is not bounded, the
categories used for impact are often geometric, with small ranges at the low
end and progressively larger ranges for the upper categories. For an impact
assessment using five categories, definitions might be:
• Very low: Less than 1 percent impact on scope, schedule, cost, or
quality
• Low: Less than 5 percent impact on scope, schedule, cost, or quality
• Moderate: Less than 10 percent impact on scope, schedule, cost, or
quality
• High: Less than 20 percent impact on scope, schedule, cost, or
quality
• Very high: 20 percent or more impact on scope, schedule, cost, or
quality
Risks are assigned to one of these categories based on the most
significant predicted variance, so a risk that represents a 10 percent schedule
slip and negligible change to other project parameters would be categorized
as “moderate.” As with probability assessment, the more ranges there are, the
better the characterization of risk, but the harder it will be to achieve project
team consensus.
Similar assessment may also be devised to look at specific kinds of risk
separately, such as cost risk or schedule risk, to determine which are most
likely to affect the highest project priorities.
The most precise assessment of impact requires quantitative estimates
for each risk. Few risks relate only to a single aspect of the project, so there
may be a collection of measurement estimates, generally including at least
cost and schedule impact. Cost is conceptually the simplest because it is
unambiguously measured in dollars, yen, euros, or some other easily
described unit, and any adverse variance will directly affect the project
budget. Schedule impact is not as simple because not every activity duration
slippage will necessarily represent an impact to the schedule. Activities off
the critical path will generate schedule impact only for adverse variances that
exceed the available float.
As with other project estimating, determining cost and schedule
variances attributable to risks is neither easy nor necessarily accurate.
Quantitative assessments of risk impact may look precise, but the accuracy of
such estimates is often questionable, due to optimism and other bias.
Optimism bias leads to general underestimation of risk impact, similar to the
effect it has on project estimates in general. In particular, as with probability,
most people tend to align their expectations with their preferences
(overestimating beneficial outcomes and discounting adverse ones), so the
underestimation for potential damage from risks may be even greater than for
project estimates in general. Other sources of bias can also lead to
underestimation of impact, including anchoring, availability, and
representativeness—all of which tend to result in estimates that are based on
inappropriate or irrelevant data.
The discussion of risk impact so far has focused on measurable project
information; even the qualitative categories tend to be based on numerical
ranges or percentage change. Limiting impact assessment to such factors
overlooks risk impact that may be difficult to quantify. For some risks such
an approach may ignore factors that may well be the most significant.
Because the impact resulting from these other factors can be hard to
determine with precision, it is generally ignored or assumed to be
insignificant in project risk assessment. Categories for these more
“qualitative” types of impact, listed in sequence from the most narrow
perspective to the broadest, include:
• Personal consequences
• Career penalties
• Loss of team productivity
• Team discord
• Organizational impact
• Business and financial consequences
Measurable consequences for some of these factors may be roughly
quantified, at least in the short term. The last two types of impact, which are
the most severe, can probably be estimated by someone in your organization,
although probably not by you or your team. And even estimates made by
others who have a wider perspective may vastly underestimate the true long-
term overall effects.
In all of these cases, it is at least difficult to include the possible
consequences of these factors into your risk analysis in a way that permits
straightforward assessment. Despite the challenges, it is worthwhile to
carefully consider and describe the potential impact from these factors,
because the true overall impact for many project risks may well be dominated
by them. More detail follows, along with some suggestions about how to use
these factors when prioritizing your risks. Although not exhaustive, the lists
that follow should provide guidance and a starting point.
Many risks faced by projects include potential personal consequences
that can be quite severe, ranging from inconveniences and aggravations to
major impositions. These include:
• Marital problems, divorce, and personal relationship troubles
• Cancelled vacations
• Missed family activities
• Excessive unpaid overtime
• Fatigue and exhaustion
• Deterioration of health
• Exposure to unsafe conditions, poisonous or volatile chemicals,
dangerous environments, or undesirable modes of travel
• Loss of face, embarrassment, lowered prestige, bruised egos, and
reduced self-esteem
• Required apologies and groveling
Major project difficulties can lead to a variety of career penalties, and
personal reputations may suffer, leading to:
• Job loss
• Lowered job security
• A bad performance appraisal
• Demotion
• No prospect for promotion
Both during and following a major risk, team members may work less
efficiently. Loss of team productivity may result from:
• More meetings
• Burnout
• Increased communication overhead, especially if across multiple time
zones
• Added stress, tension, pressure
• More errors, inaccuracies
• Chaos, confusion
• Rework
• Additional reporting, reviews, interruptions
• Individuals assuming responsibility for work assigned to others
• Exhaustion of project reserves, contingency
Even if productivity is unaffected, team discord may rise. The success
of a project relies on maintaining good teamwork among your project
contributors. When things start to unravel, the consequences can include:
• Conflict, hostility, resentment, and short tempers
• Lack of cooperation and strained relationships
• Low morale
• Frustration, disappointment, and discouragement
• Demoralization and disgruntlement
Project risk consequences may lead to organizational impact that
extends well beyond your current project’s prospects for success. Some of
these include:
• Delayed concurrent projects
• Late starts for following projects
• Resignations and staff turnover
• Loss of sponsor (and stakeholder) confidence, trust, and goodwill
• Questioning of methods and processes
• Ruined team reputations
• Micromanagement and mistrust by supervisors
• Required escalations and expediting of work
• The need to get lawyers involved
Finally, some risks will have significant business and financial
consequences. Although these effects may well be estimated and quantified,
the true impact is generally measurable only after—and often well after—the
project is closed. Some examples are:
• Loss of business to competitors and competitive disadvantage
• Bad press, poor public relations, and loss of organizational reputation
• Customer dissatisfaction and unhappy clients
• Loss of future business and lowered revenues
• Reduced margins and profits
• Loss of client trust and confidence
• Complications resulting from failure to meet legal, regulatory,
industry standards, or other compliance requirements
• Damaged partner relationships
• Reduced performance of the project deliverable
• Compromised quality or reliability
• Rushed, inadequate testing
• Missed windows of opportunity
• Continued cost of obsolete systems or facilities
• Inefficient, unpleasant manual workarounds
• Service outages and missed service-level agreements
• Bankruptcy and business failure (if the project is big enough)
Although for some risks the short-term quantifiable impact on your
project’s schedule or budget may be modest, the overall consequences,
particularly some of the items on the last two lists, will have major impact on
the organization. Even though these potential impacts may be primarily
qualitative, it is desirable to integrate them into your risk assessment and
prioritization. One way to do this is to apply impact criteria such as in the
five-level assessment demonstrated in the following table.
Risk
Impact
Criteria
Very Low Any impact that can be handled within a single status cycle and
would likely not be visible outside the project team
Low Any impact that can be dealt with within the project team and
having no anticipated long-term effects
Moderate Any impact that would result in significant project replanning or
that could lead to a noticeable and inconvenient effect for the
organization
High Any impact that would threaten the project’s objective (failure to
meet one or more of the project’s triple constraint parameters) or
that might lead to significant, measurable longer-term business
impact for the organization
Very High A project “showstopper” that would result in cancellation, or a risk
that has potential for overall long-term business impact in excess
of the project’s budget
Analysis based on these criteria remains subjective, but it provides a
practical way to assess the relative importance of project risks—even risks
where measurable impact is difficult to pin down.
Qualitative impact assessment using three to five categories is usually
relatively easy, and it is sufficient for prioritizing risks based on severity.
Techniques such as polling, interviewing, team discussion, and reviews of
planning data are effective for assigning risks to impact categories. As with
probability assessment for each risk, the best foundation for quantitative
estimates of impact is history, along with techniques such as Delphi,
computer modeling, and consulting peers and experts.
For quantitative assessments of impact in situations that frequently
repeat, statistics may be available. A good way to provide credible
quantitative impact data is to select the mean of the distribution for initial
estimates of duration or cost and use the difference between that estimate and
the measured “90 percent” point. This principle is the basis for Program
Evaluation and Review Technique (PERT) analysis. The PERT estimating
techniques were discussed in Chapters 4 and 5. Other aspects of PERT and
related techniques for dealing with project uncertainty are covered later in
this chapter and in Chapter 9.
Qualitative Risk Assessment
The minimum requirement for risk assessment is a sequenced list of
risks, rank-ordered by perceived severity. You can sort the listed risks from
most to least significant using your assessment of loss-times-likelihood. If
your list of risks is short enough, you can quickly arrange the list based on a
few passes of pair-wise comparisons, switching any adjacent risks where the
more severe of the two is lower on the list. The most serious risks will bubble
to the top, and the more trivial ones will sink to the bottom. This technique is
generally done by a single individual.
A similar technique, related to Delphi, combines data from lists sorted
individually by each member of a team. The risks on each list are assigned a
score equal to their position on the list, and all the scores for each risk are
summed. The risk with the lowest total score heads the composite list, and the
rest of the list is sorted based on the aggregate scores. If there are significant
variances in some of the lists, further discussion and an additional iteration
may lead to better consensus. The resulting list will be more objective than a
sequence created by an individual, and it represents the whole team.
Although these sorting techniques result in an ordered risk list, such a
list shows only relative risk severity, without indication of the project
exposure that each risk represents.
Risk Assessment Tables
Qualitative risk assessment based on categorization of both probability
and impact provides greater insight into the absolute risk severity. A risk
assessment table or spreadsheet where risks are listed with category
assignments for both probability and impact, as in Figure 7-1, is one
approach for this. (This data should also be part of your project risk register.)
Figure 7-1. Risk Assessment Table
After listing each risk, assign a qualitative rating (such as
high/moderate/low) for both probability and impact. Consider all potential
impact, not just that which is easily measured, and be skeptical about
probabilities. Fill in the last column, “Overall Risk,” based on loss-times-
likelihood. Although any number of rating categories may be used, the
quickest method that results in a meaningful sort uses three categories
(defined as in the earlier discussions of probability and impact) and assigns
either combinations of the categories or weights such as 1, 3, and 9 for low,
moderate, and high, respectively. An example of a sorted qualitative
assessment for five risks might look like Figure 7-2.
Figure 7-2. Qualitative Risk Assessment Example
For the data in the last column, categories may be combined (as
shown), factors multiplied (the numbers would be 27, 9, 9, 3, and 1), or
“stoplight” icons displayed to indicate risk (red for high, yellow for moderate,
and green for low). From a table such as in Figure 7-2, you can select risks
above a certain level, such as moderate, for further attention.
Risk Assessment Matrices
An alternative method for qualitative risk assessment involves placing
risks on a two-dimensional matrix, where the rows and columns represent the
categories of probability and impact. The matrices may be two by two, three
by three, or larger. Risk matrices are generally square, but they may have
different numbers of categories for probability and impact. Figure 7-3 is a
typical example of a five-by-five matrix.
Figure 7-3. Risk Assessment Matrix Probability
Such matrices are often displayed in color, with green cells in the lower
left, yellow ones in the middle, and red cells in the upper right. Versions like
this are also referred to as heat maps. The farther up and to the right a risk is
assessed to be, the higher its overall assessment. Risks are selected for
management based on whether the cell in the matrix represents a risk above
some predetermined level of severity. An organization’s risk tolerance (or
appetite) is generally bounded by one of the sets of lighter gray cells in the
matrix. Two-dimensional assessment matrices can be useful for displaying
modest numbers of risks, but they do have some shortcomings. One is the
implied equivalence of risks along the central diagonal connecting low-
probability, high-impact risks and high-probability, low-impact risks. In fact,
there is a big difference between frequently encountered risks having trivial
impact and low-probability showstopper risks. The first may warrant little or
no consideration, but you can ignore the latter only at your peril. A second
issue with the heat map is the quality of the data in it. Especially for five-by-
five matrices, placement within the middle categories for both probability and
impact may imply precision exceeding what is reasonable for most risks.
A matrix such as in Figure 7-3 is usually applied to the analysis of risks
having negative consequences (threats). This type of diagram may also be
used to assess uncertain project opportunities. Some of the opportunities
discussed in Chapter 6 relate to events that might or might not happen. For
these opportunities, assessment is based on likelihood and gain (instead of
loss). An example of this type of opportunity might be buying something
needed by the project that occasionally goes on sale. Once the opportunity to
purchase the item at a reduced price is recognized, managing this “risk”
might involve delaying the purchase to potentially take advantage of a better
price. For most projects, there are far fewer uncertain opportunities than risks
with adverse consequences.
For analysis of uncertain opportunities, the definition of probability is
unchanged. The impact is also similar, but for opportunities the categories
relate to beneficial variances, not harmful ones. Using the same matrix, you
can assess potentially positive events to determine those that deserve further
attention—again by focusing near the corner representing the combination of
highest impact and probability. Another variant on this matrix technique joins
together the threat matrix and a mirror-image opportunity matrix into a single
matrix (for this case, five cells high and ten cells wide). You find the highest
impact in the middle using the combined matrix, so the uncertain events most
deserving of your attention will be those in the cells near the top and center of
the combined matrix.
Assessing Options
Standard project network charts do not generally permit the use of
conditional branching. Because it is not uncommon to have places in a
project schedule where one of several possible alternatives, outcomes, or
decisions will be chosen, you need some method for analyzing the situation.
One qualitative way around this limitation is to construct a baseline plan
using the assumption that seems most likely and deal with the other possible
outcomes as risks. If it is not possible to determine which outcome may be
most likely, a prudent risk manager will usually select the one with the
longest duration (or highest cost) to include in the project baseline, but any
one option may be selected. Assessing the risk associated with choosing
incorrectly involves determining the estimated impact to the project when
something different occurs, weighted by the probability of this happening
(loss-times-likelihood once again). List all significant workflow alternatives
in your risk register and assess them with your other project risks.
Data Quality Assessment
Not all risks are equally well understood. Some risks happen regularly,
and data concerning them is plentiful. Other project risks arise from work that
is unique compared with past projects. Assessment of probability and impact
for these risks tends to be based on inadequate information, so it’s common
to underestimate overall risk.
Even with qualitative risk assessment, these poorly understood risks
can be identified and singled out for special treatment. For each assessment,
consider the quality, reliability, and integrity of the data used to categorize
probability and impact. Where the information seems weak, seek out experts
or other sources of better information. You can also err on the side of caution
and raise your probability and impact estimates to elevate the visibility of the
risk.
Other Impact Dimensions for Qualitative Assessment
Although a risk that has high probability and impact will require your
attention, those that relate to work well into the future may not need it
immediately. Other aspects of risk that may enter into qualitative assessment
are urgency and surprise. The impact of even a modest risk can cause harm to
your project overall if it happens early and affects the perception of your
competence or the teamwork of your contributors. Risks tend to cascade, so
early problems may result in more trouble later in the project. If a risk relates
to work that is imminent, factor this into your impact assessment, increasing
impact estimates where justified.
Similarly, some risks are relatively easy to see coming. Other risks,
such as the examples from the PERIL database concerning late deliverables
from an outsourcing partner, are hard to detect in advance. Consider the
trigger events for each risk when estimating impact, and increase it for risks
where the harm may be amplified by the surprise factor.
Risks Requiring Further Attention
The main objective of qualitative risk assessment is to identify the
major risks by prioritizing the known project risks and rank-ordering them
from most significant to least. The sequenced list may be assembled using
any of the methods described, but the use of three categories (low, moderate,
and high) for both probability and impact generally provides a good balance
of adequate analysis and minimal effort and debate. However you analyze
and sort the list, you need to partition the risks that deserve further
consideration from risks that seem too minor to warrant a planned response.
It is good practice to prioritize the project risks on your risk register
based on severity. The first several risks on your prioritized risk register
nearly always require attention, but the question of how far down the list to
go is not necessarily simple. One idea is to read down the list, focusing on the
consequences and the likelihood of each risk until you reach the first one that
won’t keep you awake at night. A gut feel test such as this is not a bad way to
initially set the boundary for your sorted risk register. A similar idea using
consensus has team members individually selecting the cutoff point, and then
discussing as a team where the line should be, based on individual and group
experiences. You can also set an absolute limit, such as moderate overall risk,
or you can use a diagonal stair-step boundary from the upper left to the lower
right in a matrix. Whatever method you choose, review each of the risks that
are not selected to ensure that there are none below the line that warrant a
response, carefully considering any risks that could result in severe
consequences.
Following this examination, you are ready to prepare an abridged list
of risks for potential further quantitative analysis and management.
Quantitative Risk Assessment
As stated earlier in the chapter, quantitative risk assessment involves
more effort than qualitative techniques, so qualitative methods are generally
applied first for risk sorting and selection. This is not absolutely necessary,
though, because qualitative methods using tables and matrices have
quantitative analogues that can also be used to prioritize your risk register.
Additional techniques for quantitative project risk assessment include
sensitivity analysis, statistical methods, risk decision trees, and computer
simulations.
Quantitative Risk Assessment Tables
For quantitative assessment, tables similar to Figures 7-1 and 7-2 may
be used by replacing the categories for probability and impact with absolute
numerical estimates. For each risk, estimate the impact in cost, effort, time
(but only time in excess of any available scheduling flexibility), or other
factors, and then assess overall risk as the product of the impact estimates and
the selected probability. One drawback of using this method for sequencing
risks is that for some risks, it may be difficult to develop precise consensus
for both the impact and probability. A second, more serious issue is that
impact may be measured in more than one way (as examples, time and
money), making it difficult to determine a single uniform quantitative
assessment of overall risk.
Although you could certainly list impacts of various kinds, weighted
using the estimated probabilities, you may find it difficult to sort based on
this data. This can be overcome by selecting one type of impact, such as time,
and converting the impact of other kinds into an equivalent project duration
slip (as was done for the PERIL database). You could also develop several
tables, one for cost, another for schedule, and others for scope, quality,
safety, or any other type of impact for which you can develop meaningful
numerical estimates. You can then consistently sort each table and select risks
from each for further attention. This multiple-table process also requires you
to do a final check of unselected risks to detect any that are significant only
when all potential consequences are considered in aggregate.
Two-Dimensional Risk Graphs for Quantitative Analysis
A qualitative matrix such as the one in Figure 7-3 may be converted to
a quantitative tool by replacing the row and column labels with perpendicular
axes. Probability can be plotted on the vertical axis from 0 to 100 percent,
and impact may be plotted on the horizontal axis, from zero to some upper
limit (perhaps using an exponential scale). Each risk identified represents a
point in the two-dimensional space, and risks requiring further attention will
again be found up and to the right, beyond a boundary defined as risky. As
with tables, this method is most useful when all risks can be normalized to
some meaningful single measure of impact such as cost or time.
Alternatively, you may employ several graphs, each based on a different
impact measure.
A variation on this concept plots risks on a pair of axes that represent
estimated project cost and project schedule variances, representing each risk
using a bubble that is sized proportionately with estimated probability instead
of a single point. Because impact is higher for bubbles farther from the
origin, several boundaries are defined for the graph. A diagonal close to the
origin defines significant risk for the large (very likely) bubbles, and other
diagonals farther out define significant exposure for the smaller bubbles. In
Figure 7-4, several risks are clearly significant. Risk F has the highest total
impact, and Risk E is not far behind. Others would be selected based on their
positions relative to the boundaries of the graph.
Figure 7-4. Risk Assessment Graph 15%
Sensitivity Analysis
The damage actually caused by a given risk involves more than just a
simple assessment of impact. Schedule risks not affecting resources are
significant only when the estimated slippage exceeds any available float. For
simple projects, a quick inspection of the plan using the risk list will
distinguish the risks that are most likely to cause substantial damage. For
more complex networks of activities, using a copy of the project database that
has been entered into a scheduling tool provides a fast way to detect risks
(and combinations of risks) that are most likely to result in project delay.
What-if schedule analysis uses worst-case estimates to investigate the overall
project impact for each risk. By sequentially entering your worst-case
durations and then backing them out, you can see the quantitative schedule
sensitivity to each schedule risk.
Unlike activity slippage, all adverse cost variances contribute to budget
overruns. However, for some projects not all cost impact is accounted for in
the same way. If a risk results in an out-of-pocket expense for the project,
then it impacts the budget directly. If the cost impact involves a capital
purchase, then the project impact may be only a portion of the actual cost,
and in some cases the entire expense may be accounted for elsewhere. An
increase in overhead cost, such as a conference room commandeered as a war
room for a troubled project, is seldom charged back to the project directly.
Increased costs for routine communications, duplication, shipping, and other
services are frequently not borne directly by individual projects. Travel costs
may also not be allocated directly. Although it is generally true that all cost
and other resource impact is proportionate to the magnitude of the variance, it
may be worthwhile to segregate potential direct cost variances from any that
are indirect.
Decision Trees
When only a small number of options or potential outcomes are
possible, decision trees can also be useful for quantitative risk assessment.
Decision tree analysis is a quantitative version of the qualitative assessment
process for assessing options discussed earlier in this chapter. Decision trees
are generally used to evaluate alternatives prior to selecting one of them to
execute. The concept is applied to risk analysis in a project by using the
weights and estimates to ascertain potential impact for specific alternatives.
Whenever there are points in the project where several options are
possible, each can be planned and assigned a probability (the sum for all
options totaling 100 percent). As with PERT, an expected estimate for either
duration or cost may be derived by weighting the estimates for each option
and summing these figures to get a blended result. Based on the data in
Figure 7-5, a project plan containing a generic activity (that might be any of
the three options) with an estimate of 16 days would result in a more realistic
plan than simply using the 12-day estimate of the most likely option. The
schedule exposure of the risk situation here may be estimated by noting the
maximum adverse variance (an additional four days, if the activity is
schedule critical) and associating this with an expected probability of 35
percent. (An alternative treatment would be to assume the worst and schedule
20 days, treating the other possibilities as opportunities to be managed.)
Figure 7-5. Decision Tree for Duration
Decision analysis may also be used to guide project choices that have
varying costs. You can use decision trees to evaluate expected monetary
value for alternatives to explore expected costs and potential cost variances.
Decision analysis can help in minimizing project risks whenever there are
several alternatives, such as either upgrading existing equipment or
purchasing new hardware. The analysis of costs in Figure 7-6 argues for
replacement to minimize cost variance (none, instead of the $20,000 to
$120,000 associated with upgrade) and for upgrade to minimize the expected
cost. As is usual on projects, there is a trade-off between minimizing project
parameters and minimizing risk: You must decide which is more important
and balance the decisions with your eyes open.
Figure 7-6. Decision Tree for Cost
Simulation and Modeling
Decision trees are useful for situations where you have discrete
estimates. In more complex cases, options may be modeled or simulated
using Monte Carlo or other computer-based techniques. If the range of
possibilities for an activity’s duration or cost are assumed to be a statistical
distribution, the standard deviation (or variance) of the distribution is a
measure of risk. The larger the range selected for the distribution, the higher
the risk is for that activity. For single activities, modeling with a computer is
rarely necessary, but when several activities (or all the project’s activities) are
considered together, computer-based simulations are useful and effective.
Use of both software tools and manual approximations for this are key topics
in Chapter 9.
PERT Methodology
The term “PERT,” discussed earlier, has assumed a number of
meanings for project management. The most common usage, which actually
has little to do with PERT (Program Evaluation and Review Technique)
methodology, is associated with the graphical network of activities used for
project planning, often referred to as a PERT chart. Logical project networks
are used for PERT analysis, but PERT methodology went beyond the
deterministic, single-point estimates of duration to which PERT charts are
generally limited. A second, slightly less common meaning for PERT relates
to three-point estimating (discussed in earlier chapters), but the original
purpose of PERT methodology was actually much broader.
The principal reason PERT was originally developed in the late 1950s
was to help the U.S. military quantitatively manage risk for large defense
projects. PERT was used on the development of the Polaris missile systems,
on the NASA manned space projects, including the Apollo moon missions,
and on countless other government-funded projects. The motivation behind
all of this was the observation that as programs became larger, they were
more likely to be late and to have significant cost overruns. PERT was
created to provide a better basis for setting expectations on these massive,
expensive endeavors.
PERT is a specific example of quantitative risk analysis, and it can be
applied to both schedule exposures (PERT Time, discussed in Chapter 4) and
budget exposures (PERT Cost, discussed in Chapter 5). PERT is based on
some statistical assumptions about the project plan, requiring both estimates
of likely outcomes (which are always generated) and estimates of the
uncertainty for these outcomes (which was new). PERT techniques may be
used to analyze all project activities or only those that represent high
perceived risk. In either case, the purpose of PERT was to provide data on
overall project risk, for schedule, cost, or both. PERT concepts for range
estimates are useful in gathering risk information about project activities,
particularly concerning the pessimistic (or worst-case) estimates. PERT,
along with other methods such as computer-based Monte Carlo analysis,
depends on the concept of three-point activity estimate data to analyze risk
for the project as a whole. Assessing overall project risk using PERT
methodology and other techniques will be explored in detail in Chapter 9.
Statistical Concepts and Probability Distributions
Three-point range estimates for project activities started with PERT
methodology. Nearly all project analysis prior to the 1950s was based
primarily on single-point, deterministic estimates. PERT methodology
assumed a continuum of possibilities. It used three-point estimates to define a
Beta distribution, a bell-shaped probability density function that could skew
to the right or left. Figure 7-7 is an example of a Beta distribution fitted to
three estimates for activity duration. This example uses the traditional 1
percent tails to bound the range of possibilities, but PERT analysis can also
be based on 5 or 10 percent tails. The Beta distribution was used initially
because it was flexible enough to accommodate different “shapes,” was not
hard to understand (and draw), and was simple enough to be used for the
relatively primitive computer analysis available for projects at the time.
Figure 7-7. Typical Beta Distribution
Probability distribution functions, or even discrete data values defined
by a histogram, may better describe the range of potential impact for a given
risk. Some additional distribution types commonly used today include:
• Triangular: A linear rise from optimistic estimate to the most likely,
followed by a linear decline to the pessimistic estimate
• Normal: The Gaussian bell-shaped curve, with the most likely and
expected values both at the center of a symmetric distribution
• Uniform: All values in the range are assumed equally likely, also
with the most likely and expected values both at the midpoint
Many other more exotic statistical distributions are available for
modeling, along with limitless possible histograms. Triangular (a skewed
example is in Figure 7-8), uniform (Figure 7-9), and other bounded types of
distributions are “closed,” in that all expected data points are confined within
defined numerical bounds. Beta (Figure 7-7), normal (Figure 7-10), and other
similar distributions are “open,” with no theoretical upper (or lower) limit on
possible values.
Figure 7-8. Triangular Distribution
Figure 7-9. Uniform Distribution
Figure 7-10. Normal, Gaussian Distribution
The precise shape of the distribution you choose, and even whether it is
bounded or not, will generally have only a small effect on the two parameters
that matter the most for risk analysis: the mean and the standard deviation of
the distribution. Assessment of risk is based primarily on these two
parameters, and they vary little, among the distribution types available. In
addition, although it is theoretically possible to carry out a detailed risk
analysis mathematically, it is impractical. Project risk analysis using
probability distributions is most commonly done by computer simulation or
by rough manual methods that approximate the results. From a practical
standpoint, the choice of a specific distribution for each activity has only a
minimal effect on the quantitative assessment of risk for activities. For
project risk analysis, the choice of a particular density function for activity
data is not terribly crucial.
To illustrate this, Figures 7-8, 7-9, and 7-10 show expected duration
estimates calculated using the weighted average PERT formula discussed in
Chapter 4 with limits of 15 and 21 days. The expected durations, te, vary
somewhat between the distributions, but for quantitative risk assessment you
would select some value above the mean. A 90 percent point is not
uncommon for this, and for each of the distributions in the examples, all will
be quite close to the upper (tp) estimate. Because tp is 21 days, the 90 percent
point for each of these distributions will be roughly 20 days (rounded off to
the nearest whole day), regardless of the distribution selected. There are ways
to calculate all this with very high precision, displaying many (seemingly)
significant digits in the results. Considering the precision and expected
accuracy of the input data, though, the results are at best accurate only to the
nearest whole day. Arguments over the “best” distribution to use and endless
fretting over how to proceed are a poor investment of your time. Assessment
of uncertainty will rely on the estimated variance for the chosen distribution,
which for all these examples will be similar because the ranges defined are
the same.
As you can see, almost any reasonable choice of distribution will result
in comparable results for activity risk analysis, so use the option that you find
most appropriate and easiest to work with.
At the project level, where uncertainty data for all the work is
combined, the distributions chosen for specific activities become even less
relevant. The more uncertain activities that are modeled for a project, the
more the overall project-level cost and duration assessment tends to
approximate a normal, bell-shaped curve. Chapter 9, on project-level risk
assessment, explores this topic in some detail.
Setting Estimate Ranges
Even though it generally matters little what distribution you select for
your range estimates, the error bars you define matter a great deal. Setting the
range to be too narrow (which is a common bias) will materially diminish the
quantitative perception of risk. Risk, assessed using PERT or similar
techniques, is based on the total anticipated range of possible outcomes,
which varies directly with the estimation uncertainty.
Arriving at credible upper and lower limits for cost and duration
estimates is difficult. One way to develop this data is through further analysis
of potential root causes of each activity that has substantial perceived risk. As
discussed in Chapter 4, reviewing worst-case scenarios is a powerful tool for
estimating the upper limits. Be realistic about potential consequences; it is
human nature to minimize or overlook the potential impact of risks.
When sufficient historical information is available, the limits (and
possibly even the shape) of the distribution may be inferred from the data.
Discussions and interviews with experts, project stakeholders, and
contributors may also provide information useful in setting credible range
boundaries.
In any event, quantitative assessment of risk impact depends on
credible three-point (or at least expected and worst-case) project estimates.
Key Ideas for Activity Risk Analysis
• Assess probability and impact for each project risk.
• Understand and work to minimize biases.
• Use qualitative risk analysis to prioritize risks.
• Apply quantitative risk analysis techniques to better
understand significant risks.
• When using PERT or related techniques, keep things simple.
Panama Canal: Risks (1906–1914)
As with any project of the canal’s size and duration, risks were
everywhere. Based on the assessment of cost and probability, the most severe
were diseases, mudslides, the constant use of explosives, and the technical
challenges of constructing the locks.
The problem of diseases had been lessened on the U.S. project, but
health remained a concern. Both of the first two managers cited tropical
disease among their reasons for resigning from the project. Life in the tropics
in the early 1900s was neither comfortable nor safe. The enormous death toll
from the earlier project made this exposure a top priority.
Mudslides were common for both the French and the U.S. projects
because the soil of Panama is not stable, and earthquakes made things worse.
Whenever the sloping sides of the cut collapsed, there was danger to the
working crews and potential serious damage to the digging and railroad
equipment. In addition, it was demoralizing to face the repair and rework
following the slides, and the predicted additional effort required to excavate
repeatedly in the same location multiplied the cost of construction. This risk
affected both schedule and budget; despite precautions, major setbacks were
frequent.
Explosives were in use everywhere. In the Culebra Cut, massive
boulders were common, and workers set off dynamite charges to reduce them
to movable fragments. The planned transit for ships through the lake created
by the dams under construction was a rain forest filled with large, old trees.
These, too, had to be removed with explosives. The dynamite of that era was
not stable, especially in the tropics. It exploded in storage, in transit to the
work sites, while being set in place for use, and in many other unintended
situations. The probability of premature detonation was high, and the risk to
human life was extreme.
Beyond these daunting risks, the largest technical challenge on the
project was the locks. They were gigantic mechanisms, among the largest and
most complex construction ever attempted. Although locks had been used on
canals for a long time, virtually all of them had been built for smaller boats
navigating freshwater rivers and lakes. Locks had never before been
constructed for large oceangoing ships. (The canal at Suez has no locks; as
with the original plan for Panama, it is entirely at sea level.) The doors for the
locks were to be huge and therefore heavy. The volume of water held by the
locks when filled was so great that the pressure on the doors would be
immense, and the precision required for the seams where the doors closed to
hold in the water was also unprecedented for manufactured objects so large.
The locks would be enormous boxes with sides and bottoms formed of
concrete, which also was a challenge, particularly in an earthquake zone. For
all this, the biggest technological hurdle was the requirement that all
operations be electric. Because earlier canals were much smaller, usually the
lock doors were cranked open and shut and the boats were pulled in and out
by animals. (To this day, the trains used to guide ships into and out of the
locks at Panama are called electric mules.) The design, implementation, and
control of a canal using the new technology of electric power—and the
hydroelectric installations required to supply enough electricity—all involved
emerging, poorly understood technology. Without the locks, the canal would
be useless, and the risks associated with resolving all of these technical
problems were enormous.
These severe risks were but a few of the many challenges faced on the
canal project. Each was singled out for substantial continuing attention. At
the end of Chapter 8, we will explore how these challenges were managed.
Chapter
8
Managing Activity Risks
Statistics are no substitute for judgment.
—HENRY CLAY, U.S. SENATOR
Risk assessment provides a prioritized risk register. When you use this
list, it becomes clear just how much trouble your project is in. An
accumulation of significant scope risks may indicate that your project is
literally impossible. Too many schedule or resource risks may indicate that
your project is unlikely to complete within its constraints. Project risk
management can be a potent tool for transforming a seemingly doomed
project into a merely challenging one.
Managing risk begins with your prioritized risk register. Based on your
sorted list, you can set the boundary between the most significant and least
significant risks. Risk response planning uses this boundary as a guide; all the
risks above the cutoff line will deserve at least some attention. In addition,
though, a prudent project leader reviews the whole list, at least briefly. The
most important reason for this is to reconsider all risks with significant
consequences. When the potential impact for a risk exceeds acceptable limits,
a response may be in order even if the probability is estimated to be low.
There may also be low-rated risks for which there are simple, cheap
responses. It makes little sense to ignore risks for which there are trivial
cures.
For each risk you deem significant, you can then seek root causes to
determine your best management strategy. For risks where the project team
has influence over the root cause, you can develop and analyze ideas to
reduce or eliminate the risk and then modify the project plans to incorporate
these ideas wherever feasible. For risks that cannot be avoided or that remain
significant, you can also develop contingency plans for recovery should the
risk occur.
Root Cause Analysis
What, if anything, can be done about a risk depends a great deal on its
causes. For each identified risk that is assessed as significant, you must
determine the source and type of risk that it represents.
The process for cause-and-effect analysis is not a difficult one. For risk
analysis, it begins with the listed risks and their descriptions. The next step is
to brainstorm possible sources for the risk. Any brainstorming process will be
effective as long as it is successful in determining conditions or events that
may lead to the risk. You can begin with major cause categories (such as
scope, schedule, and resource) or simply think about specific factors that may
lead to the risk. However you begin the analysis, complete it by organizing
the information into categories of root cause. Some redundancy between
items listed in the categories is common.
Cause-and-effect analysis using fishbone diagrams, so called because
of their appearance, was popularized by the Japanese quality movement guru
Dr. Kaoru Ishikawa. (They are also sometimes called Ishikawa diagrams.)
These diagrams may be used to display root causes of risk visually, allowing
deeper understanding of the source and likelihood of potential problems.
Organize the possible causes into a branching diagram similar to the one in
Figure 8-1. Note that some causes may themselves have multiple potential
sources. Continue the root cause analysis process for each significant risk in
the project.
Fishbone-type diagrams are useful for displaying sources of risk. This
so-called fault tree structure is also employed for bow tie analysis. The initial
part of a bow tie diagram is based on a root cause hierarchy and includes
information about prevention strategies. The remainder of the bow tie
diagram focuses on the consequences of the risk event, including your plans
for recovery. You will find more on bow tie analysis and an example at the
end of this chapter.
Categories of Risk
In dealing with risk, there are really only two options. In an
advertisement some years ago, the options were demonstrated pictorially
using an egg. On the left side of the picture was an egg falling toward a
pillow held in a person’s hand. On the right side was a broken egg oozing
over the flat, hard surface it had smashed into, with a second hand swooping
in holding a paper towel. The left side was titled “Prevention” and the right
side “Recovery.” Management of risk in projects always involves these
tactics—prevention to deal with causes and recovery to deal with effects.
Figure 8-1. Fishbone Diagram
The three categories of project risk are controllable known risks,
uncontrollable known risks, and unknown risks. All risks listed in your risk
register are known risks and are either under your control or not. For any
listed risk it is possible to plan for response, at least in theory. The third
category, unknown risks, is hidden, so specific planning is not generally
possible. The best method for managing unknown risk involves setting
project reserves, in schedule or budget (or both), based on the measured
consequences of unanticipated problems on similar past projects. Keeping
track of specific past problems also converts your past unknown risks into
known risks. Managing unknown project risk is addressed in Chapter 10.
Root cause analysis not only makes known project risks more
understandable, it also shows you how to best manage each risk. Based on the
root cause or causes, you can determine whether the risk arises from factors
you can control and may therefore be preventable or it is due to
uncontrollable causes. When the causes are out of your control, risk can be
managed only through recovery. These strategies are summarized in Figure
8-2.
Figure 8-2. Risk Management Strategies
Known controllable risks are at least partially under the control of the
project team. Risks such as the use of a new technology, small increases in
complexity or performance of a deliverable, or pressure to establish
aggressive deadlines are examples of this. Working from an understanding of
the root causes for these problems, you may be able to modify project plans
to avoid or minimize the risk.
For known uncontrollable risks, the project team has essentially no
influence on the source of the risk. Examples are loss of key project staff
members, business reorganizations, and external project factors such as
weather. When these problems are significant, your best tactic is to deal with
effects afterward should the risk occur, using a contingency plan you
prepared in advance.
It is common for a root cause analysis to uncover some causes that you
can control as well as some that you cannot for the same risk. Responding to
risks with several possible sources may require both replanning and
preparation for recovery.
Although the dichotomy between controllable and uncontrollable may
seem simple, it often is not. The perceived root causes of a risk vary
depending on the description of the risk. To take the example of the fishbone
diagram in Figure 8-1, many of the root causes seem out of the control of the
project team as long as the risk is described as the loss of a particular person.
If the exposure were redefined to be the loss of a particular skill set, which is
probably more accurate, then the root causes would shift to ones that the
project might influence through cross-training, negotiating for additional
staff, or other actions.
Review your risk register, considering options for reframing risks that
might provide you with more control and risk response alternatives. Even
when a risk seems to be uncontrollable, the venerable idea from quality
analysis of “Ask why five times” may open up the perspective on the risk and
reveal additional options for response. If weather, earthquakes, or other
natural disasters are listed as risks to particular activities, probe deeper into
the situation to ask why and how that particular problem would affect the
project. The risk may be a consequence of a project assumption or a choice
made in planning that could be changed, resulting in a better, less
problematic project. Shifting the time, venue, infrastructure, or other
parameters of risky activities may remove uncontrollable risks from your
project, or at least diminish their potential for harm.
Selecting Risks to Address
One of the main purposes of qualitative risk assessment is to prioritize
risks into rank order to assist in making decisions about whether and how to
deal with identified potential problems. Qualitative methods are useful for
this, but they rarely provide as clear a picture as you need. The heat map view
of risks (as in Figure 7-5) often comes with a crisp-sounding set of high-risk
cells in the grid that deserve attention, with the rest of the map considered
low risk. Even without considering the inherent lack of precision and
symmetry problems discussed in the last chapter, it is never that simple.
What appears to be a simple decision is actually often quite
complicated. An effective tactic for dealing with the decision of which risks
warrant attention starts with a simpler grid than the standard risk assessment
matrix. The grid in Figure 8-3 recognizes that even your uncertainty may be
uncertain. The grid begins with a defined threshold for high, based on
stakeholder risk tolerance. The threshold for high probability will be in the
vicinity of 30 percent or so, high enough that disregarding threats of this sort
would result in frequent unpleasant surprises. Low for probability would fall
below the threshold and be sufficiently small to be considered unlikely by
key stakeholders. Between high and low, the grid has provision for uncertain
probability, reflecting that some events are infrequent enough that assessing
their likelihood is really just a guess.
Figure 8-3. Risk Assessment Considering Uncertainty (the Easy
Cases)
Similarly, you define a threshold for high impact that aligns with
significant and visible damage to the project or organization in the eyes of
your stakeholders (for example, inevitable changes to the project objective or
some other impact that could exceed the project’s cost). Low impact will
generally consist of consequences that are invisible outside the project, and
uncertain catches cases where there is no reliable basis (at least within the
project) for assessing the results.
The corner cells with labels in Figure 8-3 are the easy cases.
Where the impact and probability assessments are high-high, you need
to take the risks seriously. The safest course is to treat these risks the same
way you would issues or problems. Plan to develop a response in advance,
and accept these risks only when you can devise no credible or cost-effective
response. If you find that prevention is not feasible for significant risks, work
to develop detailed contingency and recovery plans.
Where you have a credible impact and probability assessments of low-
low, most risks can be safely accepted. For these demonstrably minor risks,
ad hoc responses will likely be sufficient.
But what about all the other cases:
• Low-probability risks with high-impact estimates?
• Risks with nonquantitative but possibly significant impact?
• Any risks where the prevention (avoid/mitigate/transfer) costs are
well below the loss-times-likelihood?
• Risks with moderate- (or low-) probability/impact assessments?
• Risks where your best probability estimates are wild guesses?
• Risks where your best impact estimates are unknown or there is a
wide spectrum of potential significance?
One such case is the right-hand column of the grid in Figure 8-3, where
impact is estimated to be high. You will manage these if possible when the
probability is also high, but what do you do about the cases where your best
probability assessment is either low or unknown? This is the realm of black
swans. However unlikely they appear to be, they do sometimes occur.
Because the impact will be material, it is best to manage most of these risks
and develop responses at least for all risks with unknown probability. Take
all risks seriously whenever potential impact exceeds what you (or your
organization) can afford. It’s prudent to be skeptical of all low-probability
risk estimates because many are based more on wishful thinking than on any
analytical analysis. Accept these risks only when the cost of any response
exceeds the expected risk or you can devise no effective response (and the
project would still make financial sense even if the risk occurs). Maintain any
of these risks you choose to accept in your risk register, and at least develop
contingency and recovery plans.
Essentially the same strategy may be applied to the top center column
of the grid, where the probability is high and impact is unknown. You clearly
should manage most of these risks as well because they are likely to occur
and could potentially cause damage to your project.
The remainder of the center column, where probability is unknown or
low, is dangerous to ignore for the same reason. Probabilities aside, the
effects of such risks could be project-threatening. In determining your
response, consider worst-case impact. If you can determine the potential
range for impact, focus on what the worst outcome might be. Manage most of
the risks whose consequences could exceed what your stakeholders will
tolerate. Generally, accept these risks only if the cost of a response is
comparable with the worst-case cost of the risk.
The remaining cases on the grid contain low-impact risks with either
high or uncertain probabilities. Because the impact for these cases is small
and can be contained within your project, you will probably accept most of
these cases. Recovery from such risks requires revisions to plans and staff
assignments and will tax whatever reserves you have established for your
project, but all this generally falls within the purview of competent project
management. You should always consider managing any risks in these (and
any other) categories where you can devise an effective response that
involves only trivial project changes. (Many contract-related risks can be
mitigated with a thorough review of all the documents, which, although not
much fun, is not very difficult. Effective project communication is an
effective preventative for many kinds of risk, and this is really just the project
leader’s job.) Also consider responses for any risks that could recur
frequently and represent an aggregate impact from all the instances that might
prove significant. Figure 8-3 with the remaining cells populated is shown in
Figure 8-4.
Retain even the risks you accept on your risk register, and plan to
monitor and reassess their impact periodically, especially on longer projects.
To summarize, develop a response for risks in your risk register for any of the
following reasons:
• They are significant risks for which you have a cost-effective
response.
• They are risks with high or unknown impact where a response is
justified, regardless of assessed probability. (Remember, black swans
do happen.)
Figure 8-4. Risk Strategies Based on Assessment
• They are minor risks that have simple, low-cost, effective responses.
You may choose to accept risks in your risk register for any of the
following reasons:
• They are significant risks to which no response can be found.
• They are significant risks where a response is identified but thought
too costly.
• They are minor risks that do not warrant attention in advance.
Risk Response Planning
Two basic options are available for risk management: dealing with
causes and dealing with effects. There are, however, variations on both of
these themes.
Risk Response Techniques
Dealing with the causes of project threats involves risk prevention—
eliminating the risk (avoidance), lowering its probability or potential impact
(mitigation), or making it someone else’s problem (transfer). Avoidance of
risks requires changing the project plan or approach to remove the root cause
of the risk from your project. One way to avoid falling off a cliff is to avoid
cliffs. Mitigating actions do not remove a risk completely, but they do serve
to reduce it. Some mitigating actions reduce the probability of a risk event,
such as inspecting your automobile tires before a long trip. Other mitigations
reduce the risk consequences, such as wearing a seat belt when driving to
minimize injury. Neither of these actions prevents automobile problems, but
they do serve to reduce the overall risk by lowering the loss and/or
likelihood.
Similarly, some damaging risks may be transferred to others. Many
kinds of financial risks may be transferred to insurance companies; you can
purchase coverage that will compensate your losses in the event of a casualty
that is covered by the policy. Again, this does not remove the risk, but it does
reduce the financial impact should the risk occur. Transfer of risk can deal
with causes if the impact of the risk is primarily financial, but in other cases it
may be used to deal with risk effects—aiding in the recovery.
Throughout most of this chapter, the term “risk” will be used to
describe an uncertain event that could harm the project—a threat. Not all
uncertain project events are threats, however. There may also be uncertain
opportunities where risk management strives to increase the probability or
impact. Benefiting from uncertain project opportunities involves embracing
these “positive risk” situations. Similar tactics are applied to these potential
opportunities, analogous (though reversed) to those just outlined for
prevention of threats. Where you might avoid threats by replanning to
remove the potential for harm, you would replan the project to exploit or to
capture the opportunity. You work to make it a certain part of the project. In
the case mentioned in Chapter 7 of an item that might go on sale, you might
investigate the planned timing for the sale and schedule the purchase around
it. Mitigation serves to reduce the probability or impact of a threat, and the
corresponding tactic is to enhance the plan to pursue opportunity, making the
potential benefits more likely or more helpful. In the case of the sale, you
might be unable to determine when (or even if) it might occur, but you could
time your purchases around the dates for a sale from last year on the theory
that this year’s sale would be most likely then. As with threats, sometimes the
strategy involves strength in numbers. Where threats may be transferred to
limit their impact, opportunities may be improved when shared. Cost
reductions for purchased items comparable to a sale might be available if you
can find others with similar needs and make purchases together to take
advantage of favorable quantity pricing. As discussed in earlier chapters,
managing opportunities generally involves choices. Choices and decisions,
including those involving uncertain opportunities, may require trade-offs and
affect other aspects of your project.
Dealing with the effect of a threat may be done either in advance
(contingency planning) or after the fact (acceptance). (Uncertain
opportunities generally need no particular contingency planning; those not
managed are usually ignored.) Some minor risks are too insignificant to
consider preventing. Prevention strategies for other risks may prove too
expensive. For any of these situations, acceptance may be appropriate; simply
plan to deal with the consequences of the problem if and when it occurs. For
more serious problems where avoidance, mitigation, and transfer are
ineffective, impractical, too costly, or impossible, contingency planning is
usually the best option.
For some risks, one of these response strategies will be sufficient; for
others, it may be necessary to use several.
Timeline for Known Risks
As discussed briefly in Chapter 6, each activity risk will have a signal,
perhaps more than one, indicating that the risk has crossed over from a
possibility to a certainty. This signal, or trigger event, may be in advance of
the risk or coincident with it. It may be visible to everyone involved in the
project, or it may be subtle and hidden. For each risk, strive to define a
trigger event that provides as much advance notification of the problem as
possible. Consider the risk: “A key project team member quits.” One possible
trigger event might be the submission of a resignation letter. This is an
obvious trigger, but it is a late one. There are earlier triggers to watch for,
such as a drop in motivation, erratic attendance, frequent “personal”
telephone calls, or even an uncharacteristic improvement in grooming and
dress. These triggers are not foolproof, and they require more attention and
effort to monitor, but they may also foreshadow other problems even if the
staff member does not intend to leave.
In addition to one or more trigger events, identify the portions of the
project plan where the risk is most probable, being as precise as possible. For
some risks, there may be a single exposure related to one specific activity;
more general risks (such as loss of key staff members) may occur throughout
the project.
Risk management decisions and plans are made in advance of the
trigger event, and they include all actions related to avoidance, mitigation, or
transfer, as well as preparation for any contingent actions. Risk management
responses that relate to recovery fall on the project timeline after the risk
trigger but are used only if necessary. For each significant risk that you
cannot remove from the project, assign an owner to monitor for the trigger
event and to be responsible for implementing the contingency plan or
otherwise working toward recovery. The risk management timeline is
summarized in Figure 8-5.
Dealing with Risk Causes
After every risk is categorized and you have identified the risks for
which the project team could influence some or all of the causes, you are
ready to begin developing response possibilities for threat prevention,
including avoidance, mitigation, and transfer (or for uncertain opportunities,
exploit, enhance, and share). Analyze all the options you and your team
develop, examining both the cost of the idea and its potential benefits. If
good, cost-effective ideas are proposed, the best of them are candidates for
inclusion in your draft project plan. Prevention ideas must earn their way into
the project plan. Even excellent ideas that completely remove a risk should
probably be bypassed when their overall cost exceeds the expected loss-
times-likelihood for the risk. The final process step is to integrate appropriate
proactive risk responses into your preliminary project plan and review the
plan for new risks and unintended consequences as a result of the changes.
Planning for risk responses begins with generating ideas.
Brainstorming with your project team is a good way to generate a range of
possible choices. It is also useful to discuss risks with peers and others who
may have relevant experience, and it may be worthwhile to consult experts
and specialists for types of unfamiliar risks.
Few known risks are completely novel, so it is quite possible that many
of the risks you face have been addressed on earlier projects. A quick review
of project retrospective analyses, final reports, lessons learned, and other
archived materials may provide information on what others did in response
when faced with similar risk situations they encountered. In addition to
finding things that did not work and are worth avoiding, there may be useful
ideas for effectively dealing with the risks you need to manage.
Figure 8-5. Risk Management Timeline
Also, many ideas are available in the public domain, in papers, books,
and articles and on the Web. References on project management, particularly
those tailored to projects like yours, are filled with practical advice. Life
cycles and project management methodologies also provide direction and
useful ideas for managing risks.
A number of possible preventative actions follow in the next several
pages, including tactics for risk avoidance, mitigation, and transfer. These can
be useful in seeding a brainstorming exercise or in planning for specific
responses. These tactics include ideas for dealing with the worst of the risks
in the PERIL database, especially those characterized as black swans. The
ideas listed here include some that may be appropriate only for particular
kinds of projects, but many are useful for any project.
Risk Avoidance
Avoidance is the most thorough way to deal with risks because it
obliterates them. Unfortunately, avoidance is not possible for all project risks
because some risks are tightly coupled to project requirements. Avoiding
risks in your project requires you to reconsider choices and decisions you
made in defining and planning your project. Most of Chapters 3, 4, and 5
concerned using project planning processes to identify risks. Although some
of the risks you discovered may be unavoidable, a review of the current state
of your plan may turn up opportunities to replan the work in ways that
remove specific serious risks. Your review may even uncover risks where the
problems arise from environmental or infrastructure aspects that could (and
should) be changed.
Tactics for avoiding scope risks suggested by the material in Chapter 3
include:
• Identify the minimum acceptable deliverable; avoid overdesign (gold
plating).
• Negotiate and clearly document all interface deliverables expected
from other projects.
• Avoid untried, unfamiliar, or “bleeding-edge” technology whenever
practical.
• Plan to design using standard, modular, or well-understood methods;
look for ways to achieve project specifications using older, tried-and-
true technologies.
• Buy instead of make.
• Avoid not-invented-here thinking; be willing to leverage work done
by others.
Many of your schedule risks are consequences of planning. You may
be able to remove sources of schedule risk using ideas covered in Chapter 4:
• Reduce the number of critical paths.
• Modify the work to have fewer activity dependencies.
• Schedule the highest uncertainty activities as early as possible.
• Avoid having the same staff members working on two successive or
concurrent critical (or near critical) activities.
• Decompose lengthy activities further.
• Reschedule work to provide greater flexibility.
Resource risks may also be a consequence of choices you made in
resource planning. Explore opportunities to avoid these risks using the
concepts of Chapter 5:
• Obtain names for all required project roles.
• Get explicit availability commitments from all project staff (and from
their managers).
• Work to limit commitments by project staff to other projects,
maintenance and support work, and other time conflicts. Explicitly
document those that remain.
• Modify plans to reduce the load on excessively committed staff.
• Use the best people available for the most critical activities.
• Educate team members to use more efficient or faster methods, and
do it early in the project.
• Use mentoring to build teamwork and establish redundancy for
critical skills.
• Upgrade or replace older equipment to make work more efficient, and
do it at the project start.
• Automate manual work when possible.
• Locate and gain access to experts to cover all skill areas not available
on the project team.
• Minimize dependence on a single individual or other resource for
project work.
• When you use outside services, use the same suppliers that you (or
others that you trust) have used successfully in the past.
• Establish contract terms with all suppliers that are consistent with
project objectives.
Avoidance tactics are not limited to these ideas by any means.
Anything that you can realistically do to eliminate the root cause of a risk by
modifying your plans or by successfully lobbying for changes outside your
project has the potential for risk avoidance.
Risk Mitigation
Mitigation strategies are also essential for risk management because
avoidance can never deal with every significant project risk. Mitigation
strategies serve to reduce the probability and/or the impact of potential
problems. Some generic ideas for risk mitigation include:
• Good communication and risk visibility
• Using specialists and generalists
• Strong sponsorship
• Continuing user involvement
• Clear decision priorities
One of the least expensive and strongest preventative actions a project
leader can take is to communicate more—and more effectively. Visible risks
and risk consequences always affect how people work. If all the team
members are aware how painful the project will become following a risk,
they are likely to work, to the best of their ability, in ways that minimize the
risk. Communication can also significantly reduce risk probabilities.
Communicate. Communicate. Communicate.
Another broad strategy for managing risk relates to project staffing.
Difficult projects benefit from having a mix of specialists and generalists.
Specialists are essential on complex projects because no one can know
everything, and specialists can generally complete assigned work in their
specialties much faster than a generalist. However, a project team composed
only of specialists is not very robust and tends to run into frequent trouble.
This is because project planning on specialist-heavy projects is often intense
and detailed for work in the specialists’ areas, and remarkably sketchy for
other work. Also, such teams may lack broad problem-solving skills.
Generalists on a project are needed to fill in the gaps and ensure that as much
of the project work as possible is visible and well planned. Generalists are
also best for solving cross-disciplinary problems. As the head generalist, the
project manager should always reserve at least a small percentage of his or
her time for problem solving, helping out on troubled activities, and general
firefighting. Even when the project leader has a solid grasp of all the key
project issues, it is useful to have other generalists on the team in case several
things on the project go wrong at the same time. Generalists can reduce the
time to solution for problems of all kinds and minimize schedule impact.
Managing project risk is always easier with friends in high places.
Establish and work to sustain strong sponsorship for your project. Although
strong sponsorship does not ensure a risk-free project, weak (or no) upper-
level sponsorship is a significant source of risk. Form good working
relationships with your project sponsor and key stakeholders, and work to
understand their expectations for project information. Reinforce the
importance and value of the project regularly, and don’t let sponsors forget
about you. Update your management frequently on project progress and
challenges, and escalate promptly when situations and problems require
authority you lack. Validate project objectives with sponsors and customers,
and work to set realistic expectations. Using your budget and staffing plans,
get commitments for adequate funding, staffing, and expertise. Strong
sponsorship reduces timing problems and other risk impact and lowers the
probability for many kinds of resource risks.
Project risk will increase, particularly on lengthy projects, whenever
the project team is disconnected from the ultimate customers for the
deliverable. Establish and maintain contact with the end users or with people
who can represent them. Seek strong user buy-in, and work with users to
avoid scope gaps by validating all acceptance and testing criteria. Establish
measurable criteria, and determine what will be required for the users to
deem the project a success. Identify the individual or individuals who will
have the final word on this, and stay in contact with them. Agile methods
deeply involve users in the development process, reducing many types of
deliverable-related risk. The probability of scope risk and the likelihood of
late project schedule difficulties are both reduced by ongoing user
involvement.
A final general strategy for lowering project risk is setting clear
decision priorities for the project. Validate the priorities with both the
sponsors and the end users, and ensure that the project priorities are well
known to the project team. Base project decisions on the priorities, and know
the impact of failing to meet each priority established for the project. This not
only helps manage scope risks, it also permits quick decisions within the
project that minimize scope creep and other change-related impact.
Mitigation strategies for scope risks. Mitigating scope and technical
risks involves shifts in approach and potential changes to the project
objective. Ideas for mitigating scope risks include:
• Explicitly specify project scope and all intermediate deliverables, in
measurable, unambiguous terms, including what is not in the
deliverable. Eliminate wants early—make them explicitly part of
scope or drop them.
• Gain acceptance for and use a clear and consistent specification
change control process.
• Adopt iterative or agile methods to manage scope based on user
feedback and current priorities.
• Build models, prototypes, and simulations, and get user and
stakeholder feedback.
• Test with users, early and often.
• Schedule risk-prone, complex work early.
• Obtain funding for any required outside services.
• Translate, competently, all project documents into relevant languages.
• Minimize external dependency risks.
• Consider the impact of external and environmental problems.
• Keep all plans and documents current.
The most significant scope risks in the PERIL database were caused by
changes. Minimizing change risk involves the first two tactics—scope
definition and change management. Scope risk is high for projects with
inadequate specifications. Although it is true that a thorough, clear definition
of the deliverable is often difficult on complex projects, failure to define the
results adequately leads to even greater difficulty. Closely inspect the list of
features to be included to verify that all the requested requirements are in fact
necessary. Employ iterative development techniques or other methods to
refine uncertain requirements as early as possible.
The second necessary tactic for reducing change risk is to uniformly
apply an effective process for managing all changes to project scope. To
manage risks on large, complex projects, the process is generally formal,
using forms, committees, and extensive written reporting. For projects done
under contract, risk management also requires that the process be described
in detail in the contract signed by the two parties. On smaller projects, even if
it is less formal, there still must be uniform treatment of all proposed
changes, considering both their benefits and expected costs. For projects
using agile methods, adopt a disciplined process to manage decisions and
scope adjustments based on relevant priorities and frequent user feedback.
For your project, adopt a process that rejects (or at least defers) all changes
that fail the cost-justification test. It is not enough to have a change
management process; mitigating scope risks requires its disciplined use.
Scope risks are often hard to evaluate at the beginning of complex
projects. One way to gain better insight is to schedule work during planning
in order to examine feasibility and functionality questions in parallel with
other analysis. Use prototypes, simulations, and models to evaluate concepts
with users. Schedule early tests and investigations to verify the feasibility of
untried technology. Identify potential problems and defects early through
walkthroughs and scenario discussions. Also consider scale risks. Even if
there are no problems during small-scale, limited tests, scope risks may still
remain that will be visible only in full-scale production. Plan for at least some
rudimentary tests of functionality in full-scale operation as early in the
project as practical. Schedule work to uncover issues and problems near the
beginning of the project or during early development iterations. Be prepared
to modify your plan and assumptions or even to abandon the project, based
on what you learn.
Although it is risky to defer difficult or unknown activities until late in
the project, it may be impractical to begin with them. To get started, you may
need to complete some simpler activities first and then move on to more
complicated activities as you build expertise. Do your best to schedule the
risk-prone activities as early in your project as you are able.
Lack of skills on the project team also increases scope risk, so define
exactly how you intend to acquire all needed expertise. If you intend to use
outside consultants, plan to spend both time and effort in their selection, and
ensure that the necessary funding to pay for them is in the project budget. If
you need to develop new skills on the project team, identify the individuals
involved and plan so that every contributor is trained, in advance, in all the
needed competencies. If the project will use new tools or equipment,
schedule installation and complete any needed training as early in the project
as practical.
Scope problems also arise from faulty communications. If the project
depends on a distributed team that speaks several languages, identify all the
languages needed for project definition and planning documents and provide
for their translation and distribution. Confusion arising from project
requirements that are misinterpreted or poorly translated can be expensive
and damaging, so verify that the project information has been clearly
understood in discussions, using interpreters if necessary. It is also critical to
provide written follow-up after meetings and telephone discussions.
Scope often depends on the quality and timely delivery of things the
project receives from others. Mitigating these risks requires clear, carefully
constructed specifications to minimize the possibility that the things that you
receive might be consistent with the requirements but inappropriate for the
project’s intended use. If you have little experience with a provider, finding
and using a second source in addition to the first may be prudent, even
though this will increase the cost. The cost of a redundant source may be
small compared to the cost of a delayed project.
External factors also lead to scope risks. Natural disasters such as
floods, earthquakes, and storms, as well as not-so-natural disasters like
computer viruses, may cause the loss of critical information, software, or
necessary components. Although there is no way to prevent the risks,
provision for some redundancy, adequate frequent backups of computer
systems, and less dependency on one particular location can minimize the
impact for this sort of risk.
Finally, managing scope risk also requires tracking of the initial
definition with any and all changes approved or accepted during the project.
You can significantly lower scope risk by adopting a process that tightly
couples all accepted changes to the planning and requirements management
processes, as well as by making the consequences of scope decisions visible
throughout the project.
Mitigation strategies for schedule risks. Schedule risks may be
minimized by making additional investments in planning and revising your
project approach. Some ideas to consider include:
• Use expected estimates when worst cases are significant.
• Schedule highest-priority work early.
• Manage external dependencies proactively.
• Before adopting a new technology, explore possibilities for using
older methods.
• Use parallel, redundant development.
• Send shipments early. Avoid reliance on just-in-time.
• Know customs requirements and use experienced services for
international shipments.
• Be conservative in estimates for training and new hardware.
• Break projects with large staffs into parallel efforts.
• Partition long projects into a sequence of shorter ones.
• Schedule project reviews.
• Reschedule work coincident with known holidays and other time
conflicts.
• Track progress with rigor and discipline, and report status frequently.
The riskiest activities in the project tend to be the ones that have
significant worst-case estimates. For any activity where the most likely
estimate is a lot lower than what could plausibly occur, calculate an expected
duration using the Program Evaluation and Review Technique (PERT)
formula. Use these estimates in project planning to provide some reserve for
particularly risky work and to reduce the schedule impact.
Project risk is lower when you schedule activities related to the highest
priorities for the project as early as possible, moving activities of lower
priority later in the project. For each scheduled activity, review the
deliverables and specify how and when each will be used. Wherever possible,
schedule the work so that there is a time buffer between when each
deliverable is complete and the start of the activities that require them. If any
activities produce deliverables that seem to be unnecessary, either validate
their requirement with project stakeholders or remove the work from the
project plan.
Many schedule risks are caused by delays that may be avoided through
more proactive communication. Whenever decisions are needed, plan to
remind the decision makers at least a week in advance and get commitment
for a swift turnaround. If specialized equipment or access to limited services
is required, put an activity in the plan to review your needs with the people
involved somewhat before the scheduled work. If scarce equipment for some
kinds of project work is a chronic problem, propose adding capacity to lower
the risk on your project, as well as for all other parallel work. The
preventative maintenance schedules for production systems are generally
determined well in advance. Monitor availability schedules for needed
services, and synchronize your plans with them to reduce conflicts and
delays.
New things—technology, hardware, systems, or software—are
common sources of delay. Manage risk by seeking alternatives using older,
known capabilities unless using the new technology is an absolute project
requirement. A lower-tech alternative may in some cases be a better choice
for the project anyway, or it could serve as a standby option if an emerging
technology fails to meet your needs. Identify what you would need to do or
change in the project to complete your work without the newer technology.
One cause of significant delay is developing a specific design and then
sending it out to be built or created before it can be tested. It may take weeks
to get the tangible result of the design back, and if it has problems, the entire
cycle must be repeated, doubling the duration (or, worse, it may not work the
second time either). In areas such as chip design, more than one chip will be
made on each wafer anyway, and it might be useful to design a number of
slightly different versions that can all be fabricated at the same time. Most of
the chips will be of the primary design, but other variations created with it
can also be tested, thus increasing the chances of having a component that
can be used to continue with project work. In other cases, slightly different
versions may be created in parallel, such as printed circuit boards, mechanical
assemblies, or other newly designed hardware. Although this may increase
the project cost, protecting the project schedule is often much more
important. Varying the parameters of a design and evaluating the results may
also be useful for understanding the principles involved more thoroughly,
which can reduce risks for future projects.
Delays due to shipping problems are significant on many projects and
in many cases can be avoided simply by ordering or shipping items earlier in
the project. Just because it is generally thought to take a week to ship a piece
of equipment from San Jose, California, to Bangalore, India, does not mean
you should wait until a week before it is needed in India to ship it. There are
only two ways to get something done sooner: work faster or start earlier.
With shipping, expediting may not always be effective, so it is always
prudent to request and send things that require physical transport well ahead
of the need, particularly when it involves complex paperwork and
international customs regulations. Use only shipping services with a good
performance record, knowledge of legal requirements, and an ability to track
shipments.
Similarly, delay may result from the need to have new equipment or
new skills for the project. The time necessary to get new equipment installed
and running or to master new skills may prove longer than you think. If you
underestimate how long it will take, project work that depends on the new
hardware or skills could have to wait. Planning proactively for these project
requirements will remove many risks of this sort from your project (and, as
mentioned earlier, it also lowers the chances that you might lose, or never
get, the required funding). Estimate these activities conservatively, and
schedule installations, upgrades, and training as early in your project as
practical—well before they are needed.
Large projects are intrinsically risky. If a project requires more than 20
full-time staff members, explore the possibility of partitioning it into smaller
projects responsible for subsystems, modules, or components that can be
developed in parallel. However, when you decompose a large program into
autonomous smaller projects, be sure to clearly define all interfaces among
them, in terms of both specifications required and timing. Although the
independent projects will be easier to manage and less risky, the overall
program could be prone to late integration problems without adequate
systems-level planning and strong interface controls.
Long projects are also risky. Work to break projects longer than a year
into phases that produce measurable outputs. A series of short evolutionary
projects will create value sooner than a more ambitious longer project, and
the shorter projects are more likely to fall within a reasonable planning
horizon of less than six months. This is a central principle for evolutionary
software development and agile methodologies, used to deliver intermediate
results sooner and to manage both scope and schedule risk.
If a lengthy project must be undertaken as a whole, adopt a rolling-
wave planning philosophy. At the end of each project phase, plan the next
phase in detail and adjust plans for the remainder of the work at a summary
level. Make adjustments to the project plans for future phases as you proceed
to reflect what has been learned in the previous phases, including changes to
the project deliverable, shifts in project staffing, and other parameters of the
project objective. Rolling-wave planning requires that the project team
conduct a thorough project review at the end of each phase and be prepared
to continue as planned, continue with changes, or abort the project.
Schedule risk also arises from time conflicts outside the project. Check
the plan for critical project work that may conflict with holidays, the end of
financial reporting periods, times when people are likely to take vacations, or
other distractions. Verify that intermediate project objectives and milestones
are consistent with the personal plans of the staff members responsible for the
work. On global projects, collect data for each region to minimize problems
that may arise when part of the project team will be unavailable because of
local holidays. Avoid known project time conflicts by accelerating or
delaying the planned work around them.
Finally, commit to rigorous activity tracking throughout the project,
and periodically schedule time to review your entire plan: the estimates, risks,
work flow, project assumptions, and other data. Publish accurate schedule
status regularly.
Mitigation strategies for resource risks. Mitigating resource risks
includes ideas such as:
• Avoid planned overtime.
• Build teamwork and trust on the project team.
• Use expected cost estimates where worst-case activity costs are high.
• Obtain firm commitment for funding and staff.
• Keep customers involved.
• Anticipate staffing gaps.
• Minimize safety and health issues.
• Encourage team members to plan for their own risks.
• Delegate risky work to successful problem solvers.
• Rigorously manage outsourcing.
• Detect and address flaws in the project objective promptly.
• Rigorously track project resource use.
One of the most common avoidable resource risks on modern projects
is planned overtime. Starting a project with full knowledge that the deadline
is not possible unless the team works overtime for much of the project’s
duration is a prescription for failure. Whenever the plan shows requirements
for effort in excess of what is realistically available, rework the plan to
eliminate it. Even on well-planned projects, there are always plenty of
opportunities for people to stay late, work weekends and holidays, lose sleep,
and otherwise devote time to the project from their side of the work/life
balance. Projects that require overtime from the outset also face significant
risks due to low productivity because of poor motivation and potential
turnover.
Resource risk is lower on projects whenever motivation is high.
Motivation is a key factor in whether people will voluntarily work overtime,
and low motivation is frequently a root cause of many resource-related risks.
Complex projects are always difficult. When they succeed, it is not because
they are easy; it is because the project team cares about the project. Project
leaders who are good at building teamwork and getting people working on
the project to trust and care about each other are much more successful than
project leaders who work impersonally at a distance.
Teamwork across cross-functional project boundaries is also important.
The more involvement in project planning, start-up or launch activities, and
other collaborative work you do early in the project, the more team cohesion
you can count on. People who know and trust each other will back each other
up and help to solve each other’s problems. People who do not know each
other well tend to mistrust each other and create conflict, arguments, and
unnecessary project problems. Working together to plan and initiate project
work transforms it from the “project leader’s project” to “our project.”
Financial risk is also significant for many projects. For activities in the
project that have significant worst-case costs, estimate a realistic expected
cost and use it to reflect the potential financial exposure and in determining
the proposed project budget.
As with schedule risk, adequate sponsorship is essential to resource
risk management. Get early commitment from the project’s sponsor for
staffing and for funding, based on planning data (a discussion of negotiating
for this follows in Chapter 10). The priority of the project is also under the
control of the project sponsor, so work to understand the relative priority of
the project in his or her mind. Strive to obtain the highest priority that is
realistic for your project (and document it in writing). If the project has more
than one sponsor, determine who has the most influence on the project. In
particular, it is good to know who would be able to make a decision to cancel
your project, so that you can take good care of them and keep them aware of
your progress. It is also useful to know who in the organization above you
would suffer the most serious consequences if your project does not go well
because these managers have a personal stake in your project, and they will
be most useful when risk recovery requires escalation.
Too little involvement of customers and end users in definition, design,
and testing is also a potential resource risk, so obtain commitments early on
all activities that require it. Also, plan to provide reminders to them in
advance of the project work that needs their participation.
Risks resulting from staffing gaps can be reduced or detected earlier
through more effective communication. Assess the likelihood that project
staff (including you) might join the project late because of ongoing
responsibilities in prior projects whose completion is delayed. Get credible
status reports from these projects, and determine how likely it is that the
people working on them will be available to work on your project. If the
earlier projects are ending with a lot of stress and overtime, reflect the need
for some recovery time and less aggressive estimates in your project plans for
the affected team members. Also plan to notify any contributors with part-
time responsibilities on your project in advance of their scheduled work.
Loss of project staff due to safety or health problems is always
possible, so a review of activities involving dangerous work is a good idea.
Modify plans for any activities that you suspect may have health or safety
risks in order to minimize the exposure. You may be able to make changes to
the environment, time, or place for the work or to mitigate the risk by
modifying the practices used. Also consider the experience and skills of any
contributor who might be exposed to risks, and work to replace or train any
team members who have insufficient relevant background.
For any activity risk for which the assigned team members are part of
the risk, involve those individuals in developing a response. In addition to
potentially finding more and better ideas for prevention, this will tend to
sensitize them to the impact of the problem and may greatly reduce the
likelihood of the risk.
For new, challenging, or otherwise risky activities, strive to find
experienced contributors who have a reputation for effective problem
solving. Although you cannot plan creativity or innovation, you can always
identify people who seem to be good at it.
Outsourcing is a large and growing source of resource risk on projects.
The discussion in Chapter 5 includes a number of exposures, and mitigating
these risks requires discipline and effort. For each contract with a service
provider that your project depends on, designate a liaison on the project team
to manage the relationship. Do this also for other project teams in your own
organization that you need to work with. If you plan to be the liaison, ensure
that you have sufficient time allocated for this in addition to all your other
responsibilities. Involve the owner of each contract relationship in the
selection, negotiation, and finalization of the agreement. Ensure that the
agreement is sufficiently formal (a contract with an external supplier, a memo
of understanding or similar document for an internal supplier) and that it is
specific as to both time and technical requirements for the work, consistent
with your project plan. Provide incentives and penalties in the agreement
when appropriate, and, whenever possible, schedule the work to complete
earlier than your absolute need.
With any project work performed out of the view of the project team,
schedule reviews of early drafts of required documents. Also, participate in
inspections and interim tests, and examine prototypes. Identify and take full
advantage of any early opportunities to verify tangible evidence of progress.
Plan to collect status information regularly, and work to establish a
relationship that will make it more likely that you will get credible status
information, including bad news, throughout your project.
A significant risk situation on fee-for-service projects is a lack of
involvement of the technical staff during the proposal and selling phases.
When a project is scoped and a contract commitment is made before the
project team has any involvement in the project, resource risks (not to
mention schedule and scope risks) can be enormous. This price-to-win-the-
business technique is far too common in selling fee-for-solution projects, and
it often leads to fixed-price contracts with large and seemingly attractive
revenues that are later discovered to require even larger and extremely
unattractive expenses. Some projects sold this way may even be impossible
to deliver at all. Prevention of this risk would be reasonably easy using time-
travel technology, by turning back the clock and involving the project team in
setting the terms and conditions for any agreement. Because such a risk may
already be a certainty when the project team gets into project and risk
planning, your only recourse is to mitigate the situation as best you can.
Minimizing the risks associated with committed projects based on little
or no analysis requires the project team to initiate the processes of basic
project and risk planning as quickly as they can, doing bottom-up planning
based on the committed scope. Using best-effort planning information,
uncover any expectations for timing and cost that are out of line with reality.
Timing expectations are visible to all, so any shifts must be dealt with
internally as well as with the customer, which may require contract
modifications. Resource and cost problems can be hidden from the customer,
but they still will require internal adjustment and commitment to a realistic
budget for the project, even if it significantly exceeds the amount that can be
recovered under the contract. If this is all done quickly enough, before
everyone has mentally settled into expectations based on the price to win the
contract, it may even be possible to adjust the fees in the contract. Although it
may be tempting to adopt a safe-so-far attitude and hope for the miracle that
would allow project delivery consistent with the flawed contract, delay will
nearly always make things worse. The last, best chance to set realistic
expectations for such a project is within a few days of its start. After this, the
situation becomes progressively uglier and more expensive to resolve.
It is also important to document and make these price-to-win situations
visible in order to minimize the chances of future recurrence. Organizations
that chronically pursue business like this rarely last long.
Finally, establish resource metrics for the project, and track them
against realistic planning data. Track progress, effort, and funding throughout
the project, and plan to act quickly when the information shows that the
trends show adverse variances against the plan. Keep resource status
information visible through regular reporting.
Risk Transfer
Along with avoidance and mitigation, transfer is a third option for risk
prevention. It is most effective for risks where the impact is primarily
financial. The best-known form of transfer is insurance; for a fee, someone
else will bear the financial consequences of your risk. Transfer works to
benefit both parties. The purchaser of the insurance avoids the risk of a
potentially catastrophic monetary loss in exchange for paying a small (by
comparison) premium. The seller of the insurance benefits by aggregating the
fees collected to manage the risk for a large population of insurance buyers,
who may be expected to have a stable and predictable average risk and to
include only a small percentage who will generate claims. This sort of
transfer is not extremely common for projects, but it is used. Unlike other
strategies for mitigation, transfer does not actually do anything to lower the
probability or diminish the nonfinancial impact of the risk. With transfer, the
risk is accepted, and it either happens or it does not. However, any budgetary
impact will be borne outside the project, limiting the resource consequences,
and insurance payouts can fund your recovery efforts.
Transfer of scope and technical risk is often the justification for
outsourcing, and in some cases this might work. If the project team lacks a
needed skill, hiring an expert or consultant to do the work transfers the
activities to people who may be in a better position to get it done.
Unfortunately, though, the risk does not actually transfer to the third party;
the project still belongs to you, so any risk of nonperformance is ultimately
still yours. Should things not go well, the fact that a bill for services will not
need to be paid will be of small consolation. Even the possibility of eventual
legal action is unlikely to help the project. Using outsourcing as a risk
transfer strategy is very much a judgment call. In some cases, the risks
accepted may significantly exceed the risks managed, no matter how
carefully you write the contract.
Implementing Preventative Ideas
Avoidance, mitigation, and transfer nearly always have costs,
sometimes significant costs. Before you adopt any ideas to avoid or reduce
risks, some analysis is in order.
Comparing Costs and Benefits
For each risk to be managed, estimate the expected consequences in
quantitative terms. For each proposed risk response, assess the incremental
costs and timing impact involved. After comparing this data, consider
business-justified preventative actions for inclusion in the project plan.
The expected cost of a risk, as usual, is based on loss-times-likelihood.
For this, you need the probability in numerical terms, as well as estimates of
the risk impact in terms of financial, schedule, and possibly other factors.
For a risk that was assessed as having moderate probability, the
historical records may provide an estimated probability of about 15 percent.
The impact of the risk must also be assessed quantitatively. For a risk that
represents three weeks of schedule slip and $2 million in cost and a
probability of 15 percent, the expected risk impact will be about one-half
week (which is probably not too significant) and $300,000 (which would be,
for most projects, very significant). In each case, this is 15 percent of the total
impact, shown graphically in Figure 8-6.
The consequences of each idea for avoiding or mitigating the risk in
time and money should be compared with the expected impact estimates to
see whether they are cost-justified. If an idea only mitigates a risk—lowering
the impact or probability of the problem—then the comparison is generally
between the cost for mitigation and difference between the before-and-after
estimates for the risk.
Determining whether a preventative is justified is always a judgment
call, and it may be a difficult one. It is made more so because the data is often
not very precise or dependable, making comparisons fairly subjective. The
exercise of comparing costs for risk prevention with the expected impact is
important, though, because it is human nature to attempt to prevent problems
whenever possible. You should not necessarily prevent a risk just because
you can. Seeking a risk-free project is illogical for two reasons. First, it is
impossible. All projects have some residual risk no matter how much you do
to avoid it. Second, a project with every possible risk prevention idea built
into the plan will be far too expensive and time-consuming to justify.
Figure 8-6. Expected Impact
For each potential idea that reduces or removes a project risk, contrast
the expected costs of the risk with the cost of prevention before pulling it into
the project plan. In the preceding case, with the expected half week of delay
and $300,000 in expense, an idea that requires a week of effort and costs $1.5
million would most likely not be adopted because the cure is nearly as bad as
the relatively unlikely risk. This situation would be similar to paying more for
insurance than the cost of the expected loss. A preventative that costs less and
requires little effort, though, may well represent a prudent plan modification.
Responding to some risks with high impact even though they seem to
have low assessed probabilities and expected consequences that position
them below your cutoff line on the rank-ordered list can be prudent, as
discussed earlier in this chapter. A decision to manage the example risk here
should also consider whether a $2 million unanticipated expense could be
absorbed by the organization. The incremental cost of the risk will never be
$300,000; it will either be nothing or $2 million. If a $2 million outlay is not
acceptable, a MiniMax strategy would lead you to invest in a risk response if
you can identify one that is effective and does not invalidate your project’s
overall net value.
Even if some of the ideas you generate for risk prevention prove to be
not cost-justified, the same (or similar) approaches may still have application
as contingency plans.
Managing the “Right” Risks
The decision to respond to a given risk can be complex. The question
posed in Chapter 1, “Can you manage project risks?” is difficult to answer
precisely because projects are always uncertain.
Risks, by definition, may or may not occur. There are no guarantees
that the actions you take to manage them will be beneficial because some of
the risks you choose to address will not happen. (In fact, they may not happen
precisely because of actions you took to manage them.) It is also true that
risks you choose not to manage might work out fine because at least some of
those also will not occur. In statistics, the concepts of Type 1 and Type 2
errors are used to characterize false positives (such as when a medical test
indicates a patient has a disease that is not present) and false negatives (such
as the opposite, a medical test that indicates a patient is free of a disease that
he or she has).
There are four possible outcomes for any given risk. It will either
happen or not, and we will choose to respond to it or not. The following table
summarizes these cases:
Type 1 errors in risk management are the risks we manage that do not
happen. They involve waste because the investment made in responding did
not appear ultimately to be necessary. For projects, this is not good, but the
other type of error, risks we accept that do befall us, is almost always much
worse. Inevitably both kinds of error are possible, and there is ample
opportunity even on smaller projects for second-guessing.
Because the overall consequences are generally less severe for Type 1
errors, most experienced project leaders tend to have a bias toward
responding to risks to minimize problems, particularly risks that represent
substantial (or unknown) impact. This is reflected in the table in Figure 8-4.
As a practical matter, though, it is never that easy. Justifying action and
obtaining resources in advance of risks that do not seem to be very likely can
be very tough to sell. Key stakeholders may not believe your analysis and
may fail to support your proposals to manage risks. Whenever you decide to
manage a risk that fails to develop, there is high potential for at least some
after-the-fact criticism: “You squandered resources doing unnecessary work.”
For risks that never happen, you can never prove that a risk-preventative
action was justified, and in most cases you will not even be able to show with
any precision that your estimates of potential harm were accurate. For these
Type 1 cases, however, at least you were ready, and sometimes there are
positive effects of your actions (contributors trained in new skills, backup
equipment available, or other longer-term benefits) that may partially justify
the work you did.
The Type 2 case involves failing to manage a risk that happens. The
decision to do this during planning is not particularly difficult because
accepting a risk does not require you to do anything other than note and
monitor the work (which presumably you are already doing anyway). You
may also be unable to respond to some risks even if you want to because of
resource or other constraints that preclude any action or because your
proposal to respond was not approved by your sponsor or key stakeholders.
Even low (or assumed to be low) probability risks do happen, however. The
PERIL database is filled with black swans that caused a lot of anguish to
project teams that were not expecting any trouble. Criticism following the
risk, especially if the effect is substantial, can be very harsh: “How could you
fail to see and manage this [now, in retrospect] obvious problem?”
Overall, it is best to respond to most significant identified risks, and it
will be easiest to do this if you identify thresholds for both probability and
impact that align with your stakeholder’s risk tolerance. If a risk representing
a month of slip or a few hundred thousand dollars of unanticipated expense is
unacceptable, use your risk assessment data to justify responding to risks that
could exceed these limits. Document your risk plans, share them with key
stakeholders and decision makers, and use your communications to defer
(some) of the later criticism for risk management investments that you do not
use. In particular, whenever the primary reason you did not respond to a
major potential project problem was a lack of funding, support, or other
approval, document the particulars. Misery may or may not love company,
but it is always preferable not to be catching abuse all by yourself.
Updating Your Plans
Integrating your risk responses into your plans is the final step in risk
response planning. For each cost-justified (or otherwise approved) risk
avoidance, mitigation, or transfer idea, you need to update your project
planning documents. (Uncertain opportunities may also entail changes related
to exploiting, enhancing, and sharing of risks.) Most ideas will require
additional or different work, so the project work breakdown structure (WBS)
may shift, and there will likely be revisions to activity effort and duration
estimates. Any added work will require staffing, so the profiles in your
resource plan will also require updating. When updated plans create conflicts
with existing project constraints, you will face more replanning, which may
generate additional project risks.
Before adoption, each risk response idea must earn its way into the
project by lowering, not increasing, project risk. Before any modifications,
review the plan for unintended consequences and document the justification
for all additional project work.
Dealing with Risk Effects
For some risks, your best strategy may be to deal with risk effects
rather than causes. Avoidance, mitigation, and transfer, when justified and
added to the project, all serve to make a project less risky, but risks will
inevitably remain. For some risks, you have no influence on the root causes
or can find no preventative action that was cost-effective. For other risks, you
may have mitigation strategies that help but still leave substantial residual
risk. For most of the significant risks that remain, you either need to develop
contingency plans or decide to accept the risk.
Contingency Planning
Contingency planning deals with risk effects by generating plans for
recovery or fallback. The process for contingency planning is exactly the
same as for any other project planning. It is best conducted at the same level
of detail and using the same methodologies and tools as other project
planning.
Each contingency plan begins with the trigger event that signals that
the risk has occurred. The most effective risk triggers precede the risk
consequences by as much as possible. Early triggers increase the number of
potential recovery options, and in some cases they may permit you to reduce
the impact of the risk, so verify that the trigger event you plan to use is the
best option available.
Each risk to be managed with a contingency plan must also have an
owner. The risk owner should be involved with developing the initial
contingency plan, be willing to monitor for the trigger event, and be
responsible for maintaining the contingency plans. If the risk should occur,
the risk owner will be responsible for beginning to execute the contingency
plan, working toward project recovery. The owner of a project risk will most
often be the same person who owns the project activity related to the risk, but
for risks with particularly severe, project-threatening consequences, the
project leader may be a better choice.
General contingency planning strategies. Contingency planning for
risks often starts with leftover ideas. Some ideas may have been considered
for schedule compression (discussed in Chapter 6) but were not used. Others
could be risk prevention strategies that were not adopted in the preliminary
baseline plan for cost or other reasons. Although some of these ideas may be
simply adopted as contingency plans without modification, in other cases
they may need to be modified for after-the-fact use. Prevention strategies you
considered but did not use, such as using an alternate source for components
or schedule compression strategies for expediting outsourced activities, can
be documented as contingency plans with no modification. Risk avoidance
ideas you did not adopt can serve as contingencies after minor changes.
Employing an older technology, for example, might require additional work
to back out any dependencies on a newer technology that fails.
Contingency planning in itself is a powerful risk prevention tool
because the process of planning for recovery shows clearly how difficult and
time-consuming it will be to recover from problems. This provides additional
incentive for the project team to work in ways that will avoid risks. Always
strive to make risks and risk planning as visible as possible in project
communication. Your project team can work to avoid the potential problems
only if they are aware of them.
Contingency planning strategies for schedule risks. Whenever a risk
results in a significant delay, the contingency plan must seek an alternate
version of the work flow that provides either a way to expedite work so that
you can resume the project plan at some later point or a way to complete the
project on an alternate basis that minimizes impact to the project deadline.
Recovery involves the same concepts and ideas used for schedule
compression, discussed in Chapter 6. The baseline plan will require revision
to make effort available for recovery immediately following the risk, so other
work will need to be shifted, changed, or eliminated. You may be able to
delay the start of less crucial planned activities, postponing them to later in
the project. Any noncritical activity work that is simultaneous with or
scheduled to follow the risk event could be interrupted or postponed to allow
more focus on recovery. Some activity dependencies might be revised to
allow project activities to progress out of the planned sequence, freeing
contributors to work on recovery. In all of these cases, necessary activities
shift to later in the schedule, increasing the impact of future risks and creating
new failure modes and exposures as additional project work becomes
schedule critical.
It might even be possible to devise faster alternative approaches for
later project activities that could obtain acceptable (but possibly less
satisfactory) results.
Crashing project activities scheduled for later in the project to decrease
their duration can also help if the project has sufficient budget reserve or
access to the additional staffing. Shorter durations will permit later start dates
for scheduled work and potentially free up project effort for recovery. Simply
adding staff to the project to work on recovery may also be an option, if you
can get commitment from additional contributors. If you do plan to add
people, include all training and project familiarization required as part of your
baseline plan to minimize the inevitable disruption that follows the addition
of new staff. Without adequate preparation, absorbing new contributors will
delay your project even more.
It may not be possible to replan the project to protect the deadline,
especially if the risk relates to work late in the project. In such a case, the
contingency planning serves to minimize the slippage and to provide the data
necessary to document a new, delayed completion date.
A generic schedule contingency strategy involves establishing schedule
reserve for the project. Establishing schedule reserve is explored in more
detail in Chapter 10.
Contingency planning strategies for resource risks. For risks that
require significant additional resources, contingency planning involves
revising the resource plans to protect the project budget or at least to limit the
damage. Again, the process for this parallels the discussion for dealing with
resource constraints in Chapter 6.
The most common strategy is also one of the least attractive—working
overtime and on weekends and holidays. This tried-and-true recovery method
works adequately on most projects, providing that the resource impact is
minimal and project staffing is not already working significantly beyond their
normal workdays and workweeks. If the amount of additional effort required
is high, or if the project team is stretched too thin when the risk occurs, this
contingency strategy can backfire and actually make things worse by
lowering motivation, leading to higher staff turnover.
For some projects, contributors may be assigned to the project but
underused during part of it. If this is the case, shifting work around in the
schedule may allow them to assist with risk recovery and still effectively
meet other commitments. This tactic, like dealing with schedule risks using
float, tends to increase overall project risk later in the project.
Substituting approaches other than those planned may also reduce the
resources needed for the project, but whenever this is possible, it is generally
more appropriate to do it as part of the baseline plan. If there is a better way
to obtain an acceptable result, you should incorporate them into your baseline
plans, not view them as recovery tactics.
Particularly for resource risks, it may be impossible to avoid damage to
the overall resource plan and budget. All adverse variances increase the total
project cost, so there may be few (or no) easy ways left to cut back other
expenses to compensate.
Minimizing the impact of risk recovery involves contingency planning
that revises resource use in ways that protect the budget as much as possible.
Tactics such as assigning additional staff to later critical path activities—
borrowing people from other, lower-priority projects—may have little budget
impact. Expediting external activities using incentive payments and
outsourcing work planned for the project team may also be possible, but seek
approval in advance for the additional cost as part of your contingency
planning. If a contingency plan requires any training or other preliminary
work to be effective, prepare for this by making these activities part of your
baseline project plan.
A generic resource contingency strategy involves establishing a budget
reserve for the project, similar to the schedule reserve discussed earlier.
Budget reserve is discussed further in Chapter 10.
Contingency planning strategies for scope risks. Contingency
planning for scope risks is not too complicated. The plans involve either
protecting the specifications for the deliverable or reducing the scope
requirements. Attempting to preserve the requirements is done by adding
more work to the schedule (using tactics summarized previously), using
additional resources, or both. In most cases, it is difficult to assess in advance
the magnitude of change that this may require because the level of difficulty
in fulfilling requirements for modern projects is highly variable—from
relatively trivial in some cases to impossible in others. Contingency plans for
scope risks usually provide for some level of recovery effort, followed by a
review to determine whether to extend the project or to modify the scope
consistent with the current deadline (or, in extreme cases, to abandon the
project).
For many projects, scope risks may be managed by modifying the
project objective in order to provide most of the value of the project
deliverable in a way that is consistent with schedule and resource objectives.
The process for this, similar to that discussed in Chapter 6, starts with a
prioritized list of specifications. It may be possible to drop some of the
requirements entirely or to defer them to a later phase or project. There may
also be potential for relaxing some of the requirements, making them easier
to achieve. Although this can be done effectively for some projects in
advance, contingency planning for scope risks generally includes a review of
project accomplishments and any shifts in assumptions, so your decisions on
what to drop will be based on current data.
Risk Acceptance
For some risks, it may not be possible or worthwhile to plan
specifically for recovery. As outlined earlier in the chapter, some risks having
trivial consequences do not deserve much attention in advance. Other risks
may be significant but lack any effective response. Risks such as these
(assuming that the project still makes business sense) are generally accepted.
Acceptance as a general risk management technique also includes both
transfer and contingency planning because in both of these situations the risk
causes are not influenced and the risk either happens or it does not. For
transfer and for contingency planning, specific responses are planned in
advance to assist in recovery. For some risks, though, neither of these options
may be practical. When the consequences of a risk are sufficiently unclear, as
may be the case for some scope risks and many other project exposures,
planning for recovery in advance may be impossible. An example of this
might be a stated requirement to use new technology or hardware for the
project. In such a case, many potential problems, ranging from the trivial to
the insurmountable, are possible.
When a specific risk response is not an option, choices are still
available. If the risk is sufficiently serious, it may be the best course to
abandon the project altogether as too risky or consider a major change in the
objective. It is most common to review the status of all risks in your risk
register and proceed with the project having accepted the remaining overall
risk. If you choose to go forward, it is prudent to document accepted risks
thoroughly, discuss them with your sponsor and stakeholders, and secure
project-level schedule and budget reserves to assist in managing them. In
addition to hoping for the best, identify triggers and owners for all significant
accepted risks in your risk register, and ensure that each of them is actively
monitored as part of your tracking and execution.
Documenting Your Risk Plans and Risk Owners
For risks with multiple potential consequences or particularly severe
effects, you may want to generate more than one contingency plan. Before
finalizing a contingency plan (or plans), review them for overall cost and
probable effectiveness. If you do develop more than one response for a risk,
prioritize the plans, putting first the plan you think will be most effective.
Document all contingency plans, and include the same level of detail as
in the project plans: WBS, estimates, dependencies, schedule, resources
required, the expected project impact, and any relevant assumptions. For each
risk response plan, clearly specify the trigger event to detect that the risk has
happened. Also, include the name of the owner who will monitor the risk
trigger, maintain the contingency plan, and be responsible for its execution if
the risk occurs.
As part of the overall project documentation, document your risk
response plan, and work to make the risks visible. One method for increasing
risk awareness is to post a top-ten risk list (revised periodically) either on the
project Web site or with posters on the walls of project work areas. Ensure
adequate distribution and storage of all risk plans, and plan to review risk
management information at least quarterly.
Maintain your risk register as part of your overall risk management
plan, and use it to monitor risks. For each risk listed, include:
• A detailed description of the risk
• The risk owner, plus any others with assigned roles and
responsibilities
• The activities affected by the risk (including WBS codes)
• Any qualitative or quantitative risk analysis results (probability,
impact, and overall assessment)
• A summary of risk response actions in the project plan
• The risk trigger event
• Expected residual risk exposure
• A summary of contingency and fallback plans
Add risk plans to the other project documentation, and choose an
appropriate location for storage that is available to all project contributors and
stakeholders.
Managing a Specific Risk
Some years ago, a large multinational company initiated a yearlong
effort to establish a new European headquarters. Growth over the years had
spread people, computers, and other equipment all over Geneva, Switzerland,
and the inconvenience and expense for all of this had grown unacceptable.
The goal was to consolidate all the people and infrastructure into a modern,
new headquarters building. This effort involved a number of high-profile,
risky projects, and I was asked to manage one of them.
One particularly risky aspect of the project involved moving two large,
water-cooled mainframe computers out of the older data center, where the
systems had operated for many years, and into a more modern center in the
new headquarters building. In the new location, the systems would be
collocated with all the other headquarters computers and the
telecommunications equipment that tied them to other sites in Europe and
around the world. Both systems were critical to the business, so each was
scheduled to be moved over a three-day holiday weekend. It was essential
that each system be fully functional in the old data center at the end of the
week before the move and fully functional in the new data center before the
start of business following the holiday, three days later.
Most of the risks were fairly mundane, and they were managed by
means of thorough planning, adequate staffing, and extensive training, all
committed months in advance. Other precautions, such as additional data
backups, were also taken. The move itself was far from mundane, though,
because the old data center, for some reason, had been established on the fifth
floor of a fairly old building. The elevator in the building was small, about
one meter square, and could carry no more than the weight of three or four
people (who had to be on very friendly terms). When the systems were
originally moved into the building, a system-sized door had been cut into the
marble façade of the building, and a crane with a suspended box was used to
move the systems into the data center. Over the years, upgrades and
replacements had been moved in and out using the same method. (See Figure
8-7.)
Figure 8-7. Suspending Computing in Geneva
Up to the time of this project, only older hardware being replaced had
ever been moved out of the data center this way. In these cases, if there had
been a mishap it would not have affected operations because the older
systems were moved out only after the replacement systems were
successfully moved in and operational. For the relocation project, this was
not the case. Both systems had to be moved out, transported, and reinstalled
successfully. Any problem that arose 20 meters in the air would result in a
significant and expensive service interruption that would last far longer than
the allocated three days.
The new data center was, sensibly, at ground level; eliminating the
need to suspend multimillion-dollar mainframes high in the air was one of the
main reasons the project was undertaken. Successful completion of the
project would mean ground-level systems in the new data center and far
easier maintenance for all future operations.
In addition to the obvious risk of a CPU plummeting to the ground, the
short timing of the project also involved risks such as weather, wind, traffic,
injuries to workers, problems with the crane, and many other potential
difficulties. The assessment for most of these other risks resulted either in
adjustments in staffing, updates to the plan, or acceptance (depending on staff
experience and confidence that most of the anticipated problems could be
dealt with during the move).
The one remaining risk that concerned all of us was that one of the
mainframe computers might fall and smash into the sidewalk. The
consequences of this could not be managed during the three-day weekend, so
a lot of analysis went into exploring ways to manage this risk.
Risk assessment was the subject of significant debate, particularly with
regard to probability. Some thought it low, citing, “This is Switzerland; we
move skiers up the mountains this way all the time.” Others, particularly
people from the United States, were less optimistic. In the end, the consensus
was moderate. There was less debate on risk impact, which in this case was
literal. In addition to issues of cost and delay, there were significant other
concerns, such as safety, the large crater in the pavement, the noise, and
computer parts bouncing for blocks around.
The primary impact was in time and cost, and deemed high, so
considerable planning went into mitigating the risk. A number of ideas were
explored, including disassembly of the system for movement in pieces using
the elevator, building a lift along the side of the building (the two systems
were to be moved a month apart, so this cost would have covered both), using
padding or some sort of cushion on the ground, and a number of other even
less practical ideas. The disassembly idea was considered seriously but
deemed inappropriate because of timing and the discouraging report from the
vendor that “those systems do not always work right initially when we
assemble them in the factory.” The external lift idea was a good one, but
hardware that could reach to the fifth floor was unavailable. A large net or
cushion would have minimized the spread of debris but seemed unlikely to
ensure system operation. It was not until the problem was reframed that the
best idea emerged. The risk was not really the loss of that particular system; it
was the loss of a usable system.
A plan to purchase a new system and install it, in advance, in the new
data center would make the swift and successful move of the existing
hardware unnecessary. Once operations were transferred to the new
hardware, the old system could be lowered to the street and, if the removal
was successful, sold as used equipment. This was an effective plan for
avoiding the risk, but it had one problem—cost. The difference between the
salvage value of the current machine and the purchase price of a new one was
roughly $2 million. This investment was far higher than the expected
consequences of the risk, so it was rejected as part of the plan. We decided to
take as many precautions as possible and accept the risk.
All this investigation made the contingency planning easy because the
research we had done into acquiring a new system was really all that was
necessary. We ordered a new system and got a commitment from the vendor
to fill the order with the next machine built if there were any problems
moving the existing system. (The vendor representatives were happy to agree
to this, because they were heavily involved in many aspects of the
relocation.) Once the move had been completed successfully, the order could
be canceled with no penalty.
The consequences documented for the contingency plan were that the
system would be unavailable for about three weeks, and the incremental cost
of the replacement system would be roughly $3 million.
As it turned out, the same staff and basic plan were employed for both
mainframe moves, and both went without any incident. Although the
contingency plan was not used, everyone felt that the risk planning had been
a good investment. The process revealed clearly what we were facing, and it
heightened our awareness of the overall risk. It uncovered many related
smaller problems that were eliminated, which saved time and made the time-
critical holiday weekend work much easier. It also made all of us confident
that the projects had been carefully and thoroughly planned and that we
would be successful. Even when risk management cannot eliminate all the
risks, it is worthwhile to the project.
Bow Tie Analysis for Documenting Risk Responses
As discussed in Chapter 6, bow tie analysis provides a graphic
technique for documenting the root causes of risks. In addition to this, it is
also a powerful way to show the consequences of a risk, along with the
actions planned to manage it both before and (if needed) after. The name
“bow tie” derives from the overall appearance of the graphical format. The
causes and preventions fan in from the left into the risk event in the center.
Responses and consequences fan out to the right. The narrowing of the graph
in the center (similar in appearance to a bow tie) focuses on the point where
control could be lost.
Bow tie analysis and diagrams are often used for risks involving public
health and safety exposures, They can be very effective in conveying a
thorough summary of the risk situation and the effectiveness of the strategies
in place for dealing with it. Bow tie diagrams provide a simple format for
displaying the information in your project risk register. These diagrams are
often used to summarize the management of risks associated with airline
safety, tunnels, bridges, dams, power plants, and many other significant
sources of public concern.
Bow tie fault tree and recovery analysis can also be a useful tool for
failure diagnosis and was employed after the massive oil spill in 2010
following the failure of the BP Deepwater Horizon oil drilling mechanism. A
fault tree showing the sources of the problems in the Gulf of Mexico, coupled
with analysis of the recovery effort, helped in establishing needed
preventative and recovery requirements for future subsurface marine oil
wells.
Figure 8-8 shows a partial bow tie analysis for the computer system
relocation in the previous section.
Figure 8-8. Bow Tie Analysis Example
Key Ideas for Managing Activity Risks
• Determine root causes.
• Avoid, mitigate, or transfer risks with adverse consequences
whenever feasible.
• Develop contingency plans for remaining significant risks.
• Document risk plans and keep risk data visible.
• Monitor all risks in your risk register.
• Thirty grams of prevention is worth half a kilogram of cure
(approximately).
Panama Canal: Risk Plans (1906–1914)
Risk management represented one of the largest investments for the
Panama Canal project. Of the risks mentioned in Chapter 7, most were dealt
with using effective and, in several cases, innovative means.
The risk of disease, so devastating on the earlier project, was managed
through diligence, science, and sanitation. The scale and cost of this effort
were significant, but so were the results. Widespread use of methods for
mosquito control under the guidance of Dr. William Gorgas was effective on
a scale never seen before. Specific tactics used, such as frequently applying
thin films of oil on bodies of water and the disciplined dumping of standing
water wherever it gathered (which in a rain forest was nearly everywhere),
were so effective that their use worldwide in the tropics continues to this day.
Once the program for insect control was in full effect, Panama was by far the
healthiest place anywhere in the tropics. Yellow fever was eliminated.
Malaria was rare, as were tuberculosis, dysentery, pneumonia, and a wide
range of other diseases common at the time. Not only were the diseases
spread by mosquitoes virtually eliminated, work also went much faster
without the annoyance of the omnipresent insects. Although some estimates
put the cost at US$10 for every mosquito killed, the success of the canal
project depended heavily on Dr. Gorgas to ensure that the workers stayed
healthy. This risk was managed thoroughly and well.
For the risk of frequent and sudden mudslides, there were no elegant
solutions. As the work commenced, it seemed to many that “the more we
dug, the more remained to be dug.” Unfortunately, this was true; it proved
impossible to use the original French plan for the trench in the Culebra Cut to
have sides at 45 degrees (a 1:1 slope). This angle created several problems,
the largest of which was the frequent mudslides. In addition, the sides of the
cut pressed down on the semisolid clay the excavators were attempting to
remove, which squeezed it up in the center of the trench. The deeper the
digging, the more the sides would sink and the center would rise; like a fluid,
it would seek its level. The contingency plan was inelegant but ultimately
effective—more digging. The completed canal had an average 4:1 slope,
which minimized the mudslides and at least partially stabilized the flowing
clay. This brute-force contingency plan not only resulted in much more soil
to dispose of, it represented about triple the work. Erosion, flowing clay, and
occasional mudslides continue to this day, and the canal requires constant
dredging to remain operational.
Dealing with the risks involved with building the enormous locks
required a number of tactics. As with the mudslides, the massive concrete
sides for the locks were handled by brute force and overengineering. Cement
was poured at Panama on a scale never done before. The sides of the locks
are so thick and so heavily reinforced that even after close to a century of
continuous operation, with thousands of ship passages and countless
earthquakes, the locks still look much as they did when they were new.
The mechanical and electrical challenges were quite another matter.
The locks were colossal machines with thousands of moving parts, many of
them huge. Years of advance planning and experimentation led to ultimate
success. The canal was a triumph of precision engineering and the use of new
steels. Vanadium alloy steels used were developed initially for automotive
use, and they proved light and strong enough to serve in the construction of
doors for the locks. Holding the doors tightly closed against the weight of the
water in a filled lock required a lot of mass, mass that the engineers wanted to
avoid moving every time the doors were opened or closed. To achieve this,
the doors are hollow. Whenever they are closed, they are filled with water
before the lock is filled, providing the necessary mass. The doors are then
drained before they are opened to allow the ships raised (or lowered) in the
locks to pass through.
Even with this strategy, moving doors of this size and weight required
the power of modern engines. The choice of electrical operation was
complicated and required much innovation (the first all-electric factory in the
United States was barely a year old at the time of this decision), but
electricity provided a number of advantages. With electric controls, the entire
canal system can be controlled centrally. Scale models were built to show the
positions of each lock in detail. The lock systems are all controlled using
valves and switches on the model, and mechanical interlocks beneath the
model prevent errors in operation, such as opening the doors on the wrong
end of a lock or opening them before the filling or draining of water is
complete. In one place, operators can monitor overall status for all 12 locks.
When George Goethals began to set all of this up, he realized that
neither he nor anyone else had ever done anything like it. For most of the
controls and the more than a thousand electric motors the canal required,
Goethals managed risk by bringing in outside help. He awarded a sizable
contract to a rapidly growing U.S. company known for its expertise in
electrical systems. Although it was still fairly small and not known
internationally, the General Electric (GE) Company had started to build a
worldwide reputation by the time the Panama Canal opened. This was a huge
contract for GE, and it was the company’s first large government contract.
Such a large-scale collaboration of private and public organizations was
unknown prior to this project. The relationship used by Goethals and GE
served as the model for the Manhattan Project during World War II and for
countless other modern projects in the United States and elsewhere. For good
or ill, the rise of the modern military-industrial complex began in Panama.
Despite the project’s success in dealing with most risks, explosives
remained a significant problem throughout construction. As in many
contemporary projects, loss of life and limbs while handling explosives was
common. Although stringent safety precautions helped, the single largest
cause of death on the second Panama Canal project was TNT, not disease.
For this risk, the builders found no solutions or viable alternatives, so
throughout the project they were quite literally “playing with dynamite.”
Chapter
9
Quantifying and Analyzing Project Risk
Knowledge is power.
—FRANCIS BACON
Information is central to managing projects successfully. Knowledge of
the work and potential risk serves as the first and best defense against
problems and project delay. The overall assessment of project risk provides
concrete justification for necessary changes in the project objective, so it is
one of the most powerful tools you have for transforming an impossible
project into one that can be successful. Project-level risk rises steeply for
projects with insufficient resources or excessively aggressive schedules, and
risk assessments offer compelling evidence of the exposure this represents.
Knowledge of project risk also sets appropriate expectations for the project,
both for the deliverables and for the work that lies ahead. The focus of this
chapter is analyzing overall project risk, building on the foundation of
analysis and response planning for known activity risks discussed in Chapters
7 and 8.
Project-Level Risk
Considered one by one, the known risks on a project may seem
relatively easy to deal with, overwhelming, or somewhere in between.
Assessing risk at the activity level is necessary, but it is not sufficient. You
also must develop a sense of overall project risk. Overall project risk arises,
in part, from all the aggregated activity-level risk data, but it also has a
component that is more pervasive, coming from the project as a whole. High-
level project risk assessment was discussed in Chapter 3, using methods that
required only information available during initial project definition. Those
high-level techniques—the risk framework, the risk complexity index, and
the risk assessment grid—may also be reviewed and revised based on your
project plans.
As the preliminary project planning process approaches completion,
you have much more information available, so you can assess project risk
more precisely and thoroughly. There are a number of useful tools for
assessing project risk, including statistics, metrics, and modeling and
simulation tools. Risk assessment using planning data may be employed to
support decisions, to recommend project changes, and to better control and
execute the project.
Some sources of overall project risk include:
• Unrealistic deadlines: High-tech projects often have inappropriately
aggressive schedules.
• No or few metrics: Measures used for estimates and risk assessment
are inaccurate guesswork.
• “Accidental” project leaders: Projects are led by team members
skilled in technical work but with no project management training.
• Inadequate requirements and scope creep: Poor initial definition
and insufficient specification change control are far too common.
• Project size: Project risk increases with scale; the larger the project,
the more likely it is to fail.
Some of these project-level risks are well represented in the PERIL
database, especially scope creep. Methods for determining overall project risk
can be effective in both lowering their impact and determining a project’s
potential for trouble. In addition, overall risk assessment scores can:
• Build support for less risky projects and terminate (or modify)
excessively risky projects
• Compare projects and help set relative priorities
• Provide data for renegotiating overconstrained project objectives
• Assist in determining required management reserve
• Facilitate effective communication and build awareness of project
risk
The techniques, tools, ideas, and metrics described in this chapter
address these issues.
Aggregating Risk Responses
One way to assess project risk is to add up all the expected
consequences of all of the project risks. To generate this, you need to sum the
estimated cost (or time) involved multiplied by the risk probability (the loss-
times-likelihood) aggregated for each risk in the project.
Another method for assessing project-level risk is accumulating the
consequences of the contingency plans. For this, sum the expected costs for
all the plans—their estimated costs weighted by the risk probabilities.
Similarly, you can calculate the total expected project duration increase
required by the contingency plans using the same probability estimates. For
example, if a contingency plan associated with a risk having a 10 percent
probability will cost $10,000 and slip the project by ten days, the contribution
to the project totals will be $1,000 and one day (assuming the activity is
critical), respectively.
You may also generate similar data by using the differences between
Program Evaluation and Review Technique (PERT)–based expected
estimates and the most likely activity estimates. Summing these estimates of
both cost and time impact for the project will generate an assessment roughly
equivalent to the contingency plan data.
Although these sums of expected consequences can provide a sense of
overall project risk, they will tend to underestimate total risk, for a number of
reasons. First, this analysis assumes that all project risks are independent,
with no expected correlation. The assumption of negligible correlation is
generally inappropriate for real projects; most project risks become much
more likely after other risks have occurred. Project activities are linked
through common methodologies, staffing, and other factors. Also, projects
have a limited staff, so whenever there is a problem, nearly all of the project
leader’s attention (and much of the project team’s) will be on recovery.
Distracted by problem solving, the project leader will focus much less on all
the other project activities, making additional trouble elsewhere that much
more likely.
Another big reason that overall project risk is underestimated using this
method is that the weighted sums fail to account for project-level risk factors.
Overall project-level risk factors include:
• Inexperience of the project manager
• Weak sponsorship
• Reorganization, business changes
• Regulatory issues
• Lack of common practices (life cycle, planning, and so forth)
• Market window or other timing assumptions
• Insufficient risk management
• Inadequate project decomposition resulting in inefficient work flow
• Unfamiliar levels of project effort
• Low project priority
• Poor motivation and team morale
• Weak change management control
• Lack of customer interaction
• Communications issues
• Poorly defined infrastructure
• Inaccurate (or no) metrics
The first two factors on the list are particularly significant. If the
project leader has little experience running similar projects successfully, or if
the project has minimal support, you can increment the overall project risk
assessment from summing expected impacts by at least 10 percent for each.
Similarly, make adjustments for any of the other factors that appear relevant
to your project. Even after these adjustments, the risk assessment will still be
somewhat conservative because unknown project risk impacts are not
included.
Compare the total expected project duration and cost impacts related to
project risks with your preliminary baseline plan. Whenever the expected risk
impact for either time or cost exceeds 20 percent of your plan, the project is
very risky. For particularly risky projects, plan to use this project risk data on
cost and schedule impact to negotiate project adjustments, justifying
management reserve, or both.
Project Modeling and Simulations
The purpose of considering overall project uncertainty is to determine
and characterize bounds for potential project outcomes. Single-value
estimates lead to deterministic-looking project analyses with crisp, exact
schedules and budgets. In reality, any project estimate can be off, some by
quite a lot. Three-point estimating and other techniques that challenge the
illusion of precision are useful for understanding risk and the spectrum of
possible project outcomes. Using three-point estimates to define a range
(discussed in Chapters 4 and 5 with regard to estimate uncertainty and in
Chapter 7 for analysis of activity risk) is a relatively simple approach for this,
based on range estimates. Simple models such as PERT methodology use
simple approximations based on three-point estimates to gauge project
uncertainty. Computer simulation techniques support the use of more
complicated (though not necessarily more meaningful or accurate)
distribution and range data. Even eyeball project analysis based on worst-case
estimates and freehand, bell-shaped distributions can provide insight into
project risk and uncertainty.
PERT and Related Techniques for Project Risk Analysis
PERT was the first method that attempted to use systematic risk
analysis to quantify overall project risk., It was created not by project
managers but at the direction of the U.S. military to deal with the increasingly
common cost and schedule overruns on very large U.S. government projects.
The larger the programs became, the bigger their overruns. Generals and
admirals are not patient people, and they hate to be kept waiting. Even worse,
the U.S. Congress got involved whenever costs exceeded the original
estimates, and the generals and admirals liked that even less.
The principal objective of PERT was to use detailed risk data at the
activity level to predict project outcomes. For schedule analysis, project
teams were requested to provide three estimates: a most likely estimate that
they believe would be the most common duration for work similar to the
activity in question, and two additional estimates that define a range around
the most likely estimate with a goal of including all realistic possibilities for
work duration.
Figure 9-1 shows a typical time distribution for PERT, defined by the
three estimates: an optimistic estimate, to, at the low end; a most likely
estimate, tm, at the peak somewhere in the middle; and a pessimistic estimate,
tp, at the high end.
Originally, PERT analysis assumed a continuous Beta distribution of
outcomes defined by these three parameters, shaped as in the graph in Figure
9-1. The Beta distribution was chosen because it is relatively easy to work
with and it can skew to the left (as in Figure 9-1) or to the right, based on the
three estimating parameters. (When the estimates are symmetric, the Beta
distribution is equivalent to the normal distribution: the Gaussian, bell-shaped
curve.) Using the three-point estimate data, you can calculate an expected
estimate, te, representing the 50 percent point for the distribution using a
simple weighted average.
Figure 9-1. PERT Estimates
Some issues with PERT were discussed in the earlier chapters, but
there is an additional issue with using PERT for project schedule analysis.
PERT systematically underestimates project risk whenever the critical path
method (CPM) shows more than one sequence of activities that could exceed
the deadline. Basic PERT calculations using expected durations will reveal a
resulting project with a somewhat longer predicted critical path, but analysis
using computer simulation will provide a more realistic assessment of overall
project schedule impact. Computer simulation uses pseudo random numbers
to generate duration estimates consistent with the activity range estimates. It
repeats the process over and over, each time based on new activity duration
estimates. CPM is used to calculate the project’s critical path for each of
these new schedules, and over many repetitions, this simulation builds a
histogram of the results.
Today’s computer simulation and modeling tools for project
management offer many alternatives to the Beta distribution. You may use
triangular, normal, Poisson, and many other distributions, or even histograms
defining discrete estimates with associated probabilities, as discussed in
Chapter 7. (For example, you may expect a 50 percent probability that the
activity will complete in 15 days, a 40 percent chance that it will complete in
20 days, and a 10 percent chance that it will complete in 30 days. These
scenarios are generally based on probabilities associated with known risks for
which worst-case incremental estimates are made—the five-day slip
associated with a contributor who may need to take a week of leave to deal
with a family situation, the 15-day slip associated with a problem that
requires complete redoing of all the work.)
As discussed in Chapter 7, the precise choice of the distribution shape
is not terribly important, even for activity-level risk analysis. At the project
level, it becomes even less relevant. The reason for this is that the probability
density function for the summation of randomly generated samples of most
types of statistical distributions (including all the realistic ones) always
resembles a normal, bell-shaped, Gaussian distribution. This is due to the
central limit theorem, well established by statisticians, and it is why the
analysis for a project with a single, dominant critical path always resembles a
symmetric, bell-shaped curve. The normal distribution has only two defining
parameters, the mean and the variance (the square of the standard deviation).
For duration estimates using the Beta distribution, the mean and standard
deviation are estimated with the formulas introduced in Chapter 4:
where te is the expected duration (the statistical
mean)
to is the optimistic duration
tm is the most likely duration
tp is the pessimistic duration
and for the standard deviation (σ):
For a project with a single, dominant critical path, the expected
duration for the project is the sum of all the expected (mean) durations along
the critical path. The standard deviation for such a project, one measure of
overall project risk, can be calculated from the estimated standard deviations
for the same activities. PERT used the following formulas:
where
tproj = Expected project duration
CPi = Critical path activity i
tei = “Expected” CP estimate for activity i
σproj = Project standard deviation
= Variance for CP activity i
These formulas are actually valid only for projects having a single
dominant critical path. When additional paths are roughly equivalent in
length to the longest one, the PERT formulas will underestimate the expected
project duration, and they will overestimate the standard deviation. For such
projects, computer simulation will provide better results than the PERT
approximations. The main reason for this inaccuracy was introduced in
Chapter 4, in the discussion on multiple critical paths. There, the distinction
between early/on time and late was a sharp one, with no allowance for
degree. Simulation analysis using distributions for each activity creates a
spectrum of possible outcomes for the project, but the logic is the same: More
failure modes lead to lowered success rates. Because any of the parallel
critical paths may end up being the longest for each simulated case, each
contributes to potential project slippage. The simple project considered in
Chapter 4 had the network diagram shown in Figure 9-2, with one critical
path across the top (A-D-J) and a second critical path along the bottom (C-H-
L).
Figure 9-2. Project with Two Critical Paths
CPM and PERT analysis, as should be expected, show that there is
about one chance in four that the project will complete on time or earlier than
the expected durations associated with each of the critical paths. The
distribution of possible outcomes for the project has about one-quarter of the
left tail below the expected dates, and the peak and right tail are above it, as
in Figure 9-3. The resulting distribution is still basically bell-shaped, but
compared with the distributions expected for each critical path, it has a larger
mean and is narrower (having a smaller standard deviation).
To consider this quantitatively, imagine a project plan that uses 50
percent expected estimates and that has a single dominant critical path of 100
workdays (5 months) and a standard deviation of five workdays. (If the
distribution of expected outcomes is assumed symmetric, the PERT
optimistic and pessimistic durations—plus or minus three standard deviations
—would be roughly 85 workdays and 115 workdays, respectively.) PERT
analysis for the project says you should expect the project to complete in five
months (or sooner) five times out of ten and in five months plus one week
over eight times out of ten (about five-sixths of the time)—pretty good odds.
If a second critical path of 100 workdays is added to the project with
similar estimated risk (a standard deviation of five workdays), the project
expectation shifts to one chance in four of finishing in five months or sooner.
(Actually, the results of one simulation based on 1,000 runs shows 25.5
percent. The results of simulation almost never exactly match the theoretical
answer.) In the simulation, the average expected project duration is a little
less than 103 workdays, and the similar five-sixths point is roughly 107
workdays. This is a small shift (about one-half week) for the expected
project, but it is a very large shift in the probability of meeting the date that is
printed on the project Gantt chart—from one chance in two to one chance in
four (as expected).
Figure 9-3. PERT Results
Similar simulations for three and four parallel critical paths of
equivalent expected duration and risk produce the results you would expect.
For three paths of 100 workdays, the project expectation falls to one chance
in eight of completing on or before 100 workdays (a simulation of this
showed 13 percent) and an expected duration of roughly 104 workdays. The
project with four failure modes has one chance in 16 (6.3 percent in the
model), and the mean for the project is a little bit more than 105 workdays.
The resulting histogram for this case is shown in Figure 9-4, based on 1,000
samples from each of four independent, normally distributed parallel paths
with a mean of 100 workdays and a standard deviation of five workdays.
(The jagged distribution is typical of simulation output.)
For these multiple–critical path cases, the mean for the distribution
increases, and the range compresses somewhat, reducing the expected
standard deviation. This is because the upper data boundary for the analysis is
unchanged, while each additional critical path will tend to further limit the
effective lower boundary. For the case in Figure 9-4, the project duration
always equals the longest of the four, and it becomes less and less likely that
this maximum will be near the optimistic possibilities with each added path.
Starting with a standard deviation for each path of five workdays, the
resulting distribution for a project with two similar critical paths has a
standard deviation of about 4.3 workdays. For three paths it is just under four
workdays, and with four it falls to roughly 3.5 workdays, as seen in Figure 9-
4. For the same reasons, the resulting distributions also skew slightly to the
left; the data populating the histograms is being compressed, but only from
the lower side.
Computer simulation analysis of this sort is most commonly performed
for duration estimates, but effort and cost estimates may also be used. As
with schedule analysis, three-point cost estimates may be used to generate
expected activity costs and to sum them for the entire project. Because all
costs are cumulative, the PERT cost analysis formulas analogous to those for
time analysis deliver results roughly equivalent to simulation.
An additional factor that reduces the accuracy of project risk models is
that, by default, all risks are assumed to be independent. In a set of risks, the
formulas, simulations, and other analysis treats each potential risk event on
its own. Yet project risks are rarely independent. Risk probabilities are
generally highly correlated for a number of reasons. Activities share staff and
resources, so problems in one part of a project’s plan often cascade into other
parts because of shared root causes, because of similar analysis defects, or
just because of the increased stress that accompanies a setback. Because risks
are correlated positively, the overall potential for adverse impact for the
project will tend to be underestimated unless the analysis includes an
adequate allowance for related risks.
Figure 9-4. Histogram Generated by Simulation
Software for Project Modeling and Decision Support
Simulation analysis uses computers, and for this reason it was
impractical before the 1960s (which is why PERT depended on simplified
approximations). Once computer-based analysis was practical, Monte Carlo
simulation techniques began to be widely used to analyze many kinds of
complex systems, including projects. Initially, this sort of analysis was very
expensive (and slow), so it was undertaken only for the largest, most costly
projects. Computational restrictions are no longer an issue with today’s
modeling tools and inexpensive desktop systems.
The issue of data quality for schedule risk analysis was also significant
in early implementations, and this drawback persists. Generating range
estimates remains difficult, especially when defined in terms of percent tails,
as is generally done when describing three-point estimates in most project
management literature. Considering that the initial single-point most likely
estimates are generally not very precise to start with, the two additional upper
and lower boundary estimates are likely to be even worse. Because at least
some of the input data is inexact, the garbage-in/garbage-out problem is
always a concern with Monte Carlo schedule analysis.
This, added to the temptation for misuse of the optimistic estimates by
overeager managers and project sponsors, has inhibited widespread use of
computer simulation for many projects. This is unfortunate because even if
range estimate analysis is applied only to suspected critical activities using
manual approximations, it can still provide valuable insight into the level of
project risk. Some effective methods require only modest additional effort,
and there are a number of techniques, from manual approximations to full
computer simulation. A summary of choices follows.
Manual approximations. One way to apply these concepts was
discussed earlier in this book. If you have a project scheduling tool and have
entered your project schedule information into the database, most of the
necessary work is already done. The duration estimates in the database are a
reasonable first approximation for the optimistic estimates or for the most
likely estimates (or for both). To get a sense of project risk, make a copy of
the database and enter new estimates for every activity where you have a
worst-case or a pessimistic estimate. The Gantt chart based on these longer
estimates will display end points for the project that are farther out than in the
original schedule. By associating a normal distribution with these points, a
rough approximation of the output for a PERT analysis may be inferred.
The method used for scaling and positioning the bell-shaped curve can
vary, but at least half of the distribution ought to fall between the lower likely
boundary and the upper pessimistic limits defined by the end points of the
two Gantt charts. Because it is very unlikely that all the things that could go
wrong in the project will actually happen, the upper boundary should line up
with a point several standard deviations above the mean, far out on the
distribution tail. (Keep in mind, however, that even your most pessimistic
worst-case schedule accounts for no unknown project risk.) The initial values
in the scheduling database are probably somewhere below the mean of the
distribution, although the exact placement should be a function of perceived
accuracy for your estimates and how conservative or aggressive the estimates
are. A histogram similar to that in Figure 9-5, using the initial plan as about
the 20 percent point (roughly one standard deviation below the mean) and the
worst-case plan to define the 99 percent point (roughly three standard
deviations above the mean), could serve as a first approximation.
Figure 9-5. PERT Approximation
If the result represented by Figure 9-5 looks unrealistic, it may improve
things if you calculate expected estimates, at least for the riskiest activities on
or near a critical path. If you choose to do the arithmetic, a third copy of the
database can be populated with expected estimates, defining the mean (the 50
percent point) for the normal distribution. The cumulative graph of project
completion probabilities equivalent to Figure 9-5 looks like Figure 9-6.
Figure 9-6. Cumulative PERT Estimates
Although this sort of analysis remains subjective, the additional effort
it requires is small once you generate a preliminary schedule for the project,
and it can provide valuable insight into project risk.
One of the most valuable things about techniques that make schedule
risk visible is that they provide a concrete, specific result. The results of this
analysis will either look reasonable to you or seem “wrong.” If the results
seem realistic, they are probably useful. If they do not look credible, it
usually indicates that additional planning is warranted. Improbable-looking
results are a good indication that your activity list is incomplete, your
estimates are inaccurate, you missed some dependencies, you underestimated
some risks, or your preliminary plan has some other defect.
Even this quick and dirty type of schedule risk approximation provides
insight into the thoroughness of your project plan.
Computer spreadsheets. The next step up in sophistication involves a
computer spreadsheet. This is particularly useful for resource analysis, where
everything is cumulative. Spreadsheets are a very easy way to quickly assess
three cost (or effort) estimates to derive an overall project-level budget
analysis. A list of all the activities in one column with the most likely and
range estimates in adjacent columns can be readily used to calculate expected
estimates and variances for each activity and for the project as a whole. Using
the PERT formulas for cost, it is simple to accumulate and evaluate data from
all the project activities (not just from the critical path). The sum of all the
expected costs and the calculated variance can be used to approximate project
budget risk. Assuming a normal distribution centered on the sum of the
expected cost estimates with a spread defined by the calculated standard
deviation approximates the range that may be expected for project cost.
For the reasons outlined earlier, similar duration estimate analysis will
underestimate the expected project duration and overestimate the standard
deviation, but it could be useful for a simple or small project.
Computer scheduling tools. True Monte Carlo simulation analysis
capability is not common in most low-end and midrange computer-based
scheduling tools, and what is built in to support three-point activity duration
estimates tends to be implemented in quirky and mysterious ways. It is
impractical to list all the available scheduling tools here, so the following
discussion characterizes them generically.
Dozens of such tools are available for project scheduling, ranging from
minimalist products that implement rudimentary activity analysis to high-end,
Web-enabled enterprise applications. Often, families of software offering a
range of capabilities are sold by the same company. Almost any project
management scheduling tool may be used for determining the project critical
path, but schedule risk analysis using most of these tools, even some fairly
expensive ones, often requires the manual analysis discussed previously or
the purchase of additional, specialized software (more on this specialized
software follows). In general, scheduling tools are set up for schedule
analysis using single-point estimates to determine critical path, and three-
point estimate analysis requires several copies of the project data (or a scratch
pad version for what-if analysis) to analyze potential schedule variance.
Some products (including Microsoft Project) provide for the entry of three-
point estimates and some rudimentary analysis, but this is typically based on
calculations (as with PERT), not simulation.
Some high-end project management tools, which are both more
capable and more costly than the more ubiquitous midrange tools, provide
integrated Monte Carlo simulation analysis, either built-in or as optional
capabilities. Even with the high-end tools, though, schedule simulation
analysis requires an experienced project planner with a solid understanding of
the process.
Computer simulation tools. Tools that provide true Monte Carlo
simulation functionality are of two types, designed to be either integrated
with a computer scheduling tool or for stand-alone analysis. Again, many
options are available in both of these categories.
Quite a few applications are designed to provide simulation-based risk
analysis that either integrate into high-end tools or “bolt onto” midrange
scheduling packages. If such an add-on capability is available for the
software you are using, simulation analysis can be done without having to
reenter or convert any of your project data. With the stand-alone software,
project information must be input a second time or exported. Unless you also
need to do some nonproject simulation analysis, Monte Carlo simulation
tools designed to interface directly with scheduling applications are generally
a less expensive option.
In addition to products specifically designed for Monte Carlo schedule
analysis, general-purpose simulation applications are available, including
decision support software and general-purpose statistical analysis software.
For the truly masochistic, it is even possible to do Monte Carlo simulations
using only a spreadsheet. (Microsoft Excel, for example, includes functions
for generating random samples from various distribution types as well as
statistical analysis functions for interpreting the data.)
Whatever option you choose, there are trade-offs. Some techniques are
quick and relatively easy to implement, providing subjective but still useful
insight into project risk. Other, full-function Monte Carlo methods offer very
real risk management benefits, but they also come with costs, including
investment in software, the generation of more data, application expertise,
and increased effort. Before deciding to embark on an elaborate project
Monte Carlo simulation analysis, especially the first time, carefully consider
the costs and added complexity.
A primary benefit of any of this risk analysis is the graphic and visible
contrast between the deterministic-looking schedule generated by point-
estimate critical path methods, and the range of possible end points (and
associated probabilities) that emerge from these methods. The illusion of
certainty fostered by single-estimate Gantt charts is inconsistent with the
actual risk present in modern projects. The visible variation possible in a
project is a good antidote for excessive project optimism.
Also, keep in mind that precise-looking output may foster an illusion of
precision. The accuracy of the output generated by these methods can never
be any better than that of the least precise inputs. Rounding duration
estimates to whole days for input is general practice yet results with many
decimal places are reported, especially by Monte Carlo simulation software.
This is particularly ironic considering the quality of typical project estimates.
In project environments that currently lack systematic project-level risk
analysis, it may be prudent to begin with a modest manual approximation
effort on a few projects and expand as necessary for future projects.
Integrated Schedule/Cost Assessment
In the discussions of schedule and resource risk earlier in the book,
there was a good deal of emphasis on the interrelationship between time and
cost, particularly in relation to duration and cost/effort estimating. It is always
risky to advance a project where the timing estimates are inconsistent with
the staffing or financial assumptions.
The linkage between schedule and cost is also significant at the overall
project level. Aggregated schedule risk (whether assessed through
aggregating risk data or by using modeling or simulation techniques such as
those explored later in this chapter) will invariably directly affect costs. There
are a number of reasons for this, including:
• Work that takes longer than expected nearly always requires
additional effort and therefore funding.
• Slippage of activities and milestones often results in expediting,
crashing, or other resource-consuming tactics for following work, in
an attempt to recover the schedule.
• Doing work later than it was originally scheduled may entail
additional costs, including contract fee adjustments, replacement of
perishable or other time-sensitive resources, extended use of facilities
or specialized expertise, last-minute rescheduled travel, and other
unanticipated expense.
• Penalties and other direct financial consequences may be caused by
any deadline delays (often exacerbated by a reduction in the value of
a late deliverable).
Carefully consider the cost consequences of your overall project
schedule uncertainty, both within your project and on other work and parallel
projects that could be affected by extended resource usage, slippage of
critical dependencies, “borrowed” staff, and other factors.
System Analysis
It is always a good idea to revisit your scope risks as part of your
overall project risk assessment, particularly for complex system projects.
Review your plans and initial design work, examining your scope
holistically. Inspect your flowcharts, functional block diagrams, defined
cases, subsystem decomposition, function or feature point assessment, or
other complexity analysis. Look for potential failure modes, excessive
interdependencies or other linkages, and other system-level indications of
structural risk.
Contrast your analysis with that done for similar, past projects, and use
their experiences encountering unanticipated system difficulties as a guide
when assessing system-related project risk. If you lack past assessments of
complexity, consider reviewing the initial documents for previously
completed work to create some, and resolve to start collecting data going
forward.
Critical Chain Considerations
Critical Chain Project Management (CCPM) has enjoyed some
popularity in project management circles for well over a decade. Discussion
of CCPM started with the publication of a novel in 1997 by Eliyahu Goldratt,
Critical Chain. The novel describes applying concepts of the Theory of
Constraints to project plan analysis. The essential notion of the Theory of
Constraints is based on identifying resource constraints (or bottlenecks, or
pinch points) and then eliminating or neutralizing them. The Theory of
Constraints can be extraordinarily effective when fine-tuning the workflow
for manufacturing processes. Because projects are also about workflow,
Goldratt asks, “Why not use the Theory of Constraints to optimize them,
too?” The basic steps for constraint management are:
• Identify the most significant constraint.
• Exploit it by rescheduling preceding work to ensure that the
constraint (or bottleneck process) is running without interruption.
• Subordinate other processes to the constraint, providing buffer
capacity where needed to maximize throughput.
• Elevate the constraint, by increasing its capacity. Add resources
where needed to alleviate bottlenecks and improve related processes.
• Repeat. Once you are successful in removing the worst constraint, a
new pinch point will appear. Continuously improve to optimize the
system.
Applying these ideas to a project may lead to more robust, appropriate
project plans. It may also be used to create riskier projects with more
numerous failure modes. CCPM is often characterized as a way to compress
project schedules, based on the assumption that almost all duration estimates
are “padded” and can be reduced. Once all project estimates have been
trimmed and a new critical path calculated, portions of the time “saved” can
be allocated back to small feeding buffers along the new critical path(s) and
as a project buffer at the end of the project. Buffers are owned at the project
level, and the resulting project, including all the buffers, is assumed to be
both realistic and significantly shorter than the original plan. There are a few
reasons to be skeptical of this for real projects.
CCPM project analysis starts with the assumption that duration
estimates are uniformly too conservative and can be trimmed (using arbitrary
percent reductions, analysis based on the so-called procrastinating student
syndrome, assumptions derived from Parkinson’s Law, or other ideas). Data
in the PERIL database (not to mention common sense) should at a minimum
lead to healthy doubts about this; estimates are frequently too optimistic to
start with, not systematically too long.
In addition, projects are unique and inherently uncertain. It is perfectly
reasonable to optimize a manufacturing or other process that will be used
over and over, and for these processes you can collect precise, reliable
measurements to support your optimization effort. Most projects are poor
candidates for significant optimization efforts. You will only execute them
once, so there may be little to gain from the sort of analysis CCPM may
require. The lack of reliable data (remember, most project estimates are at
least partially based on guesses) provides another reason to be reluctant to
engage in excessive analysis.
CCPM also explicitly assumes that there will never be any multitasking
or sharing of resources between projects. While this may be desirable, it is
not realistic in actual modern projects.
Nonetheless, the main concepts of CCPM are really essentially similar
to project realities familiar to most project leaders. Many have observed that
the uniqueness of CCPM lies more in its vocabulary than in its substance.
The establishment of arbitrary project deadlines not related to schedule
analysis is not at all uncommon. Aggressive scheduling of deadlines is often
a result of pursuing a top-down goal, an opportunity choice made at project
initiation that results in a strong bias for adverse project schedule uncertainty
(and very little chance of early completion). The buffers of CCPM,
particularly the project buffer at the end, are equivalent to schedule reserves,
which are a widely understood and common technique for managing overall
project risk.
Even though CCPM is based on shaky assumptions and uses confusing
terminology, its application may be consistent with well-established
techniques for understanding and managing overall project risk. However,
project leaders who do employ CCPM will be wise to remain wary of
unrealistic or arbitrary assumptions, size the buffers consistently with overall
project risk, and retain ownership and control of all buffers and reserves at
the project level. In project environments that discourage establishing and
managing reserves, adopting some CCPM concepts could prove helpful.
Adoption of CCPM has been relatively rare in organizations, even
among those who consider its fundamental ideas compelling. CCPM as
described in its literature is difficult to adopt for managing complex projects
because of a lack of project management software tools that support it. Tools
for critical path analysis and even for simulation of uncertainty using Monte
Carlo techniques are easy to find and use, but applications that do a good job
with resource constraint analysis and project buffer management are not
common.
Questionnaires and Surveys
Questionnaires and surveys are a well-established technique for
assessing project risk. These can range from simple, multiple-response survey
forms, to assessments using computer spreadsheets, Web surveys, or other
computer tools. However you choose to implement a risk assessment survey,
it will be most effective if you customize it for your project.
Several years ago, I had the opportunity to help revise a risk
assessment survey implemented using a Microsoft Excel spreadsheet. A
dozen items were included, and each was given a score from 1 (low risk) to 5
(high risk). The 12 areas probed were:
1. Completeness of business requirements
2. Estimated labor effort
3. Likelihood of scope change
4. Use of remote staff
5. Credibility of project objective
6. Accuracy of cost estimates
7. Experience with required technology
8. Expected staff stability
9. Use of new skills or contract staff
10. External dependencies
11. Accuracy of duration estimates.
12. Other potential risk factors
For each item, the spreadsheet provided a detailed description and
guidance for the five possible responses. As an example, for item 2, the
additional information included, “This item addresses scale. Assess project
risk based on staff effort.” “1. Project is less than 3000 person-hours,” “2.
Project is under 6000 person-hours,” “3. Project is under 10,000 person-
hours,” “4. Project is under 25,000 person-hours,” “5. Project exceeds 25,000
person-hours.”
The items were not equally weighted. Of the first 11 items listed, the
initial four had a slightly higher weight, and the last three had slightly lower.
The weighted calculation generated a risk assessment rating between 1 and 5
for each project. Item 12 was not used unless its value exceeded the overall
calculated risk score for the first 11. If it was greater, that score replaced the
calculated risk score.
Every project, regardless of size, was required to submit the risk
survey. The survey was put to several uses. Any project with a low risk score
(1 or 2) was eligible to use a minimized version of the standard project
methodology and required to submit fewer documents and reports. Projects
having a high risk score (4 or 5) were required to include a minimum budget
reserve to be used in managing risk. The surveys also provided data for
analyzing risk across the portfolio of many hundreds of projects executed in
the organization each year.
Many organizations have and use risk surveys similar to this one. If a
survey or questionnaire is commonly used for projects similar to yours, very
little customizing may be required. Even if a format is available, it is always a
good idea to review the questions and fine-tune the survey before using it. If
you do not have a standard survey format, the following example is a generic
three-option risk survey that can be adapted for use on a wide range of
project types.
This survey approach to risk assessment also works best when the
number of total questions is kept to a minimum, so review the format you
intend to use and select only the questions that are most relevant to your
project risks. An effective survey may need to probe only a few key areas—
never more than about 20. If you plan to model yours on the following
survey, review each of the questions, and include only those most relevant to
your project. If you develop your own survey, limit the number of responses
for each question to three to five clearly worded responses. Ensure that the
listed responses address all relevant possibilities, with no gaps or overlaps
(for example: “1,” “2,” “3 or more”).
Once you have finalized the risk assessment questionnaire, the next
step is to collect data. Gather responses for each question from contributors
who participated in project planning.
Risk survey data is useful in two ways. First, you can analyze all the
data to produce an overall assessment of risk. This can be used to compare
projects, to set expectations, and to establish risk reserves. Second, you can
scan the responses question by question to find particular project-level
sources of risk—questions whose responses are consistently in the high-risk
category. Risk surveys can be very compelling evidence for needed changes
in project infrastructure or other project factors that increase risk. For high-
risk factors, ask, “Do we need to settle for this? Should we consider changes
that could reduce project risk?” Also investigate any questions with widely
divergent responses among your contributors. Conduct additional discussions
to establish consensus and common understanding within your project team.
Using a Project Risk Questionnaire
The list in Figure 9-7 provides questions typical of a qualitative risk
survey. Review the questions and pick a few that reflect your project
environment. Effective surveys are short, so limit the survey to about a dozen
total questions. Change them as necessary; section 2, “Technical Risks,”
normally requires the most intensive editing. The three sections focus on:
1. Project external factors (such as users, budgets, and schedule
constraints)
2. Development issues (such as tools, software, and hardware)
3. Project internal factors (such as infrastructure, team cohesion, and
communications)
When collecting data, encourage contributors to choose the response
that best describes your project. Whenever the best response seems to lie
between two choices, pick the one of the pair farther to the right.
After you have collected the survey data you can interpret the
information by assigning values of 1 to selections in the first column, 3 to
selections in the middle column, and 9 to selections in the third column. For
each item, sum up the responses, then divide each sum by the number of
responses tallied. To assess risk, use evaluation criteria such as:
• Low risk: 1.00–2.00
• Medium risk: 2.01–4.00
• High risk: 4.01–9.00
Average all questions to determine overall project risk, using the same
criteria. Although the results of this kind of survey are qualitative, they can
help you to identify sources of high risk in your project. For any items with
medium or high risk, consider changes to the project that might lower the
risk. Focus particularly on questions generating consistent responses in the
third column. Brainstorm ideas, tactics, or project changes that could shift the
response, reducing overall project risk.
Example Questions for a Risk Questionnaire
Section 1. Project Parameter and Target User Risks
1-1. Scope (project deliverable specification) stability.
Change is unlikely Small change is possible Changes are likely or
definition is incomplete
1-2. Project budget/resources
Committed and realistic Probably sufficient, with Insufficient or unknown
margin/reserve defined
1-3. Project Deadline
Realistic Possible; margin/ reserve
defined
Overly aggressive or
unrealistic
1-4. Total project length
Less than 3 months 3 to 12 months More than 12 months
1-5. Total effort-months estimated for the project.
Less than 30 30 to 150 More than 150
1-6. Peak size of core project team (key contributors critical to the
project).
5 or fewer 6 to 12 More than 12
1-7. Project manager experience
Finished more than one comparable
project successfully
Finished a project about the
same size successfully
None, or has done only
smaller or shorter projects
1-8. User support for the project objective (scope, schedule, and
resources)
Enthusiastic General agreement Small or unknown
1-9. Prioritization of scope, schedule, and resources (constrained,
optimized, accepted)
Known and agreed upon; only one
parameter is constrained.
Two parameters are
constrained, but one is
flexible.
No priorities set, or all
parameters are constrained.
1-10. Number of different types of users (market segments)
1 2 3 or more
1-11. Project team interaction with users during project
Frequent and easy At project start and end only Little or none
1-12. User need for the project deliverable
Verified as critical to user’s business Solves a problem; increases
user efficiency
Not validated or unknown
1-13. User enthusiasm generated by the project deliverable at project
start
High Some Little or none
1-14. User acceptance criteria for the project deliverable
Well defined Nearly complete Definition incomplete
1-15. User environment and process changes required to use the
project deliverable
None Minor Significant
1-16. User interface to operate or use the project deliverable
Identical to one now in use Similar to one now in use New or represents major
changes
1-17. Testing planned with actual users of the project deliverable
Early, using models or prototypes Midproject, at least for key
subdeliverables
Late in project; Beta test
Section 2. Technical Risks
General
2-1. Complexity of development
Less than recent
successful projects
Similar to recent successful
projects
Unknown or beyond recent similar projects
2-2. Development methodology
Standardized Similar to other recent
projects
Ad hoc, little, or none
2-3. Minimum team experience with critical development technologies
More than 1 year 6 months to 1 year Little or none
2-4. Tools, workstations, and other technical resources
Established, stable, and
well understood
All have been used before Some new facilities or tools required
2-5. Planned reuse from earlier projects
More than 75 percent 40 to 75 percent Little or none
2-6. Early simulation or modeling of deliverable
Will be done with existing
processes
Planned but will need new
processes
Not planned or not possible
2-7. Technical interfaces required (connections of this project’s
deliverable into a larger system or to deliverables from independent
projects)
None (stand-alone) and
well understood
Less than 5 and all are to
existing systems
More than 5 or more than 1 that is new
(parallel development)
Hardware
2-8. Hardware technology incorporated into deliverable
All established, existing
technology
Existing technology in a new
application
New, nonexistent, or unknown
technology
2-9. Testing
Will use only existing facilities
and processes
Will use existing facilities with
new processes
Unknown, or new facilities
needed
2-10. Component count
Number and type similar to
recent successful projects
Similar number, but some new
parts required
Unknown, larger number, or
mostly unfamiliar components
2-11. Component sources
Multiple reliable, managed
sources for all key components
More than one identified source
for all key components
A single (or unknown) source for
at least one key component
2-12. Component availability (lead times, relative to project duration)
Short lead times for all key
components
One or more key components
with long but known lead times
One or more key components
with unknown lead times
2-13. Mechanical requirements
All significant processes used
before
Some modification to existing
processes required
New, special, or long lead
processes needed
Software
2-14. Software required for deliverable
None or off-the-shelf Mostly leveraged or reused Mostly new development
2-15. Software technology
Very high-level language only
(4GL)
Standard language (C++, Java,
PERL, COBOL)
New or low-level language
(assembler)
2-16. Data structures required
Not applicable or relational Other database or well-defined files New data files
database
2-17. Data conversion required
None required Minor Major or unknown
2-18. System complexity
No new control or algorithm
development
Little new control or algorithm
development
Significant new or unknown
development
2-19. Processing environment of deliverable
Single system Multisystem but single site Distributed, multisite system
Section 3. Structure Risks
3-1. Project sponsorship and management commitment to project
objective (scope, schedule, and resources)
Enthusiastic Supportive Neutral or none
3-2. Project priority
High Moderate Low
3-3. Project manager experience
Success on recent similar project Managed part of a recent similar
project
Low or none on this sort of
project
3-4. Project manager authority
Most project decisions made by
PM
Limited decision making and
budget control
None; all decisions escalated
to others
3-5. Project manager focus
Full time on this project More than half time spent
managing this project
Less than half time spent
managing this project
3-6. Project plan
Plan is realistic and bottom-up Plan seems possible and has
defined reserve for
schedule/budget
Plan is unrealistic or no plan
exists
3-7. Project version control and change management
Well-defined and rigorously used
process
Informal but effective process Little or no change control
3-8. Project life cycle
Well defined with clear milestones
and phase deliverables
Defined but not rigorously used No formal life cycle
3-9. Project staffing
Available and committed All key people identified Significant staffing unknowns
remain
3-10. Subprojects
This project is independent of
other work
All related subprojects are well
defined and coordinated
Related subprojects are
loosely coupled or not clearly
defined
3-11. Project work environment
Your site; workplace known and
conducive to project progress
Some work must be done in an
unknown or poor work
environment
Mostly off-site or in a poor
work environment
3-12. Staffing commitment
All key people are full time Mix of full-time and part-time
staffing
All part-time or external
staffing
3-13. Team separation
Co-located Single site Multisite
3-14. Team enthusiasm for the project
High Adequate Reluctant or unknown
3-15. Team compatibility
Most of team has worked together
successfully
Some of team has worked
together before
New team
3-16. Lowest common manager for members of the core project team
Project leader Up to two levels in same
organization
More than two levels up, or
none
3-17. Number of outside organizations or independent projects that this
project depends on for inputs, decisions, or approvals
None One other More than one
3-18. Project dependence on external subcontractors or suppliers
Little or none (less than 10 Minor (10 to 25 percent) Significant (more than 25
percent) percent)
3-19. Quality of subcontractors
High—with relevant
subcontractors used
Good—solid references from
trusted sources
Doubtful or unknown
experience (or none)
3-20. Project communication
Frequent (weekly) face-to-face
status gathering and written
reporting
Sporadic, informal, or long-
distance status and reporting
Ad hoc or none
3-21. Project tracking
Frequent (weekly) reporting of
actual progress versus plan
Project leader tracks and deals
with plan exceptions reactively
Informal or none
3-22. Project documentation
Accurate, current documents are
online for project team
Current status and schedule are
available to project team
Documents known only to
project leader, or none
3-23. Project issue resolution
Well-defined process; issues
tracked and closed promptly
Informal but effective process Issues are not easily resolved
in a timely fashion
Analysis of Scale
Quantitative project analysis using all the preceding techniques, with
either computer tools or manual methods, is based on details of the project
work—activities, worst cases, resource issues, and other planning data. It is
also possible to assess risk based on the overall size of the project because the
overall level of effort is another important risk factor. Projects only 20
percent larger than previous work represent significant incremental risk.
Analysis of project scale is based on the overall effort in the project
plan. Projects fall into three categories—low risk, normal risk, and high risk
—based on the anticipated effort compared with earlier, successful projects.
Scale assessment begins by accumulating the data from the bottom-up project
plan to determine total project effort, measured in a suitable unit, such as
effort-months. The calculated project scale can then be compared with the
effort actually used on several recent, similar projects. In selecting
comparison projects, look for work that had similar deliverables, timing, and
staffing so that the comparison will be as valid as possible. If the data for the
other projects is not in the form you need, do a rough estimate using staffing
levels and project duration. If there were periods in the comparison projects
where significant overtime was used, especially at the end, account for that
effort as well. The numbers generated do not need to be precise, but they do
need to fairly represent the amount of overall effort actually required to
complete the comparison projects.
Using the total of planned effort-months for your project and an
average from the comparison projects, determine the risk:
• Low risk: Less than 60 percent of the average
• Normal risk: Between 60 percent and 120 percent of the average
• High risk: Greater than 120 percent of the average
These ranges center on 90 percent rather than 100 percent because the
comparison is between actual past project data, which includes all changes
and risks that occurred, and the current project plans, which do not. Risk
arises from other factors in addition to size, so consider raising the risk
assessment one category if:
• The schedule is significantly compressed
• The project involves new methods or technology
• 40 percent of the project resources are either external or unknown
Project Appraisal
Analysis of project scale can be taken a further step, both to validate
the project plan and to get a more precise estimate of risk. The technique
requires an appraisal, similar to the process used whenever you need to know
the value of something, such as a piece of property or jewelry, but you do not
want to sell it to find out. Value appraisals are based on the recent sale of
several similar items, with appropriate additions and deductions to account
for small differences. If you want to know the value of your home, an
appraiser examines it and finds descriptions of several comparable homes
recently sold nearby. If the comparison home has an extra bathroom, a small
deduction is made to its purchase price; if your house has a larger, more
modern kitchen, the appraiser makes a small positive adjustment. The process
continues, using at least two other homes, until all factors normally included
are assessed. The average adjusted price that results is taken to be the value
of your home—the current price for which you could probably sell it.
The same process can be applied to projects because you face a similar
situation. You would like to know how much effort a project will require, but
you cannot wait until all the work is done to find out. The comparisons in this
case are two or three recently completed similar projects, for which you can
ascertain the number of effort-months that were required for each. (This starts
with the same data used by the analysis-of-scale technique.)
From your bottom-up plan, calculate the number of effort-months your
project is expected to take. The current project can be compared to the
comparison projects, using a list of factors germane to your work. Factors
relevant to the scope, schedule, and resources for the projects can be
compared, as in Figure 9-7 (which was quickly assembled using a computer
spreadsheet).
Figure 9-7. Project Appraisal
One goal of this technique is to find comparison projects that are as
similar as possible, so the adjustments will be small and the appraisal likely
to be accurate. If a factor seems similar, no adjustment is made. When there
are differences, adjust conservatively, such as:
• Small differences: ±2–5 percent
• Large differences: ±7–10 percent
The adjustments are positive if the current project is bigger and
negative if the comparison project seems more challenging.
The first thing you can use a project appraisal for is to test whether
your preliminary plan is realistic. Whenever the adjusted comparison projects
average to a higher number of effort-months than your current planning
shows, your plan is almost certainly missing something. Whenever the
appraisal indicates a difference greater than about 10 percent compared with
the bottom-up planning, work to understand why. What have you
overlooked? Where are your estimates too optimistic? What activities have
you not captured? Also, compare the project appraisal effort-month estimate
with the resource goal in the original project objective. A project appraisal
also provides early warning of potential budget problems.
One reason project appraisals will generally be larger than the
corresponding plan is due to risk. The finished projects include the
consequences of all risks, including those that were invisible early in the
work. The current project planning includes data on only the known risks for
which you have incorporated risk prevention strategies. At least part of the
difference between your plan and an appraisal is due to the comparison
projects’ unknown risks, contingency plans, and other risk recovery efforts.
In addition to plan validation, project appraisals are useful in project-
level risk management. Whenever there is a major difference between the
parameters of the planned project and the goals stated in the project objective,
the appraisal shows why convincingly and in a very concise format. An
appraisal may also be useful for assessing risk due to scale and for providing
data needed to justify project-level resource reserves.
A project appraisal is also a very effective way to initiate discussion
with your project sponsor of options, trade-offs, and changes required for
overconstrained projects. All this will be addressed in Chapter 10.
Scenario Analysis
Computer simulation using range estimates for cost and duration
represents one type of scenario analysis. You can also deepen your insight
into overall project risk through the use of narratives. Review your plans,
playing a movie in your head as you consider the scheduled work, week by
week. Look for instances where parallel projects or other work may be in
conflict. Consider staffing profiles and verify that shared or scarce resources
will be sufficient. Overall, imagine the work as you expect it to proceed, and
think about what will be keeping you up at night.
Note the portions of your schedule that represent the greatest potential
exposure, initiate further analysis, and consider possible plan adjustments to
better manage the risks.
Project Metrics
Project measurement is essential to risk management. It also provides
the historical basis for other project planning and management processes such
as estimation, scheduling, and resource planning. Metrics drive behavior, so
selecting appropriate factors to measure can have a significant effect on
motivation and project progress. HP founder Bill Hewlett was fond of saying,
“What gets measured gets done.” Metrics provide the information needed to
improve processes and to detect when you should modify or replace an
existing process. Established metrics also are the foundation of project
tracking and control, establishing the baseline for measuring progress.
Defining, implementing, and interpreting a system of ongoing measures is
not difficult, so it is unfortunate that on many projects it either is not done at
all or is done poorly.
Establishing Metrics
Before deciding what to measure, carefully define the behavior you
want and determine what measurements will be most likely to encourage that
behavior. Next, establish a baseline by collecting enough data to determine
current performance for what you plan to measure. Going forward, you can
use metrics to detect changes, trigger process improvements, evaluate process
modifications, and make performance and progress visible.
The process begins with defining the results or behavior you desire.
For metrics in support of better project risk management, a typical goal might
be to reduce unanticipated project effort or to improve the accuracy of project
duration estimates. Consider what you might be able to measure that relates
to the desired outcome. For unanticipated project effort, you might measure
“total effort actually consumed by the project versus effort planned.” For
estimation accuracy, a possible metric might be “cumulative difference
between project estimates and actual durations, measured at the project
conclusion.”
Metrics are of three basic types: predictive, diagnostic, and
retrospective. An effective system of metrics will generally include measures
of more than one type, providing for good balance.
1. Predictive metrics use current information to provide insight into
future conditions. Because predictive metrics are based on speculative
rather than empirical data, they are typically the least reliable of the
three types. Predictive metrics include the initial assessment of the
project’s return on investment, the output from the quantitative risk
management tools, and most other measurement forecasts based on
planning data.
2. Diagnostic metrics are designed to provide current information about
a system. Based on the latest data, they assess the state of a running
process and may detect anomalies or reveal future problems. The
unanticipated effort metric suggested previously is based on earned
value, a project metric to be discussed later in this chapter.
3. Retrospective metrics report after the fact on how the process
worked. Backward-looking metrics report on the overall health of the
process and are useful in tracking trends. Retrospective metrics can be
used to calibrate and improve the accuracy of corresponding
predictive metrics for subsequent projects.
Measuring Projects
The following section includes a number of useful project metrics. No
project will need to collect all of them, but one or more measurements of
each type of metric, collected and evaluated for all projects in an
organization, can significantly improve the planning and risk management on
future projects. These metrics relate directly to projects and project
management. A discussion of additional metrics, related to financial
measures, follows this section.
When implementing any set of metrics, you need to spend some time
collecting data to validate a baseline for the measurements before you make
any decisions or changes. Until you have a validated baseline, measurements
will be hard to interpret, and you will not be able to determine the effects of
process modifications that you make. You will find more discussion on
selecting and using metrics in Chapter 10.
Predictive project metrics. Most predictive project metrics relate to
factors that can be calculated using data from your project plan. These
metrics are fairly easy to define and calculate, and they can be validated
against corresponding actual data at the project close. Over time, the goal for
each of these should be to drive the predictive measures and the retrospective
results into closer and closer agreement. Measurement baselines are set using
project goals and planning data.
Predictive project metrics serve as a distant early warning system for
project risk. These metrics use forecast information, normally assessed in the
early stages of work, to make unrealistic assumptions, significant potential
problems, and other project risk sources visible. Because they are based
primarily on speculative rather than empirical data, predictive metrics are
generally the least precise of the three types. Predictive project measures
support risk management in a number of ways:
• Determining project scale
• Identifying the need for risk mitigation and other project plan
revisions
• Determining situations that require contingency planning
• Justifying schedule and budget reserves
• Supporting project portfolio decisions and validating relative project
priorities
Predictive metrics are useful in helping you anticipate potential project
problems. One method of doing this is to identify any of these predictive
metrics that is significantly larger than typically measured for past, successful
projects—a variance of 15 to 20 percent represents significant project risk. A
second use of these metrics is to correlate them with other project properties.
After measuring factors such as unanticipated effort, unforeseen risks, and
project delays for 10 or more projects, some of these factors may reveal
sufficient correlation to predict future risks with fair accuracy. Predictive
project metrics include:
Scope and Scale Risk
• Size-based deliverable analysis (component counts, number of major
deliverables, lines of noncommented code, blocks on system
diagrams)
• Project complexity (interfaces, algorithmic assessments, technical or
architecture analysis)
• Volume of expected changes
• Number of planned activities
Schedule Risk
• Project duration (elapsed calendar time)
• Total length (sum of all activity durations if executed sequentially)
• Logical length (maximum number of activities on a single network
path)
• Logical width (maximum number of parallel activities)
• Activity duration estimates compared with worst-case duration
estimates
• Number of critical (or near critical) paths in project network
• Logical project complexity (the ratio of activity dependencies to
activities)
• Maximum number of predecessors for any milestone (fan-in)
• Total number of external predecessor dependencies
• Project independence (ratio of internal dependencies to all
dependencies)
• Total float (sum of total project activity float)
• Project density (ratio of total length to total length plus total float)
Resource Risk
• Total effort (sum of all activity effort estimates)
• Total cost (budget at completion)
• Staff size (full-time equivalent and/or total individuals)
• Activity cost (or effort) estimates compared with worst-case resource
estimates
• Number of unidentified activity owners
• Number of staff not yet assigned or hired
• Number of activity owners with no identified backup
• Expected staff turnover
• Number of geographically separate sites
Financial Risk—Expected Return on Investment (ROI)
• Payback analysis
• Net present value
• Internal rate of return
Overall Risk
• Number of identified risks in the project risk register
• Quantitative (and qualitative) risk assessments
• Adjusted total effort (project appraisal: comparing baseline plan with
completed similar projects, adjusting for significant differences)
• Survey-based risk assessment (summarized risk data collected from
project staff, using selected assessment questions)
• Aggregated overall schedule risk (or aggregated worst-case duration
estimates)
• Aggregated resource risk (or aggregated worst-case cost estimates)
Diagnostic project metrics. Diagnostic metrics are based on
measurements taken throughout the project, and they are used to detect
adverse project variances and project problems either in advance or as soon
as is practical. Measurement baselines are generally set using a combination
of stated goals and historical data from earlier projects. Diagnostic metrics
are comparative measures, either trend-oriented (comparing the current
measure with earlier measures) or prediction-oriented (comparing
measurements with corresponding predictions, generally based on planning).
Based on project status information, diagnostic project metrics assess
the current state of an ongoing project. Risk-related uses include:
• Triggering risk responses and other adaptive actions
• Assessing the impact of project changes
• Providing early warning for potential future problems
• Determining the need to update contingency plans or develop new
ones
• Deciding when to modify (or cancel) projects
A number of diagnostic project metrics relate to the concept of earned
value management (EVM). These metrics are listed with resource metrics and
described, following this list of typical diagnostic project metrics:
Scope Risk
• Results of tests, inspections, reviews, and walkthroughs
• Number and magnitude of approved scope changes
Schedule Risk
• Key milestones missed
• Critical path activity slippage
• Cumulative project slippage
• Number of added activities
• Early activity completions
• Activity closure index: The ratio of activities closed in the project so
far to the number expected
Resource Risk
• Excess consumption of effort or funds
• Amount of unplanned overtime
• Earned value (EV): A running accumulation of the costs that were
planned for every project activity that is currently complete
• Actual cost (AC): A running accumulation of the actual costs for
every project activity that is currently complete
• Planned value (PV): A running accumulation of the planned costs for
every project activity that was expected to be complete up to the
current time
• Cost performance index (CPI): The ratio of earned value to actual
cost
• Schedule performance index (SPI): The ratio of earned value to
planned value
• Cost variance (CV): The difference between earned value and actual
cost, a measurement of how much the project is over or under budget
• Schedule variance (SV): The difference between earned value and
planned value
Overall Risk
• Risks added after project baseline setting
• Issues opened and issues closed
• Communication metrics, such as volumes of e-mail and voicemail
• The number of unanticipated project meetings
• Measured impact on other projects
• Risk closure index (ratio of risks closed in a project divided by an
expected number based on history)
Many of the metrics listed here are self-explanatory, and many are
routinely included in status reporting. Exceptions include the EVM metrics—
EV, AC, PV, CV, SV, CPI, SPI, and the rest of the EVM alphabet soup. The
definitions make them seem complex, but they really are not that
complicated. EVM is about determining whether the project is progressing as
planned, and it begins with allocating a portion of the project budget to each
planned project activity. The sum of all these allocated bits of funding must
exactly equal 100 percent of the project staffing budget. As the project
proceeds, EVM collects data on actual costs and actual timing for all
completed activities so that the various metrics, ratios, and differences may
be calculated. The definitions for these diagnostic metrics are all stated in
financial terms here, but mathematics of EVM are identical for equivalent
metrics that are based on effort data, and a parallel set of metrics defining this
may be substituted. The terminology for EVM has changed periodically, but
the basic concepts have not.
The basic principle of EVM is that every project has two budgets and
two schedules. It starts with one of each, making up the baseline plan. As the
project executes, another schedule and another budget emerge from actual
project progress data.
The combination of planned funding and timing may be graphed as a
curve as in Figure 9-8, starting at zero and meandering up and to the right
until it reaches the data point that represents the scheduled end of the project
and the cumulative funding for the project. (The metric for the cumulative
budget is Budget at Completion, marked as BAC in Figure 9-8.) The
expected funding consumption curve describes the PV metric, sometimes
called the budgeted cost of work scheduled (BCWS). The combination of
actual spending and actual activity completion may be plotted on the same
graph as the AC metric, also called the actual cost of work performed
(ACWP). These two metrics may be calculated at any point in the project,
and if the project is exactly on schedule they may be expected to match. If
they do not, something is off track. Because PV and AC are based on
different schedules and budgets, you cannot really tell whether there is a
timing problem, a spending problem, or some combination. To unravel this,
we can use EV, which may also be identified as the budgeted cost of work
performed (BCWP). As project work is completed, EV accumulates the cost
estimates associated with the work, and it may also be plotted on the graph.
These three basic EVM metrics are presented in the following table:
Figure 9-8. Selected Earned Value Measurement Metrics
As a project progresses, both PV and AC may be compared with EV.
Any difference between AC and EV—in the figure, this is shown as CV, or
cost variance—must be due to a spending issue because the metrics are based
on the same schedule. Similarly, any difference between PV and EV—SV, or
schedule variance on the graph—has to be due to a timing problem. There are
indices and other more complex derived metrics for EVM, but all are based
on the fundamental three: EV, PV, and AC.
There is much discussion concerning the value of EVM. It can
represent quite a bit of overhead, and for many types of complex projects,
tracking data at the level required by EVM may be considered overkill. EVM
typically can accurately predict project overrun at the point where 15 percent
of the project budget is consumed.
If the metrics for EVM seem impractical for your projects, the related
alternative of activity closure index (listed with the schedule metrics)
provides similar diagnostic information based on the higher granularity of
whole activities. This metric provides similar information with a lot less
effort. Activity closure rate is less precise, but even it will accurately spot an
overrun trend well before the project halfway point.
Retrospective project metrics. Retrospective metrics determine how
well a process worked after it completes. They are the project environment’s
rearview mirror. Measurement baselines are based on history, and these
metrics are most useful for longer-term process improvement. Use
retrospective project metrics to:
• Track trends
• Validate methods used for predictive metrics
• Identify recurring sources of risk
• Set standards for reserves (schedule and/or budget)
• Determine empirical expectations for unknown project risk
• Decide when to improve or replace current project processes
Retrospective project metrics include:
Scope Risk
• Number of accepted changes
• Number of defects (number, severity)
• Actual size of project deliverable analysis (components, lines of
noncommented code, system interfaces)
• Performance of deliverables compared to project objectives
Schedule Risk
• Actual project duration compared to planned schedule
• Number of new unplanned activities
• Number of missed major milestones
• Assessment of duration estimation accuracy
Resource Risk
• Actual project budget compared to planned budget
• Total project effort
• Cumulative overtime
• Assessment of effort estimation accuracy
• Life cycle effort percentages by project phase
• Added staff
• Staff turnover
• Performance to standard estimates for standardized project activities
• Variances in travel, communications, equipment, outsourcing, or
other expense subcategories
Overall Risk
• Late project defect correction effort as a percentage of total effort
• Number of project risks encountered
• Project issues tracked and closed
• Actual measured ROI
Financial Metrics
Project risk extends beyond the normal limits of project management,
and project teams must consider and do what they can to manage risks that
are not strictly project management. A number of methods and principles are
used to develop predictive metrics that relate to the broad concept of ROI,
and an understanding of these is essential to many types of modern projects.
As discussed in Chapter 3 with market risks, ROI analysis falls only partially
within project management’s traditional boundaries. Each of the several ways
to measure ROI comes with benefits, drawbacks, and challenges.
The Time Value of Money
The foundation of most ROI metrics is the concept of the time value of
money. This is the idea that a quantity of money today is worth more than the
same quantity of money at some time in the future. How much more depends
on a rate of interest (or discount rate) and the amount of time. The formula
for this is:
where
PV is present value
FV is future value
i is the periodic interest rate
n is the number of periods
If the interest rate is 5 percent per year (0.05) and the time is one year,
$1 today is equivalent to $1.05 in the future.
Payback Analysis
Even armed with the time value of money formula, it is rarely easy to
determine the worth of any complex investment with precision, and this is
especially true for investments in projects. Project analysis involves many
(perhaps hundreds) of parameters and values, multiple periods, and possibly
several interest rates. Estimating all of this data, particularly the value of the
project deliverable after the completion of the project, can be very difficult.
The most basic ROI model for projects is simple payback analysis,
which assumes no time value for money (equivalent to an interest rate of
zero). This type of ROI metric has many names, including break-even time,
payback period, or a return map. Payback analysis adds up all expected
project expenses and then proceeds to add expected revenues, profits, or
accrued benefits, period by period, until the value of the benefits balances the
costs. Because projects rarely generate benefits before completion, the
cumulative financials swing heavily negative, and it takes many periods after
the revenues and benefits begin to reach break-even.
The project in the graph in Figure 9-9 runs for about five months, with
a budget of almost $500,000. It takes another six months, roughly, to
generate returns equal to the project’s expenses. Simple payback analysis
works fairly well for comparing similar-length projects to find the one (or
ones) that recovers its costs most rapidly. It has the advantage of simplicity,
using predictive project cost metrics for the expense data and sales or other
revenue forecasts for the rest.
Refining simple payback analysis to incorporate interest (or discount)
rates is not difficult. The first step is to determine an appropriate interest rate.
Some analyses use the prevailing cost of borrowing money, others use a rate
of interest available from external investments, and still others use rates based
on business targets. The rate of interest selected can make a significant
difference when evaluating ROI metrics.
Figure 9-9. Simple Payback Analysis
Once an appropriate interest rate is selected, each of the expense and
revenue estimates can be discounted back to an equivalent present value
before it is summed. The discounted payback, or breakeven point, again
occurs when the sum, in this case the cumulative present value, reaches zero.
For a nonzero interest rate, the amount of time required for payback will be
significantly longer than with the simple analysis because the farther into the
future the revenues are generated, the less they contribute due to the time
value of money. Discounted payback analysis is still relatively easy to
evaluate, and it is more suitable for comparing projects that have different
durations.
Payback analysis, with and without consideration of the time value of
money, is often criticized for being too short term. These metrics determine
only the time required to recover the initial investment. They do not consider
any benefits that might occur following the breakeven point; so a project that
breaks even quickly and then generates no further benefits would rank higher
than a project that takes longer to return the investment but represents a much
longer, larger stream of subsequent revenues or benefits.
Net Present Value
Total net present value (NPV) is another method to measure project
ROI. NPV follows the same process as the discounted payback analysis, but
it does not stop at the break-even point. NPV includes all the costs and all the
anticipated benefits throughout the expected life of the project deliverable.
Once all the project costs and returns have been estimated and discounted to
the present, the sum represents the total present value for the project. This
total NPV can be used to compare possible projects, even projects with very
different financial profiles and time scales, based on all expected project
benefits.
Total NPV effectively determines the overall expected return for a
project, but it tends to favor large projects over smaller ones, without regard
to other factors. A related idea for comparing projects normalizes their
financial magnitudes by calculating a profitability index (PI). The PI is a
ratio, the sum of all the discounted revenues divided by the sum of all the
discounted costs. PI is always greater than one for projects that have a
positive NPV, and the higher the PI is above one, the more profitable the
project is expected to be.
Even though these metrics require additional data—estimates of the
revenues or benefits throughout the useful life of the deliverable—they are
still relatively easy to evaluate.
Internal Rate of Return
Another way to contrast projects of different sizes is to calculate an
internal rate of return (IRR). IRR uses the same estimates for costs and
returns required to calculate total net present value, but instead of assuming
an interest rate and calculating the present value for the project, IRR sets the
present value equal to zero and then solves for the required interest rate.
Mathematically, IRR is the most complex ROI metric because it must be
determined using iteration and trial and error. For sufficiently complicated
cash flows, several values may even be possible for IRR (this occurs only if
there are several reversals of sign in the cash flows, so it rarely happens in
project analysis). These days, using a computer spreadsheet (or even a
financial calculator) makes determining IRR fairly straightforward, if good
estimates for costs and revenues are available. For each project, the interest
rate you calculate shows how effective the project is expected to be as an
investment.
Using ROI Estimates
All of these ROI methods are attempts to determine the “goodness” of
financial investments, in this case, projects. Theoretically, any of these
methods is an effective way to select a few promising projects out of many
possibilities or to compare projects with other investment opportunities.
Because of their differing assumptions, these methods may generate
inconsistent ranking results for a list of potential projects, but this is rarely
the biggest issue with ROI metrics. In most cases, the more fundamental
problem is with input data. Each of these methods generates a precise
numeric result for a given project, based on the input data. For many projects,
this information comes from two sources that are historically not very
reliable: project planning data and sales forecasts. Project planning data can
be made much more accurate as planning progresses using metrics and
adjustments for risk. Unfortunately, project ROI calculations are generally
made before much planning is done, when the project cost data is still based
on vague information or guesswork. In many cases, the estimates come from
top-down wishful thinking that is not related to planning at all.
Estimates of financial return are an even larger problem. These
estimates are not only usually very uncertain (based on sales projections or
other speculative forecasts), they are also much larger numbers, so they are
more significant in the calculations. For product development projects, in
many cases revenue estimates are higher than costs by an order of magnitude
or more, so even small estimating errors can result in large ROI variances.
ROI metrics can be very accurate and useful when calculated
retrospectively using historical data, long after projects have completed. The
predictive value of ROI measures calculated in advance of projects can never
be any more trustworthy than the input data, so a great deal of variation can
occur.
Key Ideas for Project Risk Analysis
• Survey contributors and stakeholders for risk assessments.
• Use worst-case estimates, contingency plan data, or Monte
Carlo simulation analysis to estimate project uncertainty.
• Estimate project scale in effort-months.
• Establish and use project metrics.
Panama Canal: Overall Risks (1907)
When John Stevens first arrived in Panama, he found a lack of progress
and an even greater lack of enthusiasm. He commented, “There are three
diseases in Panama. They are yellow fever, malaria, and cold feet; and the
greatest of these is cold feet.” For the first two, he set Dr. William Gorgas to
work, and these risks were soon all but eliminated from the project.
For the cold feet, Stevens himself provided the cure. His intense
planning effort and thorough analysis converted the seemingly impossible
into small, realistic steps that showed that the work was feasible; over time,
the ways and means for getting the work done became well documented and
credible. Even though there were still many specific problems and risks on
the project, Stevens had demonstrated that the overall project was truly
possible. This was quite a turnaround from John Wallace’s belief that the
canal venture was a huge mistake.
With Stevens’s plan, nearly every part of the job relied on techniques
that were in use elsewhere, and almost all the work required had been done
somewhere before. Project funding was guaranteed by the U.S. government.
Thousands of people were able and very willing to work on the project, so
labor was never an issue. The rights and other legal needs were not a
problem, especially after Theodore Roosevelt had manipulated the politics in
both the United States and in Panama to secure them. What continued to
make the canal project exceptional was its enormous scale. As Stevens said,
“There is no element of mystery involved, the problem is one of magnitude
and not miracles.”
Planning and a credible understanding of overall project risk are what
convert the need for magic and miracles (which no one can confidently
promise to deliver) into the merely difficult. Projects that are seen as difficult
but possible are the ones that succeed; a belief that a project can be completed
is an important factor in how hard and how well people work. When it looks
as though miracles will be necessary, people tend to give up, and their
skepticism may very well make the project impossible.
Chapter
10
Managing Project Risk
Let us never negotiate out of fear,
but let us never fear to negotiate.
—JOHN F. KENNEDY
It is rare to encounter a project where everyone involved feels things
are adequately under control. There never seems to be enough time, funding
and staffing seem too low, and there are generally a few technical challenges
yet to figure out. Managing project-level risk involves understanding all of
this well enough early in your work to set realistic project expectations and, if
necessary, to negotiate at least minor changes to the project. Although
completely dealing with project risks and issues is never possible, shifting
things to minimize the worst problems may be sufficient. Once a project is
seen to be feasible, hard work, with a bit of inspiration, cleverness, and luck,
will often be enough to let you close the rest of the gap.
Managing project risk begins with the risk assessments and plans of the
preceding chapters. This chapter builds on that foundation, discussing how to
effectively use risk and project data to influence necessary changes, to clearly
communicate project risks, and to adopt ongoing risk management practices
that detect new risks promptly and minimize problems throughout the project.
Project Documentation Requirements
One of the only things less interesting than assembling project
documentation is reading a lengthy description of what it must include.
Because projects come in all sizes, shapes, durations, and complexities, the
requirements for project documentation—the written descriptions for project
deliverables, plans, and other relevant information—vary a great deal.
Whether the documentation is lengthy and elaborate or fairly informal, it
serves as your basis for project execution and control. Project teams that fail
to put adequate documentation in place know too little about their projects
and carry more risk. In addition, when you lack data, you have a much lower
chance of influencing necessary changes to your project because your
proposals and negotiations will not have enough facts supporting them.
Although it is certainly possible to overinvest in project documentation, it is
far more common on today’s projects to do too little. Prudent project risk
management tends to err on the side of capturing more, rather than less, data.
Project documentation is most effective when it is available in layers.
At the most detailed level, there is the thorough, everything-including-the-
kitchen-sink version of the project plan, needed by the project team. For
others, such lengthy detail is neither necessary nor appropriate. You also need
clear, summary-level documentation that can be used in discussions with
sponsors, stakeholders, and others who are less involved with the project but
will take part in project discussions, negotiations, decisions, escalations,
problem solving, and other project communication.
Thorough project documentation created during your planning and risk
assessment gives you a foundation for validating your project plan. It also
provides the leverage you need to negotiate project modifications when it is
necessary to transform an overconstrained project that is sure to fail into one
that is realistic. The ultimate goal of this process is to establish a project
baseline consistent with both the project objective and a realistic plan.
Ongoing project risk management also requires periodic plan reviews and an
effective change management process, and these also rely on thorough
documentation.
Project documents fall into three categories: definition documents,
planning documents, and periodic project communications.
Definition documents are generally assembled earliest. They include
items such as:
• A high-level project overview
• A scope statement and a summary of the project objective
• The project proposal (or data sheet, project charter, or whatever the
overall description of the project may be called)
• Project stakeholder and sponsor analysis
• Project staffing and organization information
• Significant assumptions and project constraints
• Methodologies or life cycles to be used
• Risk management plans
• Process documentation for managing specification changes
Additional necessary documentation may include detailed specification
documents, a high-level project financial analysis, the project budget, detailed
release or acceptance specifications, any market research reports or user
investigations, and any other specific project data required by your
organization.
Planning documents are also assembled in the earliest project stages,
but it may be modified and augmented throughout the project as a result of
approved changes or new information. Typical project planning documents
are:
• The project work breakdown structure (WBS) and activity list
• The project schedule
• The project resource plan
• Functional plans (for quality, support, test, and other aspects)
• The risk register and risk management plans
• Planning assumptions and constraints
Periodic project communications accumulate throughout the project.
They include:
• Status reports
• Meeting minutes
• Specification change notices
• Project reviews
• Phase transition, development iteration, or stage-gate documents
• Interim and final project retrospective reports and lessons learned
Project documents are most useful when they have a consistent, easy-
to-read format, so adopt an existing format (or define one) that is effective for
each piece of documentation and stick with it. Especially for lengthy
documents, use a format that begins with a high-level summary or abstract
that is no longer than half a page of text. It is always risky to bury important
information on page 43 of a project report. For each project document,
identify an owner (often the project leader) who will be responsible for
creation, maintenance, and distribution. Define how and when document
changes can or should be made. When there are approved changes, determine
how you will provide up-to-date documents and mark old versions obsolete.
Documents have value only if the people who need them have ready
access to them. Storing documents online (with appropriate access security)
is an effective way to ensure that all team members will have access to, and
will be working from, the same information. Establish a centralized location
for any paper documents (or several, for geographically separated teams) that
is well known and easily accessed. Whether your project documents are in a
notebook, in a file cabinet, or on a server, keep them available and current.
Project Start-Up
One of the most significant problems on modern projects is lack of
team cohesion, particularly for projects that have geographically separated
teams. Completing a difficult project requires teamwork, trust, and a
willingness to look out for and help the others on the project. Under tension,
chains tend to break at the weakest link; projects staffed by virtual teams
have nothing but weak links.
One method for countering this problem and minimizing the risks that
result when projects must be staffed by people who do not know each other is
to hold a project start-up workshop. A start-up workshop (sometimes referred
to as a project launch, a kickoff meeting, a planning workshop, or a project
initiation meeting) is an event intended to initiate the project processes and to
build teamwork. A well-run start-up will achieve a common understanding of
the project goals and priorities and avoid wasted time and redundant efforts.
It also builds a more cohesive team that will get a fast, efficient start on the
project.
Typically, you will want to hold these workshops early in the planning
process, at the start of project execution, and before each major new phase of
the project. The precise objectives will vary somewhat for workshops held at
these different times, but all start-ups focus on team building and on common
project understanding. Achieving these objectives will substantially reduce
many types of project risk.
Justifying and Preparing for the Workshop
One reason given for not holding start-up workshops is cost.
Particularly for global teams who must travel to take part in a face-to-face
workshop, costs and travel time can be significant. But the cost of not doing a
project start-up is also high; serious problems and loss of productivity can
result whenever people are uncooperative or misunderstand information in
complex projects. For complex projects, it is never a choice between the
expense of a project start-up workshop and saving money; it is between
investing a relatively small amount of time and money early or spending a lot
more time and money on risks and inevitable problems later in the project.
Establishing common objectives and language for the project and building
relationships among the project team members minimizes risk and creates the
environment needed for a successful project.
Work to justify a face-to-face start-up workshop early in the project. If
the timing or cost aspects of a project start-up genuinely make an in-person
meeting impossible, at least plan and hold a meeting, or a series of meetings,
using videoconferencing or other teleconferencing technology. Such a
meeting is less effective at building relationships and trust, but it will be
much better than doing nothing.
Productive project start-up workshops need a well-planned agenda and
sufficient time to accomplish the activities listed. Determine the people who
should participate in the workshop and get their commitment. Prepare and
distribute all the information that participants will need to review in advance,
and have all needed project information available throughout the workshop.
Holding the Workshop and Following Up
Begin the meeting with personal introductions, especially for
contributors who don’t know each other. Open the start-up workshop with a
review of the meeting agenda, project objectives, ground rules, and other
necessary background information.
Throughout the workshop, have someone capture issues, questions,
action items, and other data produced by the team. As the workshop
progresses, work together with the attendees to review, develop, and improve
the project definition and planning documents.
Toward the end of the workshop, review the issues and assumptions
captured and assess them for project risks. Risk identification is a significant
by-product of start-up workshops, so explicitly add any newly uncovered
risks and significant issues to your project risk register for further analysis
and follow-up. Wrap up the workshop by identifying all assignments, due
dates, and owners for all action items and other required additional work.
Close the meeting by thanking the participants for their contributions.
After the workshop, integrate the work done during the workshop into
the appropriate project documents, and put the updated documentation where
it can be referenced and used. Analyze new risks, and plan responses for all
that are significant. Follow up on all action items and other assignments made
during the workshop, either by bringing them to closure or by incorporating
them into your project plans.
Selecting and Implementing Project Metrics
Project metrics are fundamental to project risk management. Some
metrics relate to risk triggers, and others may provide trend data that
foreshadows future project problems. The value of project metrics depends
on what and how much is measured. A project is a complex system, so you
will need a number of metrics to adequately monitor process. Defining too
many metrics also causes problems, starting with the excessive cost and
effort required to collect them. Strive to define a minimum set of project
metrics that you need to give a balanced view. There are examples of many
project metrics in Chapter 9.
Selecting Metrics
Useful metrics are objective; if they are evaluated by several people,
each person will get the same result. Good metrics are also easy to
understand and to collect. Clarify how and what you need to measure, and
verify through discussion that everyone involved understands the process
consistently. Define the units and precision to be used for the measurements,
and use the same units for all collection, evaluation, and reporting. For
example, you might decide that all measurements for duration estimates be
rounded to the nearest full workday. Also determine how often to measure.
You need to collect data frequently enough to support the results you desire,
but not so often that it creates expensive overhead. Capturing data too often
may also generate noise, that is, variations in the data that have little or no
meaning.
Prioritize any metrics you are considering, using criteria such as
criticality, relationship to risks, contribution to potential process
improvement, linkage to desired behaviors, or availability of data. Collect
only metrics that will make a meaningful difference; never collect data just
because you can. An effective set of metrics also provides tension—
improvement of one measure may diminish another one. Opposing a metric
measuring speed of execution with another measuring defects or quality will
result in more appropriate behavior than either measurement by itself. Work
to minimize gaming of the metrics by eliminating factors that might improve
the measurement without achieving any desired results. It is possible to
subvert almost any metric, so define them in terms that minimize differing
interpretations and loopholes.
Finally, work to ensure that any metrics collected are used primarily
for process monitoring and improvement, not as a basis for punishment.
Metrics are powerful tools for identifying opportunities for beneficial change
and determining trends, but the quality of the data that people provide will be
less useful if they know that it will also be used to evaluate their
performance. Once metrics are identified with processes used to rank and
cancel projects, the reliability of future data deteriorates substantially. Use
metrics for process control and improvement, not to generate criticism of the
project team. If any personal information is involved, ensure that the
measurements are kept confidential.
Implementing Metrics and Collecting Data
Before you start to use a project metric, work to get consensus from all
members of the project team on the definition, the planned collection and use
of the data, and the meaning of the results. Get commitment from everyone
who will collect or supply data in advance, and seek agreement not to game
the metrics.
After defining a set of metrics, the next step is to define an acceptable
or desirable normal range. For well-established metrics, baselines may
already be documented. For new measures, or for metrics used in a new
application, you need to establish a normal data range. Although you can
begin with an educated guess as a provisional baseline, you should use the
first several cycles of data collected to confirm it. Until you have established
the baseline using measurements, resist the temptation to make decisions and
process changes.
Document each metric and its parameters, and provide this data to
everyone affected. Include information such as the name of the metric, the
intended objective, data required, measurement units, measurement
frequency, the method for data collection, any formulas used, the target
acceptable range, and who is responsible for making the measurement.
After setting a measurement baseline, collect project data as planned,
and use the information to guide your project decisions. Set baselines for
diagnostic metrics early in projects, using current data or data from similar
earlier projects. For retrospective metrics, set baselines using existing data
from earlier projects, or wait until several completed projects have collected
the data required. For predictive metrics, establish corresponding
retrospective metrics (for example, validate financial return on investment
predictions against actual performance), and establish norms that plausibly
connect to the desired results. With all metrics, you should remain skeptical;
review the data, and confront any suspected gaming of the measurements.
Periodically reevaluate all metrics, especially after significant organizational
or process changes. Following changes, review the baseline and acceptable
range for each metric. Validate any necessary adjustments with new baseline
measurements before considering additional system changes.
Throughout the process, make the measurements visible. Report the
status of measured factors as planned, to all project stakeholders who need
the measurements or are affected by them. Be prompt in evaluating and
reporting the data to ensure timely feedback and early detection of significant
variances.
Establishing Reserves and Managing for Contingency
Imagine a large target with a big, red, circular bull’s-eye in the center.
If you stand 2 meters away from the target and aim a target rifle right at the
center, you should have no difficulty hitting the middle of the bull’s eye. If
you were to repeat the shot from 200 meters away, the situation changes. For
the second shot, simply aiming at the bull’s eye will not be effective because
you can no longer rely on the projectile to fly in a straight line. If you aim at
the center of the target, you will hit below its center. The parabolic arc that
controls the flight of the bullet was described with precision hundreds of
years ago by Sir Isaac Newton. Everyone knows that you need to aim higher
than the point you wish to hit in order to compensate for the effects of
gravity. The principle is so well understood that even the average middle
manager would not be tempted to hike out and give the bullet a lecture on
“flying smarter, not harder.”
Simple, short projects are analogous to the first shot. Setting a date and
planning to hit it will work more often than not because the time window is
brief, the work is fairly obvious, and the risks are small. For complex
projects, though, the analogy of the second shot is better. The longer
duration, with substantial unknowns and risks, is a different situation. Like
gravity’s effect on the flying bullet, risk has an effect on the trajectory of a
project. Project plans that set deadlines to line up exactly with the final
planned activities have little chance of completing on time, even when the
plans are based on reasonable, realistic estimates. The “force” of risk makes
such a schedule unreliable.
Management reserve is a general tactic for dealing with project risk
that helps to compensate for uncertainty. Reserve—in time, in budget, or in
both—based on expected risk may be used to develop credible schedules.
Establishing reserves is not about padding estimates or making scheduling
choices to accommodate sloppiness or team sloth; it is about using risk
assessment information to set appropriate buffers at the project level to allow
the project to deliver on commitments. In effect, management reserve is
about setting project objectives with ranges, with the size of the range, or
reserve, defined by project-level risk assessment.
Management reserve is based on two factors: expected impact from
known risks (based on contingency plans, worst-case scenarios, and
consequences of known risks you have elected to accept) and unknown risks.
Data for the first factor, discussed in detail in earlier chapters, comes from
planning processes. Unknown risk, by definition, is risks you are unable to
anticipate and describe. Explicit planning for unknown risks is not possible,
but metrics from earlier projects can provide guidance on the magnitude of
exposure. Using project risk assessment data and metrics, you can estimate
appropriate schedule and budget reserves. In effect, management reserve
provides a generic contingency plan for your overall project. Reserve is never
allocated to the activity level, and it is managed by the project leader, not by
activity owners.
Schedule Reserve
Management reserve for schedules may be implemented in several
ways. The simplest method is to estimate the amount of expected schedule
exposure, and then develop a plan that supports completion of the project
earlier than the required completion date by that amount. In dealing with
problems, project slip that stays within the reserve will still permit you to
meet the project commitment. The published project schedule could show
either only the more aggressive, target completion date or the target date as a
milestone followed by a dummy activity and then the committed deadline.
The dummy activity can have a name such as “allowance for risk,” and it has
a duration estimate equal to the schedule reserve.
For known risks, the amount of reserve needed for a given project can
be estimated using methods that have been described in earlier chapters of
this book. From Chapter 4, the idea of worst-case estimates provides one
source. Using the most likely duration estimates establishes one possible
project end date. Schedule analysis based on the worst-case estimates
calculates a second end date for the project further out. The difference
between these two dates can be used to determine the required reserve. How
you do this depends on your confidence in the data, but it is common to set
up half of the difference as a reserve—managing the work using the most
likely schedule but setting the project deadline to be a date midway between
that schedule and the worst-case end date.
A second method for determining schedule reserve is based on data
from contingency plans plus an allowance based on known, accepted risks.
This process uses the method discussed in Chapter 9 to aggregate activity risk
data. In this case, you would track and manage your project using the project
plan as a target, but your committed deadline would be later by a duration
defined by the cumulative expected consequences of your known risks.
A third way to assess schedule reserve using data from known risks,
also discussed in Chapter 9, relies on Program Evaluation and Review
Technique (PERT) analysis or Monte Carlo simulation. The histograms or
expected distributions can also be used to estimate required reserve, by
determining the duration between the most likely (30 to 50 percent
likelihood) date and some higher probability point further out that is
consistent with your project’s risk tolerance. Again, your plan supporting the
most likely dates will be used to manage the work and define the early point
of a range window of acceptable dates. The upper boundary of the window
will be the project commitment.
Estimating schedule reserve using any of these ideas will still
necessarily be incomplete. These calculated allowances for reserve are based
only on known risks. Without consideration of your unknown risk, you will
significantly underestimate the reserve allowance you need. If you have
metrics that measure typical schedule impact from unanticipated problems,
include an appropriate margin for it in your required reserve.
One common example of reserve for unknown risk is explicit in many
kinds of project plans. At the end of many construction and relocation
projects, there is an activity scheduled called a punch list, or something
similar. The purpose of this activity is to fix and close out all the defects,
problems, omissions, or other issues that will accumulate on a list during the
project. At the start of the project, a duration estimate based only on the list
would logically be zero—there are no defects yet identified. Because a
duration estimate cannot be based on explicit knowledge of the work, it is
based on the history of dozens or hundreds of similar projects. Experience
from earlier work tells you how much time and effort, on average, you can
expect between completion of the final scheduled activities and customer
sign-off. Metrics that measure unscheduled effort, the number of activities
added during projects, underestimated activities, and other indicators of plan
incompleteness are all useful for estimating typical unknown risk.
An alternative method for estimating the schedule consequences of
unknown risk is the project appraisal idea discussed in Chapter 9. The
comparison projects include the effects of unknown risk, where your planned
current project does not. Part of any difference shown in such an assessment
is due to unknown risk.
The amount of required schedule reserve varies greatly depending on
the type of project. A reserve of only a few days may be appropriate for short,
routine projects. For complicated, aggressive projects, target dates may need
to be established weeks, or even months, before the committed deadline to
deal with the many possible problems and potential sources of slippage.
Whether the reserve is short or long, remember that it, like schedule float,
belongs to the project as a whole. It is available only for problem solving, not
for personal convenience. Using reserve established to manage project risk
for other purposes (especially for scope creep) will increase project risk.
How schedule reserve is best handled will vary. On some projects,
reserve is discussed and managed in the open. Schedules posted and
distributed reflect its existence, and the status of remaining schedule reserve
is discussed in status meetings with other topics. On other projects, the
management of reserve is more covert. As far as the teams on these projects
know, the deadline for the project is the date that follows the final activity in
the plan. Although this has the desired effect of focusing attention on getting
the work done as promptly as possible, it is inconsistent with open and honest
project communications. The alternative of managing the reserve openly is
usually the better method, but it may be undermined unless you effectively
guard against two potential issues: scope creep and Parkinson’s Law.
Scope creep is always an issue on complex projects; the more time the
team spends thinking about and doing the work, the more ways they come up
with to make it “better.” In projects that possess a time buffer for risk
management, the temptation to add and modify the project scope may
become overwhelming because “we have the time available.” On all projects,
risk management depends on disciplined and thorough control of changes,
and this is particularly true of projects with visible schedule reserve. Schedule
reserve should be used only to accommodate project changes that are a direct
result of project problem solving and issue resolution. Schedule reserve is not
a tool for project improvement.
The second issue, Parkinson’s Law—work expands to fill the time
available—also presents a significant challenge. Misuse of schedule reserve,
particularly unused reserve still available late in the project, is a constant
temptation. One method for guarding against this is to establish the available
window of time for project completion and to set up rewards for the team
proportionate to any unused reserve at the end of the project. Incentives for
avoiding misuse of the reserve can be effective, but they must be developed
carefully so that they are effective in discouraging misuse and scope creep.
The best methods for reserve management ensure that all decisions are
ultimately in the hands of a project leader who will apply the available
reserve as intended, to deal with real-time problems, issues, and conflicts.
This way, the established reserve operates to counteract the effect of risk and
helps complete aggressively scheduled projects on or before their committed
deadlines.
Budget Reserve
Reserve for resources employs resource analysis and risk data to
establish a budget reserve at the project level to expedite work, add additional
resources, or take other necessary actions to stay on schedule.
The amount of reserve needed is estimated similarly to the schedule
reserve discussed earlier, from analysis of known risk using worst cases,
contingency plans, or budget analysis. For unknown risk, estimate reserve
using financial metrics from earlier projects. Base your determination of
required budget reserve on the best data you have available.
Again, it can be a challenge to be aware of the budget reserve while
resisting the temptation to use it for project modifications that have nothing
to do with risk. It is usually somewhat easier to manage budget reserve than
schedule reserve because decisions concerning money and resources are
generally made by the project leader or even higher in the organization.
Using Management Reserve
Although determining a prudent allowance for schedule and/or budget
reserve is the first step, setting it up requires discussion, negotiation, and
approval from project sponsors and stakeholders. You will need all the
planning and other data you used to calculate required reserves, but this is not
sufficient. You also need to identify and factor in your project constraints.
Requesting schedule reserve that is not consistent with a required completion
date for the project probably makes no sense, nor would a proposed budget
reserve that exceeds the expected benefit for the project. Work to keep your
analysis consistent with the goals and objectives for the project, and
understand that when your estimate for reserve exceeds what is logical for the
project, project risk is high. This may be an indication that your project
cannot be completed successfully. Abandoning such a project in favor of
better alternatives could be the best decision.
Project Baseline Negotiation
Managing project risk nearly always involves some shift in the project
objective. In the unlikely event that your bottom-up plans and risk assessment
are wholly consistent with the initial project goals, no negotiation is
necessary; validating the plan and documenting the baseline is all that you
need to do. For most projects, however, there are issues to confront, often
significant ones.
Project negotiation serves a number of purposes. The most obvious one
is to shift an overconstrained project enough to bring it in line with a realistic
plan. Other reasons for negotiation include securing sponsor support, setting
limits on project scope, and managing expectations.
Strong Sponsorship
Risky projects need all the help they can muster, so work to get and
retain high-priority and visible support for your project. Projects that have
substantial risk are generally undertaken because large potential benefits are
expected, and you should make sure that all discussions of the project
emphasize the positive results that will come from the project, not just the
risks, problems, and challenges. Build awareness of your project, early and
often, so that your management will continue to support the project in its
words and actions. Particularly on risky projects, you need commitment for
quick resolution of escalated issues, protection of the project team from
conflicts and nonproject commitments, and adequate management reserve.
You may also need sponsor approval for training to acquire new skills and to
streamline or change processes. The sponsor can also lower risk for the
project by aggressively removing organizational barriers and administrative
overhead, in addition to dealing with factors that may inhibit fast execution of
the project. Conversely, management can exacerbate risk by contributing to
these factors and initiating new work that requires people currently assigned
to your project. Strong, continuing sponsorship is one of the key factors that
separates risky projects that succeed from those that crash and burn.
Setting Limits on Project Scope
Another goal of project negotiation is to set boundaries for the project.
A great deal of risk for complex projects, as discussed in Chapter 3, arises
from the fact that there may be any number of different conceptions for what,
exactly, your project is supposed to produce. Even though you and your
project team probably have a fairly clear definition as the planning and risk
analysis come to closure, there still may be residual fuzziness in other
quarters. The project scope must be just as clear as the deadline to everyone
involved.
For discussions with sponsors, prepare project documentation that is
unambiguous about what the project will include and specific in outlining
what it will not include. Even projects employing agile methods benefit from
establishing limits and expectations for deliverables early on in the work;
understanding the overall objectives and credible foundations for creating
value will establish boundaries for delivery of useful, cost-effective results.
Setting limits on scope early, using is/is-not scope descriptions that are clear
to all, will either validate the project team’s conceptions or trigger
discussions and necessary adjustments. Making needed scope corrections at
project inception lowers overall risk and establishes consistent expectations
for all parties.
Fact-Based Negotiation
Project baseline negotiation requires definition and planning
documents. Initial discussions will focus on summaries, so writing clear,
informative summaries is essential. In preparing project information for
discussion, include a high-level objective summary, a milestone project
schedule, a high-level WBS, a project appraisal, and a summary of major
assumptions and risks. If your planning shows a major mismatch between the
current project plan and the requested project objective, you should also have
several high-level proposals describing project alternatives.
With this data in hand, your next step is to set up a meeting with the
project sponsor to discuss the project, the results of your planning, and, if
necessary, the alternatives. Begin the discussion with a presentation of your
planning results. Whenever your project plan is inconsistent with the
originally requested project objective, you need to negotiate changes.
Changes to consider include requesting additional resources, extending the
deadline, getting contributors with more experience or more training for the
people you have, reducing project scope, or any number of other options.
Having data is critical for your success because the balance of power in
such negotiations is not in your favor. Although it is relatively easy for
sponsors and managers to brush aside concerns and opinions, it is much more
difficult for them to dismiss hard facts. When there is a significant difference
between project expectations for timing and resources as seen by the project
team and their management, a half-page project appraisal (described in
Chapter 9) can be a good starting place for the discussion, showing why the
requested project is not likely to be done as quickly or inexpensively as
desired. (“Remember this project? That’s the one we had to do in two
months, and it ended up taking six.”) When the issue is a request to do a
project much faster than is possible, your project Gantt chart, showing all the
activities and durations, is an effective tool. When the deadline requested is
far too short to accommodate the work, hold up the chart and say that you can
do it on schedule only if the sponsor will select which activities to delete.
Most sponsors will quickly back down and begin a productive discussion of
alternatives, rather than randomly removing work they probably do not
understand. Any project information backed up by historical, documented
data can be a good starting point for a fact-based, not emotion-based,
negotiation.
Reducing project risk through negotiation is best done with the ideas
outlined by Roger Fisher, William Ury, and Bruce Patton of the Harvard
Negotiation Project in their book Getting to Yes. Their process of principled
negotiation is effective for win-win negotiations, where all parties get at least
some of what they seek. In project negotiations where only the sponsor wins,
everyone has actually lost. It does no one any good to force a commitment to
an impossible project. The team and project leader lose because they are
stuck on a doomed project. The sponsors, managers, and customers lose too
because they do not get what they expect and need. Principled negotiation,
done early, is essential for dealing with unrealistic projects.
Some useful ideas for project negotiations include separating the
people from the issues and focusing on interests, not positions. By sticking to
facts and mutually understood needs, you raise the discussion beyond “This
project is hard” on the project side and “You are the best project leader we
have” on the other. Although both of the statements may be true, neither one
actually addresses the real issue—that the project objective, as stated, is not
possible. As you prepare for negotiation, develop project alternatives that
provide for mutual gain, such as exploring opportunities that could increase
the original project’s benefits or segmenting the project into a sequence of
smaller projects capable of delivering value earlier. In your negotiations, base
decisions and analyses on objective criteria. Brainstorm, problem-solve, and
get everyone involved in seeking better options. Ask lots of questions, and
focus on resolving the issues, not just on arguing about the project.
Your biggest asset in all of this is your knowledge. As a result of your
project planning, no one alive knows more about the project than you do.
You also have a track record and credibility, built up over a body of prior
work. The managers and project sponsors are aware of this; that is why they
requested that you lead the project. Proceed with negotiations using your
technical and planning expertise, as well as the experience of your project
team.
Lay out the consequences of accepting a commitment to a project with
excessive residual risk in clear, fact-based terms. By using conservative
assumptions to support the analysis of the potential project problems, you
will end up with one of three possible results. The most desirable outcome is
shifting the project objective in line with, or at least closer to, your plan. For
other projects, realistic analysis of the work and risks may lead to the
conclusion that the project is not a good idea, and it is taken no further. Either
of these outcomes will avoid a failed project.
The third possibility is that your data may not be sufficiently
compelling or that your sponsors will pay no attention to it. In this case, you
may end up forced to commit to an infeasible project, with no realistic plan to
support it. Should this happen, document the situation for future reference, to
make it less likely to recur. Then you can try your best and hope for miracles
(or work on updating your résumé).
Project Plan Validation
Following discussion and negotiation, validate that you have consensus
on the project. Verify that you have a plan supporting the project objective
that is acceptable to the project sponsor and other stakeholders as well as to
you and your project team.
Use the project documents from the planning processes, with any
negotiated modifications, to establish the project baseline plan of record.
Before finalizing the plan, review it to ensure that it includes periodic risk
reassessment activities throughout (at least at major phase milestones).
During these reviews, additional risks not apparent at project start will be
identified, and your contingency plans can be updated.
Publish the final versions of the project documents and distribute them
so that the project team can access and use them to manage progress
throughout the project. Put your project documents online or in another
location where everyone has access at any time to current versions. If you use
a computer scheduling tool for project tracking, save the project schedule as a
baseline and begin tracking activity status in the database.
When you set the project baseline, freeze specifications for at least the
initial development effort and delivery of results. Set both the project scope
definition and your baseline plan at the same time, and change neither one
without using your established process for making changes. Freezing the
overall schedule and resources on a project while allowing the scope to
continue to meander is a source of massive project risk.
For risk visibility, create a top-ten list of the most significant known
risks for the current phase of your project, and post it where the project team
will be aware of it—in the team workplace, on the project Web site, or in
another prominent location. Commit to periodically reviewing and updating
the list throughout the project.
Specification Change Control
Once the project plan is accepted and you have locked in your
requirements, adopt a process to carefully consider all changes before
accepting them. After the project documents are signed off by all appropriate
decision makers—the project sponsor, customers, stakeholders, and others—
it is risky to allow unexamined changes in the project. Although new
information flows around modern projects continuously, maintaining
specification control is crucial for project success. Unmanaged change leads
to slipped schedules, budget problems, and other consequences, as seen in the
PERIL database. Even on projects employing agile methods where evolution
of scope for future development iterations is inevitable, you need to manage
risk through scrupulous control of changes in the current phase (and often for
one or more subsequent development iterations as well).
Having a process for submission, analysis, and disposition for each
proposed change lowers the risks, especially if rejection is the default
decision for submitted change requests. An effective change management
process puts the burden of proof on each change request; all changes are
considered unnecessary until proven otherwise.
Another requirement for effective change control is giving the people
responsible for the change process the authority to enforce their decisions.
Change approvers need the power to say no (or at least not yet) and make it
stick. For reasons of efficiency, some change processes establish change
screeners, who initially examine any proposed change and determine when
(or even if) a change deserves further consideration.
Even the most rudimentary project change control processes should be
documented, in writing. The formality of the actual process adopted varies a
great deal with project type, but at a minimum, it should include:
• Logging and tracking of all change requests
• A defined process for analyzing all proposed changes
• Documented criteria for accepting, rejecting, or deferring changes
• Communication of decisions and status
Change Submissions
Ideas for change generally begin in problem solving or from
recognition of an opportunity. Submissions should include information such
as:
• Why the change is necessary
• An estimate of expected benefits from the change
• The estimated impact of the change on schedule, cost, and other
factors
• Specific resources needed for the change
Document all changes submitted, and maintain an up-to-date log (or a
burn-down list, or a backlog) of submitted change proposals throughout the
project. Following submission, examine each submitted change, and if the
information is unclear or key data is missing, return the request to the
submitter for correction.
Change Analysis
Analyze all changes for both impact and cost/benefits. Impact
assessment parallels the processes used for impact analysis of risks. It begins
with high-level categorization of change impact:
• Small: Minor effect on the deliverable or project plan
• Medium: Functional change to the deliverable but little project
impact
• Large: Major change to the project objective and the deliverable
Also evaluate the costs and benefits of the change. Each change
presumably has some benefits, or it would not have been submitted. The
expected benefits need to be estimated and verified so that they can be
compared with the expected costs and other consequences.
Changes generally fall into one of several categories. Many proposed
changes resolve problems encountered on the project or fix something that is
not functioning as required. The benefits of these changes relate to the
avoided expense or time slippage that will persist on the project until the
problem is solved. Other changes arise from external factors such as new
regulatory or safety requirements, the need to comply with evolving
standards, or actions by competitors. These types of change, which are
solving real problems, complying with firm requirements, and reacting to
adverse shifts in the environment, are often unavoidable. Your project
deliverable will lose much, if not all, of its value unless the changes are
made. The benefits of both kinds of mandatory changes are usually sufficient
to justify their serious consideration.
Other project changes are intended to make the project “better” and are
on less solid ground—such as changes that add something to the deliverable,
alter something about the deliverable to improve it, or introduce new
processes or methods to be used for project work. The benefits of these
changes are more speculative and thus more difficult to analyze. Credible
estimates for increased sales, revenue, or usefulness as a result of the change
are difficult, and they tend to be optimistic. Although some opportunities for
change may result in significant benefits, many changes intended to improve
complex projects generate unintended consequences and lead to benefits that
are far smaller than expected. The impact to the project may also be difficult
to estimate, particularly if the change involves adopting a new approach to
the work. Effective change management systems are highly skeptical of these
discretionary modifications and tend to reject them. When outright rejection
is not possible, the system should at least be adept at saying not yet, allowing
the project to proceed as planned and then embarking on a follow-on effort to
pursue the new ideas or to reconsider them as part of a future development
iteration.
In all cases, a rational consideration of the net benefit of the change—
the reasonably expected benefits less the estimated costs and other
consequences—must be the basis for any good decision. This analysis should
apply to all submitted changes, regardless of their origin. If customers submit
changes, the specific consequences in terms of timing and cost must be
visible to them, and generally borne by them as well. If a project contributor
submits a change, he or she should provide ample documentation for it and
expect to fight hard to get it approved. Politically, the most difficult situation
on complex projects arises from the changes requested by sponsors and
management. Although it is never easy to say no to the people you work for,
the existence of a documented process that has been approved to manage
project change is a vital initial step, and clear, data-supported descriptions of
the consequences of requested changes are also necessary. As with risk
management generally, managing change risk effectively relies on thorough,
credible project planning data.
Disposition Options
For each potential change, you have four options: approval, approval
with modification, rejection, and deferral. The process for making a decision
on each proposed change uses the results from the analysis and documented
information on project objectives and priorities to make a business decision.
The primary criterion for the decision will generally be the assessment of
benefits versus costs, weighing the relative advantages and disadvantages of
each change. The level of formality will scale with the project, but two
aspects of the decision process are universal. The first requirement is to make
decisions promptly. Change requests, particularly those that address
problems, need quick attention. The value of urgent changes can diminish
significantly as they sit, so ensure that such changes are considered and
closed without undue delay. Even scope management processes that defer
significant changes to the end of a phase or development iteration need an
exception process for occasional prompt action. The second need is for
consistent adherence to agreed-upon requirements for decisions. Some
change systems are based on approval by a majority of those involved; some
require unanimity; and still others grant veto powers to some approvers who
have greater authority. Effective change systems avoid having too many
decision makers required for approval to minimize scheduling problems and
shorten debate, and they provide named backup approvers who can act
whenever a designated approver is not available.
An effective change management process always starts with the
presumption that changes are unnecessary and rejects all changes that lack a
compelling, credible business basis. Even for changes that have some
benefits, carefully examine them to determine whether some parts of the
change are not needed or whether the change might be deferred to a later
project, phase, or development iteration, especially if the impact significantly
interferes with committed project objectives. Seek substantial credible net
benefits even for changes you decide to approve with modifications or to
defer. Approval and acceptance of changes should be relatively rare, and
reserved for the most compelling requirements for problem solving or
delivering significant business value. The more change a project is subject to,
the higher the risk. Whatever the decision, close out all requests quickly,
within the documented time goals established for the process. Also, promptly
escalate any issues or conflicts that cannot be resolved at the project level.
Communicating the Decision
As each decision is made, document it in writing. Include the rationale
for the decision and a brief description of any project impact. Prepare and
distribute a summary of the pending, accepted, and rejected change proposals
to project stakeholders and to your project team members.
Whenever a change is not approved, respond to the submitter with an
explanation, including the rationale for the decision. If there is a specific
process for appeal and reconsideration, provide this information to the
submitter as well.
For any accepted changes, update all relevant project documents—the
WBS, estimates, schedules, specifications and other scope documents, the
project plan, charts, or any other project documents that an approved change
affects.
Even for rejected changes, retain the proposals in the project archives.
The good ideas may be worthy of consideration in follow-on projects, in
parallel projects, or in a later phase of work. When your project is over, you
can use the change history to reduce risk on future projects by carefully
reviewing the process, the decisions made, and the consequences (intended
and unintended).
Key Ideas for Managing Project Risk
• Hold a project start-up workshop.
• Select and use several project metrics.
• Determine required project reserve.
• Negotiate and commit to credible project objectives.
• Manage scope and control specification changes.
Panama Canal: Adjusting the Objective (1907)
Setting a concrete objective for a project is not necessarily a quick,
easy process. In the case of the Panama Canal, although Theodore Roosevelt
made the decision to build the canal and the Senate approved the
commitment in early 1904, the specifics of exactly what sort of canal would
be built were still not settled nearly two years later. All the data accumulated
by John Stevens led him to the same conclusion ultimately determined by the
French engineers: Building a sea-level canal at Panama was not feasible. He
estimated that a lock-and-dam canal could be completed in nine years,
possibly eight. A sea-level canal could not be built in less than 18 years, if at
all. He convinced Theodore Roosevelt of this, and he thought the matter was
settled.
This, however, was not the case. In spite of the French experience, the
lock-and-dam versus sea-level debate was still going strong in the U.S.
Senate in 1906. Showing much of the same diligence and intelligence one
might expect of today’s Senate, they took a vote on how to build the canal.
They approved construction of a sea-level canal by one vote. One
unavoidable observation from the study of past projects is that things change
little over time, and politics is rarely driven by logic.
John Stevens had just returned to Panama from Washington in 1906,
and although he was quite busy with the project, he turned around and sailed
back to the United States. He met extensively with members of both the U.S.
House of Representatives and the Senate. He patiently explained the
challenges of a sea-level canal in a rain forest with flooding rivers. He
developed data, drew maps, and generally described to anyone who would
listen all the reasons why the canal could not be built at sea level. As was true
earlier for the French, the main obstacle was the flooding of the Chagres
River, which flows north into the Gulf of Mexico parallel to the proposed
canal for nearly half of its route.
Stevens spent a lot of time with one ally, Senator Philander Knox.
Senator Knox was from Pennsylvania—specifically, he was from Pittsburgh,
Pennsylvania. Stevens worked with Knox on a speech in which the senator
described in detail why the canal must be constructed with dams and locks.
By all reports, it was an excellent speech, delivered with great eloquence and
vigor. (It was probably not entirely a coincidence that a sea-level canal
required none of the locks, steel doors, and other hardware that would come
from Senator Knox’s friends in the foremost steel-producing city in the
Americas.)
Despite all this, 31 senators still voted for a sea-level canal. Fortunately
for the project and for Stevens, 37 senators were paying attention, and the
design Stevens recommended was approved.
It had taken him more than a year, but finally John Stevens had his plan
completed and approved. Defending the feasible plan required all of his data,
principled negotiation, and a great deal of perseverance, but he ultimately
avoided the costly disaster of a second impossible canal project at Panama.
Chapter
11
Monitoring and Controlling Risky Projects
Adding manpower to a late software project makes it later.
—FRED BROOKS, AUTHOR OF THE MYTHICAL MAN-MONTH
Apart from phrasing (the very 1970s “manpower” would be replaced
by the more politically correct “people” or “staff”), it’s hard to quibble with
Fred Brooks’s statement. In fact, the effect described by Brooks applies to
projects of almost any type, not just software projects. Adding contributors to
a late project never seems to help very much because the first thing that new
people on a project need is information, so they ask blizzards of questions.
These questions are directed to the overworked people already on the project,
further slowing their progress. There are other reasons that make adding staff
late in a project counterproductive, such as the need to build trust and to
move through the team-building stages of “forming, storming, and norming.”
However, the additional staff is not the real problem. It is additional staff too
late. Monitoring and control of the work is essential to detecting problems
such as insufficient staffing early enough to avoid the need for chaotic, and
seldom successful, heroic measures. Disciplined monitoring and control finds
and fixes problems while they are still small, so the project avoids serious
trouble in the first place.
Risk management cannot end with the initial planning. Your project
starts with its plan, just as a lengthy automobile trip begins with an itinerary
based on maps and other information. But what trip ever goes exactly as
planned? As the driver continues on the trip, small adjustments based on
events and conditions are necessary. More serious issues such as vehicle
problems or automobile accidents may result in major modifications to the
itinerary. Throughout the trip, the driver must remain alert and reasonably
flexible. Managing risk in projects is about detecting things that are not
proceeding as planned in your project. Like the driver who must remain alert
and responsive to things that happen on the road, the project leader uses
tracking, reviews, and reapplication of the planning concepts discussed in the
preceding chapters to adjust to the prevailing project conditions, seeking to
bring it to a successful closure.
Effective management of project risk relies on frequent and disciplined
reassessment of new information and status as the project proceeds.
Particularly on longer projects, you cannot know everything about the work
at the beginning. Periodic project reviews are necessary to keep the project
moving and productive.
Don’t Panic
The main focus of this chapter is ongoing execution of a project with as
few detours and aggravation as possible. Risk planning helps to reveal what
might go wrong and provides responses for much of it. However, project
work is unpredictable, so things will happen. Effective project leaders strive
to remain calm when problems arise. Risk management depends on level-
headed analysis and prompt action, so work to remain composed. Recovery
from problems depends not only on a prompt and appropriate response but
also on competent execution. You will stay on track more successfully by
heeding Rudyard Kipling: “If you can keep your head when all about
you/Are losing theirs and blaming it on you. . . .”
This is much easier to say than to do, but minimizing emotions and
chaos in a crisis is the fastest route to problem recovery. Stress causes
inefficiency and mistakes, and it raises the likelihood of future risks, so do
your best to keep things running smoothly throughout your project—even
when things seem to be falling apart. Panic will only make things worse.
Applying the Plan
Predictable project progress depends on your baseline project plan. The
plan is now the road map for your work, and you can begin tracking status
and updating your project database with actual results. Status information is
primarily useful in assessing progress, but it also provides early warnings for
risks. Status data also supports longer-term risk management through process
improvement during periodic project reviews and postproject retrospective
analysis.
Risk management relies on systematic project tracking to provide the
information necessary for proactive detection of project problems while they
are still small and easily solved. Project tracking helps you anticipate
potential problems, allowing the project to avoid at least some of them.
Disciplined tracking makes it difficult to ignore early warning signals, and it
provides the data you need for effective response. Without accurate, timely
information, project problems remain hidden, so they will occur without
warning, inflicting serious damage on your plans.
Credible status data also can reduce the project worries and team stress
that arise from a lack of good information. Even when the project status
reveals bad news, the true situation viewed with credible information is
nearly always less dire than the alternatives that people dream up when they
lack data. In addition, detailed status often provides root cause and other
information you need for recovery. Factual information also helps minimize
both excessive optimism and pessimism, neither of which is helpful to a
project.
Dogmatic collection of project status and frequent comparison to the
plan guards against a common project risk—safe-so-far project reporting. As
long as the project deadline is still way out in the future, the project is not
officially late. If there is little or no credible data, project reporting can
continue to say that the project is doing fine. Only at the deadline, or perhaps
a little before it, does the project leader publicly admit that the project will
not meet its schedule commitment. This is analogous to a man who falls off a
ten-story building and reports as he passes by each row of windows, “Safe so
far!”
Projects become late one day at a time. Failure to detect this as soon as
possible allows schedule and other risks to remain undetected, grow, and
ultimately overwhelm the project.
Project Monitoring
Project monitoring can begin as soon as there is a clear, validated
baseline plan that has been approved by the project sponsor and accepted by
the project leader and team. Other prerequisites for effective project tracking
are a functioning communications infrastructure, disciplined tracking
methods, and thorough project planning data available to all team members
and stakeholders.
Decisions Related to Monitoring
Specifics concerning project status collection and storage are basic
decisions that you need to make as part of the initial project infrastructure for
your project.
You need to commit to an appropriate frequency and method for status
collection. Project tracking is usually done weekly, but for very short (such as
the development iterations in agile projects) or very urgent projects, daily
data collection may be warranted. For long projects, less frequent data
collection may be acceptable, but a cycle longer than two weeks is
inconsistent with good risk management. Online or e-mail status collection is
most common, but any method that is effective and backed up in writing can
work.
On large, complex, multiteam programs, consistent data collection is
essential, and the volume of status information can become quite a burden.
One way to manage this is through a centralized project office, responsible
for assembling, summarizing, and analyzing the data consistently for all the
project teams. This ensures current, consistent data, and also permits use of
more complex scheduling tools without the cost of so many copies and the
considerable effort that would be required for all the project leaders to master
the tool.
Project status meetings are also usually weekly. When face-to-face
meetings are not possible, use the best available telecommunications
methods. The frequency and methods used vary from project to project, but
risks rise steeply when reports, meetings, and other communication are less
frequent than weekly.
Decisions on how and where to store the project status information are
also important. Online storage of project data is best because it provides the
project team access at any time. Determine the tools and systems to be used
for collecting and storing the data, and set up appropriate security so that only
team members who should be updating project information will be able to
modify it.
The precise details for these decisions related to project monitoring will
affect your ability to manage risk, so commit to methods and frequencies that
will best serve your project.
Project Status
Project status information is of two types: hard data (facts and figures)
and soft data (anecdotal information, rumors, and less specific information).
Both types of data are useful for risk management. Hard data includes the
project metrics discussed in Chapter 9, and most of them are diagnostic
metrics—telling you how the project is proceeding. Some of the hard data
collected will relate to, or may even be, a risk event trigger, and other data
may reveal dangerous trends. Soft data can tell you the causes for your
project status; it may also provide early warnings of future problems and
risks.
Hard data. Hard project data includes metrics that assess progress,
including revised start and completion estimates for future work. Hard data
collection should be routine, easy, and not too time-consuming. On most
projects, people are so busy that if collecting hard status information is not
simple, it will not get done. At a minimum, collect:
• Schedule data, such as activities completed and activities scheduled
but not completed, milestones completed or missed, actual activity
start and finish dates, and duration remaining for incomplete activities
• Resource data, including actual effort consumed, cost data, remaining
effort for incomplete work, and missing resources
• Data regarding issues, problems, and specification changes
Soft data. Additional information of a less tangible nature also
permeates your project. Information about the project contributors may alert
you to potential threats to needed resources, individual productivity, and
other potential sources of project risk. Changes in the work environment, a
rumored reorganization, or individual team members having personal
problems may also adversely affect upcoming project work. Soft data may
also provide information on opportunities to help the project. Soft project
data includes issues such as:
• Conflicts arising from expected new projects or other work
• Falling productivity of individual team members
• Imminent infrastructure changes that could affect your project
• Delayed changes required by your project
• Potential problem situations with a common, persistent root cause
• Frequent situations requiring more authority than you have
• Long delays getting resolution of escalated issues and decisions
The Status Cycle
Project monitoring depends on a four-stage cycle that repeats
periodically (generally weekly) throughout the project. The first stage is
inbound communication, collecting of project status information. The second
stage of the cycle compares the status to the plan, evaluates the metrics, and
analyzes any variances. The third stage responds to any issues or problems
detected. The fourth and final stage is outbound communication, keeping
people aware of what has happened in the project.
The monitoring cycle provides for analysis and planning after
collecting project status information but before project reporting. This lets
you include your responses to any issues or problems in your project status
report. Any bad news you report will be received better if it is accompanied
by credible plans for recovery.
Collecting Project Status
Collecting project status is primarily your responsibility as the project
leader. Status data is your dashboard for the overall health of your project.
Whatever data you decide to collect, be dogmatic in collecting it. Projects
using agile methods often employ daily stand-up meetings where status is
quickly reported by all on three items: what was done yesterday, what will be
done today, and any expected issues. Project risk management requires data,
so do what you must to keep it flowing.
A number of factors can impede status collection. One pitfall is to
collect project status only “when there is time.” As projects proceed, the work
intensifies, and problems, distractions, and chaos build. It may be tempting in
times of stress to skip a status collection cycle. Especially during significant
problems, it is very risky to lose information. You may even find it necessary
to intensify data collection during problems or near project completion.
Other things to guard against are collecting data and then not using the
information or misusing it. After you collect status, at least incorporate a
summary of it into your overall project status report. When you fail to use
what you collect, your team members will either stop sending it or will put no
real effort into supplying meaningful data. Misuse of status information can
also be a major problem. When the status you receive is bad news, your first
temptation may be to grab a chair and break it over the head of the person
who sent it, or at least to yell a lot. One of the hardest things a project leader
has to learn is not to shoot the messenger. You need to respond positively,
even to bad news. Thanking people for bad news is never easy, but if you
routinely punish team members for providing honest data, you will quickly
stop hearing what you need to know—and project risks will escalate. It is
much better to mentally count to ten and then offer a response such as, “Well,
I wish you had better news, but I appreciate your raising this issue promptly.
What will help get you back on schedule?” The sooner everyone begins to
focus on recovery, the earlier things can get back on track.
Metrics and Trend Analysis
After comparing status, look for project problems by analyzing
variances. Variance analysis involves comparing the status information you
collected with the project baseline plan to identify any differences. Variances,
both positive and negative, need to be analyzed for impact; positive variances
may provide opportunities for improved execution of future work, and
negative variances need attention so that they do not send the project
spiraling out of control. Trend analysis on the metrics may also reveal
potential future risks and disruptions.
Diagnostic Metrics
After contrasting the status data with the plan, the first thing to do is to
validate the differences, particularly large ones. Before spending time on
impact analysis, check with the people who provided the data to make certain
that the problems (or for positive variances, any apparent opportunities) are
real. For each difference, determine the root cause of the variance, not just the
symptoms. (Root cause analysis is explored in Chapter 8.) Work with both
hard and soft project data to understand why each variance occurred. Metrics
seldom slip out of expected ranges in isolation; the project schedule,
resources, and scope are all interrelated, so problems with one of these
parameters will probably affect the others.
Armed with the underlying cause of each variance, you can best decide
how to respond. Dealing with the root cause of a problem also prepares you
for similar problems later in the project. In variance analysis, focus on
understanding the data; never just look for someone to blame.
Schedule metrics. Schedule variances are generally examined first,
whether positive or negative. Positive variances—work completed early—
may present an opportunity to pull in the start date of other work. It is also
worthwhile to discuss the early finish with the activity owner to see whether
it is the result of an approach or method that could be applied to similar work
scheduled later in the project or whether you could plausibly reduce any
duration estimates.
The more common situation is an adverse variance, which for critical
activities will impact the start of at least one scheduled project activity.
Unless work following the slip can be compressed, critical slippage will
affect all the activities and milestones later in the project, including the final
deadline. Even for noncritical activities, adverse variances are worth
investigating; the slip may exceed the flexibility in the schedule, or it might
reveal an analysis error that could invalidate duration estimates for later
project activities.
Finally, schedule variances may be due to root causes that were not
detected during risk analysis. If the root cause of a slip suggests new risks
and project failure modes, note the risks and set a time for additional risk
analysis and response planning.
Resource metrics. Resource variances are also significant. Metrics
related to earned value management (EVM) are particularly useful in
examining resources throughout the project. EVM metrics, such as the cost
performance index (CPI), measure the effort or money consumed by the
project in relation to the plan. If the consumption is low (CPI less than one)
but the schedule progress is adequate, there may be an opportunity to
complete the project under budget. If it is too low and the schedule is also
slipping, the root cause is likely to be inadequate staffing or too little of some
other available resource. Whenever project progress is too slow because of
insufficient resources, escalate the situation to higher management promptly,
especially if your project is being denied access to committed resources.
Whenever resources are being used in excess of what is expected—that
is, when CPI is higher than one or another metric shows your “burn rate” is
too high—the variance is almost certainly a serious problem. The likelihood
is strong that the project will ultimately require more resources to complete
than the plan indicates because it is very difficult to reverse resource
overconsumption. Even as early as 20 percent through the project schedule, a
project with an adverse CPI variance has essentially no chance of finishing
within budget. Using more resources than planned may cause your project to
hit a limit on staff, money, or some other hard constraint and halt the project
well before it is completed. Publicly admitting to this sort of problem is never
easy, but waiting will only make things worse. Problems like this increase
with time, and the options for recovery diminish later in the project.
Sympathy from your project sponsors and stakeholders will drop from little
to none at all if you wait too late to deliver bad news.
Some resource issues are acute, having impact on only a short portion
of the project; others are chronic and will recur throughout the work. Chronic
situations not only create project budget problems, they also may lead to
frequent overtime and constant stress on project staff. Risk probabilities rise
with increased stress and lowered motivation. Chronic resource problems
may also have an impact on your ability to execute existing contingency
plans.
Scope metrics. Although schedule and resource data provide the most
common status variances, at least some of the data relates to the project
deliverables. Either the results of tests, integration attempts, feasibility
studies, and other work will support the expectations set out in the project
requirements, or they will not. Significant variances related to scope may
indicate a need to propose project changes. Major variances may even
foreshadow ultimate project failure.
If a scope-related metric exceeds the result expected, you should
explore whether there might be an opportunity for the project to deliver a
superior result within the same time frame and budget. It may even be
possible to deliver the stated result sooner or less expensively. Although this
situation is relatively rare, it does happen, and how best to exploit such
opportunities may not be obvious. Discuss them with your project sponsors,
customers, and other stakeholders before adding something to the project
scope just “because you can.” Use your change management process to
assess the value and utility of any additional product feature before
incorporating it into the project.
When scope-related data indicates a problem that can be resolved with
additional work, the impact may be to the project schedule, resources, or
both. Consider various alternatives by analyzing what realistically can be
delivered within the project budget and deadline. Determine the most
palatable option (or options) based on relative project priorities, and propose
required changes to the project objective.
If you cannot resolve a scope problem with extra work, your remaining
options are to modify the deliverable or to abandon the project. Like resource
overconsumption problems, scope underdelivery issues are always difficult to
deal with. Some projects choose to hide the problems, hoping that someone
comes up with a brilliant idea to close the gap between what is desired and
what can credibly be delivered. This is a very high-risk strategy that seldom
works. The best course is to raise the issues as soon as you have validated the
data. If you do this early, project options are more numerous, the total
investment in the project is still relatively small, and expectations are less
locked in. Although still painful and unpleasant, this is a lot easier than
dealing with it later. When a project deliverable proves to be demonstrably
impossible, the best time to change it (or kill it) is early, not late.
In addition to the impact on the current project, scope problems may
affect other projects. Inform the leaders of projects depending on your
deliverable (or who may be using similar flawed assumptions), so that they
can develop alternate strategies or work-arounds.
Once you have completed the variance analysis, document the impact.
List the consequences of each variance in terms of:
• Predicted schedule slip
• Budget or other resource requirements
• The effect on the project deliverable
• Impact on other projects
Once you have determined the source and magnitude of the problem,
you have a basis for response.
Trend Analysis
Trend analysis does not necessarily need to be part of each monitoring
cycle, but it is a good idea to periodically examine the trends in the status
data. When the resource consumption rates or cumulative slip for the project
is moving in a dangerous direction, the trend data will make it clear. The
earlier you are able to detect and analyze an adverse trend, the easier it will
be to deal with it. Trend data may reveal a need to adjust the project end date,
increase the budget, request more staff, renegotiate contracts, or modify the
project deliverables. If so, the earlier you start, the better your chances for
success.
Unfavorable trends detected early in the project can show the need for
change when there is much more tolerance for it. Near the start of a project
the objectives remain somewhat flexible in the minds of the project sponsors,
stakeholders, and contributors. Ignoring or failing to detect adverse trends in
the status data is very risky. If trend information indicates a problem and you
take no action, the trend is likely to continue and grow. Ultimately,
something will have to be done. As it gets later in the project, the options
diminish and the changes required to reverse the trend become more extreme
and less likely to help. Also, late project interventions often create additional
problems and may even result in project failure.
Detecting and dealing with adverse project trends early enough avoids
the late project changes and cancellations that are so demotivating for project
teams. After having worked for months, or even years, on a project, even
small changes to the deliverable can be devastating to the team. Allowing
everyone to identify with an aggressive, high-tech, bleeding-edge objective
for the bulk of the project and then having to chop the heart out of it at the
last minute so that you can ship something on time is demoralizing and
embarrassing. People identify with the work they do, so late project changes
are taken very personally. Motivation on subsequent projects will be low. If
this happens often, project staff members will stop caring about their projects
and will not trust the people who lead and sponsor them. Modern projects are
successful not because they are easy; they succeed because people care about
them. Anything that interferes with this raises project risk to insurmountable
levels.
Responding to Issues
At this point in the status cycle, any significant differences between the
plan and actual project performance are visible. Treating plan variances as
issues and resolving them soon after detection, when they are still small,
allows project recovery with minimum disruption. Responding to project
issues resembles risk response planning, discussed in Chapter 8. In fact, for
issues that you anticipated as risks, the response could be as simple as
implementing a contingency plan. Base your response plan on the specifics of
the problem. If the variance is small, it may be sufficient to delegate the
response to the team members responsible for the work affected. Other
possible responses range from very minor staffing shifts or resequencing of
project activities to major changes to the project objective, or even to project
cancellation. The process for issue response closely resembles the plan-do-
check-act cycle from quality management. In planning problem responses,
work quickly but seek good solutions.
When you have captured ideas for response, analyze how each will
affect project schedule, resources, and scope. Probe for possible unintended
consequences, both in your project and for other, related work. The best of
the options developed may not present any obvious problems or require any
significant project changes (sometimes the brute-force option of just working
some additional overtime is the path of least resistance).
Larger problems may require major changes. If so, submit each option
you are considering to the change management process for review. For
significant changes, implementation may involve fundamental replanning. If
so, get buy-in from the project team and stakeholders for the revised plan.
When necessary, revalidate the objective and baseline with the project
sponsor, and update all affected documents.
Once a response plan is accepted, implement it. Communicate to the
project team and any other people involved the plan modifications and other
information required for project changes. After taking the actions in the
response plan, verify that you have solved the problem. If your actions prove
ineffective, plan for additional responses, looking for a better solution.
The situation is similar to how the fire department treats a fire. Initially
a new fire is one alarm, and one fire crew is sent out. When the fire is too
large, or it spreads, the fire department escalates to two alarms, and then, if
needed, to three or more. The escalation continues until the fire is brought
under control. Ongoing project risk management requires the same diligence,
escalation, and persistence. Significant project changes often lead to
unintended consequences. During the status cycles that follow big changes,
be particularly thorough in your data analysis and look for unexpected
results.
Communication and Risk Reporting
The final step in the status cycle is to let people know how the project
is doing. This includes project status reports and status meetings, as well as
less formal communication. Successful projects depend on a solid foundation
of clear, frequent communication. Without effective communication, project
risks may not be detected, let alone managed.
Communication on projects presents a number of growing challenges.
Distance is a well-known barrier to communication. It restricts both the type
and amount of communication possible, and it reduces informal interaction to
almost none. As project teams become increasingly global, time differences
also interfere with communication. Even phoning people on global projects
can be difficult. It seems that whenever you need to talk, it is the middle of
the night for them. Different languages and cultures are another growing
communication challenge for modern projects. Global work involves people
who speak different languages and who have different ways of working and
communicating. Sharing complicated project information in this sort of
environment is never easy, and omissions and misunderstandings are
common. Cultural and linguistic diversity in technical work is becoming the
norm, not the exception, for all types of projects. Finally, today’s projects
involve cross-functional project teams coming from diverse educational and
work backgrounds. It may be easier for an engineer in Ohio to communicate
with an engineer in Japan than it is for either of them to communicate with a
marketing manager down the hall.
As the project leader, you are the person primarily responsible for
project communication. You need to rise to these challenges and minimize
project communication risk. In today’s projects, this requires discipline and
effort.
Project Status Reports
The most visible communication for most projects is the written status
report. Ongoing risk management depends on clear, credible project
information that is understood by everyone on the project. Status reporting
that is too cursory increases risk because no one has enough information
about the project to know what is happening—leading to chaos. This may
occur because the project leader is busy or distracted and provides too little
data. It also may be the result of need-to-know project reporting, where the
project leader sends out very brief notes to each team member containing
only data on the portion of the project that each contributor is involved with.
It can even happen because the project leader dislikes writing reports.
Whatever the reason, projects with too little information become very prone
to risks, particularly risks related to dependencies and interfaces.
On the other hand, status reporting that rambles on and on is no better.
No one has time to read it all, and although the information everyone needs is
probably there, somewhere, finding it is impossible. One common reason for
long reports is a project leader who solicits individual reports from the whole
team and concatenates them into a compendium running to dozens of pages.
Time pressure can be a factor in this; there is much truth in the old saying, “If
I‘d had more time, I’d have written a shorter report.” Whatever the reason,
the result of rambling reports is also increased project risk because no one
will have the patience or time to find the information they need.
The best reports start with a short, clear summary, including current
risks. Regardless of who you are sending a status report to, begin with a brief
summary (20 lines or fewer). Be aware that sometimes the summary is all
that will actually be read and that some of the people who receive your report
will not need or want any more detail than this.
Follow the summary with additional needed information that is
concise, honest, and clear. If you commit to weekly reporting on a specific
day, do it. Understand what your stakeholders need to know and provide it in
your reports, in a consistent place and format. Any important data that people
notice is missing will probably result in unnecessary and time-consuming
telephone calls, meetings, or other interruptions.
Following your high-level summary, your project status report may
include:
• A short description of each major accomplishment since the last
report (an excellent place to name names and to recognize individual
and team accomplishments)
• Activities planned during the next status period
• A schedule summary, with planned, actual, and expected future dates
• A resource summary, with planned, actual, and expected future
resource requirements
• Significant risks, issues, and problems with your planned responses
• Project analysis, including an explanation of any variances, issues,
and plans for resolution
• Risk analysis, including the known risks in the near project future and
the status of any ongoing risk recovery efforts
• Additional detail, charts, and other information, as needed
Include only status information that you can substantiate in your
written status reports.
Risk Trigger and Metric Reporting
Many risks in your risk register will have defined triggers, specific
signals that indicate that a risk has happened or is about to occur. Others will
be related to trends or thresholds based on your diagnostic project metrics.
Throughout your project, work with the risk owners in monitoring for events
and measurements that reveal the current state of your known risks.
Incorporate what you learn in your status and other reporting, in your
risk register, and in any other risk-related communications. When reporting
on risks, focus on metrics and other fact-based data, and always include a
summary of your response efforts and recovery results.
Risks as Issues and Risk Response Status
Whenever a risk occurs, it becomes an issue. (The probability is now
100 percent.) List and manage all current risks you are responding to with
other project issues in addition to tracking your progress in your risk register.
Resist the urge to minimize the impact and consequences of risks in your
status and other reporting. It is tempting to spin adverse events and make
them appear less damaging than they are, and there are unquestionably
disincentives for candor when you are having problems. Overall, though,
hiding bad news will not make recovery any easier, and it will damage your
credibility if (or when) you do need to escalate to get help. Visible problems
are always tolerated better than those that emerge suddenly as major
disasters.
Other Reports and Presentations
You will also generally be required to do additional reporting on your
project, including periodic reports in support of organizational requirements.
Especially on longer projects, you will occasionally need to create higher-
level reports and do presentations. Presentations are an excellent opportunity
to reinforce the importance of your project, to be positive about what the
team has done, and to share your plans for the future. You can also outline
your current challenges and risks, and your plans for dealing with them.
Presentations are a particularly effective way to renew strong project
sponsorship, motivate your team, and renew enthusiasm for the project. On
longer projects, all of these factors can assist in avoiding future problems and
risks.
Top Risks
Visibility and risk communications are powerful and effective risk
mitigation strategies. Create and post a top-ten list of current risks where your
team members can see it, such as on a Web site, on a poster in your work
area, or in your team communications. People always work to avoid risks
they are aware of, particularly when they understand the impact and
consequences.
Project Status Meetings
Project status meetings are viewed by many as a necessary evil and by
nearly everyone else even less positively. Technical people, for the most part,
hate meetings, especially long ones. Considering the increase in project risk
that results from inadequate communication, this is unfortunate. The
discussions and exchanges that occur during project status meetings are
essential for avoiding risks; many potential problems never occur as a result
of timely discussions and awareness developed during status meetings.
Holding regular status meetings, even via teleconferencing, is a potent tool
for keeping difficult projects on track and risks under control.
One key to improving status meeting attendance and participation is to
keep them short. Meetings are more interesting and energized if they focus
only on important project information—what has been accomplished and
what issues are pending. Problem solving and issue resolution are
unquestionably important, but these activities rarely require the entire project
staff to be involved. Delegate problem solving and extended discussions to
smaller groups, and strive to keep your meetings brief.
Effective meetings are well structured, sticking to an established
agenda. They also start on time, set time limits for the agenda items, and end
early whenever possible. Face-to-face communication minimizes
misunderstandings and reinforces teamwork but may not always be possible.
For teleconference meetings, minimize communication risks by:
• Using the best meeting technologies available
• Ensuring that the technologies used are familiar to all participants
• Verifying that the technologies to be used are compatible and
functioning by retesting them following any changes or upgrades
However you conduct your meetings, record what was discussed and
distribute meeting minutes promptly to all project contributors (and to others
as appropriate). File meeting minutes in your project archives.
Informal Project Communications
Never limit project communications to formal reports and scheduled
meetings. Some of the most important communication on most projects takes
place at coffee machines, in hallways, and during casual conversations.
Project risks may surface far earlier in these discussions than in more formal
interactions.
Successful project leaders create opportunities for these frequent,
unstructured conversations. The idea of management by wandering around,
popularized by Dave Packard and Bill Hewlett, is a particularly effective way
to reinforce trust and build relationships within a project team. Even when
teams are distributed and you are unable to talk frequently with people in
person, there will be opportunities to do it once in a while, and you can rely
on the telephone in the meantime. A great deal of soft data and valuable
project information on project risks surfaces during casual exchanges.
Effective project leaders also work to encourage interactions among project
team members. Team cohesion, which correlates strongly with the amount of
informal communication, is one of your best defenses against project risk.
Project Archive
In addition to distributing project documents and reports to your
stakeholders and contributors, you also need to retain copies as part of your
project management information system (PMIS). This archive not only serves
as an ongoing reference during the project; it is essential for capturing the
lessons learned during postproject analysis, and it contains data that can
improve risk management on future projects.
A typical project archive contains:
• Project definition documents
• All versions of project planning documents used
• Each project status report
• Other periodic project reports and communications
• Risk register and issue logs
• A change control history
When the project is completed, the final addition will be the
postproject retrospective analysis and lessons learned.
Managing Risk Reserves
Ideally, reserves for time and budget will have been established for
your project in proportion to its risk. Reserves are used to enable the project
to meet its commitments in the face of unlikely and even unknown
challenges. Budget reserve is best used to deal with the financial effects of
risks and unforeseen, necessary expenses. Schedule reserve provides a buffer
for recovery due to slippage caused by unanticipated effort or risk-related
delays. Reserves serve to protect the project only if used exclusively to
support recovery. Strongly resist tapping them for scope creep, contributor
convenience, or other uses unrelated to risk response.
Monitor reserves as your project progresses. If you find that you are
consuming either budget or schedule reserves too fast (for example, having
less than half remaining for either at the project midpoint), discuss the
situation with your project sponsor and key stakeholders. Reserves are most
needed as you approach project completion, so whenever your reserves drop
too low, you may want to consider modifying your deadline or making other
baseline adjustments.
Project Reviews and Risk Reassessment
When you operate a complex piece of machinery such as an
automobile, you frequently need to add fuel, check the oil and the air pressure
in the tires, and make other minor adjustments. This is sufficient in the short
run, but if you never do anything more, the car will soon break down.
Periodically, you also must perform scheduled maintenance, change the oil,
replace worn-out or poorly functioning components, check the brakes and
other systems, and generally bring the vehicle back into good operational
condition.
A project is also a complex system. Monitoring and reporting on
planned activities is necessary, not unlike adding fuel to an automobile.
Unless the project is very short, you will need to do more. Longer projects
also require periodic “maintenance” in the form of project reviews. The
planning horizon for some projects may be as short as a month or two, or it
may extend to most of a year. However, no project can plan with adequate
detail beyond its planning limit, whatever it may be. Projects using agile
methods conduct reviews at the close of each development iteration. Project
reviews allow you to take a longer view, beyond the next status report, to
revalidate the project objectives, plans, and assumptions. Successful project
and risk management require cycles of review and regular reassessment to
keep the project on track.
The limited planning horizon and technical complexity also contribute
to the greater project risk of lengthy projects, and project reviews are an
effective way to better manage these factors. During a project review, one of
three scenarios will arise. Some reviews find few issues, and the project will
proceed with little or no modification to project plans. Other reviews will
reveal necessary changes and plan revisions. The project will move forward,
but only after updates modifying the objectives and project baseline. The
third possible outcome of a project review is a recommendation to cancel
future project work. Although this is not pleasant, it is ultimately better for
everyone to cancel a project that will eventually fail before investing even
more time and money.
Whatever other agenda items you set for your project review, plan to
explicitly reassess your risks and analyze your reserves. Discuss the problems
and risks you have encountered in the project so far, and brainstorm methods
for avoiding similar trouble as the project proceeds. Also, review your
existing risk list, and identify additional scope, schedule, resource, or other
risks that are now visible in the project. Add the new risks to your risk
register and reassess all of them, rank-ordering the risks based on current
information. Develop appropriate risk responses for any significant risks that
have none.
As you review your risks, also reassess the overall risk profile for the
project. As projects proceed, things change, and overall risk changes with
them—either increasing or decreasing. As the work proceeds and more is
known, project-level risk should decrease, but every project is different and it
is prudent to reassess. A project review is also a good time to check the status
of any reserves established for the project. If contingency funds are being
depleted faster than expected, determine what you need to do to ensure that
they will remain adequate. If you have used most (or all) of your schedule
reserve, consider options for increased staffing, revision of the deadline, or
other alternatives.
If changes to the project objective or reserves appear necessary, discuss
your recommendations with your project sponsor and use your change
processes to implement them.
After your review, document what you discussed and learned. Add a
summary of the review to your project archive, and communicate your
findings to your sponsor, related project teams, and key stakeholders.
Prepare a presentation to summarize the project’s progress to date and
your plans going forward. A formal presentation of project review findings
can also be useful in keeping the project visible, highlighting its
accomplishments and challenges. Accentuate the positive, emphasizing the
value and importance of the project. Ensuring that the organization remains
aware of the work, especially on lengthy projects, helps in maintaining
priorities and resources and makes overall risk management less difficult.
A project review is also a good opportunity for recognition and
celebration. Use your communications, reports, and presentations to highlight
significant accomplishments and to publicly thank specific people and teams.
Use thanks and recognition to renew enthusiasm for the project and to
motivate your project team. Project reviews are also a good time to celebrate
your accomplishments. Long projects, especially, need more parties.
Taking Over a Troubled Project
This chapter ends by exploring one additional project execution risk.
As the PERIL database shows, staff turnover is a significant problem. It can
be an especially personal one if the turnover results in your being asked to
lead a failing project. This unfortunate situation is one of a project leader’s
worst nightmares. Even if you inherit a project in progress that appears to be
in pretty good shape, it’s best to respond to such a request with, “I’ll take a
look at it and let you know as quickly as possible if any changes or
adjustments might be needed.”
Your first order of business is to find out whatever you can about the
project and to get to know the team. Although it may be interesting to dig
into why the prior project leader is no longer in the picture, this can probably
be left for later unless the information will contribute to project recovery.
Learning about the project can begin with a review of project
documents and other information in the project archive and elsewhere. If
there is a well-maintained archive of project information in a PMIS, it will be
invaluable. A new project leader who has access to such data still faces a
daunting task but will be light-years ahead of where he or she would
otherwise be. On a troubled project, though, there may be little useful
information. You quickly need to do the best you can to fill in the gaps.
For current information, spend time reviewing recent status reports. Be
skeptical and verify any information in them that is inconsistent with what
you see. Discuss the project with each project contributor, and use these
conversations to solicit suggestions for change, to build your understanding
of how things are going, and to start establishing relationships and trust.
Avoid making predictions or firm commitments while you investigate, but do
communicate openly and let people know when you expect to have better
answers.
If there is little concrete (or credible) information, you will need to
initiate a very fast planning effort to develop some. Even if there is data, at
least do a quick project planning review to validate it. Someone else’s plan
can be a good starting point, but it won’t serve as a reliable foundation for
project execution until it’s yours. An “express” planning exercise should
include, at minimum, detailed examination of all current and pending
activities, verification of the project’s committed scope, timing, staffing and
funding, and documentation of all currently identified issues and problems.
Projects may fail for many reasons, so determine the main problem or
problems. Some typical issues are:
• Schedule delays
• Excessive resource consumption
• Insufficient staff or other resources
• Scope not achievable using available technologies and capabilities
• Low priority
• Conflicts with other projects
• Weak sponsorship
Recovery requires prompt action, and the best strategy for this comes
from the medical field: triage. Once you have determined what is not going
well and listed all the project activities and issues needing attention, sort them
into three categories. Some things need immediate attention and will result in
permanent damage to the project if not addressed right away. Identify and
staff this work, stopping other activities with lower urgency where necessary.
Other matters on your list need attention but not right now, so put them aside
for the present and plan to address them soon. Other matters listed may be
hopeless. Note these and move on.
This last category is potentially very revealing because these legitimate
project problems may provide evidence that the project cannot be completed.
Even the issues that you are able to manage and resolve may require more
resources, time, or both than can be justified. Schedule time with the project
sponsor to review your response actions and the overall project. Plan to
discuss modifications to the project or even cancellation. Not all troubled
projects can be saved, and it’s better to pull the plug on a doomed project
sooner rather than later.
If the project is recoverable, your next steps after resolving the short-
term problems will be to schedule an in-depth project review, as just
described. Your goals for this are to understand the project and to engage the
project team in developing current and realistic project planning information,
including updated risk data. Once you have the truck back on the highway,
invest the time it takes to ensure that you can keep it there and out of the
ditch. Tools for this are found throughout this book.
Key Ideas for Risk Monitoring and Control
• Collect status dogmatically.
• Monitor variances and trends frequently throughout your
project.
• Respond to issues and problems promptly.
• Communicate clearly and often.
• On long projects, conduct periodic risk and project reviews.
• Be skeptical whenever assuming leadership of a project.
Conduct a quick, thorough review to initiate changes and
“make it yours.”
Panama Canal: Risk-Based Replanning (1908)
Project monitoring and prompt responses when necessary were among
the main differences between the initial nineteenth-century effort to construct
the Panama Canal and the second one. No project proceeds exactly as
planned, and the U.S. canal project was no exception. It was ultimately
successful because the managers and workers revised their plans to deal
effectively with problems as they emerged.
As the work at Panama continued, for example, it seemed that the more
they dug, the more there was to dig. Mudslides were frequent, and between
1906 and 1913 the total estimates for excavation more than doubled. The
response to this problem was not terribly elegant, but it was effective.
Following the report of a particularly enormous mudslide in the Culebra Cut,
George Goethals remarked, “Hell, dig it out again.” They had to, many times.
Some risks are managed primarily through persistence and perseverance.
As time passed, a number of factors not known at the start of the
project came into focus. By 1908, it became clear that new materials,
including the steel to be used on the canal, were making possible the
construction of much larger ships. Goethals made two significant design
changes as a result of this. The first was to commit to a wider excavation of
the Culebra Cut, increasing it to nearly 100 meters (from 200 feet to 300 feet)
to accommodate ships wider than 30 meters sailing in opposite directions.
Although this represented much additional digging, it also made the tasks of
ongoing maintenance and dredging a little easier.
The second change was to the size of the locks. Based on Goethals’s
estimates of the size of future oceangoing ships, the locks were enlarged to be
110 feet wide and 1,000 feet long. Although conversion to metric units of
these dimensions is simple, few do it, as this somewhat arbitrary choice of
dimensions became the single most important factor in twentieth-century ship
building. These dimensions are the exact size of the rectangular-hulled
PANAMAX ships, the largest ships that can transit the canal. Apart from oil
supertankers (which are generally designed for use on a single-ocean, point-
to-point route), until recently, very few ships were built any bigger than a
Panama Canal lock.
In addition to making the locks larger, Goethals made another change
to them. All the water used to operate the canal flows by gravity. Locks are
filled from the artificial lakes above them and then emptied into the ocean.
During the rainy season, this works well. In the drier parts of the year, the
depth of the lakes falls, and the water level in the cut connecting them could
fall too low to permit oceangoing ships to pass. To save water, Goethals
redesigned each of the 12 locks with multiple sets of doors, enabling smaller
ships to lock through using a much smaller volume of water.
One additional significant change was adopted midproject, primarily
for security reasons. At the start of the twentieth century, the global political
situation, particularly in Europe, was increasingly unstable. On the Atlantic
side, the geography of Panama has a long, gradual slope from the central
ridge north and a much shorter, steeper slope on the south, facing the Pacific.
On the steeper Pacific slopes, the locks in the original plan were visible from
the water, and Goethals, a military man, feared that the canal might be closed
down by projectiles fired from an offshore warship. To avoid this, he moved
the Pacific locks further inland. The change actually made the engineering
somewhat easier, as the new plan took better advantage of the more level land
farther up the slope.
George Goethals minimized risk through scrupulous management of all
changes, insisting throughout his tenure that “everything must be written
down.” Once the plan was set, the debating stopped, and all the effort went
into execution.
Chapter
12
Closing Projects
History repeats itself. That’s one
of the things wrong with history.
—CLARENCE DARROW
Reviewing the records of complex projects, it is striking how many
consecutive projects fall victim to the same problems. Common issues such
as inadequate staffing, top-down-imposed deadlines having no relationship to
the work, fixed commitments based on little or no analysis, and many other
issues listed in the PERIL database plague project after project. One
definition of insanity is repeating the same actions over and over, hoping for
a different result. More than a little risk in most projects is a direct result of
employing the same methods for projects that have caused problems in the
past.
Getting better results requires process improvement. Using a
continuous cycle of measurement, small modifications, new measurement,
and comparative analysis, you can discover ways to improve any process.
You can, as part of project closure, examine the results you obtained from the
processes that were used for each project. Achieving consistently better
results and minimizing future risks requires you to identify what worked
well, ensuring that these processes are repeated on subsequent projects. It
also requires you to identify the processes that do not work and change them.
Modifying a broken process is almost always better than repeating something
you know does not work. After the changes, if the performance of your next
project is still not good enough, you can always change it again. Postproject
analysis is a powerful and effective tool for longer-term project risk
management.
Project Closure
A number of closure activities are common to most projects, but the
specifics vary a great deal with the type of project. Project close-out generally
involves:
• Formal acceptance of completed project deliverables
• The final written report
• Close-out of all project contracts, documents, and agreements
• Acknowledgment of contributions
• A postproject retrospective analysis to capture the lessons learned
• A celebration or other event to commemorate the project
The most relevant of these to risk management is the retrospective
analysis, which is covered in detail later in this chapter.
Formal Acceptance
One of the greatest potential risks any project leader faces is finishing
the work only to be asked, on delivery, “What’s this?” Scope risk
management seeks to avoid this situation through validation of the initial
specifications, periodic revalidation of requirements, and scrupulous
management of changes. Defining all final acceptance testing, aligned with
the initial specifications, should be one of the first activities undertaken in
complex projects, as part of scope definition and planning. Even for projects
using agile methods, you will be wise to develop a clear definition of the
problem you are solving and what criteria a useful solution would need to
meet. Testing and acceptance requirements must also be modified as
appropriate throughout the project in response to authorized changes. If final
tests and acceptance criteria are defined only late in the project, it is only
through happenstance that the project deliverables will be accepted.
Managing this risk involves thorough specification of the deliverable
and frequent communication throughout the project with the people who will
evaluate and accept it. You can also minimize the risk greatly by engaging
them in discussions and evaluations of any prototypes, incremental results,
models, iterative development outputs, or other interim project deliverables.
Detailed, validated scope definition is the best way to minimize late project
surprises.
When you have completed your project, get formal acknowledgment of
this from the project sponsor and, as appropriate, from the customer and key
stakeholders. For projects undertaken on a fee-for-service basis, generate the
final billing information and ensure that the client is properly and promptly
billed. Even for projects that end in cancellation or fail to deliver on all of
their objectives, you should obtain written acknowledgment whenever
possible of the partial results or other accomplishments that you did
successfully complete.
Final Project Report
The main purpose of a final report is to acknowledge what has been
done and to communicate to everyone involved that the project is over. Every
final project report should also thank the contributors.
Contract and Document Close-Out
At project close, complete any final paperwork required for all internal
agreements and external contracts that are specific to your project. Following
final payments of all invoices, summarize the financial information and
terminate the agreements. If there are issues or problems relating to any
contracts, escalate and resolve them as soon as practical. If you have had
difficulties with any outside service providers, document them and make the
information available to other project leaders to avoid similar risks in the
future.
As part of project closure, add all final project documentation to your
project information archive.
Acknowledging Contributions
It is a small world. Once you work with people, the chances are fairly
good that you will work with them again. Managing risk in a continuing
stream of projects depends on developing and maintaining trust,
relationships, and teamwork. Recognizing the accomplishments and
contributions that people have made is fundamental to this.
On complex projects, expertise and hard work are frequently taken for
granted. When technical people finish difficult activities, often the only
feedback they get is an assignment to another, even more difficult activity.
Especially at the end of a project, you need to thank people, both in person
and in writing. For people who work for other managers, also acknowledge
their contributions to their management. Keep your remarks truthful but focus
on positive contributions. If it is culturally appropriate, praise people and
teams publicly as well. If programs are in place for specific rewards, such as
stock options or other tangible compensation for extra effort, submit
recommendations for deserving project contributors to reward them for their
work.
Celebration
Whatever the atmosphere has been in the closing days of a project,
bring each project to a positive conclusion. Celebrate the success of the
project with some sort of event. Even if the project was not a success, it is
good to get people together and acknowledge what was accomplished.
Celebrations need not be lavish to be effective; even in businesses that may
not currently be doing well financially, project teams can get together and
share food and beverages that they provide for themselves. Moving on to the
next project or another assignment is much easier when people have a chance
to bring the last project to a friendly conclusion. If your project has a global
or distributed team, arrange a similar event for each location at roughly the
same time.
Project Retrospective Analysis
Managing project risk on an ongoing basis requires continuing process
improvement. Whether you call this effort a retrospective meeting, lessons
learned, a postmortem, a postproject analysis, or something else, the
objective is always the same: improving future projects and minimizing their
risks. If the people who led the projects before yours had done this more
effectively, your project would have had fewer risks. Help the next project
leader out—it could be you.
The overall process for a project retrospective analysis is similar to the
project review process discussed in Chapter 11, but the focus is broader.
Project reviews are primarily concerned with the remainder of the current
project, using the experiences of the project so far to do course corrections. A
retrospective analysis is backward-looking and more comprehensive, mining
the history of the whole project generally for ideas to keep and for processes
to change in future projects.
Before you schedule and conduct a project retrospective, get
organizational commitment to act on at least one of the resulting change
recommendations. Performing postproject analyses time after time that
always discover the same process defects is worse than useless. It wastes the
time of the meeting participants and is demotivating. Decide how you will
use the resulting information before you commit resources to the analysis.
Preparing for and Scheduling a Project Retrospective
Thorough postproject analysis requires that you have accurate,
thorough project data. As you add the final project documents to the archive,
determine what information you need, and ensure that it will be available for
review during your project retrospective meeting. Schedule a retrospective
analysis soon after your project but not immediately after it. If it is too soon,
final documents will be incomplete and events from the last, chaotic days of
work will dominate the analysis. Don’t wait more than about two to three
weeks after the project, though, or important memories, particularly the less
pleasant ones, will begin to fade.
Allocate sufficient time. Even shorter projects can generate enough
data to justify an hour or so to look backward. Set an agenda providing time
for all contributors to comment and to collect both positive results and
proposals for process change. Encourage participants to come prepared with
specific examples of what went well and what changes they would
recommend.
Retrospective Surveys
If your business has a standard retrospective survey form, plan to use
it. A retrospective survey is an effective way to gather information about
project definition, planning, defect and issue management, decision making,
teamwork, leadership, process management, managing dependencies and
deliverables, testing, logistics, and other project processes. Standard formats
usually have lists of statements to be rated on a scale from “strongly agree”
on one extreme to “strongly disagree” on the other, along with spaces for
written comments.
If there is no survey form or the one you have does not include much in
the way of risk information, the survey form on the next page may be useful.
Plan to use the survey in addition to the discussion of processes during
the meeting. You can also use it to collect inputs from any project
contributors who are unable to participate.
Project and Risk Management Review and Assessment
Start a retrospective meeting with a statement of objectives, and review
the meeting agenda and ground rules for the meeting. At a minimum,
establish a rule to maintain a focus on the processes and to avoid attacking
individuals and “blamestorming.”
Capture ideas generated in the meeting, focusing on pluses and deltas.
Start your analysis with positives before moving to needed changes (not
negatives). Collecting positives about the project first reminds people of what
went well. Probe for specific opinions on project aspects that led to success.
Capture what worked particularly well on your project; identify any new
practices that you should repeat or extensions to existing processes that were
valuable. Also reflect on significant identified risks that you managed to
avoid (or opportunities you were able to take advantage of), and any actions
you took to achieve this.
Postproject Risk Survey
Please evaluate each of the following statements using the scale:
1—Strongly agree 2—Agree 3—No opinion 4—Disagree 5—Strongly
disagree
Also, please add any comments or feedback you have on any of these
topics.
1 2 3 4 5 The project developed and used a risk plan.
1 2 3 4 5 Project problems were dealt with quickly and were escalated
promptly when necessary.
1 2 3 4 5 Schedule problems were dealt with effectively.
1 2 3 4 5 Resource problems were dealt with effectively.
1 2 3 4 5 Project specifications were modified only thorough an effective
change control process.
1 2 3 4 5 Detailed project reviews were done appropriately.
1 2 3 4 5 Project communication was frequent enough.
1 2 3 4 5 Project communication was thorough and complete.
1 2 3 4 5 Project documentation was self-consistent and available when
needed.
1 2 3 4 5 Project status was reported honestly throughout the project.
1 2 3 4 5 Reporting of project difficulties resulted primarily in problem
solving.
1 2 3 4 5 The project had adequate sponsorship and support
throughout.
When most of the positives have been cataloged, turn your focus to
desirable changes. Identify process areas that need improvement and
practices that could be simplified or eliminated. Consider project issues and
problems that you had to deal with. Review your risk registers to identify
risks you encountered, along with any unknown risks that befell your project.
Describe any changes you could implement to better insulate your project
work from similar exposures. Brainstorm tactics for mitigating errors and
failures, and develop process recommendations for avoiding similar problems
on future projects.
Throughout the meeting, work to hear from everyone, not just a vocal
minority. As the allotted time winds down, summarize the recommendations,
and ask each participant to nominate one recommendation that he or she
believes would make the most significant difference on future projects. Work
as a group to develop consensus, if possible, on the most important change or
at least generate support from the group for one or two that top the list.
Close the meeting with reflections on the process and encourage people
to share what they learned from the project personally and how they plan to
work differently in the future.
Documenting the Results and Recommendations
Document the meeting results in a concise format with the top
recommendation (or recommendations) and key findings in a clear, short
summary at the beginning. Distribute the project retrospective report to the
participants for review and comment.
Project and Risk Management Process Improvement
Take the principal recommendations to your management and request
support for making the necessary changes. Small changes can be fairly trivial
to implement, but more significant ones may trigger new projects and require
significant data, planning, and resources to initiate. If your recommendation
is rejected, discuss alternatives with the project team and investigate whether
there might be other ways to mitigate the problem that, although less
effective, would be under your control.
In any case, take at least one issue emerging from every project and
resolve to do something different in your next project to address the problem.
Effective risk management requires your firm commitment to continuous
process improvement.
Examine your overall risk management planning and effectiveness. If
your project encountered any black swan (low-probability/high-impact) risks,
review your overall process for assessment, especially your estimation of
probabilities. If you suspect sources of bias may be responsible for incorrect
analysis of risks, consider changes to your assessment process. At a
minimum, resolve to be more skeptical of assumptions that appear to be
overly optimistic regarding negligible worst-case impact or very low
likelihood.
Process improvement rests on the plan-do-check-act cycle and requires
persistence. Managing project risk means reusing what has worked before on
your projects and fixing or replacing what has failed. Every project offers
beneficial lessons learned.
Project and Risk Data Archiving
When completed, put a copy of the results in the project archive, and
share the findings with others who could benefit from the information,
including the leaders of similar projects. If your organization has a
centralized repository for risk data, supplement it with information from your
completed risk register. Although public airing of risk experience may result
in some embarrassment, hiding adverse experiences will lead to repetition,
further pain and needless expense, and even more embarrassment. If your
organization lacks a risk data archive, work to establish one.
Key Ideas for Project Closure
• Thoroughly and accurately document the project results.
• Recognize accomplishments and thank contributors.
• Conduct a project retrospective and use the recommendations.
• Review your risk processes and update your data archives.
Panama Canal: Completion (1914)
On August 15, 1914, the first seagoing vessel crossed Panama, and the
Panama Canal opened all the way through. This huge accomplishment was
reported far and wide as the biggest news of the day. The attention lasted
only a short time, though, as soon World War I broke out in Europe and
quickly overshadowed the canal story.
In retrospect: The 80-kilometer (50-mile) lock-and-dam canal was
completed, slightly more than ten years after the congressional act that
initiated the work. About 5,000 additional lives were lost finishing the U.S.
project. Some died from disease, but most of the loss of life was due to
handling explosives (making the total death toll as high as 30,000, including
those who died in the 1800s). The canal opened six months ahead of the
schedule set earlier by John Stevens, despite all the difficulties and changes.
Even more remarkable, it finished at a cost US$23 million less than the
budget (US$352 million had been approved). The total cost for construction
was over US$600 million, including the cost of the French project. If this is
not the only U.S. government project ever to finish both early and under
budget, it is certainly the largest one to do so.
Most of the credit goes to George Washington Goethals. Although he
never failed to acknowledge his debt to John Stevens, nearly all the work was
accomplished while Goethals was chief engineer. After the opening of the
canal, Goethals remained in Panama as governor of the Canal Zone, to
oversee its early operation and deal with any problems. His thoughts on
completion of the work at Panama, delivered in March 1915, were:
We are gathered here tonight, not in the hope of
something to be accomplished, but of actual
accomplishment: the two oceans have been united. The
[mud]slides hinder and prevent navigation for a few
days, but in time they will be removed. The construction
of the Canal means but little in comparison with its
coming usefulness to the world and what it will bring
about. Its completion is due to the brain and brawn of the
men who are gathered here—men who have served
loyally and well; and no commander in the world ever
had a more faithful force than that which worked with me
in building the Panama Canal.
If you were asked to name a famous engineer, Goethals would be an
excellent choice. Although other engineers have become famous as
astronauts, politicians, and multimillionaires, Goethals is famous for
engineering, and his name is on a major New York City bridge. His
accomplishments in addition to the canal are substantial, and he remains a
significant influence in civil engineering to this day. The lessons learned
from this project are thoroughly documented (as with all projects undertaken
by the U.S. Army Corps of Engineers). They serve as the foundation not only
for the subsequent civil engineering projects of the twentieth century but also
for much of what is now recognized as modern project management.
Chapter
13
Program, Portfolio, and Enterprise Risk
Management
There are risks and costs to a program of action.
But they are far less than the long-range risks
and costs of comfortable inaction.
—JOHN F. KENNEDY
The future, for any organization, requires action and entails risk. The
subject of this book, project risk management, is a useful starting point for
managing risk, but it will rarely be sufficient. Projects are always part of
something larger. Programs are made up of projects, so program risk
management relies on project risk management, among other things. Project
portfolios are made up of projects and may also include programs, so
portfolio risk management also depends on project risk management.
Enterprise risk management includes all of these types of risk management,
along with additional considerations. This chapter explores the relationship of
project risk management to each of these higher-level perspectives.
Project Risk Management in Context
Project success or failure is generally measured against the triple
constraint of scope, time, and cost, and the risks listed in the PERIL database
reflect this perspective. The success of programs and portfolios, not to
mention the health of the enterprise as a whole, depends on successful
projects—those that meet the objectives that they commit to. However, at
each level above the project, the connection with project risk management
becomes more abstract. The focus shifts, and these managers are not
necessarily measured and evaluated based on the fate of any single project.
Risk management in these other arenas extends well beyond the concerns that
keep project leaders awake at night. The focus of program risk management
is dealing with complexity. Portfolio risk management is primarily concerned
with achieving financial goals. Enterprise risk management shifts attention to
the longer-term health and viability of the organization as a whole.
The Focus of Program Risk Management
“Program” is a term that means different things in different contexts,
but the Project Management Institute defines a program as “a group of related
projects managed in a coordinated way.” This chapter explores this type of
program, where the main objective for program management is better overall
control of interconnected projects than would be possible if they were
managed autonomously. Programs include projects that are executed in
parallel, in sequence, or both. Projects are time-limited, with a specific start
and finish. Programs may also have deadlines, but some are open-ended; only
the component projects have well-defined closure objectives. Programs may
contain a few projects, hundreds of projects, or any number in between.
Program risk management closely resembles project risk management,
and for small programs, there may be very little difference. Risk management
for the program can be little more than aggregation of the risk plans and
strategies for the included projects. For larger programs, however, there is
exponentially increasing complexity that carries risk and more focus on the
successful delivery of benefits and value, which may require risk trade-offs
among the constituent projects. Because programs are composed of related
projects, risks tend to be highly correlated. Overall program risk can be
significantly higher than what might be expected based on the risks of its
component projects.
The Focus of Portfolio Risk Management
When projects are aggregated into portfolios, the overall focus shifts
even further from the results of a particular project or program. Portfolios,
whether made up of stocks, junk bonds, subprime mortgages, or projects, are
primarily focused on money—delivering an expected financial return. For
portfolios of projects, risk in the aggregate depends more on the average
project performance than on the success or failure of any specific project. As
discussed in Chapter 1, overall risk can be managed through the aggregation
of many separate undertakings, investments, or cases. If the population of
items making up the portfolio is independent, overall risk is moderated.
Project portfolios, however, like programs, may contain related projects that
are highly correlated and increase risk.
The Focus of Enterprise Risk Management
In the abstract, an enterprise can be thought of as a bundle of projects
and other activities that strives to increase in value over time though
successful execution of those undertakings. Ideally, the appreciation in value
will be more attractive to the investors and owners than alternatives such as
stuffing money into mattresses. From this perspective, enterprise risk
management is little different from portfolio risk management, and again the
main objectives tend to be financial. At the enterprise level, though, other
risks must be managed, some of which relate to the survival and ongoing
health of the organization. Laws and regulations must be obeyed, and
principles need to be established and followed to ensure the future trust of
owners, customers, employees, and others. Where the focus of project risk
management is short term, enterprise risk management must also consider the
big picture and longer time frames. In addition, corporate officers of public
corporations in the United States and elsewhere are now faced with
significant personal penalties and potential legal prosecution. The
relationship between enterprise risk management and project risk
management is bidirectional. The financial success and overall well-being of
an enterprise depends on effective project risk management, especially for
large and high-visibility projects. Enterprise risk management, particularly in
the recent past, has been a fertile source of projects.
Program Risk Management
The line between project and program management is not exactly
precise. An endeavor with 10 people that delivers a result in six months is a
project, and an undertaking with hundreds of people working globally in a
dozen independently managed teams to deliver periodic deployments over the
course of five years is a program. Between these extremes, you will find both
very large projects and modest programs, and the difference between the two
can be fuzzy. From the perspective of risk, though, program risk management
depends heavily on the project risk management principles outlined in the
chapters of this book, with a number of added considerations.
The main purpose of program management is dealing effectively with
complexity and overwhelming detail; work that entails thousands of activities
and large numbers of contributors is unwieldy to plan, and it’s impossible to
monitor as a single effort. Program managers have daunting responsibilities.
They are accountable for the overall program objective, managing the efforts
of the individual project leaders, and often a dedicated program staff or a
program office as well. Breaking large undertakings into chunks of work that
can be effectively delegated and managed as (largely) independent projects is
done for the same reason that projects are decomposed using a work
breakdown structure: It reduces the complexity by converting the large and
complicated into parts that are easier to deal with. Managing risks at the
program level begins with ensuring adequate planning and risk management
at the component project level. Although doing this is an effective start on
program risk management, it is insufficient.
It is never possible to break up a large piece of work into a set of
totally disconnected pieces; interrelationships remain that represent program-
level risks. At a minimum, program scope connects the included projects,
along with the overall business justification for the work. From a scheduling
perspective, there are always cross-dependencies connecting the projects
within the program. None of the interconnections is entirely contained within
any of the component projects, so they need to be tracked and managed at the
program level. These program interconnections showed up in the PERIL
database both as scope defect risks due to integration issues and as schedule
dependency risks arising from project timing difficulties. Also, because
programs are generally bigger and often longer than projects, they represent
larger risk because of their scale.
For all these reasons, programs usually have a risk profile that exceeds
the sum of their parts. A collection of modest-risk component projects may
well aggregate into a high-risk program because of positive probability
correlations for project risks in the interconnected projects. There are also
cascade effects. When a risk occurs in one project, it can trigger additional
problems in several other projects, quickly spinning things out of control.
Managing project risks is necessary, but program risk management extends
well beyond it.
Planning Program Risk Management
Chapter 2 discussed the topic of planning for project risk management,
observing that for small undertakings informal risk planning is generally
sufficient. For a program, informal planning is not sufficient. Programs are
generally large, and their risks arise from many sources. Some program risks
originate from above the program, as a consequence of the strategic or other
importance of the work to the organization as a whole. Other risks arise
within the projects that make up the program, and still others are intrinsic to
the program itself.
Formal program risk planning is a part of program initiation. To get
started, map out how much effort this will require, and verify support for the
work with your program sponsor (and with your other stakeholders, as
appropriate). The overall process for program risk management mirrors the
process for project risk management: plan, identify, assess, respond, and
monitor and control. The effort for managing risk for a program is often
integrated with other ongoing responsibilities of the program staff (or
program management office), but if you plan to use a separate staff with a
separate budget, secure approvals and funding to support this. For the
program, document:
• The risk tolerance of your sponsor and key stakeholders
• The owner for program risk management (if not the program leader)
and other program staff who will participate, with their roles
• The process you will use for program risk management, including the
format for the program risk register
• The planned frequency for program risk reviews
• The location where program risk information will be stored and how
you will track and communicate program risks
• Any metrics to be used in monitoring program risks
As an example, for several years I was responsible for planning and
risk management for a large program at Hewlett-Packard. This program was
responsible for consolidating global oversight for all current fee-for-service
projects under a single, consistent set of business processes and information
technology applications. The program had direct responsibility for a budget
of several million dollars per year and had a shifting roster of about 200
contributors working on more than a dozen project teams that were either
geographically based or responsible for delivery of key functions. The
program deployed updated systems and processes for roughly four countries
in each quarterly release, and after several years the updates were in
operation in more than 50 countries worldwide.
Risk management was an important success factor for the program.
The processes used for this were well defined and documented. I used them
throughout the program to conduct monthly program risk reviews with the
rest of the program staff. In our meetings, we reviewed the risks already
listed in the program risk register, retired any that were no longer of concern,
and added new risks based on evolving program plans and external changes.
During each meeting, we reprioritized the significant risks and then outlined
risk responses and contingency plans for recovery. Following each monthly
meeting, I distributed the updated risk register to the project leaders and made
the current version available to everyone working on the program on the
program’s Web-based knowledge management system. By periodically
considering the risks and keeping them visible, we avoided quite a few
problems and kept the program on track.
Identifying Project-Related Program Risks and Interfaces
Program risk identification generally begins with a review of risks
from below, based on the planning for each component project and
identification of each project’s risks. Across the entire program, there may be
hundreds or even thousands of identified project-level risks. Nonetheless, the
program risk manager should examine all of them and provide feedback on
the analysis and response strategies, especially if any assessments appear
inconsistent or flawed.
Generally, project-level risks are best managed at the project level.
However, some should also be “promoted” to the program risk register. Some
examples:
• Project risks that are significant enough to be program showstoppers
• Project interfaces and cross-dependencies
• Novelty or substantial technical complexity (architecture, systems
engineering, and the like) that could result in integration problems or
defects
• Potential conflicts involving individuals or other resources needed by
two or more of the projects
• Significant work done by outsourced or distributed project teams
• Similar project risks identified in several projects that in aggregate
represent large overall impact
• Projects that are inherently risky overall
• Any risks that could persist as possible problems past the duration of
the project where they are identified
Cross-project dependencies, or interfaces, are one of the biggest
sources of program-level risk. An effective process for documenting and
managing these connections is central to managing these interconnections. It
is likely that most project interdependencies will be identified during basic
project planning, but the ultimate responsibility (and risk) for managing these
relationships will be at the program level.
Initial planning for all interproject predecessor/successor relationships
will begin at the project level. However, managing them may require trade-
offs and decisions that cannot be made by individual project leaders. Even
when interfaces appear to be under control at the project level, each still
represents potentially significant program risk.
Managing interface risks involves reliable, well-documented cross-
project commitments. The relationship depicted in Figure 13-1 shows a
typical interface. Each interface is partly within a project contained in the
program, but it is also partly in no-man’s-land where neither of the involved
projects has full control.
Figure 13-1. Program Interface Connecting Two Related Projects
The terms “supplier” and “customer” are useful in analyzing program
interconnections. The interface linkages initiate in the supplier project, and
they terminate in the customer project. Within any given project, at least
some external predecessor dependencies are inevitable. These will surface as
part of project schedule development, as discussed in Chapter 4.
Identification of program interfaces begins in planning for the customer
project, the project within the program that requires an input. Every such
external input for a customer project is a risk both for that project and for the
program. Within programs, project planning processes will also uncover
external successor dependencies, where projects are expected to supply
deliverables as outputs needed by other projects within the program.
At the program level, all the inputs and outputs identified by the
interrelated projects must be connected and formally documented in a written
description. All identified inputs need to be matched with an appropriate
output. Program interface management strives to resolve all identified
interfaces and incorporate them into the overall program plan.
To begin the process, the project leader of the customer project
documents all inputs required, listing specifications and requested timing.
Ideally, each documented input will be quickly associated with an output
planned by a supplier project, and there will be quick and easy agreement by
the corresponding project leader to supply it. When there are no issues with
requirements or timing, the two project leaders formally agree on the terms of
the interface, treating it as a binding contractual commitment.
For many situations, though, it is not this simple. There may be
required inputs for which there are no planned outputs. For some of these,
additional planning by a plausible supplier project may be needed to ensure
that the need is met. For others, a change of scope may be necessary, or the
customer project may need to plan to meet the need internally. Even when the
inputs and outputs appear to align, there may be issues. When there are
differences between the input specifications needed and the output
specifications planned, the program manager may need to participate in
negotiations between the project leaders and guide the process to a resolution
that serves the program.
Interface timing issues also are common, where inputs are needed
earlier than the corresponding outputs are planned. This situation resulted in
an average of nearly eight weeks of slip in the PERIL database, one of the
largest averages for schedule risks and representing an abnormally large
number of black swan risks. Significant program timing exposure results
from these problems, due to the sort of project schedule gaps. A small
program may look like an eight-month undertaking based on review of the
component project plans, as shown in Figure 13-2.
After adjusting to account for interface timing, however, the ten-month
schedule in Figure 13-3 emerges. The program manager must coordinate
reconciliation and work to resolve these conflicts.
If there are identified program outputs that are unclaimed, it may reveal
a planning gap in one or more projects. For necessary outputs, the program
manager must locate the project that has corresponding missing inputs and
work with the project leader to integrate them into the plans. Some identified
outputs may prove to be unnecessary, in which case the program manager
will work with the leader of the supplier project to eliminate them, along with
their related activities.
Figure 13-2. Initial Project Plans
Figure 13-3. Interface Timing Connections Within a Program
The process for identifying and documenting program interfaces also
helps with another common source of program risk. Programs regularly get
into difficulty because they are quickly chopped up into projects, with
minimal consideration of the resulting project cross-connections. The more
autonomous each project is, the easier it will be for the project leader to
manage. It also means fewer no-man’s-land issues for the program manager
to deal with. Integration problems, a substantial source of scope defect risk in
the PERIL database, are often the result of excessive organizational
complexity for the program. If there are ten projects in a program and 150
interfaces, there is almost certainly a less complicated decomposition of the
program into projects where more of the dependencies lie wholly within the
component projects. Excessive interfaces connecting project teams,
particularly geographically distributed teams, lead to more program failure
modes and higher risk. As project plans evolve and are integrated within the
program, monitor the number of interfaces, and keep your eyes open for a
logically less complicated program breakdown.
As planning proceeds, ensure that all interfaces are visible at the
program level, formally documented, and agreed to in writing by all of the
customer and supplier project leaders involved. Even when interfaces are
thoroughly planned and managed, they remain program risks and belong on
the program risk register.
Identifying Other Program Risks
It is rare that all program risks will be picked up in project planning.
You will need to do additional analysis and planning at the program level to
pick up any missing program risks related to external dependencies, technical
complexity, resource capacity, and other risk sources.
Some program risks are a consequence of decisions and objectives
above the program level. Strategic risks arise from organizational decisions
and objectives associated with new programs. Some assumptions made
during program initiation may be realistic and credible, and others may be
guesses and wishful thinking. Programs are large and complicated, so before
much (or any) analysis is completed, there can be significant gaps between
what is expected and what is possible. Program planning will provide the
perspective to identify unrealistic assumptions and data to manage
expectations and objectives. As you validate program objectives, describe
any potentially problematic program constraints or assumptions that you will
not be able to control, and add them to your program risk register.
Some program-level exposures are intrinsic to the program itself. Size
and scale are significant sources of risk, especially when they are measurably
larger than any successful past programs. Document program risk arising
from unprecedented staffing levels, budgets, duration, or other scale factors.
Programs generally require at least some innovation and novelty, so identify
sources of risk arising from bleeding-edge program deliverables, new
development methods or equipment, and changing processes. Identify risks
associated with any contributors who are geographically distributed,
reporting to management elsewhere in the organization, working on contract,
or otherwise not directly connected with the program. Program work can
include contributions from operational and other parts of the organization in
addition to projects, so think about potential risk sources related to support,
administration, infrastructure, and other nonproject program work. Also
consider risks related to potential program staff commitment conflicts, loss of
key program staff, queuing for program resources, effective program
communications, and ongoing motivation (particularly for long-duration
programs).
Build a program risk register similar to that used at the project level,
adding program-level risks to those promoted from the program’s projects.
Augment the list through brainstorming with the program staff (and PMO),
review of lessons learned from earlier similar programs, and scenario
analysis. The program risk register for the effort at Hewlett-Packard
discussed earlier in this section started with about 25 items and averaged
roughly 30 throughout the program. (Risks that were managed at the project
level at any given time were typically about an order of magnitude more
numerous.)
Assessing Program Risks
Program risk assessment does not really depart much from the
principles of project risk assessment described in Chapter 7. Use qualitative
assessment methods based on categories to prioritize program risks. For
significant risks, use quantitative analysis to refine your understanding and
drive response strategies. Because some of the information for risks may
come from remote or secondhand sources, be especially wary of data-quality
issues and skeptical about impact and probability estimates that seem
excessively optimistic. If risk consequences are expected to be within a wide
range, be conservative and use the worst case in your assessment. For
probability, probe connections between the risks, and increase probability
and/or impact assessments for related risks. Program risks are often highly
correlated, so carefully review risks having root causes in common or with
similar descriptions from project to project. Risks that might seem of modest
priority in the projects that make up the program may actually be significant
when aggregated at the program level. When some project risks occur, there
may be a catastrophic cascade of connected problems that could
simultaneously affect the program.
Sort the risk list and select the most significant ones, focusing on:
• Interdependencies and interfaces between projects
• Complexity and potential deliverable issues
• Staffing problems, motivation issues, and funding commitments
• Any significant program-level risks
Responses for Program Risks
As with assessment, program risk responses primarily depend on
tactics similar to those effective for project risks, as explored in Chapter 8.
For each selected program risk, consider options for avoidance, mitigation, or
transfer. If you can find no appropriate response for any of the significant
risks, develop contingency plans for recovery. Ensure that the individual
project plans include the specifics necessary for managing the important
risks, and determine how you plan to monitor for key risk triggers at the
program level.
As with risks in projects, visibility is a powerful program risk
mitigation strategy. When the consequences of program risks are apparent,
people work to avoid them. Even if they should occur, recovery from risks
that people are aware of will be faster, minimizing the impact.
One final differentiator for risk response planning at the program level
is the need to have an effective and well-established process for rapid
escalation whenever a significant risk occurs. Quick response also depends
on a preestablished program-level budget reserve for use in dealing with
contingencies. Where possible, also set up an adequate program-level
schedule reserve to protect key program deliverable deadlines.
Monitoring and Controlling Program Risks
Because risks at the program level are larger, often more distant, and
tend to become major disasters quickly, disciplined monitoring is essential.
Frequent effective communication is central to this, and it’s one of the main
responsibilities of the program manager and staff.
For the Hewlett-Packard IT program mentioned earlier, our monthly
risk management review meetings were central to our communication and
risk monitoring. We also discussed major risks regularly at our weekly
program staff meetings, and scheduled time during our semiannual face-to-
face program review meetings to plan for risks in the next phases of work. In
addition, we made discussion of important upcoming risks part of our
monthly all-hands conference calls. These were virtual program team
meetings where the program leadership team presented current program
status. All of the presentation materials to be discussed on these calls were
distributed in advance to the roughly 200 program contributors, and the
information was also archived on the program Web site for review by those
who missed the calls.
The size of the program risk register changed over time. Although it
did not drop significantly, the list of program risks we were managing also
did not expand, as seen in Figure 13-4. The overall severity profile of our
managed risks also remained stable over time.
Figure 13-4. Program Risks over Time, Categorized by Severity
Program control and effective risk management also depends on strict
control of changes. For large, complex programs, any change, regardless of
how innocent it appears, can result in major unintended consequences.
Complexity also requires a hard limit on how late changes can be made;
when changes are attempted too late they may fail in test and need to be
backed out at the last minute. This creates unnecessary work both to attempt
the change and then to remove it, effort that could have been applied
productively elsewhere in the program, such as in mitigating serious risks.
Another control strategy for programs is ongoing commitment to
process review and improvement. Doing a lessons-learned session after a
project is complete is useful, but for lengthy programs there are frequent
opportunities to find and deal with recurring program inefficiencies and
problems.
Particularly for lengthy programs, decreasing interest and motivation
can be a big risk. Work to keep people engaged by periodic program reviews,
frequent implementations and delivery of incremental value, training,
opportunities for advancement (or at least movement into new
responsibilities), and celebrations following key program milestones and
accomplishments.
Finally, programs with large numbers of contributors rarely achieve the
status of a high-performing team because too many people are involved for
the necessary interpersonal connections to develop. Large programs can,
however, build a high-performing program staff or program office team
among the smaller number of people who are responsible for planning and
managing the work over the long haul.
When I look back on the HP IT program discussed here, our biggest
success factor was the investment we made, early and often, in building
strong relationships and trust among the program staff. As a group, we all
placed the needs of the program well above the specific details of our
individual roles. There were never issues of coverage when people were
absent from the program. Each individual had a broad knowledge of the
overall effort and could fill in during times of stress (which were frequent). It
mattered little what our formal roles were; we all pitched in and got things
done. The atmosphere of one-for-all-and-all-for-one was our most effective
tactic for managing risk and ensuring a successful program.
Portfolio Risk Management
As you move up the food chain in an organization, risk management
moves from the micro to the macro, as discussed in Chapter 1. Where project
and program risk management focuses on the specific, portfolio risk
management focuses more on the aggregate. Managing portfolios begins with
establishing strategic objectives that serve the current goals of the
organization and that can be used to set criteria for evaluating potential
projects and programs. Specific details continue to matter, however, because
portfolio risk management also requires selection of projects and programs
having independent risks. When the risks in a population of items offset one
another, the overall risk—the expected variability of the aggregate outcome
—falls. Portfolio risk management tends to focus primarily on financial
returns, and selecting the right mix of projects can substantially lower the
variability.
Portfolio Risks: Specific and Overall
Portfolio risk management does not exclusively focus on the aggregate;
obtaining the best overall return also requires working to achieve good results
in each of the projects and programs that make up the portfolio. Managing
projects well depends on the techniques outlined throughout this book.
People responsible for managing portfolio risk tend to delegate the risk
management for a particular project (or program—for the purposes of this
section, the term “project” includes programs), along with all the other
management responsibilities.
Managing overall portfolio risk starts with the understanding that there
is safety in numbers. Ideally, if enough projects are in plan and the
organization is reasonably competent at managing the work, the few projects
that fail will be offset by the small number that achieve success beyond their
objectives. The theory of large numbers takes over, and the details become
less important. The performance of such a portfolio is equivalent to that of
the “average project.” Portfolio risk management primarily depends on this.
A few projects in the project portfolio will be exceptions to the idea
that only averages matter, though. Portfolio risk management also strives to
exclude projects having large potential for loss or at least to minimize their
potential for financial and other harm. Some strategic projects may carry
priority based on factors beyond short-term monetary returns. As with project
and program risk management, you must consider worst-case scenarios for
the portfolio. Determine how much risk, overall, the organization can
tolerate, in terms of financial exposure and other significant consequences.
Because this type of exposure could threaten the organization as a whole,
responding to such risks goes beyond the topic of portfolio risk management.
This is part of enterprise risk management, which is explored in the final
section of this chapter.
Planning Portfolio Risk Management
Project portfolio management is primarily concerned with categorizing,
prioritizing, and selecting projects. Best-in-class organizations have a well-
documented plan for portfolio management, including a strategy for ongoing
portfolio process assessment and improvement. Some organizations make
portfolio decisions annually and some do it more frequently, but the process
is generally periodic, not continuous. During the times when decisions are
being made, managing portfolio risk requires a good deal of interaction with
project management processes.
Planning for portfolio management begins with a number of project
management factors, including overall goals and the target mix of projects by
type for the organization. The portfolio selection and decision criteria also
rely heavily on project risk management and planning data that will be used
to assess and prioritize each project opportunity. The overall relationship
between an effective portfolio management process and project management
is depicted in Figure 13-5.
Figure 13-5. Portfolio and Project Management Linkages
The project portfolio management process relies on feedback from
projects at several stages. The list of projects to be considered for the
portfolio feeds into project initiation activities, and it depends on information
obtained from them. The portfolio selection process relies on project data
developed in planning, especially estimates for cost, duration, and risk. As
projects execute, their status provides feedback for midcourse portfolio
corrections, and it also feeds into the next portfolio decision cycle.
At all stages, project risk analysis is central to a robust portfolio
management process. Deciding which projects to initiate (or to continue)
relies on project risk assessments to ensure that exposures remain within the
organization’s risk tolerances. For a start-up company, there will be a high
tolerance for risky projects, so the portfolio process will initiate projects with
considerable uncertainty. In contrast, organizations that provide custom
solutions for fixed fees will tend to exclude risky projects in order to protect
their reputation and to avoid financial penalties. Risk information is essential
to avoiding inappropriate projects.
For all these reasons, project risk data should always be a key input for
portfolio selection decisions. Because these decisions are often made well in
advance of any detailed planning, it is a good idea to revisit the portfolio
decisions as projects develop plans and accurate data becomes available.
Planning for portfolio management also requires setting decision
criteria. Because the primary performance measurement for most portfolios is
financial return, some version of a return on investment (ROI) estimate is
inevitably at or near the top of the list of criteria. Because all types of ROI
assessment depend on two estimates—the cost of a project and its worth—
accurate data for both is desirable. As discussed in Chapter 9, the accuracy of
ROI forecasts can be poor; premature estimates of cost are generally
unrealistically low, and initial estimates of value are often ridiculously
optimistic. Using unreliable ROI estimates increases portfolio risk.
Other criteria derived from project management include overall effort,
the project risk profile (often based on a survey, such as a shortened version
of the example in Chapter 9), information based on planning, and other input
collected from the project teams. Portfolio decision criteria also include data
unrelated to project management, such as alignment with stated business
goals and strategies, assessment of markets and potential competition, and
availability of needed expertise. Selecting appropriate criteria and clearly
defining how each is to be evaluated contributes to minimizing portfolio risk.
Once listed, each criterion needs a weight. How the criteria are
weighted also affects portfolio risk, so ensure that sufficient importance is
given to risk assessment and credible project information.
Not all decision criteria are created equal. Some project selection
criteria tend to bypass the portfolio process altogether. One example is a
project’s ability to keep people out of jail. Projects undertaken to meet
industry standards or regulatory, environmental, or legal requirements
generally do not require portfolio analysis; such projects are selected and
funded without much debate. In your process planning, though, limit the
projects that can be automatically fast-tracked into plan to those that are
legitimately mandatory. Bypassing the process to accept the pet projects of
executive decision makers without adequate analysis entails a lot of risk.
Although saying no to such project proposals can also be risky, if you can
turn them down based on objective analysis, it’s better for the organization,
the project team, and ultimately even for the sponsor.
Another key consideration for portfolio planning is the mix of projects.
In any organization, options vary from mundane, incremental projects to
high-risk efforts that may well be impossible. Typical project category types
include:
• New basic research and development
• Revolutionary products, processes, or new markets
• Next generation/new platform to replace an old offering
• Evolutionary improvements to an existing product or service
• Maintenance, support, or infrastructure
Viewed from the perspective of financial return, the highest-potential
projects are usually found on the bleeding-edge end of the spectrum. If you
seek to minimize risk, however, the most desirable projects are found on the
end of the list with the more routine projects. For a given set of decision
criteria, projects in a rank-ordered list will tend to cluster based on their
category. This may result in a portfolio that is skewed, composed mostly of
only one type of project. Because the balance of projects also matters, it is
useful to define a target mix of project types that best aligns with the
organizational strategy and risk tolerance, with percentages for each project
category.
These relative proportions will vary over time and from organization to
organization, but the target mix should consistently reflect current tactical
and strategic objectives. The mix should also reflect a balance between
projects that achieve results in the short term and longer-range projects that
will best serve the organization’s future needs. Managing this requires
ongoing discipline. It is all too easy for a portfolio to become overloaded
with projects of a given type—for example, too many urgent maintenance
projects or an unhealthy number of projects dependent on speculative
technology. When the project load deviates from the overall business
objectives, it increases business risk for the organization as a whole. Define a
portfolio process that strives for a focused portfolio of good projects with
risk-and-benefit profiles consistent with business objectives.
Identifying Portfolio Risks
Project portfolio risk identification relies heavily on the project risk
identification processes described in the first half of this book.
For projects that are still embryonic, detailed analysis may not be
available. In these cases, at least develop a sense of potential risks by
reviewing problems encountered on earlier, similar projects. Brainstorming
and scenario analysis involving people with subject-matter expertise is also
effective and provides a starting point for subsequent, more detailed planning
and risk management.
Assessing Portfolio Risks and Overall Risk
Although the focus of project risk management is on loss-times-
likelihood for an individual project, assessment for a portfolio involves risk
in aggregate. Portfolio risk assessment involves both analysis of which
projects to include and exclude and an understanding of how the individual
projects relate to one another.
Because organizations always have many more promising project
concepts than can be staffed and successfully executed, project portfolio
management is a winnowing process. Determining how far down you can go
in a sorted list of project opportunities begins with a realistic appraisal of
capability. Determining overall capacity available for projects appears to be
surprisingly difficult; most organizations have an exaggerated notion of how
much they can accomplish. They also make matters worse by failing to
account for commitments that must be staffed for support, maintenance,
operations, production, and other ongoing required work. It’s not uncommon
in high-tech organizations to initiate double or even triple the number of
projects that can realistically be staffed. Skepticism is warranted when
reviewing available capacity; the too-many-projects problem is a common
and systemic portfolio risk.
The next step in the assessment process involves collecting and
evaluating information on the predefined decision criteria applied to each
project. As already discussed, relying too heavily on just estimates of ROI is
problematic. Sorting a list of projects based primarily on ROI is not
necessarily much better than arranging it randomly. In fact, it might even be
worse because portfolio analysis contrasts existing, ongoing projects with
new project proposals. Both the cost and the value data for current projects
are likely to be at least somewhat realistic, putting them at a decided
disadvantage against the speculative estimates for potential new undertakings
with data based on optimistic guesswork. Similar standards need to apply to
all projects, with clear-eyed examination of potential return. New projects
often appear to be straightforward, low risk, and high return prior to any
detailed planning. Failure to account for this bias can lead to portfolio thrash,
in which projects are regularly replaced in the portfolio by “better”
opportunities, resulting in substantial wasted effort on projects that never
complete.
Effective ROI assessment for projects also must consider uncertainty.
For each project, estimate the upside potential for gain (often this is
equivalent to the overall ROI assessment for new projects, since it’s not
likely that anyone has considered things that might go wrong). Also probe to
realistically understand the downside potential for loss for each opportunity.
Be skeptical of sales, value, profit, or other benefits assessments, especially
projects described using suspiciously round numbers. Ask about the
assumptions used to estimate the benefits, and find out how they were
calculated. Inquire about threats, competition, or other factors that could
invalidate the estimates. If there is a wide potential range, make it visible.
One additional technique for assessing financial uncertainty is Value at
Risk (VaR). VaR is a technique for estimating the maximum amount of loss
that can be expected from a financial investment. It came into widespread use
in the 1990s and built on the work in portfolio theory done by Harry
Markowitz. It incorporates risk analysis into ROI calculations and attempts to
show the level of risk being assumed so that it can be better managed. VaR is
based on some reasonable but not completely bulletproof assumptions. When
financial markets are well behaved, VaR analysis allows financial firms to
eke out a slightly larger return while remaining at the level of risk they
believe appropriate. When the markets are volatile, though, as they were in
the global 2007–2008 financial meltdown, VaR fails. VaR in those conditions
misrepresented the risk being assumed, and it contributed substantially to the
worldwide economic collapse.
The foundation of VaR is defining probability distributions for various
investments in specific time frames. Using the distributions and computer
simulations, potential returns (or losses) can be estimated. VaR is stated in
terms such as “$100 million for one week at a 95 percent confidence
interval.” This means that there is no more than a 5 percent expected chance
of losing more than $100 million in the next week. An excellent description
of the history and mechanics of VaR can be found in the book Strategic Risk
Taking by Aswan Damodarian.
Using VaR requires selecting and applying an appropriate probability
distribution for potential returns. Determining the distribution is done using
some combination of the same three techniques used to estimate
probabilities: mathematical modeling, empirical analysis of historical data, or
guessing. As in most complex situations, historical analysis and guessing
tend to dominate, but even plugging in a simple model such as the Gaussian
distribution can provide useful insight when time frames are very short and
the rising and falling variations are small and for the most part in balance.
VaR can fail, though, for a number of reasons:
• A selected probability distribution is a forecast, not a guarantee.
Actual results may (and often will) vary.
• Even if the probability distribution has generally correct parameters,
the shape may be inappropriate.
• Data used to define the distribution may be incomplete or otherwise
inaccurate.
• Conditions assumed to be stable may prove to be drifting or more
volatile than expected.
• Other assumptions may be unwarranted due to defective analysis or
dishonesty
Applying VaR to a project requires examining a longer time horizon
than for many other types of investments. The time scale will need to extend
out to the breakeven point for the project, which can be months or even years,
so project VaR involves investments that move in slow motion compared
with the usual applications for VaR. The VaR objective, however, is the
same: assessing how much money is at risk with our project investments. The
analysis for a given project begins with a basic ROI analysis. Because the
time horizon for a project is long, using a typical assumed distribution and a
high confidence interval, VaR would be quite large compared to the project
budget (unless risks are few and there is close to zero probability of
cancellation).
One project under consideration for inclusion in a portfolio might be a
project with expected financial benefits of $1,000,000, and a cost of
$750,000. A crude ROI based on these assumptions would be $250,000, or a
roughly 33 percent return. However, this is probably not a sufficiently
complete story. There will doubtless be both execution risks and some
uncertainty around the benefits, so a more realistic view might look like the
data in this table:
Assuming these probabilities are realistic, the expected return will drop
somewhat, but it remains at about 24 percent—which still looks pretty good.
Neither risks nor opportunities ever partially occur, however. Risks either
happen or they don’t. Given this view, the range of possible outcomes for this
project will be:
Minimum Value −$700,000
Expected Value (risks included) $178,750
Nominal Value (certainties only) $250,000
Maximum Value $425,000
The maximum looks like very good news; if all the good stuff happens
and none of the bad, the return is excellent. If the reverse happens, though—
we see all of the risks with none of the upside—the result is disastrous. The
expenses more than wipe out the return and the project could show a
significant loss.
Neither of these extremes is very likely, however. For a more nuanced
view of this, computer simulation can help. Using the same project data and
doing 1,000 simulation runs, the average return is about $170,400, only
slightly less than the expected return calculated using the figures for risks and
opportunities weighted using their estimated probabilities. The values can be
plotted in a cumulative graph as in Figure 13-6. For this project, assuming
that the information is realistic, there appears to be a 95 percent chance of
losing no more than about $250,000.
Based on the simulation, this project will either return nothing or lose
money almost 20 percent of the time. About 30 percent of the time, its return
will not exceed the calculated expected value. However, nearly half the time
(49.3 percent), the project will return at least $250,000, and there is about one
chance in six it will do far better than that. Of course, even this view, eye-
opening as it is, is not entirely complete. The possibility that the project will
fail or be cancelled is not included (there could be a probability estimate
associated with assumed benefit value for this), and we have assumed no
correlation among the uncertainties.
In any event, VaR analysis provides an additional tool for assessing
and managing financial exposure from investments in projects and programs.
Whatever other decision criteria may be used for portfolio analysis and
item ranking, ensure that factors estimating risk (such as ROI with range
estimates or project VaR) are part of the mix. Also strive to include input
from the project team or at least from qualified subject-matter experts in cost
estimates and other project plan–related parameters. Always provide for
explicit analysis of worst-case scenarios for any project risks that may be
particularly severe and include an assessment of risk related to the expected
scale of each project.
Figure 13-6. Potential Financial Returns (based on simulation)
In determining the evaluations for all the criteria, confront any known
organizational biases (such as a tendency to underestimate the effort for
enticing novel projects and to overestimate boring, routine ones). Work to
achieve consistent, comparable results for all the projects under
consideration.
After collecting and validating the project evaluation information, use
it to rank-order the list of opportunities. The first few items listed will be easy
to decide on: good opportunities that can be staffed are selected and put into
plan. However, the deeper in the list you go, the more complex selection
becomes.
One selection strategy creates a provisional list by determining the
cumulative cost of projects listed starting from the top of the sorted list and
drawing a cutoff line below the last project that can be staffed and funded
using about 90 percent of available capacity. Portfolio risk management
requires that some capacity be left uncommitted, primarily to deal with
project risk but also to manage organizational emergencies and to provide
capacity to exploit unforeseen opportunities. The list resulting from this
process is provisional because it is unlikely to conform to the target mix of
project types, and it may also represent inappropriate portfolio risk.
Adjusting the relative overall investments dedicated to projects in
different categories is straightforward. You exclude the lowest items on the
list that lie above the cutoff line in categories that are oversubscribed,
dropping projects until the aggregate investment is in line with your target.
Similarly, you include projects that are below the line to your provisional
portfolio to raise the cumulative budget represented in the categories that are
too small. Further adjustments may be warranted to deal with limitations on
expertise, facilities, or other organizational constraints. Additional changes
may be required to ensure that related projects are either all in plan or all out
of plan; if projects that are cross-dependent are not executed in sync, the
value they deliver can be diminished or even evaporate.
One additional factor to consider is size. The relative scale of projects
also makes portfolio management challenging. To illustrate, consider this
exchange:
A university professor asked her students how many of
her collected rocks she could fit into a big jar she had
sitting on the desk during her lecture. Examining the pile
of rocks, the class reached a consensus of perhaps six
or seven. Sure enough, when she started placing the
rocks into the jar, she reached the top with rock number
seven. No amount of jiggling or pressing would permit
her to cram rock number eight into the jar. She then
asked the class if they thought the jar was full. The
students looked at the jar, looked back at the rocks, and
decided that the jar looked full.
At that point the professor reached underneath the desk
and pulled out a bowl filled with gravel. Since these
stones were smaller than the original rocks, she was
easily able to pour most of the gravel into the jar. The
students watched them tumble down, filling in the open
spaces between the larger rocks. She asked the class
again, “Now is the jar full?”
By this time the students were starting to catch on, so
most answered, “Probably not.”
The professor again reached under her desk, and this
time pulled out a bag of sand. She was able to dump
about half of it in before reaching the top of the jar. She
asked again, “Now is the jar full?”
Most students thought it was, but suspiciously they
replied, “Not yet.”
She reached down again, lifting a bucket of water. She
proceeded to pour a good portion of it into the jar. After a
moment the professor looked at the jar filled with
soaking wet sand, gravel, and rocks. She looked back at
the class and asked, “What’s the lesson here?”
One student bravely suggested, “A vessel is not
necessarily full, even when it looks like it is?”
The professor admitted that that was not a bad lesson,
but not what she had in mind. From her desk, she picked
up one of the remaining larger rocks that she had initially
used to fill the jar. She held it over the jar and said, “If
you don’t put these big ones in first, you’ll never get
them in at all.”
In a project portfolio, there will always be some way to accommodate
an additional small project. Failing to consider the large, often strategic,
projects at the outset of the portfolio process, however, can result in a
portfolio filled to capacity with mostly smaller projects. This may leave
insufficient resources to properly support the major project opportunities, so
consider putting the large rocks in first.
It may be tempting to allocate 100 percent of your available capacity
when accepting projects into the portfolio. This is risky because retaining
zero slack will likely result in problems leading to adverse impact on all
projects.
The final step necessary for managing portfolio risk is to assess overall
risk for the proposed portfolio as a whole. This involves estimating risk
correlations for the selected projects. One of the main objectives for portfolio
management is exploiting negative correlations and using them to lower the
overall risk. This is the reason that some people invest in mutual funds
instead of individual stocks. Although the possible gains for a mutual fund
are always lower than those for a single stock, so are the potential losses. The
return for the basket of stocks in the mutual fund is more predictable and has
lower risk. This is generally true, though it isn’t always. If all the stocks in a
fund are in a single industry and subject to similar exposures and threats, they
will positively correlate. When any stock drops, they will all probably follow,
so the fund losses will mirror the losses of each stock. When project risks are
related, the same will happen in a portfolio of projects.
One tactic already discussed helps in managing this—enforcing the
proportions of the portfolio that will be devoted to projects in different
categories. In addition to this, the portfolio manager needs to consider the
projects in the provisional portfolio, examining them for, among other
factors:
• Reliance on similar new technologies or applications
• Dependence on the same resources, especially outsourced or
specialized staffing
• Significant project risks listed in common by several projects
• Potential failure modes shared by the projects
The portfolio management process seeks to select an optimal, or at
least acceptable, mix of projects to undertake. Although risk is only one of
the criteria applied to the decision process, it is a central one because the
portfolio process is an important tactic for minimizing risks to the
organization.
Each newly proposed or continuing project in a proposed portfolio has
three possible outcomes:
1. The project is accepted into the portfolio, becoming or remaining an
active project.
2. The project is accepted, but only after making changes (to scope,
schedule, or resources) before accommodating it in the portfolio.
Some projects may be lowered to an acceptable level of risk through
transfer (that is, by purchasing insurance to deal with excessive
financial exposure), by converting the project to a joint venture and
sharing the risks (and rewards) with a partner organization, or through
other adjustments.
3. The project is rejected. Some (perhaps most) project ideas should be
turned down or postponed for reconsideration at a later time.
Before finalizing a list of projects as the in-plan portfolio, ensure that
both the individual project risks and the overall cumulative risks have been
thoroughly evaluated and the candidate list is consistent with the
organization’s risk tolerance. Identify any particularly risky projects that are
accepted into the portfolio, and ensure that the executives responsible for the
portfolio will have adequate visibility of the projects’ progress and will
monitor them at least monthly.
Portfolio decisions are never permanent; successful portfolio
management must periodically revisit the selection process, including risk
assessment. Portfolio reviews are typically conducted about once per quarter
and may also be needed following the completion of a particularly large
project. Portfolio reviews revisit the portfolio assumptions and criteria and
manage portfolio risk by considering project status information, especially
data on troubled projects.
The portfolio review process is essentially the selection process
described earlier, but one of the key risk objectives in a review is detecting
and weeding out inappropriate projects early. This ensures that the mix of
ongoing projects will continue to encompass the best available project
opportunities. Best-in-class high-technology companies find and cancel
questionable projects early, before much investment is made.
Other goals for the portfolio review are maintaining a balance of
projects and keeping the project portfolio requirements within the capacity
limits of the organization. Immediately after a portfolio is determined,
additional good project ideas will surface. One reason for maintaining some
unused capacity is to permit the organization to exploit new, unexpected
opportunities, so adding some of these ideas to the portfolio is not necessarily
a problem. However, there is frequently little discipline used in selecting and
starting new projects, and the standards used for putting them in plan are not
always as rigorous as those used for the initial portfolio decisions. This can
quickly lead to a list of in-plan projects that have inadequate resources;
progress will falter and stall for many of them. The if-some-is-good-more-
must-be-better philosophy creates both excessive project and portfolio risk. It
is not uncommon for the projects undertaken by high-tech organizations to
require resources that are double, or even triple, what is actually available.
Resource underestimation is a common project problem, as demonstrated by
the data in the PERIL database. Making matters worse, the extra projects
crammed into plan are often urgent, which tends to shift the mix toward
short-term projects. This zero-sum game will result in inadequate resources
being devoted to strategic projects that are more important overall to the
organization, increasing future risk. Portfolio reviews manage risk by
adjusting imbalances and trimming the project list back to what can be
adequately staffed and managed.
Monitoring and Controlling Portfolio Risks
The portfolio management process is not usually something that
requires a lot of day-to-day attention. Portfolio risk is mostly managed in the
selection and review processes. Several matters, however, need ongoing
attention.
Monitor high-level status for all the projects in your portfolio at least
monthly. The portfolio monitoring process operates in parallel and depends
on the project execution and control processes, as illustrated in Figure 13-5.
For each project, define and track a few diagnostic project metrics such as
those described in Chapter 9. A number of software tools are available for
monitoring a collection of projects that can be used to implement a project
dashboard for the portfolio. Dashboards can be quite useful and, for larger
project portfolios, may be necessary. For modest project portfolios, though,
ongoing oversight using a handful of key measures does not usually need to
be quite so complicated; a spreadsheet or a deck of presentation slides for
tracking and reporting will likely suffice.
Most project portfolios have a small number of high-risk projects, and
these need particular attention. At least monthly, conduct an in-depth review
of progress. Work to detect issues early that might develop into major
problems. For all projects in the portfolio that are currently in trouble, focus
on what is necessary to bring them back under control. Allocate additional
resources, revise expectations, or make other changes. Use the available
reserved resource capacity to resolve the issues, and deal promptly with any
problems that are escalated from the projects needing management attention.
Managing bad news at the portfolio level, as at the project level,
requires a single-minded focus on problem solving and resolution.
Responding to unfavorable status information with criticism, punishment, or
even disapproval can take a situation from bad to worse. Motivation on risky
projects is often tenuous, and you need a motivated, enthusiastic project team
to solve tough problems. A troubled project staffed by disillusioned,
depressed contributors will likely never recover.
If, after a sincere effort, there appears to be no plausible recovery
scenario for a project, cancel it and get it out of the portfolio. A key job of the
portfolio manager is to limit the losses when a project is headed irretrievably
toward failure.
It is also necessary to monitor overall resource use and to detect when
projects are competing for the same resources. Whenever scarce resources
lead to contention, adjust the portfolio, shutting projects down temporarily
(or even permanently) if necessary. When important projects are delayed
while queuing for scarce resources, consider acquiring more capacity or at
least ensure that the queuing is based on project priority, not just first-
come/first-served.
One additional wrinkle at the portfolio level comes from the essentially
financial basis used to measure success or failure. Assumptions made for
projects are often overtaken by events, especially with long-duration projects.
Also, as projects progress, the estimates for cost and value are likely to
change. Changes inside your organization or even outside can significantly
alter the overall evaluation for any given project, and some of these changes
may substantially diminish a project’s expected value. As new information
becomes available, reevaluate the affected projects to determine whether they
still deserve to be in the portfolio.
Overall, managing risk in a project portfolio involves ongoing
dedication to ensuring that needed resources are available, risks are
anticipated and managed, decisions and other required management actions
are timely, barriers to progress are removed, and problems are solved. A
portfolio filled with understaffed, poorly funded, trouble-ridden projects
represents unacceptable risk in any organization.
Enterprise Risk Management
The final section of this chapter climbs one level higher in the
organization. Enterprise risk management encompasses all the project,
program, and portfolio risk management concepts and more. One type of
enterprise risk management takes a traditional view of risk, as an uncertainty
with a potential for harm, in this case to the organization as a whole. There’s
also a more narrowly defined concept for enterprise risk management that has
emerged recently, with government regulation and industry standards as its
foundation. Both types of enterprise risk management place greater emphasis
on the long term than do the types of risk management discussed previously.
We explore the relationship between project risk management and both of
these types of enterprise risk in the remainder of this chapter, beginning with
the more conventional perspective.
Organizational Threats in General
Enterprise risk relates to project risk management because projects
both contribute to enterprise risk and are employed to manage it. Projects
create organizational risk for all the reasons discussed throughout this book.
Managing enterprise risk that arises from individual projects is generally
delegated to lower levels of the organization. Risk management of this type
relies on the techniques for project risk management outlined in Chapters 8
and 10 for projects and on the ideas for managing program and portfolio risks
explored earlier in this chapter. With the exception of the most major black
swan risks that could materially damage the entire organization, few risks
associated with projects are actively managed at the enterprise level.
Although project risk is not generally a big concern to the enterprise
risk manager, the converse is not true. The impact of enterprise risk
management on projects is quite substantial. The purpose of enterprise risk
management is to ensure the ongoing viability of an organization. Enterprise
risk managers may focus their attention on a number of specific areas that
may affect projects, including:
• Safety and security
• Fraud and financial liability
• Casualty loss and disaster preparedness
• Organizational reputation and brand protection
• Intellectual property management
This is only a partial list, of course. Many other specific concerns may
represent potential for loss or damage to the enterprise. One line of defense
used to manage enterprise risk is defining and enforcing processes for the
organization that are designed to minimize exposure. For example, legal
contract templates and review processes limit financial risks. They also
include mandatory provisions intended to limit other types of risk to the
organization, such as nondisclosure terms protecting intellectual property.
Mandatory training for well-defined, documented standards for business
ethics, enterprise controls, and other business processes are essential to
managing enterprise risk. Worker safety is also important to the enterprise.
Reflecting the origins of the company manufacturing gunpowder two
centuries ago, DuPont still requires stringent processes for safety in all
locations and mandates periodic safety meetings for all employees, including
people who are based in offices at headquarters where the safety risks tend
toward paper cuts.
These and other actions at the enterprise level aimed at managing risk
relate to project risk management because they influence the risks faced by
each individual project. Conformance to risk-related policies set by the
organization is intended to reduce project risk, and organizationwide
standards and rules provide leverage for enforcing risk management methods
that a project leader may otherwise lack. In addition to the policies and
procedures a project is subject to, each deliverable created by a project must
also meet the established standards for the protection of confidential
information, security, reliability, and other organizational mandates. Staying
within the bounds of accepted organizational expectations is good risk
management.
For some projects, the link to enterprise risk management is even more
fundamental. In any given year, some fraction of the projects undertaken in
an organization will address enterprise risks. Some of these projects will
implement new safety procedures or replace faulty equipment. Others will
develop techniques or algorithms that limit threats to security, eliminate
fraud, or deal with other sources of potential loss. Enterprise risk
management is a fertile source for projects.
The Millennium, or Y2K, bug was a massive example of this that
affected companies worldwide. As the end of the twentieth century
approached, the consequences of decades of software developed and
implemented using only the last two digits in dates to represent the year
began to loom ominously. Most organizations trace their recognition of this
as a real and immanent threat to a 1993 article in ComputerWorld written by
Peter de Jager. In his piece titled “Doomsday 2000,” he spelled out in some
detail what would occur as the world’s clocks ticked over from December 31,
1999, to January 1, 2000. Despite the title, the article was less about the end
of the world as we know it and more about the breadth of the problem and the
magnitude of the effort it would require to deal with it. To quote from de
Jager’s article:
One IS person I know of performed an internal survey
and came up with the following results: of 104 systems,
18 would fail in the year 2000. These 18 mission-critical
systems were made up of 8,174 programs and data-
entry screens as well as some 3,313 databases. With
less than seven years to go, someone is going to be
working overtime. By the way, this initial survey required
10 weeks of effort. Ten weeks just to identify the
problem areas.
This article raised a lot of concern because by the early 1990s
computers were incorporated in all conceivable applications, from defense
systems and automated factory control to determining the moisture in clothes
dryers and the color of toasted bread. The article also provided some good
advice for separating the important from the not so important. The main point
was to separate the real risks, those that represented significant, permanent
potential harm, from the rest. Not all computers were necessarily at risk.
What mattered was whether a date function was employed, and how it was
used. For some situations the problems were transitory, such as for real-time
applications that rely on information for only a few days or hours. For other
cases, the harm would be only temporary because it could be easily detected
and corrected after the fact (often manually and at substantial cost but without
much external publicity). Once the problem was publicized, programmers all
over the world began to consider the possible consequences of disregarding a
key portion of each stored date in their applications. A great deal of attention
was paid to financial and payroll systems in order to ensure that paychecks
would be correct and savings accounts would not be wiped out.
There were, however, situations where the impact would not be
temporary or easily fixed, as well as cases where the risks might have
enormous consequences that were not easily diagnosed. There were
legitimate questions concerning missiles erroneously being launched, critical-
care hospital equipment going haywire, and airplanes falling from the sky.
Most of the extreme scenarios were low probability propositions, and this
was known at the time. In a recent conversation, de Jager recalled responding
with incredulity to a prediction that Y2K might result in “losing power in the
United States forever.” Again, the point of the article was not that we were
facing the end of civilization. As de Jager stated in 1993, “It is very difficult
for us to acknowledge that we made a ‘little’ error that will cost companies
millions of dollars. . . . We must start addressing the problem today or there
won’t be enough time to solve it.”
As with any risk, analysis of Y2K came down to loss-times-likelihood.
Overall assessment of the Y2K risk was fairly straightforward. The
probability of malfunction of some sort on January 1, 2000, for many
software applications was high, essentially certain. Impact was not difficult to
estimate for most cases either. For many situations, it was also high. Even for
situations where the estimated economic impact appeared to be modest, there
could be other enterprise-level considerations. Given the publicity, especially
near the end of 1999, few organizations were willing to appear unprepared.
Having difficulties related to such a highly publicized problem would make
companies look incompetent and do damage to their reputations. Even though
the measurable impact in such cases might have been hard to estimate with
precision, it was nonetheless quite real. As was discussed in Chapter 7, this
kind of qualitative risk impact often represents the most significant
consequence of a risk, particularly as viewed from the enterprise level.
I saw the evolution of Y2K response at the project level firsthand, as an
internal engineering and project management consultant with Hewlett-
Packard. At HP, the risks were unquestionably real, and there was universal
recognition that timely action was necessary. Hundreds of projects at HP
were initiated to deal with Y2K. As at many companies, a lot of legacy
software at HP was carefully inspected. Some projects rewrote or replaced
applications. Other projects upgraded computer hardware to eliminate the
potential for problems.
Estimates for such project work and infrastructure changes for all
companies, governments, and other organizations worldwide range into the
hundreds of billions of dollars, a massive amount of money invested in risk
management.
At the project level, the impact of Y2K was mostly limited to technical
projects of this sort. Risk exposure at the enterprise level, though, for some
organizations extended well beyond this. Companies involved in providing
IT products and services had the additional risk of potential lawsuits and
damage to their corporate reputations. The threats went well beyond expense;
there was a real potential for loss of customers and a fundamental threat to
the business as a whole.
Managing this at HP initiated still more Y2K-related projects and
work. In 1998, Ted Slater was involved in managing a business crisis
communications program as part of his responsibilities in marketing in the
Americas. The program was not initially related to Y2K, but as 2000
approached, it was expanded to cover corporate-level Y2K response for the
entire company, worldwide. The focus was dealing effectively with any and
all customer problems, especially any that had the potential for generating
public relations or legal problems. The primary goal was to “do the right
thing for the customer” and to do it fast. The effort involved:
• Establishing well-defined, rapid escalation processes, particularly for
cases where there were any potential safety or health consequences
• Quickly involving all people who would play a role
• Maintaining effective and visible communication with all parties
• Identifying one individual responsible for all external
communications and management of a consistent single message for
each situation
The primary objective was to protect the firm’s reputation and brand
identity by acting swiftly to solve problems and “make the customer whole.”
Preparations for Y2K involved simulations that tested the processes required.
These tests ensured that they would function as planned. The scenarios
resulted in improvements to training materials and shifts in preparation in the
lead-up to Y2K, for which HP was well prepared.
Slater reports that a small number of HP customer situations arose with
the beginning of January 2000, but only a tiny fraction of the worst-case
estimates and none that was significant. This particular enterprise risk at HP
was well managed.
As at HP, Y2K risk management everywhere proved to be successful.
As 1999 ended, there were many problems—mostly small and quickly fixed
—but only a few disasters. Although the consequences of Y2K were
apparently minimal, the actual consequences did include a good deal of
cleanup work that was neither publicly reported nor visible, particularly in
areas where the threat was not taken seriously. However, some significant
problems did surface despite all the publicity and preparation, including one
case involving an application used in the United Kingdom to screen pregnant
women. The software tragically provided faulty reports for months before its
date-related defect was diagnosed and could be repaired.
The absence of massive fallout from Y2K is seen as a satisfactory
result made possible by the skillful application of risk management.
Nevertheless, this lack of fallout has also been characterized by some as
evidence that Y2K was much ado about nothing. There seems little doubt to
me that the risks were real and that doing nothing would have been ugly.
The very existence of this debate, however, raises a fundamental issue
about risk management in general and not just at the enterprise level.
Managing risks is never free, and for Y2K the costs were quite large. For any
risk we choose to manage, we must invest real time and money, which are
easily measured, right now. We generally make a choice to act when the
potential costs and consequences of inaction appear to be even higher, as
John F. Kennedy stated in the quote at the start of this chapter.
Choosing to act, however, changes everything. A response that
removes or mitigates a risk makes it impossible to know what would have
happened without that action. Because of this, it’s rarely possible to prove
conclusively that managing a risk was worthwhile. If, as was common for
Y2K, you mitigate the risk by examining and fixing deficient software or
avoid the risk by dumping older systems and applications and replacing them,
the cost of inaction can never be determined with certainty. Estimates of the
avoided impact will forever remain an uncertain forecast, open to conjecture.
You can’t measure something if it doesn’t happen. Particularly in retrospect,
people often criticize the expense of managing risk, either because they do
not understand (or don’t care about) the potential consequences or because
they don’t believe the impact or probability for the risk. Especially in the
current climate of short-term organizational thinking, making investments
right now to manage risks that may or may not occur in the future can be
quite hard to sell.
Enterprise Risk Management Based on Standards
Enterprise risk management has also come to mean something much
more specific, especially in the United States. A number of organizations
have codified practices for managing enterprise risk using this label. One of
them is the Committee of Sponsoring Organizations of the Treadway
Commission (COSO), a U.S. government–initiated organization. COSO and
other groups have defined frameworks and standards for managing enterprise
risk that have had substantial influence on organizationwide risk
management.
COSO is the current incarnation of a commission initiated by the U.S.
Congress in the 1980s that was formed to address issues concerning
inaccurate financial reporting, particularly by companies on the brink of
failure that nevertheless managed to publish healthy-looking financials. It
was led by James Treadway, a former head of the U.S. Securities and
Exchange Commission, and comprised five U.S.-based financial standards
organizations, each involved with some aspect of financial accounting or
auditing. In 1992, COSO published the COSO Internal Control—Internal
Framework, which defined tightened standards for financial reporting. The
framework addressed enterprise risk assessment but not in much detail. It
called for determining risk significance (impact) and likelihood or frequency,
but it did not specify how this was to be carried out. It also outlined the need
to determine how to manage the risks and what actions to take, but it left the
details on this to the management of each enterprise. In the wake of
additional reporting irregularities, including the now well documented
shenanigans of Enron, WorldCom, Tyco, and others, COSO expanded the
control framework to include enterprise risk management. COSO initiated
this project in 2001, engaging PricewaterhouseCoopers. The project
culminated in 2004 with the publication of the COSO Enterprise Risk
Management—Integrated Framework.
One of the main reasons that this framework has had such wide-
ranging influence is its relationship in the United States with the Sarbanes–
Oxley Act of 2002 (SOX) and increasingly with regulatory legislation around
the world similar to SOX. To meet the requirements set out by SOX and
equivalent laws in other countries, companies must establish and follow well-
defined and controlled processes for their public reporting, and risk
management has become a central aspect of this.
This book is not primarily about enterprise risk management in general
or COSO in particular, but the practice and discipline of project risk
management have been influenced extensively by COSO and similar
standards organizations. It is useful to understand the broad outlines of the
COSO enterprise risk management framework to ensure that your projects are
aligned and conducted consistently with enterprise requirements.
The COSO enterprise risk management framework includes eight
interrelated components that are to be defined consistently at all levels of the
organization, from the board of directors all the way down to the trenches
where projects are managed:
1. Internal environment: Includes standards, processes, codes of ethics
and conduct, and much of what was discussed in Chapter 2 regarding
risk management planning. Risk tolerance here is referred to as risk
appetite.
2. Objective setting: The what? question. At the enterprise level, this
starts with setting strategy and includes tactics, goals, and current
projects. The process for this overlaps with and includes the project
portfolio process explored earlier in this chapter. This is also where
measures are defined that will be used throughout the organization.
3. Event identification: Risk identification for the enterprise, including
(but not limited to) project risk identification as covered in Chapters 3
through 5.
4. Risk assessment: Both qualitative and quantitative analysis of overall
enterprise risk, using techniques consistent with those discussed in
Chapters 7 and 9.
5. Risk response: This component defines precisely the same responses
as Chapters 8 and 10: avoid, mitigate (here called reduce), transfer
(here called share), and accept.
6. Control activities: This and the last two COSO enterprise risk
management framework items align with the practices outlined in
Chapter 11 on risk monitoring and control. Emphasis is on ownership
of the risk responses and on the use of retrospective analysis for
feedback (as described in Chapter 12).
7. Information and communication: Communication is always
fundamental to good management at all levels. Emphasis here is on
credible, frequent reporting and retention of information.
8. Monitoring: Tightly coupled with control activities, with particular
prominence for metrics. Concepts such as Robert Kaplan’s balanced
scorecard are commonly part of this at the enterprise level.
Overall, the road map outlined by COSO enterprise risk management is
highly compatible with what is found in the Project Management Institute’s
Guide to the Project Management Body of Knowledge, in this book, and in
most other useful guidance on managing business risk.
COSO is not alone in the field of enterprise risk management
standards. The Risk and Insurance Management Society is aligned with the
global insurance industry and has a similar defined set of guidelines. The
International Organization for Standardization (ISO) has adopted an
international risk management standard, ISO 31000. The ISO standard lists
seven techniques for managing risk, but they are equivalent to avoid,
mitigate, transfer, and accept.
There are others as well, and the future will doubtless bring still more
standards for managing risk. Regardless, the basic content is not likely to
change materially; the fundamental ideas for risk management that have
worked in the past are quite durable. No matter what, though, there will
continue to be a stream of new projects created as a direct consequence of
enterprise risk management. The program that I was responsible for planning
at Hewlett-Packard described in the program risk management section of this
chapter was largely a consequence of the regulatory changes in the United
States and elsewhere. In particular, the requirements outlined in Section 404
of SOX call for a top-down risk assessment and impose standards for
reporting. This has led to a tightening of processes for companies throughout
the United States. At HP, it also involved replacing disparate tracking and
management methods in the fee-for-service project businesses worldwide to
ensure consistency. The trend toward better internal controls, more audits,
and improved process testing appears to be here to stay.
Key Ideas for Program, Portfolio, and Enterprise Risk Management
• Manage risk well in every project.
• Understand and manage program-level risks, particularly those
that involve cross-project dependencies, resource contention,
and program “showstoppers.”
• Minimize portfolio risk through use of appropriate criteria,
including risk and unbiased assessment of project
opportunities.
• Determine relative risks for projects and programs, and use
risk correlation analysis to lower project risk.
• Manage enterprise risk through dogmatic monitoring and
periodic maintenance of the project portfolio.
• Understand and comply with your organization’s policies and
standards for enterprise risk management.
Panama Canal: Over the Years
When the project finishes, the project team moves on. The deliverable
remains, however, and things are rarely static. The success of the Panama
Canal was as predicted, which was both good and bad. The growing traffic
through the canal in its first years of operation required increasingly frequent
filling and draining of the locks. The locks were filled from above using
water from Gatun Lake and drained to the sea, so the water required
depended on the volume of traffic. The more ships that passed through the
locks, the more water had to be drained out of the lake. Even a tropical rain
forest has dry seasons, so it was not uncommon for the water level to drop
periodically. When the water was too shallow in the roughly 13-kilometer
Gaillard Cut that sliced through the continental divide in central Panama, the
canal shut down.
This enterprise risk was increasingly troublesome as the years passed.
It interfered with the operation of a two-ocean U.S. Navy, which was one of
the main reasons for the U.S. canal project in the first place. After several
decades of periodic difficulty keeping the canal operational year-round, a
sizable follow-on project was initiated to ensure a more reliable supply of
water. This project constructed yet another dam, this one further up Chagres
River above Gatun Lake. In 1935, the Madden Dam was completed, creating
Alajuela Lake and the supply of additional water that the canal depends on to
this day.
Chapter
14
Conclusion
Whether you think you can do a thing, or not,
you are probably right.
—HENRY FORD
Risk management processes provide a way to learn whether your
project is feasible—whether you should believe it is possible. A feeling of
confidence, based on credible information, is a powerful determinant of
success, and project risk information is a key source of the data that people
need. Even when the verdict of the risk assessment is negative, it leads you to
better alternatives.
This book contains a wide range of ideas and techniques for project
risk management. It is fair to ask whether all of these are always necessary,
and the answer is simple: no. Each is essential to some projects at some
times, but it is hard to imagine any project that would benefit sufficiently
from everything discussed in this book to justify doing all of it. Besides,
some of the concepts covered represent alternative approaches to similar ends
and would be redundant.
So, how much is appropriate? The answer to this, like the answer to
every other good question relating to project management, is that it depends.
Projects vary so widely that there can be no one-size-fits-all answer. The
trade-off between the value of risk information developed and the effort and
cost associated with obtaining it always makes deciding how much project
risk management to do a judgment call.
That said, there is at least one useful guideline. Do enough planning
and risk management to convince yourself that the project is, in fact, possible.
The quote from Henry Ford applies to projects of all kinds. People
successfully deliver on ridiculously difficult objectives with amazing
regularity, when they believe that they can. When people are confident that
they will be successful, they persist until they find a way to get things done.
Conversely, even the most trivial projects fail when the people working on
them lack confidence. Their belief in failure becomes self-fulfilling; no one
puts in much effort. Why bother?
Demonstrating to all concerned that your project is at least plausible
defines the minimum investment in project planning and risk assessment that
is prudent. If you can do this with informal discussions and capture the
necessary information on index cards or yellow sticky notes, do it that way
and get to work. If your project warrants more formality—and most complex
projects do—determine what you need to do to provide confidence to the
project team and establish a baseline for status tracking and change
management. But remain practical. Getting more involved than necessary in
computer tools and complex analysis techniques is just as inappropriate to
project and risk management as doing too little.
The most successful strategy for making permanent process
improvements is to define your objective clearly in measurable terms and
then to make small process additions and adjustments over time, assessing
whether they are effective and helpful. Continuing this strategy over a
sequence of projects will result in effective control of risk at an acceptably
modest cost in time and effort. Adding a lot of new overhead to a project
environment all at once is not only expensive but also distracts at least the
project leader from other project issues, often creating more problems than it
solves.
Think about all the ideas and techniques in this book in the same way
that a craftsperson views his or her tools. The tool set has tools that are used
every day, tools that are used only once in a while, and even a few tools that
have never been used, at least so far. The entire set of tools is important
because even the unused tools have applications, and the craftsperson knows
that when the need arises, the right tool will be available.
Choosing to Act
Charles Bosler, chairman of the Risk Management Specific Interest
Group (RiskSIG) and noted authority on project risk management, says,
“Risk is simple. It is anything that requires you to make choices about the
future.” If you are currently doing little to manage risk, consider some of the
following choices for your future. If your project success rate improves, this
may be enough. If problems persist, add a few more ideas, and keep trying.
Although risk can never be eliminated from projects completely, it can
always be reduced, often with relatively minor incremental effort. Here are
suggestions for getting started on managing project risk.
Scope Risks
Minimize risk by thoroughly defining project scope. Every aspect of
the project deliverable that remains fuzzy, ill defined, or “flexible” represents
a real failure mode. If you do not know enough to define everything, consider
using agile methods to convert the project into a sequence of smaller efforts
that you can define, one after the other, and perform reviews and testing as
the interim subprojects complete. As you proceed, refine the scope definition
and the next steps. If actually breaking the project into incremental pieces is
not feasible, use a straw man specification to document as much specific
detail as you can and invite criticism. Always validate the scope definition
with project sponsors, customers, and key stakeholders, and set the
expectation that every scope change will require significant justification.
Schedule Risks
Project planning is the foundation for managing schedule risk, and
planning for the immediate short-term activities (at minimum) is never
optional. Based on the profile for the work, identify all the project activities
that are similar to past work that has caused trouble. For every project
estimate, set a range based on your confidence or, better yet, probe for the
worst cases and document their consequences. For projects that carry
significant risk, negotiate some schedule reserve, but in any case establish a
credible plan that could complete at a date prior to the committed deadline.
Resource Risks
Most resource risks relate to bottlenecks and constraints. Past project
resource problems are likely to recur unless you develop plans to avoid
similar situations. Perform sufficient resource analysis to reconcile your
requirements and skill needs with the project budget and available staff.
Focus sufficient attention on contracts and other aspects of outsourcing and
procurement. For particularly risky projects, negotiate a budget reserve.
General Risks
Examine your plan and brainstorm probable risks with the project
team. List known risks and determine probability and impact for each risk
using at least high/moderate/low assessments. Prioritize and distribute a risk
register containing significant risks. At a minimum, use the risk register to
make the project exposures visible. Develop prevention or recovery
responses for the most substantial risks. Whether you choose (or are even
able) to respond to risks you have identified, awareness of them makes a
difference. Risk visibility can be the factor that separates success from
failure.
Managing Your Risks
The remaining minimum requirements for risk management relate to
tracking and change control. Dwight Eisenhower said, “In preparing for
battle I have always found that plans are useless, but planning is
indispensable.” Eisenhower recognized that few things ever go exactly as
planned, which is especially true for projects. The exercise of planning never
predicts the future precisely, but it does provide what you need to measure
progress and quickly detect problems. For risk management, tracking
progress at least once a week for all current project activities is prudent.
Failure to do this periodic monitoring allows project slippage and other
problems to quickly expand and cascade, and they can soon become
insurmountable. Dogmatic, frequent tracking of project work is crucial to
ongoing risk management. You can use thorough, disciplined tracking to
detect many risk situations before they occur or at least while they are small.
Small problems can be resolved quickly, preserving the project plans and
objectives; large problems can easily take a project down.
Project control is also central to risk management. During a running
project, many things are going on that a project leader cannot control. Use the
controls you do have to your best advantage. One of the most important
controls the leader does have is the process for managing project changes.
Projects with no ability to control specification changes are almost certainly
impossible. Another thing leaders control is the flow of information. Use
project reports, meetings, and discussions to communicate risks and to keep
project issues and progress visible.
Long-term improvement of project risk management relies on
postproject analysis. Through this, you can assess project results and make
recommendations for more (or different) processes devoted to risk
management and project planning, execution, and control.
Succeeding with failure-prone projects requires three things. The first
—thorough planning based on unambiguous objectives—is the primary
subject of this book. The second is diligent tracking and control of changes,
covered in Chapter 11. The third requirement, which is project specific and
beyond the scope of this (or any single) book, is relevant expertise.
Risk management is much easier when you are lucky, and this third
element of success, expertise, represents the most obvious way to boost your
luck. To the best of your ability, staff the project with a range of skills,
including specialists in each field that the project is likely to need. Projects
with experienced practitioners are much better equipped to deal with the
twists and turns in a typical project trajectory. Recovery from risks is quick
and effective when a few battle-scarred veterans know what needs to be done
and what has worked in the past. It never hurts to recruit at least some people
for the project who have reputations as generalists known for their problem-
solving talents. Once your team is together, you can boost your luck further
by rehearsing contingency plans for significant potential problems. Whenever
you do need to recover from a problem, you want to be competent and
efficient.
Through all of this, never lose sight of the main objective: to manage
your project to successful completion. The project management ideas
presented here are components of the means to this end. Treat the ideas and
concepts of this book as your risk management toolbox. When it makes
sense, use the processes just as they are described. You may need to tailor
other ideas to make them work in your environment. If a risk management
idea promises you little current value, hold it in reserve. Above all, persevere.
Inside every impossible project lies a perfectly credible one, waiting for you
to break it free. Also remember that a little risk is not a bad thing; as Ferengi
Rule of Acquisition 62 points out, “The riskier the road, the greater the
profit.”
Panama Canal: The Twenty-First Century
Projects have a beginning and an end, but there is nearly always a next
project. At Panama there have been many over the years, such as widening of
the Gaillard Cut, and the new dam built upstream in the 1930s to ensure
continuous operation through the drier seasons described at the end of
Chapter 13. The largest operational issue for the canal that has yet to be
successfully addressed has been the limit on ship size imposed by the lock
dimensions chosen by George Goethals.
To accommodate larger ships, excavation began in the late 1930s for a
set of larger locks for both sides of the canal. This work was interrupted by
World War II and has remained uncompleted until recently. Various
alternatives for permitting transit by larger ships have been investigated over
the intervening decades. Planning for this even included a proposal that was
seriously considered in the 1950s to create Ferdinand de Lesseps’s
envisioned sea-level canal using thermonuclear bombs, a project estimated to
require about 300 detonations. Enterprise risk management might have been a
good reason to pass on this project, but the main reason appears to have been
cost.
As the twenty-first century began, so did a new era for the canal.
Following the 1999 turnover by the United States, the canal is now operated
by Panama. It remains a vital link in world shipping, but to ensure this into
the future, the first major operational change in a century of canal operations
is nearing completion—adding a third transit through the isthmus. After a
seventy-year interruption, work has resumed on a new set of locks. These
new locks are parallel to the existing locks on the Atlantic and Pacific sides
of the canal and are nearly twice as wide, 40 percent longer, and 25 percent
deeper. This new route will permit transit of larger ships in addition to
quicker transit for the PANAMAX freighters currently using the canal. As
with the original transits, which will remain in service, primary traffic will
flow inbound in the mornings and outbound in the evenings. The new locks
will hold nearly four times the volume of water required to operate the
current locks and will employ elaborate and clever plumbing to conserve and
reuse water, allowing the existing lakes to provide an adequate supply year-
round.
The current project started well in 2007, with a budget of 5.25 billion
Panamanian balboas (or U.S. dollars; the balboa has been pegged to the
dollar since 1903), including a contingency of about 20 percent. The target
for completion at that time was in 2014, to coincide with the 100-year
anniversary of the first ship to cross Panama through the canal. The plan
expected completion of the new locks no later than 2015.
The magnitude of this project is comparable to the original work, and it
faces many of the same risks and challenges of the project a century earlier,
including unstable soils, earthquakes, and soggy weather. As of late 2014, the
project is $1.6 billion over budget and running 12 to 14 months late. Part of
this delay is due to a multiweek work shutdown over who would bear the cost
overrun. Completion of the new transit is now expected in late 2015.
The canal story continues to evolve. Discussions of a fourth transit in
Panama have begun. There is also growing competition. A canal through
Nicaragua is (yet again) in the planning stages. The Suez canal is being
widened, providing an alternate connecting Asia with Europe and the eastern
coast of the Americas. No doubt there will be many future projects and much
risk to manage all of them.
Appendix
Selected Detail from the PERIL Database
The following information is excerpted from the Project Experience
Risk Information Library (PERIL) database. (These risks are an illustrative
subset selected from the database, representing less than three months of
schedule slippage. The 20 percent of the risks that resulted in more than three
months of impact are discussed in Chapters 3, 4, and 5.)
Scope Risks
• New product features were added at every weekly meeting and stage
review.
• Project was based on standards still in draft form. Several options are
possible, but project is staffed to pursue only one.
• Conversion from legacy system caused unanticipated problems
leading to delays of three to ten days per module to fix.
• Data conversion problems made the implementation of a new system
dependent on manual data reentry.
• Functionality for e-mail was added late to a document retrieval
project.
• Processes were changed and made more complex late in the project.
• A solution project was priced to win with few details on the work.
• The sponsor demanded specification changes late in the project.
• User interface requirements for a new database system were not
specific enough.
• A key telecommunications requirement was detected late.
• Component failure required finding a replacement and redoing all
tests.
• A 1,000-hour test was required at project end. Failure halfway
required repairs and a complete test rerun.
• A critical component broke because the packaging for it was too
flimsy to withstand the stress of standard shipping.
• Test hardware did not work, so all tests had to be conducted
manually.
• A complex system was designed in pieces. When integration failed,
redesign was required.
• Two related projects failed to synchronize, missing their release.
• A poorly implemented Web tool caused ongoing support issues.
• A problem solution was developed based on assumed root cause. The
cause was actually something else and resulted in a major slip.
• A purchased electronic component failed. It was necessary to design a
new one late in the project.
• The delivery of the content started before the requirements were
finalized.
• An application was found to need its own server, causing delay for
installation.
• In a large system conversion, new applications were not able to work
with existing data as expected.
• Midproject, scope was expanded to include the accounts receivable
process.
• The database designed into the system was changed, requiring more
resources and causing delay.
• An expected operating system release was canceled; the project was
forced to use a prior version.
• A new CPU chip to be used in the product was assumed the same as
the old version but required an additional heat sink and mechanical
design work.
• Original scope missed supply chain issues and could not be used
without changes.
• Scoping was documented and estimated based on data from only one
customer.
• The product was developed for multiple platforms but worked on
only two. The project was delayed to fix some, but others were
dropped.
• Market research and competitive analysis information was faulty but
not discovered until late in the project.
• New technology was used, hoping for faster performance. It did not
work well and resulted in redesign and rework.
• An instrument system built for a customer had been designed using
the current model of PC. A new version was released that was
incompatible, and project completion required finding and using an
older salvaged PC.
• A system using new components failed in final tests. Obtaining
replacement older components proved to be difficult.
• All the individual components passed their tests, but the assembled
system failed.
• A problem with transaction volumes that was not detected in test
showed up in production.
• Purchased software was limited and inflexible, which necessitated
workarounds and additional software.
• Late design changes required manufacturing retooling at the last
minute.
• “Minor” changes were added and accepted late in the project. This
doubled the work in the final phase and delayed the project.
• A database set up for the client did not have sufficient free space for
all the growing accounts.
• The development team misinterpreted a number of requirements.
• Documentation was provided in only one of the two required
languages, causing a delay for translation.
• Network configuration sometimes caused backups to fail but only
intermittently; troubleshooting was hard.
• PC board failure required redesign and fabrication.
• An upgrade to software was required. The planning and training for
this caused delays.
• New software was installed by IT. It didn’t work, and fixing it caused
a delay.
• Metrics from many sites were required. When collected, the data was
inconsistent, causing unanticipated additional work.
• The online badge printing requirement was completely missing from
the scope definition.
• Proprietary data was needed, which the owners were unwilling to
provide. After some delay, they finally shared partial information.
• Expected release of a new operating system expected slipped. This
forced the project team to use the prior version, which was missing
needed functionality.
• Although the system functioned well in Germany, it had no German
documentation. Translation resulted in delay.
• A solution project elected to integrate a new, untried technology.
• Software modules in the system did not work together as planned.
• A major bug could be fixed only by moving to a later software
version.
• The system move was delayed by last-minute system changes that
made backups take too long.
• Scope was changed after the writers had completed their initial draft.
• A large print run of materials was scrapped and redone because of
late changes required by legal.
• After the project was “complete,” significant rework was required
before customer approval.
• The design team failed to collect the details on what was to be
displayed to users.
• The project deliverable eventually collapsed because of vibration in
transit that caused nuts and bolts to work loose.
• Bugs were reported in user test that should have been caught earlier
by QA.
Schedule Risks
• The quantity of CPU processor chips needed was not available.
• There were too few disc drives and insufficient physical space for the
needed number.
• Conversion normally requires six months from the date a contract is
signed, but project goal was four months.
• Software development was underestimated by a factor of three.
• None of the project staff knew the technology.
• Training for a new tool took more time than planned.
• Because the water supply available to complete project was
inadequate, water had to be trucked in.
• Expert opinion estimated two weeks, but the work took eight.
• Needed components were delayed because of an internal supplier
problem.
• Work estimated displayed chronic optimism on completion dates.
• Multiple-phase rollout was delayed near the end because the systems
needed were temporarily out of stock.
• Decisions were delayed without apparent reason.
• International leased line order was delayed while awaiting
management approval.
• The systems required were on back order for six months, so the
project was forced to use a competitor’s system.
• The business counterparts were not in agreement on which option to
choose.
• A special peripheral needed for the project deliverable was
discontinued.
• Compilers and open source libraries needed were not available.
• Partner organizations were late with promised work, and even then
their deliverables did not work as expected.
• Field engineers experienced long learning curves.
• The customer insisted on a deadline shorter than the plan.
• Development scheduled in parallel led to frequent rework.
• Needed skilled resources were unavailable.
• A three-week test took seven because of learning curves and ramping
time.
• New hires were used for critical work, which required time for
training.
• Senior management approval for software licenses was delayed.
• The system needed was delivered to the wrong building and was lost
for weeks.
• The shipping requirements changed. Some shipments bounced, others
got stuck in customs.
• Metrics required by a process improvement project were collected
and delivered late.
• With a 12-hour time difference and heavy dependence on e-mail,
even simple questions took two to four days to resolve.
• International shipment of parts was estimated to take six weeks, but it
actually averages nine.
• Some parts were damaged in shipping and had to be reordered.
• Space was unavailable, so the project was forced to implement in the
old space.
• Infrastructure changes caused last-minute problems.
• A sole-source chip supplier was reliable for low volume, but at high
volume (and lower cost) it had quality problems that created delays.
• Components that could have been purchased were developed by the
team, which took longer than expected.
• The system integration task was not broken down to small,
manageable pieces in the project plan.
• There were chronic problems getting timely management decisions.
• Disaster recovery tests were delayed at project end because the
hardware required was tied up solving another customer’s problem.
• Some critical equipment needed for the project came from a pool of
hardware in another country, which was delayed in customs.
• Parts of the development team had a 12-hour time difference.
• Bugs took an average of two to three days longer to fix than
anticipated.
• Defective parts were received, and reordering doubled the time
required.
• There were frequent delivery problems on international shipment with
customs and paperwork.
• Firewall changes typically had taken 25 days, but the estimates were
capped at 15.
• Estimates for cabling were too optimistic.
• The deliverable expected from a related project arrived on time, but
the project could not use it.
• A flood shut down the data center, resulting in delay to restore power
and clean up.
• Customer-supplied hardware did not work, and replacements were
needed.
• A system was taken down for scheduled maintenance when needed
by the project.
• There was no coordinated shipment of system components, so the last
part to arrive delayed installation.
• A dependency on another project was not discovered until project
end.
Resource Risks
• Project needed $150,000 per month in supplies but had a limit of
$100,000.
• The senior system analyst, who was fully trained on the application,
resigned.
• The travel budget for the project was cut, which led to inefficient
long-distance collaborations.
• A key subcontractor went out of business, and it took two months to
find a replacement.
• Midway in design stage, an important engineer had a family
emergency and had to leave the country for a month.
• Two technicians were reassigned to a more business-critical project
midway through system development.
• The government contract required that the staff have only U.S.-born
nationals, but there were too few.
• The only experienced programmer gave notice and left the company.
• Halfway through the project, three of the engineers had to return to
China because of visa issues.
• A key engineer was pulled off the team to work on another project.
• The project manager was unavailable because of jury duty.
• Money for needed software was not in the current budget, so the
project was delayed to push the expense into the next quarter.
• Contract negotiations delayed the start of work.
• The project leader resigned and was not promptly replaced.
• Outsourcing the order entry process delayed all U.S.-based
customers.
• Legacy systems were not retired as planned, and the project team got
tied up with unplanned support work.
• Critical skills unique in the head of a programmer were lost when he
had a heart attack.
• Critical training had to be postponed because of a last-minute
emergency leave by the lead designer.
• For cost reasons, an Asian supplier was chosen, but qualification and
paperwork caused delays.
• Initial stages of the project were outsourced to a professor who started
late and lacked needed information.
• Last project tied up and exhausted the staff; so the following project
started late and slowly.
• A key contributor was lost while solving problems related to a
previous project.
• An engineer critical to the project left the company.
• Team members were reassigned to other, higher-priority projects.
• Only one employee had both the COBOL and relational database data
conversion experience needed and she had other conflicting
commitments.
• A valuable resource was pulled off project to work on a higher-profile
project.
• Team members were lost to a customer hot site.
• A consultant broke both arms three weeks before project end.
• Two projects depended on one resource for completion, and the other
project had higher priority.
• The system architect who knew how to integrate all the components
fell sick and was hospitalized.
• An earthquake in Taiwan made part of the project team unavailable.
• There was a lack of money for needed equipment.
• Pricing negotiations stalled project work until they could be resolved.
• Slow renewal of the contract for a consultant caused a work
interruption.
• The contract had no penalties for missing deadlines and a one-week
task took three weeks.
• Outsourced tasks were slipping, but this was not known until too late.
• At a critical stage of the project, the medical director left the
company.
• Late in project, the budget and staff were cut. This resulted in delays,
forced overtime, and team demotivation.
• Key people resigned, leaving too few to complete the project on time.
• On a very long project, enthusiasm and motivation fell, and task
execution stretched out.
• Key work in flu season was delayed when most of the staff was out
ill.
• The team was frequently diverted from the project to perform support
activities.
• A key resource was pulled off the project twice to fix bugs in a
previous product.
• The lead engineer was stuck in Japan for two weeks longer than
expected because of a visa problem.
• A packaging engineer was working on another high-priority project
when needed.
• Key welding staff members were out with the flu.
• Manufacturing volumes spiked, which diverted several project
contributors.
• An unannounced audit midproject caused delay to participate and
respond.
• An important team member was grounded in the Middle East during a
regional war.
Index
AC (actual cost), 266
acceptance criteria, in scope document, 63
acceptance of final project, 322–323
acceptance of risk, 223–224
acknowledging contributions, 323–324
activities in schedule, 86–87
estimating duration of, 87–105
owner of, 92
responsibility for, 126
revising dependencies for, 148–149
sequencing of, 99–100
timing of risky, 103
activity risk analysis, 161–188
in Panama Canal project, 161–188
qualitative, 161–163, 172–177
quantitative, 161–163, 177–186
risk impact in, 166–172
risk probability in, 163–166
activity risk management, 189–231
bow tie analysis for, 228
categories in, 190–193
documentation in, 223–224, 228
key ideas for, 229
in Panama Canal project, 229–231
preventative idea implementation for, 214–218
risk effects in, 218–223
risk response planning in, 196–214
risk selection in, 193–196
root cause analysis for, 190
specific risks in, 224–227
actual cost (AC), 266
actual cost of work performed (ACWP), 267
ACWP (actual cost of work performed), 267
agenda for status meetings, 313
aggregation
of risk responses, 234–235
in work breakdown structure, 70
analysis of scale, 257–258
anecdotal information, and project management benefits, 28–29
appraisal of project, 258–260
approximations, manual, 242–244
architecture, in risk complexity index, 66
archive/archiving, 314, 323, 328
Aristotle, on beginning well, 49
assets in balance sheet, 73
assumptions analysis, 155
attendance at status meetings, 313
availability of staff, 71, 115, 120
average projects, in project portfolio, 343
avoiding risks, 196, 200–202
BAC (Budget at Completion), 267
Bacon, Francis, on knowledge, 232
bad news on status, response to, 304
balance sheet, 73
baselines
for metrics, 282
negotiations on, 288–291
BCWP (budgeted cost of work performed), 267
behavior, metrics encouraging, 261–262
bell-type distribution curve, 97
Berra, Yogi, on observation, 22
best practices, 4
Beta distribution, 183, 184
bias, 39–40, 42, 162–164, 168
“black swans,” 45–47, 337
as resource risk, 113–115
as schedule risk, 84–86
as scope risk, 54–56
Boehm, Barry, 90
Bosler, Charles, 368
bow tie analysis, 157, 228
BP Deepwater Horizon oil spill, 228
brainstorming, 154, 190, 339
“break-even,” 271
Brooks, Fred
The Mythical Man-Month, 130
on software projects, 299
Budget at Completion (BAC), 267
budgeted cost of work performed (BCWP), 267
budgeting, 133
budget reserve, 287
business consequences, of risks, 170–171
calculator, 65
calendar duration estimates, 92, 94–95
Canal Bulletin, 20
Canal Record, 135
capacity
for multiple projects, 347
need for excess, 111
career, penalties, 169
case studies, on benefits of project management, 30–32
cause-and-effect analysis, 190
causes of risk, dealing with, 196–197, 199–200
CCPM (Critical Chain Project Management), 247–249
celebration, 324
change
and improved results, 321
and need for planning, 26
process of, 293–296
and scope risk, 50
change analysis, 293–294
change management, for specifications, 292–296
change risks, 50–53
change submissions, 293, 295–296
CHAOS Report, 22
checking phase of project, 129
Clark, Kim, Revolutionizing Product Development, 120
Clay, Henry, on statistics, 189
closing projects, 321–328
contract and document close-out, 323
formal acceptance, 322–323
key ideas for, 328
and retrospective analysis, 324–328
coaching, 38
COCOMO (Constructive Cost Model), 90, 91
collecting project status, 304
Colombia, 18
Committee of Sponsoring Organizations of the Treadway Commission (COSO), 362–364
communication, 14, 39, 310–314
of change proposal decision, 296
in COSO framework, 364
final project report, 323
informal on project, 314
periodic on project, 278
status reports, 310–312
see also meetings
Compagnie Universal du Canal Interoceanique, 19
competence of staff, 119
computer simulation, for project risk analysis, 242–246
ComputerWorld, 358–359
conditional branching, 175–176
confidentiality risk, 73–76
Confucius, on knowledge, 161
consequences of event, 5
constraint analysis, project, 137–141
constraints, 136
CCPM and, 247–248
key ideas for managing, 159
Constructive Cost Model (COCOMO), 90, 91
contingency plans, 219–222, 309
documentation, 223–224
for resource risks, 221–222
for schedule risks, 220–221
for scope risks, 222
contingency recovery plans, 190
contract, completing final paperwork, 323
contracting, 126–127
contributions, acknowledging, 323–324
control activities, in COSO framework, 364
controllable known risks, 191–193
COSO (Committee of Sponsoring Organizations of the Treadway Commission), 362–364
COSO Enterprise Risk Management—Integrated Framework, 363–364
COSO Internal Control—Internal Framework, 362–363
cost estimates
adjusted for uncertainty, 131
and budgeting, 130–133
and technical staff, 19
cost performance index (CPI), 266, 306
costs
of project management, 28
of project risk management, 14–15
risk analysis and, 13
of risks, 214–216
schedules and, 246–247
of start-up workshops, 280
variance, 179–180
cost variance (CV), 266
CPI (cost performance index), 266, 306
CPM (critical path methodology), 100–103
“crashing” schedule, 150–153
criteria, 8–9
Critical Chain (Goldratt), 247
Critical Chain Project Management (CCPM), 247–249
critical path methodology (CPM), 100–103
cross dependencies in program, 333
cross-project dependencies, and program-level risk, 335–336
cumulative cost of projects, and project selection, 351
CV (cost variance), 266
Darrow, Clarence, on history, 321
data archives, 36–37
data collection, 282–283, 302
data quality assessment, 176
deadlines, 301
failure to meet, 130
imposed, 83
sponsors and, 290
from stakeholders, 88
decision criteria, in portfolio management, 345–346
decision process
for change request, 295–296
and delay risk, 82
and monitoring, 302
for outsourcing, 124
in risk prevention, 215–216
for taking action, 368–371
decision trees, 180–181
defect risks, 53–54
defects, and scope risk, 50
definition documents, 277–278
de Jager, Peter, 358–360
delayed starts, 112–114
delay risks, 80–82, 84, 85
delegation, 71
de Lesseps, Ferdinand, 18, 19
deliverables
accepting, 322–323
defining, 56–64
descriptions, 277
proposed changes, 145
value of, 27
Delphi estimates, 91
denial, 39
dependency risks, 52–53, 56, 83–84
“black swans,” 84–86
interfaces, 104–105
revising for activities, 148–149
in schedule, 80
development projects, 60
diagnostic metrics, 262, 265–269, 305–308
Dill, Robert, 135
disposition, of change proposal, 295–296
distractions, 121
distribution functions, 183–185
documentation
of change process, 293
of change proposal decision, 296
close-out, 323
online storage of, 279
of program, 334
of program interfaces, 336–337
requirements for, 277–279
of resource risks, 133–134
of retrospective meeting results, 327
of risk plans, 223–224
of risks, 39, 158–159, 339
of schedule risks, 105–106
of scope, 61–63
of scope risk, 76–77
types, 277–279
doing phase of project, 129
duration estimates, 92, 93, 96–99
earned value (EV), 266
earned value management (EVM), 265–269, 306
education, risk management, 38
effects of risk, dealing with, 197
effort estimates, 92, 127
by project phase, 129–130
resource factors and, 94
risk-adjusted, 128–130
Eiffel, Gustav, 19
Eisenhower, Dwight, 370
empirical data, 6, 163
employees, see project team members; staff
end users, project team contact with, 203
enterprise risk management, 357–366
based on standards, 362–365
COSO framework, 363–364
focus of, 332
impact on projects, 357–358
key ideas in, 365
and organizational threats, 357–362
in Panama Canal project, 365–366
equipment, 132, see also hardware
estimate risks, 80, 82–85, 87–89
estimates
of costs, 130–133
revisiting, 119–121
risk-adjusted effort, 128–130
setting ranges for, 186
types of, 92
estimating techniques, 89–99
EV (earned value), 266
event identification, in COSO framework, 364
Event Tree, 157
EVM (earned value management), 265–269, 306
expectations, 4, 6
expected duration, 10
expenses, control over, 27
experience, learning from, 5
experts, 90, 156
extreme programming (XP), 61
face-to-face communications, 313
fact-based negotiations, 289–291
failed projects, 4–5
anatomy of, 17–21
avoiding, 5
financial basis for measuring, 356
reasons for, 23
taking over, 317
failure, or success, 330
failure modes, awareness of, 12
Fault Tree, 157
feasibility, 49, 367
final project report, 323
financial consequences of risks, 170–171
financial metrics, 270–274
internal rate of return, 273
net present value, 272–273
payback analysis, 271–272
ROI estimates, 273–274
time value of money, 270–271
financial reporting, commission on inaccuracies, 362–363
financial risk, predictive metrics, 265
“firefighting,” minimizing, 13
fishbone diagrams, 190, 191
Fisher, Roger, Getting to Yes, 290
float, 101, 147–148
follow-up for start-up workshop, 280–281
Ford, Henry, on confidence, 367
formulas, for estimates, 90
gambling, knowing odds, 8
“gaming” the measurements, 282, 283
Gantt, Henry, 17–18, 47–48
Gantt chart, 242
General Electric Company, 231
generalists, in staff, 202–203
Geneva, Switzerland, corporate headquarters, 224–227
Getting to Yes (Fisher, Ury and Patton), 290
global projects, and communication, 310
Goethals, George Washington, 107, 134–135, 231, 319–320, 328–329
“gold plating,” 60
Goldratt, Eliyahu, Critical Chain, 247–248
Gorgas, William Crawford, 78, 134
guessing in estimates, 95
Guide to the Project Management Body of Knowledge (PMBOK® Guide), 14–16, 49, 86–87, 162
hard data, on project status, 302–303
hardware
and delay risk, 81–82
failures, 53
for Panama Canal, 159
Hewlett, Bill, 65, 108, 261, 314
high-risk projects, commitments for, 14
histogram, 6, 116–117
historical data, for estimates, 89–90
holidays, and global project schedule, 95
impact, 10–11
imposed deadlines, 83
impossibility, 46, 49
industry norms, 128
information
in COSO framework, 364
and delay risk, 81
lack of, and schedule, 88
in negotiations, 290
on troubled project, 317–318
infrastructure dependencies, 84, 86
insurance firms, 9
integration defects, 53–54
interconnected projects, 83
interest rate, and payback analysis, 271–272
interfaces, 104–105, 335–338
internal environment, in COSO framework, 363
internal rate of return, 273
International Organization for Standardization (ISO), 364
“Internet time,” 26
interruptions, impact, 120–121
Ishikawa, Kaoru, 190
“is/is not” technique, for scope documentation, 62
ISO (International Organization for Standardization), 364
issues, responding to, 309–310
judgment in estimates, 82–85
justification, of project, 13
Kennedy, John F.
on negotiating, 276
on risk, 330
key ideas
for identifying resource risks, 134
for identifying schedule risks, 106
for identifying scope risks, 77
for managing project risk, 296
for program, portfolio, and enterprise risk management, 365
for project closure, 328
for project risk analysis, 274
for project risk planning, 47
for risk monitoring and control, 319
“kickoff” meeting, 279
known risks, 191–193, 198–199
Knox, Philander, 297
large projects, 29
late starts for staff, 111
leaders, optimism of, 19
learning curve, 82, 84, 85
legal dependencies, 84
liabilities, in balance sheet, 73
losses from investment, minimizing, 69
loss of staff, 110–111, 115
“loss” times “likelihood,” 5, 7
macro-risk, 5, 7–8
“management by wandering around,” 314
management reserve, 14, 283–288
for budget, 287
covert vs. open handling of, 286
monitoring of, 315
for schedule, 284–287
using, 288
managers, beliefs about project management, 27–28
market risk, 73–74
Markowitz, Harry, 348
mathematical model, for risk probabilities, 163
mean, 7, 10
measurement baselines, 269
medium-size projects, 29
meetings
for project analysis, 39
for project start-up, 279–281
on project status, 302–303, 310, 313–314
for retrospective analysis, 325–327
metrics, 36, 261–262
baselines for, 282
collecting data for, 282–283
diagnostic, 305–308
establishing, 261–262
in reports, 312
selecting, 281–282
and trend analysis, 305–308
micro-risk, 5, 8–11
military project, Panama Canal as, 48
Millennium bug, 358–362
mitigation strategies, 204–213
for schedule risks, 206–209
for scope risks, 204–206
modeling, 181, 182, 235–241
computer simulation, 242–246
PERT, 236–241
for valuing process, 29
money, time value of, 270–271
money risks, 109, 113–114
monitoring
in COSO framework, 364
of portfolio risks, 355–356
of program risks, 341–342
of projects, 301–304
of risky projects, see risky projects
Monte Carlo simulation techniques, 242, 245
motivation, 111, 115, 127, 356
Mythical Man-Month, The (Brooks), 130
negotiations
on baseline, 288–291
fact-based, 289–291
for outsourcing, 125
to set scope limits, 289
win-win, 290
net present value, 272–273
“noise” in data capture, 281
Normal distribution, 183, 184
“not to exceed” limitations, 127
objective
defining, 368
focus on, 371
plan vs., 138
setting in COSO framework, 363
online storage, of documentation, 279
“open office” environment, 121
opportunity management, 11–12, 141–144
optimism, and estimates, 39–40, 88, 96–99, 150
optimism bias, 162–164, 168
organizational bias, 39–40
organizational risk tolerance, 34
organizational threats, 357–362
outsourcing
costs, 132
negotiations for, 125
procurement process for, 121–127
outsourcing risks, 109, 112–114, 121–130
overhead, 27, 120
ownership in WBS, 70–72
Packard, David, 9, 108, 314
Panama Canal project
completion of, 328–329
continued plans to improve, 371–372
costs of, 329
costs of failed efforts, 21
first attempt, 17–21
locks, 230–231, 320
objective adjustment for, 297–298
objective setting for, 77–78
overall risks of, 274–275
over the years, 365–366
plan improvement for, 159–160
planning for, 106–107
resources for, 134–135
risk-based replanning, 319–320
risk planning for, 229–231
risks with, 186–188
second, 47–48
Panama railroad, 18
parallel execution, 147
Pareto diagram, 31, 44–45
Parkinson, C. Northcote, on work, 79
Parkinson’s Law, 79, 287
participation in status meetings, 313
Patton, Bruce, Getting to Yes, 290
Patton, George S., on good vs. perfect plan, 136
payback analysis, 271–272
people risks, 109–112, 114–115
perfection, vs. practicality, 79
performance, vs. plan, 309
PERIL (Project Experience Risk Information Library) database, 32, 36, 40–47
“black swan” risks in, 84–86
details, 373–380
measuring impact in, 42–43
resource risks in, 378–380
risk causes in, 43–45
schedule risks in, 80, 376–378
scope risk in, 373–376
sources for, 42–43
periodic project communications, 278
periodic project reviews, 301
personal consequences, risk of, 169
PERT (Program Evaluation and Review Technique), 96–99
for cost estimates, 131
for project risk analysis, 182–185
and reserve assessment, 285
for scheduling, 242–243
pessimistic estimates, 96–99
plan
applying, 300–301
objective vs., 138
performance vs., 309
updating, 218
planned value (PV), 266
planning
above project level, 26–33
assessing options and updating, 153–154
documentation for, 278
overall process, 24–33
for Panama Canal, 19
portfolio risk management, 344–346
program risk management, 333–335
at project level, 25–26
resources, 115–118
for risk, 22, 33
validation, 291–292
value of, 370
planning data, 35
planning horizon, 105
PMBOK® Guide (Guide to the Project Management Body of Knowledge), 14–16, 49, 86–87, 162
PMO (project management office), 38
population mean, 6
portfolio management, 24
portfolio risk management, 342–356
decision criteria for, 345–347
focus, 331
key ideas in, 365
planning for, 344–346
project management and, 344
review process, 354–355
risk assessment for, 347–355
risk identification for, 346–347
risk monitoring/controlling for, 355–356
practicality, vs. perfection, 79
predictive metrics, 262, 263
preliminary analysis, 137
presentation, on project review, 317
preventative ideas, implementing, 214–218
priorities of project, 13, 138–139, 203
probability, 5, 10, 163–166, 183–185
process improvement, 38, 321, 327
procurement, 121–127
procurement risk, 127
productivity, 119–120, 169–170
program interface, 335–338
program management
key ideas in, 365
purpose of, 332–333
program risk management, 332–342
assessing risks in, 340
focus, 331
identifying risks for, 333–339
monitoring/controlling risks in, 341–342
planning, 333–335
risk responses for, 340–341
program risk register, 335, 341
program risks
assessing, 340
identifying, 333–339
monitoring and controlling, 341–342
responses for, 340–341
project control, 370
project data archives, 36–37
project documents, 277–279
project environment, 120–121
project hours per day, 94
projections, 9
project-level risk, 47, 232–235
project life cycles, 128, 129
project management
cost benefit of, 30
local data showing value of, 27
methodology for, 33
and portfolio management, 344
and project monitoring, 301–304
Project Management Knowledge Areas, 14
project management office (PMO), 38
project portfolio management, 13
project reviews, 301, 315–317
project risk analysis, 232–275
aggregating risk responses for, 234–235
and appraisal, 258–260
critical chain in, 247–249
financial metrics for, 270–274
integrated schedule/cost assessment in, 246–247
key ideas for, 274
of Panama Canal project, 274–275
project metrics for, 261–270
questionnaires/surveys for, 249–257
of scale, 257–258
scenario analysis in, 261
simulation and modeling in, 235–246
system analysis in, 247
project risk management, 276–298
analysis in portfolio management, 344–345
benefits of, 12–14
in context, 330–332
costs of, 14–15
key ideas of, 296
process of, 14–16, 276–298
projects
appraisal of, 258–260
closure of, 321–324
failure rate of, 22
possible outcomes of, 354
program interface connecting, 335–338
retrospective analysis of, 324–328
screening of, 9
selection of, 24
size of, 351–353
subdividing program into, 338
taking over troubled, 317–319
project scale, analysis of, 257–258
project status, meetings on, 302–303, 310, 313–314
project team members
adding late in project, 299
building connections among, 314
building relationships, 280
discord between, 170
early involvement by, 57
PV (planned value), 266
qualitative risk assessment, 161–165, 172–177
quantitative analysis, two-dimensional, 178–179
quantitative risk assessment, 177–186
decision trees for, 180–181
simulation and modeling for, 181, 182
tables, 178
questionnaires for risk assessment, 249–257
queuing problems, 111
rare event, large-impact, 46–47
RBS (risk breakdown structure), 36, 43–44
recovery
and contingency plans, 191
of troubled project, 318–319
regulatory dependencies, 84
relative size estimating, 91
request for proposal (RFP), 122–123
reserve, see management reserve
resource analysis
histogram for, 116–117
spreadsheets for, 244
resource factors, and effort estimates, 94
resource metrics, variance, 306
resource planning
histogram analysis, 116–117
staff acquisition, 118–121
resource risks, 108–135, 369
avoiding, 201–202
contingency plans for, 221–222
and cost budgeting, 133
and cost estimating, 130–133
diagnostic metrics for, 266
documentation of, 133–134
and effort estimates, 128–130
key ideas for identifying, 134
mitigation strategies for, 209–213
and outsourcing, 121–127
in Panama Canal project, 134–135
predictive metrics for, 264
and resource planning, 115–118
retrospective metrics for, 270
sources of, 108–115
and staff acquisition, 118–121
resources
minimizing, 139
modification, 146–147
opportunities for efficient use, 143
planning, 115–118
reserve for, 287
underestimating for portfolio needs, 355
response plan to variance, 309
retrospective analysis, 155, 324–328
documentation of, 327
meeting for, 325–327
survey for, 325, 326
retrospective metrics, 262, 269–270
return on investment (ROI), 270–271, 273–274, 348
return on investment (ROI) risk, 157
Revolutionizing Product Development (Wheelwright and Clark), 120
RFP (request for proposal), 122–123
risk, getting started managing, 368–371
risk acceptance, 223–224
risk analysis, 6, 12
key ideas, 274
qualitative, 161–163
quantitative, 161–163
risk probability, 163–166
Risk and Insurance Management Society, 364
risk assessment, 14
analysis of scale, 257–258
assessing options for, 175–176
complexity index for, 66–67
in COSO framework, 364
data quality assessment for, 176
framework for, 64–65
grid for, 67–68
matrices, 174–175
prioritizing, 177
for proposed portfolio as whole, 353
qualitative, 172–177
quantitative, 177–186
questionnaires and surveys for, 249–257
simulation and modeling for, 235–241
tables, 172–174, 178
tools, 63–68
risk assessment scores, 233
risk breakdown structure (RBS), 36, 43–44
risk detection methods, 154–158
assumptions analysis, 155
brainstorming, 154, 190
expert interviews, 156
retrospective analysis, 155, 324–328
root-cause analysis, 156, 190
scenario analysis, 155
SWOT analysis, 156
risk effects, dealing with, 218–223
risk impact, 166–172
risk management, 189, 276
avoiding risks, 196–197, 200–202
defining for project, 33–37
infrastructure for, 37–40
minimum requirements for, 370–371
mitigation strategies for, 204–213
processes and tools for, 35
risk selection for, 216–218
for specific risk, 224–227
strategy for, 34
see also project risk management
risk management plan, 37
risk prevention, cost comparisons, 214–216
risk reassessment, and project reviews, 315–317
risk register, 158–159, 176, 189
maintaining, 224
program, 339, 341
response for risks on, 195–196
risk responses
aggregation of, 234–235
in COSO framework, 364
planning of, 189, 196–200, 340
reporting of, 312
risks, 5–11
big, 45–47
categories of, 191–193
fine-tuning plans to reduce, 14
key ideas for monitoring, 319
planning for, 22
tolerance for, 345
visibility of, 292
see also program risks
risk tolerance, of stakeholder, 34
risk triggers, 312
risky projects, 299–320
and archives, 314
and communication, 310–314
metrics for, 305–308
and Panama Canal project review, 319–320
and plan application, 300–301
and responding to issues, 309–310
and reviews/reassessment, 315–317
and risk reserves, 315
and status collection, 305–308
and taking over troubled project, 317–319
and trend analysis, 308
ROI, see return on investment
Roosevelt, Theodore, 47, 48, 107, 135, 297
root-cause analysis, 156, 190
rules, for estimates, 90
“safe so far” project, 301
Santayana, George, on remembering the past, 4
SAPPHO Project, 58
Sarbanes-Oxley Act of 2002 (SOX), 363
scale, 66, 263–264
scenario analysis, 155, 261
schedule
computer tools for, 244–245
“crashing,” 150–153
modification of, 147–153
opportunity to improve, 144
and path convergence, 104
as priority, 139
for risky activities, 103
for risky project, 14
schedule performance index (SPI), 266
schedule reserve, 284–287
schedule risks, 79–107, 369
and activity definition, 86–87
and activity sequencing, 99–105
avoiding, 201
contingency plans for, 220–221
diagnostic metrics for, 265–267
documentation of, 105–106
and estimation of activity duration, 87–99
mitigation strategies for, 206–209
in Panama Canal project, 106–107
predictive metrics for, 264
resource risks and, 246–247
retrospective metrics for, 269
sources of, 80–86
schedule variance (SV), 266, 305–306
scope
dependencies, 52–53
documentation of, 61–63
modification, 145
opportunities, 142–143
as priority, 139
setting limits for project, 289
and slippage, 45
scope creep, 51, 52, 55–56, 60, 286–287
scope defect, 56
scope gaps, 51, 55
scope metrics, 306–308
scope risk, 49–78, 369
assessment tools for, 63–68
avoiding, 200–201
contingency plans for, 222
deliverables and, 56–63
diagnostic metrics for, 266
documenting, 76–77
key ideas for identifying, 77
managing, 322
mitigation strategies for, 204–206
in Panama Canal project, 77–78
predictive metrics for, 263–264
retrospective metrics for, 269
risks related to, 73–76
setting limits of, 68–69
sources of, 50–56
and work breakdown structure, 69–73
screening criteria, by banks, 9
selection, of projects, 24
sensitivity analysis, 179–180
sequencing schedule activities, 99–100
shape of histogram, 6
simulation, 181, 182, 235–241, 245–246
skill requirements of staff, 118–119
slippage, scope change and, 45
small projects, 29
soft data, 302, 303
software
costs, 132
evolutionary development, 61
problems, 53
for project risk analysis, 242–246
software development projects, 60
Software Engineering Institute, 33
SOX (Sarbanes-Oxley Act of 2002), 363
specialists, in staff, 202
specifications, change management for, 292–296
SPI (schedule performance index), 266
sponsorship, strength of, 288–289
spreadsheets, for resource analysis, 244
staff
acquisition of, 118–121
costs, 132
loss of, 110–111
and risk management, 201–203
training additional, 146–147
turnover, 127, 317
see also project team members
stakeholders
risk tolerance of, 34
and time constraints, 88
standard deviation, 10, 97
standards, 8–9, 364
Standish Group, 22
start-up workshop for project, 279–281
holding meeting and follow-up, 280–281
justifying and preparing for, 280
statistical tools, 7
status data, collecting and making use of, 304
status reports, 310–312, 318
Stevens, John, 78, 106–107, 134, 159–160, 274–275, 297–298, 328
straw-man definition document, 59–60
stress, minimizing, 300
“subprime” mortgages, 9
success, 330, 356
successful projects, 5
Suez Canal, 19, 372
suppliers, 124
surveys for risk assessment, 249–257
SV (schedule variance), 266, 305–306
SWOT analysis, 156
system analysis, 247
Taleb, Nassim Nicholas, Fooled by Randomness, 46
Taylor, Fred, 47–48
technical input, problems from lack of, 19
technical projects, 4, 53
attitudes toward planning, 25
guidelines on feasibility, 367–368
risk assessment, 63
time available, 79
technical staff, and cost estimates, 19
technology, in risk complexity index, 66
teleconference meetings, 313
templates, 36
Terman, Frederick, 108, 338
terminating project, information for decision, 23
testing final project, 322
Theory of Constraints, 247–248
thinking phase of project, 129
timeline, for known risks, 198–199
time value of money, 270–271
timing expectations, 9–10
tools, for risk management, 35
top-down deadline pressure, 88
top risks, 313
total risk, underestimating, 234
tracking project process, 26, 301–303
status cycle, 303–304
for technical projects, 302
trade-offs in plan, 140, 141
training, 146–147, 358
transfer of risk, 196, 213–214
travel, costs, 132–133
Treadway, James, 362
trend analysis, 305–308
Triangular distribution, 183, 184
triggers, 312
troubled projects, 317–319, 356
T-shirt estimations, 91
two-dimensional quantitative analysis, 178–179
Type 1 errors, 217
Type 2 errors, 217–218
uncertainty, 7
estimate adjustment for, 96–99
increasing level of, 10
management reserve to compensate for, 284
and opportunity management, 12
reduction of, 32
uncontrollable known risks, 191, 192
Uniform distribution, 183, 184
unknown risks, 191, 284, 286
“unnecessary” activity, 72
Ury, William, Getting to Yes, 290
validation, of project plan, 291–292
value analysis, 157
Value at Risk (VaR), 348–351
variance, 10
analysis, 305
as issue, 309
visibility constraints, 105
voluntary delegation, 71
Wallace, John Findlay, 77–78
WBS, see work breakdown structure
what if analysis, 101, 179
Wheelwright, Steven, Revolutionizing Product Development, 120
win-win negotiations, 290
work breakdown structure (WBS), 69–72, 86, 137, 218
work packages in WBS, 70, 86
worst-case analysis, 83, 101, 284
XP (extreme programming), 61
Y2K bug, 358–362
About the Author
TOM KENDRICK, PMP has over 35 years of project and program
experience, including senior positions with Hewlett-Packard and Visa. A
respected author, he received PMI’s David I. Cleland Project Management
Literature Award for the previous edition of this book. He lives in San
Carlos, California.
Connect with Tom Kendrick at tkendrick@FailureProofProjects.com
and visit his website: www.failureproofprojects.com.
http://tkendrick@FailureProofProjects.com
http://www.failureproofprojects.com
Free Sample Chapter from The AMA
Handbook of Project Management, Fourth
Edition by Paul C. Dinsmore, PMP, and
Jeannette Cabanis-Brewin
Be sure to read The AMA Handbook of Project Management, Fourth
Edition by Paul C. Dinsmore, PMP, and Jeannette Cabanis-Brewin (978-0-
8144-3339-3), also available as an ebook (978-0-8144-3340-9). A must-read
for any project management professional or student.
Projects are the life blood of any organization. Revised to reflect the
latest changes to A Guide to the Project Management Body of Knowledge
(PMBOK®) and the Project Management Professional Exam®, the fourth
edition of The AMA Handbook of Project Management provides readers with
a clear overview of a complex discipline. Covering everything from
individual projects to programs and strategic alignment, the book compiles
essays and advice from the field’s top professionals and features new
chapters on stakeholder management, agile project management, program
management, project governance, knowledge management, and more.
Updated with fresh examples, case studies and solutions to specific project
management dilemmas, it remains an essential reference to the critical
concepts and theories all project managers must master.
For more information, please visit: www.amacombooks.org
Here’s a free sample from the book. . . .
http://www.amacombooks.org
PREFACE
When the lunar module Eagle landed in the Sea of Tranquility at 13 hours, 19
minutes, 39.9 seconds Eastern Standard Time on July 20, 1969, the event was
hailed as one of history’s major milestones. It was also one of the most
fascinating and significant spin-offs of the U.S. space program and was the
development of flexible yet precise organizational structures, forms, and tools
that allowed people to work together to reach challenging goals. Out of that
grew the modern concept of project management.
Since the Apollo days, project management, applicable both to individual
endeavors and to a series of projects called programs, has been applied to
many new fields of activity. With the trend toward accelerated change, the
scope of project management has expanded from construction projects and
aerospace to encompass organizational change, research and development
(R&D) projects, high-tech product development, banking and finance,
nonprofit services, environmental remediation—in fact, just about every field
of human endeavor.
When it first appeared in 1993, this handbook was a major contribution to
the field, pulling together expert practitioners to share their advice on topics
such as designing adequate organizational structures, generating and
maintaining teamwork, and managing the project life cycle. The second
edition, released in 2005, was designed to complement and supplement the
Project Management Institute’s Guide to the Project Management Body of
Knowledge (PMBOK® Guide), third edition, and to provide supporting
materials for those preparing to take the certification exam or working to
maintain their certification. We have retained this feature, though the last two
editions, updating the chapters in Section One to the new standard, the
PMBOK® Guide, fifth edition, in this book.
As in previous editions, we have retained many of the original authors,
keeping those chapters that stand as classics in the field. However, with the
pace of change, we have also eliminated a few chapters that had become
dated in order to include new developments in the discipline. As a brief
overview, the fourth edition changes comprise the following:
• One hundred percent of the chapters have had editorial revisions.
• All of the chapters that repeat in this edition have been updated, either by
the author or by another expert in the field.
• Four chapters have been deleted, either because they were no longer
relevant or because we chose to replace them to improve coverage of the
topic.
• Four chapters are by new authors, replacing chapters on the same topics
with updated content and a fresh voice.
• Eleven chapters are on new topics by new authors, covering stakeholder
man agement to sustainability, agile project management to project
management in healthcare, closing processes, and everything in between.
• And, of course, it is all, to the best of our knowledge, in line with the fifth
edition of the PMBOK® Guide.
HOW TO USE THIS BOOK
Students who are taking introductory courses in project management as part
of a degree in another field (for example, engineering, information
technology, business administration, manufacturing or production
management, construction management, and so on), or who are studying for
degrees in the field of project management, will find the book invaluable. As
a complementary and supplementary text, the handbook does not contain
materials already published in the PMBOK® Guide, but it is designed to help
those studying project management understand and integrate the materials
contained in that standard, as well as project management concepts and issues
that currently are not included in the PMBOK® Guide.
The book targets a broad audience, including not only the traditional
project management faithfuls, but also professionals involved in
organizational development, research, and other associated fields. The book
provides a ready reference for anyone involved in project tasks, including
upper management executives, project sponsors, project managers, functional
managers, and team members. It addresses those working in any of the major
program- and project-oriented industries, such as defense, construction,
architecture, engineering, product development, systems development, R&D,
education, and community development. Whether you are preparing for
advancement in the project management field through certification or by
completing university courses in the field, this handbook will be a valuable
reference. For those using the book in a classroom setting, discussion
questions provided at the end of each chapter help students and peers initiate
fruitful discussions about concepts, problems, and ideas in their chosen field.
Organization of the Handbook
Section One: The Project Management Body of
Knowledge: Comprehension and Practice
This section is designed specifically to aid the reader in learning the basics of
project management and in preparing for taking the Project Management
Professional (PMP) certification exam. Chapters 3 through 17, in fact,
correspond to chapters of the PMBOK® Guide, fifth edition, that are tested
on the PMP exam. This section includes the fundamental knowledge areas
and describes the processes required to ensure that projects are brought to
successful completion.
The organization of the book is specifically designed to raise interest and
to lead readers to further analysis of the project management field. Those
preparing for certification are generally studying the field of project
management for the first time. Guide does not deal with, and the PMP
certification process does not test, concepts of project management that
extend beyond the bounds of the individual project. Yet the project manager
must survive and thrive within highly competitive business organizations,
interacting with other organizations both within their employer’s organization
and from other organizations that have an interest or stake in the project. It is
anticipated that as students work through the materials in the first section,
they will be generating questions concerning these other aspects of project
management that clearly fall outside the individual project (for example, the
individual’s career potential, the expected contributions of projects to the
organization, the requirements to manage multiple projects simultaneously,
leadership concepts that cut across organizational lines, management of the
power structures and conflicts that typically surround projects, and the
interaction of the projects with other major departments of the organization,
such as accounting, finance, and other groups being affected by the results of
the project). These broader issues are explored in Sections Two through Five
of the handbook.
Section Two: The Profession of Project Management
Section Two covers the field of project management as a rapidly growing
profession that is being supported and developed by a number of professional
organizations, particularly in the United States, Europe, and Australia. This
section documents the growth and creation of the profession, identifies the
major professional organizations contributing to its development, discusses
the status of this new profession with a global perspective, and reviews the
impact of this professionalizing process on the practitioner of project
management and on the supporting organizations. Ethics, professionalism,
and career development are the primary topics covered in this section.
Section Three: Organizational Issues in Project
Management
Even a certified professional cannot escape the realities of organizational life,
and increasingly, the role of the project manager catapults the individual out
of the single-project milieu and into organizational issues: multiple projects,
programs, performance measurement, portfolio selection and management,
enterprise systems, organizational culture and structure, and alignment with
strategy. These areas have become crucial issues in project management. Top
professionals and academics with specific expertise in these areas have been
sought out to provide tutorials on these topics in Section Three.
Section Four: Issues, Ideas, and Methods in Project
Management Practice
Politics, new methodologies and organizational structures, globally diverse
teams, breakthrough technologies, Agile, and sustainability—Section Four
brings together writers on some of the leading-edge topics in project
management. One thing that is certain about project management: it is not
going to remain static for another ten years or even ten months. The chapters
in this section provide a glimpse of where the discipline and the organizations
in which it is practiced may be heading.
Section Five: Industry Applications of Project
Management
With the growth of project management in all industry sectors, this section of
the book could be one hundred chapters long; it was difficult to limit it to a
handful of industries. As professionals, the students will need to understand
how the basic accepted concepts of project management must be adapted to
the environments found in different industries and professions. Section Five
identifies a number of specific industries, technologies, and specialty areas in
which project management is widely used and recognized, and examines the
differing priorities of the project manager in each of these different venues.
The overall thrust of this section is to demonstrate that the basic concepts of
project management apply universally across these venues, even though the
specific concepts and ideas may have different priorities and influences on
project management practices in each venue. New to this section in the fourth
edition are chapters on project management in healthcare, marketing,
financial services, and infrastructure development.
Best-Sellers from AMACOM
Emotional Intelligence for Project Managers, Second Edition
ISBN: 978-0-8144-3278-5
The second edition includes several expanded sections on self-awareness and
self-management, as well as a new chapter on using EI to lead Agile Teams
and a close look at Servant Leadership. Without the people skills necessary to
lead effectively, even the most carefully orchestrated project can fall apart.
This indispensable guide gives project managers the tools they need to create
winning teams and get the job done right and on time.
Lead with a Story: A Guide to Crafting Business Narratives That
Captivate, Convince, and Inspire
ISBN: 978-0-8144-2031-7
In the world of business, storytelling has emerged as a vital skill for every
leader and manager, with major companies encouraging its use as a means to
sell ideas, communicate a vision for the future, and inspire commitment.
Whether it’s in a speech or a memo, communicated to one person or a
thousand, using stories to convey your ideas allows you to engage others
emotionally and to effortlessly make them remember and “experience” your
ideas on a tremendously powerful, personal level.
People Styles at Work…. and Beyond
ISBN: 978-0-8144-1343-2
The book reveals the strengths and weaknesses of four different people
styles, providing practical techniques that work both on the job and off. Now
including all new material on personal relationships, parenting, and more, this
is the ultimate guide anyone can use to enhance even the most difficult
relationships.
Just Listen: Discover the Secret to Getting Through to Absolutely
Anyone
ISBN: 978-0-8144-1404-0
Barricades between people become barriers to success, progress, and
happiness; so getting through is not just a fine art, but a crucial skill. Just
Listen gives you the techniques and confidence to approach the unreachable
people in your life, and turn frustrating situations into productive outcomes
and rewarding relationships.
About AMACOM
Who We Are
AMACOM is the book publishing arm of the American Management
Association. Our broad range of offerings helps readers worldwide enhance
their personal and professional growth and reach into the future to understand
emerging trends and cutting-edge thinking.